This is a Request for Proposal (RFP) issued by Dane County's Department of Waste & Renewables for infrastructure upgrades and solar array installation at the closed Verona Landfill in Wisconsin. The solicitation is divided into two categories: Category 1 encompasses landfill infrastructure upgrades including site assessment, permitting, and construction oversight, while Category 2 covers solar design, construction, and operations. Proposers may respond to one or both categories. The project seeks to develop a minimum 3.0 MW solar photovoltaic system on approximately 50 acres of closed landfill property across four parcels (062/0608-141-8501-0, 062/0608-141-8021-1, 062/0608-141-9002-0, and 062/0608-141-9521-4), with proposals encouraged to maximize use of available space. The RFP was released on December 18, 2024, with a deadline for questions on February 4, 2025, and proposal submissions due on February 18, 2025, at 2:00 pm via the County's electronic procurement portal. A non-mandatory on-site tour is scheduled for January 28, 2025, at 11:00 am. The contract term is a maximum of five years for the Professional Service Agreement, Development Agreement, or Memorandum of Understanding, with a land lease minimum of 20 years and options to extend.
Category 1 pricing will be submitted as a fixed fee covering all phases of work, while Category 2 pricing will be presented as a business plan detailing ownership options, revenue sharing, and environmental attribute allocation. Dane County will retain ownership of renewable energy credits and environmental attributes for at least the first 3.0 MW, with excess megawatts available for negotiation. The project is open to various ownership models, including third-party ownership of landfill gas rights, and encourages creative proposals that minimize capital and operating costs while maximizing return to the County. Proposers must have at least five years of business experience and demonstrate prior involvement in at least two similar projects. Category 1 proposals require a minimum of one professional engineer, while Category 2 proposals require a minimum of one licensed electrician, engineer, or relevant certified professional. Funding sources include the Inflation Reduction Act Section 48E or 45Y Clean Electricity Production Credits with brownfield development bonuses and other applicable tax credits. No specific budget amount is provided, and rates must be maintained without increase through December 31, 2026. The project supports Dane County's goals of achieving 100% renewable electricity for county operations and reducing countywide greenhouse gas emissions by 50% by 2030, with carbon neutrality targeted by 2050.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL
RFP 324018
INFRASTRUCTURE UPGRADES AND SOLAR ARRAY INSTALLATION
FOR CLOSED VERONA LANDFILL
County of Dane
City-County Building, Room 425, 53703
Madison, WI 53703
RELEASE DATE: December 18, 2024
DEADLINE FOR QUESTIONS: February 4, 2025
RESPONSE DEADLINE: February 18, 2025, 2:00 pm
RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:
https://procurement.opengov.com/portal/countyofdane
County of Dane
REQUEST FOR PROPOSAL
Infrastructure Upgrades and Solar Array Installation for Closed Verona
Landfill
I. Introduction II. RFP Overview
III. Contract Term IV. Design Requirements and Considerations V. Project Scope of Work
VI. RFP Response Requirements & Evaluation Criteria VII. Pricing Proposal
VIII. Proposer Questionnaire & Uploads
Attachments:
A - Draft Service Agreement
B - Example Land Lease
C - 1992 Landfill Cap Construction Cross Section
D - Previous WI DNR Closure Plan Modification to Construct Solar Panels Approvals
E - Site Map with Gas Collection System
F - Landfill Prairie Seed Mixture
G - Milestone Worksheet
Request For Proposal #RFP 324018 Title: Infrastructure Upgrades and Solar Array Installation for Closed Verona Landfill
1. Introduction
1.1. Summary
The Dane County (County) Department of Waste & Renewables (W&R) is inviting proposals for the design, permitting, construction, and operation of a solar array development to be located at the closed Verona Landfill
(4654 Maple Grove Drive, Verona, WI). The scope of work will include two categories:
Category 1: Landfill Infrastructure Upgrades
Phase 1: Site Assessment Phase 2: Site Assessment for Beneficial Use of Landfill Gas Phase 3: Permits Phase 4: Construction Documents Phase 5: Construction Oversight
Category 2: Solar Design, Construction, and Operations
Each category is detailed in the Scope of Work. Proposers may choose to respond to one or both of the categories.
W&R is responsible for the management and operation of Dane County owned landfills, a renewable natural gas
(RNG) facility, Clean Sweep (a household hazardous waste and electronics recycling program), a construction and demolition (C&D) recycling facility, and various other recycling programs for materials like tires and shingles.
W&R’s mission is to provide environmentally sound and sustainable waste management and renewable energy solutions for current Dane County residents and future generations.
The closed Verona Landfill is managed by W&R. The closed landfill is a part of a larger County complex which includes the Badger Prairie Needs Network, the Badger Prairie Health Care Center, Dane County Consolidated Food
Service, and Badger Prairie County Park. The four parcels being considered for solar array development are:
062/0608-141-8501-0 062/0608-141-8021-1 062/0608-141-9002-0 062/0608-141-9521-4
The landfill contains both a leachate collection system and landfill gas collection system (GCS). Until recently, the landfill gas was used in two combustion engines that had been producing 175 kW of power. The electricity was used to offset the electricity consumption of the Badger Prairie Health Care Center, Badger Prairie Needs Network, and Dane County Consolidated Food Service. The gas generated from the landfill will eventually decrease to a non-viable level for electrical generation. Dane County will maintain gas collection and electrical generation as long as it is environmentally and fiscally responsible.
Dane County has the goals of reducing greenhouse gas emissions by 50% countywide by 2030 and becoming carbon neutral by 2050. Dane County has the goal to be carbon neutral for county operations by 2030. A key objective in achieving these goals is transitioning Dane County’s electrical consumption to renewable energy sources. This transition to 100% renewable electricity was achieved by the County in 2024. The transition was accomplished through regional utility grid portfolio upgrades and Dane County renewable energy projects, such as the Yahara Solar Project and the Dane County Regional Airport Solar project.
An increase in electrical demand from growing County operations will require additional renewable electricity and is the primary motivation for this project.
https://www.danecounty.gov/PressDetail/11003 https://daneclimateaction.org/initiatives/Airport-Solar
1.2. Contact Information
Project Contact:
Alex Thomas
Carbon Offset Program Manager
Email: thomas.alex@danecounty.gov
Phone: (608) 516-1542
Procurement Contact:
Alex Thomas
Carbon Offset Program Manager
Email: thomas.alex@countyofdane.com
Phone: (608) 516-1542
Department:
Waste & Renewables
1.3. Timeline
Release Project Date December 18, 2024
On-site Tour (Non-Mandatory) January 28, 2025, 11:00am
4654 Maple Grove Drive, Verona, WI
Question Submission Deadline February 4, 2025, 5:00pm
Question Response Deadline February 11, 2025, 5:00pm
Proposal Submission Deadline February 18, 2025, 2:00pm mailto:thomas.alex@danecounty.gov tel:(608)516-1542 mailto:thomas.alex@countyofdane.com tel:(608)516-1542
2. RFP Overview
2.1. General Solicitation Process
Obtain RFP documents from the procurement.opengov.com/portal/countyofdane website. The Proposer is responsible for checking back regularly to obtain necessary Addenda.
Interested Proposers are required to register with the County's eProcurement Portal to submit a proposal. Registration is free.
• Register by clicking “Sign Up” at https://procurement.opengov.com/login.
• Create a username, password, and activate an account.
• Select project categories that your company would like to receive future solicitation notifications for.
Note: The project category 91200 is used for this proposal, and similar projects.
• Locate the solicitation by searching for the RFP Number, Organization, or Proposal Title.
• Subscribe to “New Project Updates” to receive notifications about the solicitation.
Message procurementsupport@opengov.com with any questions regarding account set up.
If you need any additional information or have questions about this RFP, please call Alex Thomas at 608-516-1542 or send an email to Thomas.alex@danecounty.gov.
2.2. Eligibility Requirements
To be considered for this project, the Proposer must meet or exceed the following criteria:
• Have at least one registered professional with the appropriate license for the category of work
a. Category 1 proposals should include a minimum of one (1) professional engineer
b. Category 2 proposals should include a minimum of one (1) licensed electrician, engineer, or other relevant certified professional to be responsible for solar design and construction drawings
• Have been in business for a minimum of five (5) years.
• Have been responsible for the design, permitting, and construction of at least two (2) projects similar in scope and size of the requested services.
• Consideration will be given to joint ventures consisting of two (2) or more firms organized for the purpose of furnishing professional services as a single entity, providing the assignment of and provisions for continuity of the various responsibilities within the joint venture are approved by the County, and further providing that the combined firms constituting the joint venture meet the eligibility requirements listed above.
2.3. Proposal Submission
Interested Proposers are required to follow the steps, outlined below, to submit a Proposal.
• Click on "Draft Response" to submit a Proposal.
• Upload all required documents and answer all questions under Section 8.
o Complete the Contact Information Questionnaire.
o Complete the Addenda Questionnaire.
o Complete the Question and Answer (Q&A) Questionnaire.
o Complete the Fair Labor Practices Questionnaire.
o Submit Proposer W-9.
https://procurement.opengov.com/portal/countyofdane mailto:Thomas.alex@danecounty.gov o Submit the RFP Response Document.
▪ Documents must include all relevant and pertinent information outlined in Section 6 titled “RFP
Response Requirements & Evaluation Criteria”.
▪ Documents must be saved in .pdf format. The file name should include the RFP # and name of company submitting the Proposal. Please title document: "RFP #324018_[Vendor Name]_RFP Response".
o Submit the Pricing Proposal and upload any additional Pricing Proposal documents.
o Submit any Supplemental Material.
o Complete the “Designation of Confidential and Proprietary Information” Questionnaire.
• Confirm your Proposal is complete and select “Submit Proposal”.
Proposals must be submitted electronically via the County's eProcurement Portal before the deadline included in this RFP. Late Proposals will be rejected unless otherwise specified. Dane County is not liable for any cost incurred by Proposers in replying to this RFP.
2.4. Evaluation
Dane County reserves the right to accept or reject any proposal submitted.
Dane County will review submitted proposals and score each proposal against the evaluation criteria and may schedule candidates to appear before an interview panel. Those appearing for an interview must be prepared to discuss their approach for the design of this work, methodology, project team, a timetable, the basis of their fee schedule and answer questions from staff.
2.5. Award
W&R reserves the right to negotiate an Agreement after selecting the successful firm(s). W&R reserves the right to award Category 1 work to one firm and Category 2 work to another firm, or to award all of the work to a single firm. Selection is based on the proposal submitted and subsequent interviews. Therefore, the proposals must be complete. Submission of a proposal will constitute a valid offer, which may be accepted by the County for a period of ninety (90) calendar days following the proposal due date.
2.6. Contracting
Work will be initiated under a Professional Service Agreement (PSA), Development Agreement (DA) or
Memorandum of Understanding (MOU). Negotiation of the land lease or other agreement for solar construction and operation will be initiated after successfully meeting milestones established in the DA or MOU.
An example agreement is included as Attachment A and an example Land Lease is included as Attachment B.
Proposer should clearly state any limitations or conditions they may have to such agreements as part of their RFP
Response document.
3. Contract Term
The term for any PSA, DA, or MOU will be for a maximum of five (5) years from the execution date.
The term for the land lease will be a for a minimum of 20 years, with options to extend.
4. Design Requirements and Considerations
The following are to be considered in the design of the project.
4.1. Size of Solar Development
As the County’s operations expand with new construction and building expansions, additional renewable energy will be needed to maintain a 100% renewable status. The County estimates that development of a 3.0 MW system by 2027 will allow the County to maintain its commitment of a 100% renewable electricity but development proposals should maximize use of the available space. Excess MWs and their environmental attributes are available for negotiation.
• The estimated space available for solar array development at the closed Verona is 50 acres. To maximize beneficial use of the closed landfill and the efforts brought forth from this RFP, proposals should maximize use of available space while maintaining access to landfill infrastructure.
• Proposals will only be considered if they include a minimum 3.0 MW photovoltaic system.
4.2. Closed Landfill Integrity and Considerations
Project must maintain environmental integrity of the existing landfill cap and all designs will be subject to
Wisconsin Department of Natural Resources (WDNR) approval.
• The landfill was originally closed and capped in 1987. The cap consisted of 2 feet of compacted clay and 6 inches of topsoil.
• The landfill cap was reinstalled from 1992 to 1998. The existing cap consists of 2 feet of compacted clay,
1.5 feet minimum of rooting zone soil, and 6 inches of topsoil. The current landfill cap specifications can be seen in Attachment C
• In order to maintain the environmental integrity of the landfill cap, array anchors must follow a ballast design.
4.3. Wisconsin Department of Natural Resources (WDNR) Approval
All designs for closed landfill development are subject to WDNR approval. The WDNR has approved two solar array installations on closed landfills in the past (Attachment D). The first project received WDNR approval in 2017 for the Rock River Generating Station ash disposal facility and landfill. This project was a 2.1 MW system on 15 acres of closed landfill, using concrete grade beams as array anchors. The second project received WDNR approval in 2022 for the City of Milwaukee’s North College Avenue Closed Landfill. This project was a 2.25 MW system on
10.25 acres of closed landfill, using pre-cast concrete ballast blocks as array anchors.
The WDNR does not specify the design for solar array projects on landfills, however the following must apply to any completed project:
• Explosion proof.
• Accounts for potential settlement of waste.
• Maintains the final cover of the landfill and prevent erosion of final cover soils.
• Protects all engineered features of the landfill, such as monitoring wells, leachate collection system piping, and gas extraction system piping and gas wells.
• Maintains access to all engineered features of the landfill for County operation and maintenance purposes.
The WDNR approval process for development projects on closed landfills is further outlined on the WDNR’s website, linked here. (https://dnr.wisconsin.gov/topic/Landfills/development.html).
https://dnr.wisconsin.gov/topic/Landfills/development.html)
W&R is currently in the process of submitting an application to WDNR to modify the existing air permit to an ROP-
A air permit. This is expected to be completed prior to initiation of the project.
4.4. Existing Gas Collection System
The closed Verona Landfill has a gas collection system (GCS) that consists of 31 active gas wells with 6” diameter
High Density Polyethylene (HDPE) gas header piping that conveys the landfill gas to the blower and generator buildings. A map of the GCS is included as Attachment E. The average gas production is 125 standard cubic feet per minute and average gas composition is standard for the industry. All upgrades to the GCS infrastructure must be completed prior to installation of the solar array.
The County anticipates the following improvements will be required among other recommendations, following an assessment of the GCS:
• Installation or replacement of up to 6 gas extraction wells with required piping and drilling.
• Replacement of up to 1,000 feet of gas header or lateral piping.
• Installation of a pneumatic liquid extraction pump system, which must include air compressor and air supply piping.
• Replacement or repair of up to 31 wellheads for improved tuning and maintenance.
All solar designs must maintain access to gas wells and other key infrastructure. Solar arrays shall not compromise or negatively affect existing buried or above ground infrastructure.
4.5. Leachate and Gas Condensate Management
A 10,000-gallon leachate collection tank is located on the south side of the closed Verona Landfill. The tank stores the gas condensate collected in the GCS and the leachate that is collected from perforated piping installed at the bottom of the waste. The liquid is pumped regularly from the tank and hauled to Madison Metropolitan Sewer
District for treatment. A permanent connection to the sanitary system or replacement and upsizing of the tank will be required.
The tank is accessed from the southern access road and any solar array design shall maintain access to this tank.
A smaller tank is located on the northeast side of the landfill. This tank will need to be assessed for its value in continued use, necessary improvements, or abandonment as part of the Scope of Work.
4.6. Stormwater Management
There are no existing stormwater retention or detention basins on the site. The selected Proposer (Firm) will be responsible for identifying any stormwater analysis or upgrades that are needed for the project.
4.7. Existing Gas Migration System
The site includes two separate perimeter gas migration systems that monitor for the presence of landfill gas outside of the limits of waste. Each of these systems includes a small blower to prevent gas from migrating off site. These systems shall be integrated into any site control upgrades, alarms, or monitoring system. The detection sensors for these systems, as well as the control panels, must be included in the site assessment and evaluated for repairs or replacement as needed.
4.8. Existing Onsite Electrical Generation
The GCS system includes a blower that conveys the landfill gas to two CAT Engine generator sets (one (1) CAT 3412
Turbo Aspirated engine and one (1) CAT 3412 Natural Aspirated engine) and a combustion flare. The engines were originally installed in 1995 and rebuilt in 1997-1998.
For over 20 years, W&R helped reduce electricity costs for the Badger Prairie campus by generating renewable electricity from the landfill gas produced by the closed Verona Landfill. W&R sold electricity to the facilities for approximately $0.07/kWh. This is well below the utility’s current rate for electricity which is approximately
$0.12/kWh. A Power Purchase Agreement for any excess energy production with Wisconsin Power and Light
(WPL) has been in place for this electricity since 1995. The solar array must have a separate interconnect and interconnect agreement with WPL.
In May 2024, one of the generators’ controllers failed which made the unit inoperable. At that time, W&R continued to generate electricity with the backup generator while upgrades were investigated. The necessary site upgrades were estimated at over $1.5M which was not included in the 2024 budget. In July 2024, the remaining generator failed. W&R intends to make the required upgrades or replace the system to continue to generate electricity from the landfill gas if return on investment (ROI) can remain less than 10 years. Alternatively, W&R will consider proposals for third-party ownership of the landfill gas rights if it can be beneficially used and remain compliant with landfill monitoring and air permit requirements.
Upgrades or replacement of the onsite electrical generation equipment must include switchgear replacement with the following drawings and specifications:
• Tie breaker control and protection
• Generator control and protection
• Voltage regulators
• Fuel blending controls and protection
4.9. Environmental Attributes
W&R shall maintain ownership of any Carbon Credits, Renewable Energy Credits, or any other environmental attribute associated with at least the first 3.0 MWs of this project. Development proposals should maximize use of the available space. Excess MWs and their environmental attributes are available for negotiation.
For the purpose of this project, environmental attributes are defined as:
• Carbon Credits are defined as o (a) any carbon offset, carbon sequestration, or carbon utilization credits or certificates, emission reduction credits, emission allowances, green tags, tradable renewable credits or Green-e products related to carbon markets; and o (b) any other carbon market-based benefit and resource.
• Renewable Energy Credits (RECs) are defined as any credit or certification, emission reduction credit, or other generation credit associated with renewable energy production.
4.10. Prairie Planting
W&R has created over 120 acres of native prairie and was the first landfill in Wisconsin to obtain WDNR approval for a native prairie seed mix on a large portion of landfill cover. The native seed mixture approved for use on the
Dane County Landfill Site No. 2 is included in Attachment F.
Unless technically or economically prohibitive, the solar array development must use native prairie seed mix upon restoration and reseeding. Upkeep and maintenance during the establishment period, typically the first 3 to 5 years, will be required. Please indicate in your Proposal if you believe it will be technically or economically prohibitive.
4.11. Funding
Past County solar projects, such as the Yahara Solar Project, are structured such that the County leases the land for solar array development and in return, the County gains ownership of project generated environmental attributes, such as RECs, and their value. The Leasee, or their subleasee, funded and owns the solar array and is responsible for solar array interconnection, infrastructure, operation, and maintenance but in exchange retains ownership over the generated electricity and its value.
The County projects a need for a 3.0 MW solar array to meet its renewable electricity goals. The estimated space available for solar array development at the closed Verona is approximately 50 acres. To maximize beneficial use of the closed landfill and the efforts brought forth from this RFP, proposals should maximize use of available space while maintaining access to landfill infrastructure. Excess MWs and their environmental attributes are available for negotiation.
W&R also intends to leverage all available funding sources for this project, including but not limited to the Inflation Reduction Act (IRA) Section 48E Clean Electricity Production Credits or Section 45Y Clean Electricity Production Credits and the bonus for brownfield developments as well as any other relevant tax credits or incentives. If the successful Firm’s business model results in the Firm funding, developing, and/or owning the solar array, the County is open to creative agreements to make use of any funding sources that are only available to municipal government entities, if any such funding sources exist.
5. Project Scope of Work
5.1. Category 1: Landfill Infrastructure Upgrades
Subsection 5.1.1 – Phase 1: Site Assessment
The Firm shall perform a site wide evaluation of the GCS, gas migration system, electrical generation equipment, liquids management systems, and final cover system, and prepare a Site Assessment that identifies required maintenance and upgrades needed to maintain landfill operations during the construction and operation of a solar array.
Firm will be responsible to review existing monitoring and maintenance records, facilitate an on-site investigation to perform a conditions assessment (including video camera investigations and surveying), and identify conditions which affect the long-term care and operation of the site, with special considerations for maximizing gas collection.
Firm will be required to conduct on-site visits to complete the Site Assessment.
At a minimum, the Site Assessment must contain:
• Summary of Site History
• Summary of Existing Conditions and Recommendations o Site Grading and Maintenance
• Areas of settlement that need regrading to promote positive drainage.
• Clearing and grubbing, including tree intrusion of perimeter of landfill.
o Gas collection system
• Identification of gas extraction wells that need to be redrilled.
• Identification of areas where additional gas extraction is needed and where new wells will be installed.
• Identification of header or lateral piping that needs replacement.
• Identification of areas of atmospheric air intrusion and proposed corrective action.
• Evaluation of the gas migration systems and replacement of outdated sensors and electrical components.
• Capital and operating cost estimate for installation of pneumatic pumps and a compressed air system.
o Liquids management systems
• Conceptual design and cost estimate for permanent connection to the sanitary system.
• Evaluation of the leachate volumes and cost estimate for tank replacement or upsizing.
• Evaluation of condensate knockout in the blower building and proposal for automation or gravity draining system.
o Capital cost estimates for all recommended site and system improvements.
Subsection 5.1.2 – Phase 2: Assessment for Beneficial Use of Landfill Gas
The Firm will provide an additional assessment for the beneficial use of landfill gas from the Closed Verona Landfill.
For all options, removal of onsite generation equipment must be included in the scope of work. Potential replacement options include but are not limited to a new or refurbished electrical generation set with fuel blending capabilities, micro–Renewable Natural Gas generation, or onsite Compressed Natural Gas generation and dispensing.
At minimum, the assessment for beneficial use of landfill gas must include the following:
• Summary of Site History
• Summary of Existing Conditions and Recommendations
• Electrical generation system evaluation
• Evaluation of quality and quantity of landfill gas and identification of possible beneficial uses.
• Capital and operating cost estimate for repair or replacement of the generator set and for upgrading electrical controls to FERC standards.
• Capital and operating cost estimate for any proposed alternative for beneficial use of landfill gas.
• Identification of any revenue sources including Power Purchase Agreement, direct sale, environmental attribute generation and sale.
• Return on Investment analysis.
Following the completion of the assessment for beneficial use of landfill gas, if W&R determines that beneficial use is technically or economically feasible, W&R will issue a contract addendum to add the Beneficial Use of Landfill
Gas design and construction assistance work to the Scope of Work.
Alternatively, W&R is open to third-party ownership of the landfill gas rights from the Closed Verona Landfill, if it can be beneficially used and remain compliant with landfill monitoring and air permit requirements. Proposers seeking third-party ownership of the landfill gas rights must submit a proposed business plan and ownership model for W&R evaluation.
Subsection 5.1.3 – Phase 3: Permits
W&R conducts maintenance for the closed Verona Landfill, subject to regulation and compliance of the WDNR’s
Waste and Materials Management Division. Any significant changes to the operation of the closure maintenance activities will require pre-approval by WDNR Waste and Materials Management. Firm will be responsible for obtaining these approvals.
Firm will be responsible for drafting and supporting any needed permit modification applications with the WDNR Waste and Materials Management Division for the existing Closure Plan and WDNR Air Program Air Permit.
Subsection 5.1.4 – Phase 4: Construction Documents
Firm to design W&R agreed upon upgrades and prepare drawings and specifications (Construction Documents) for construction purposes. Construction Documents must comply with industry standard and WDNR recognized CQA protocols. The Construction Documents must provide the detailed requirements for the successful construction of the project and be compliant with all applicable building and safety codes. Construction drawings will include:
• Title page
• Legends and Notes
• Existing Conditions
• Grading Plan as necessary
• Demolition Plan (at minimum, demolition of non-viable electrical generation equipment)
• Erosion Control and Stormwater Management Plan
• Planned GCS Layout
• Landscaping Plan
• Electrical Drawings
• Mechanical Drawings
• Relevant Details
Additionally, an Opinion of Probable Cost, broken down by line item, shall be included in completed Construction
Documents.
Construction Documents may be required to comply with W&R Master Specifications Division 00 and Division
01. Examples of Division 00 and 01 may be found at Dane County’s Procurement Portal.
The Construction Documents must be internally consistent in terms of coordination between work of the Firm and any consultants, requirements of various divisions or trades, and drawings and specifications.
Subsection 5.1.5 – Phase 5: Construction Oversight
Firm shall provide contractor selection, conduct construction oversight, and final as-built documents. Firm shall prepare and attend a pre-bid meeting and provide bid clarifications to the Construction Documents, as necessary.
Contractor Selection Contractor Selection will start after construction documents have been approved by W&R, and will end with the start of construction. Contractor selected for this work must be qualified and possess landfill experience. Work must be overseen by a qualified landfill engineer. The Firm must provide copies of necessary engineer certification and experience.
Firm must answer all pre-bid questions and prepare any additional addenda as necessary. Addendums prepared to clarify or correct errors, omissions, or negligence by Firm, must be done at Firm’s expense.
Construction Oversight The Firm shall provide a landfill experienced professional engineer to oversee construction. W&R will retain stop work authority for the purposes of safety and landfill integrity. W&R shall have the authority to require change orders and will compensate the Firm accordingly.
Firm will be required to attend and organize a pre-construction meeting.
Firm will be responsible for the professional review, and approval or rejection of drawings, samples and other submittals during construction to determine conformance with the specific portions of the Construction
Documents.
• Deviation from the Construction Documents must be brought to the attention of W&R and concurrence received from W&R before any approval is given.
Firm will be required to attend weekly construction progress meetings and act as an on-site technical and professional advisor to W&R and point of contact for construction. Firm will be responsible for arranging, leading, and publishing minutes of the weekly construction progress meetings.
At substantial completion, W&R will schedule a construction inspection meeting. Firm must attend and provide a written punch-list to W&R. The punch-list must contain items found not to be complete, in need of correction, in need of replacement or otherwise not in accordance with the Construction Documents. Firm must perform or witness and document functional testing. Firm must provide W&R with the results of the functional testing and provide recommendations for corrective measures where systems do not meet design intent.
Record Documentation Firm will provide a set of Construction Documents, on which daily records of changes and deviations will be recorded. At completion of the project, the Firm will generate Record Drawings based on the marked-up documents and surveying records to show changes made during the construction process.
Record Drawings must be completed and submitted to W&R within ninety (90) calendar days of substantial completion. The consequences of addenda, change orders and other circumstances known by the Firm to have caused change must be included in the Record Drawings.
The Firm must provide an Operating and Maintenance Manual for systems and operable mechanical equipment on the project, both powered and manual. Manuals must be provided to W&R. These manuals must include:
• Manufacturer's Instruction for Maintenance and Operation of Equipment and Systems, including a Spare
Parts List; and
• Equipment Data Sheets including recommended maintenance procedures.
Subsection 5.1.6 – Required Meetings
Project Kick-off Meeting: This meeting will be used to discuss roles and responsibilities, site history, expectations, project challenges and opportunities, current operating conditions, and overall timeline for completing the work.
Biweekly Meetings: These meetings will be held every two weeks for the duration of the project. These meetings will act as review meetings for drafts of deliverables, timeline update meetings, and the venue for any other communication needs that arise during the project.
Agency meetings: These meetings will be held after the submission of the WDNR Landfill Closure Plan Modification application and the WDNR Air Permit Modification Application. Anticipate a minimum of two (2) agency meetings.
Pre-Construction Meeting: This meeting will allow Firm, and W&R to coordinate construction schedule, submittal review timelines, critical path items, and discuss any potential challenges for construction. This meeting will occur prior to construction.
Weekly Construction Progress Meetings: These meetings will allow Firm, and W&R to ensure timely completion of construction work, address any questions, and coordinate upcoming activities. These will replace the Biweekly
Meetings.
Substantial Completion Inspection Meeting: This will walk through the entire construction project in order to develop a project close-out punch-list.
Subsection 5.1.7 – Deliverables Provide Site Assessment as outlined above to W&R. Assume two (2) review iterations and that each iteration will require two (2) weeks for review by W&R. (5.1.1)
Provide Site Assessment for Beneficial Use of Landfill Gas as outlined above to W&R. Assume two (2) review iterations and that each iteration will require two (2) weeks for review by W&R. (5.1.2)
Provide draft permit applications, as outlined above, to W&R. Assume one (1) review iteration for each deliverable and one (1) week review by W&R (5.1.3).
Provide Construction Documents as outlined above, to W&R at 50%, 75%, and 95% design. Assume one (1) review iteration for each deliverable and two (2) week review by W&R (5.1.4).
Provide draft punch-list to W&R. Assume one (1) review iteration with one (1) week review by W&R. Provide final punch-list to W&R and contractor.
Provide Record Documents, as outlined above, to W&R. Assume one (1) review iteration with one (1) week review by W&R.
Subsection 5.1.8 – Pricing Pricing for the Category 1 work will be a fixed fee for all work related to preparation and submittal of each of the above subsections (Base Fee 1).
5.2. Category 2: Solar Design, Construction, and Operations
Subsection 5.2.1 – Solar Design Work
The following work is to be included in the Development Agreement or Memorandum of Understanding:
Sizing and Preliminary Design The Firm will create and present a preliminary design, which will consist of a site map showing the approximate solar array layout with GCS, estimated size (MW), and estimated annual production (kWh’s).
Solar Array Construction Drawings
Firm will provide Solar Array Construction Drawings that incorporate the following:
• Title page
• Legend and general notes
• Existing conditions (at a minimum showing utilities, monitoring points, GCS, and limits of waste)
• Site plan showing Array layout and diagram including but not limited to:
o Access roads o Access Paths to GCS and Liquid management infrastructure
• Electrical and Mechanical Drawings including but not limited to:
o One-line electrical diagram o Photovoltaic racking system o Solar Photovoltaic panels o Inverters o Junction boxes o Balance-of-system components o Internal Direct Current (DC) and Alternating Current (AC) systems o DC wiring and conduit o AC wiring and conduit o Circuit brakers and disconnects o Transformers and switchgear(s)
• Grading plan, as necessary
• Utility and interconnection plan
• Stormwater and erosion control plan
• Site security plan
• Clear identification of how the designed system meets WDNR requirements for solar array installation on closed landfills (See subsection 4.3)
Permits and Rezoning
Dane County Zoning Firm will be responsible for rezoning or subdividing the following parcels to allow for renewable energy generation on the closed Verona Landfill. W&R will be responsible for submitting the application. The Firm is required to prepare the necessary supporting documents. The parcels are as follows:
Parcel Number Size (Acres) Zoning Code Renewable Energy Generation 062/0608-141-8501-0 39.7 RE Not Allowed 062/0608-141-8021-1 35.1 RE Not Allowed 062/0608-141-9521-4 16.0 RE Not Allowed 062/0608-141-9002-0 0.7 GC Not Allowed
28.1 RM-16 Conditional Use
WDNR Closure Plan Modification Application The Firm will be responsible for submitting the WDNR Closure Plan Modification Application For this application, WDNR is anticipated to focus on the requirements in subsection 4.3.
Interconnection Agreement Firm will be responsible to complete an interconnection application and agreement with the relevant utility provider, WPL.
W&R will support the work but the Firm will be responsible for providing any required documentation to obtain this agreement.
Firm shall communicate with Dane County any potential impacts the new interconnection may have on the existing interconnection and/or electrical infrastructure at the site.
Subsection 5.2.2: Construction, Commissioning, and Operation
The following phases of work are to be included in the Land Lease agreement:
Solar Construction
Firm will execute construction of the Verona Landfill Solar Array and provide final as-built documents. No solar array construction can begin without coordination with or completion of Category 1 (5.1) scope of work.
https://www.alliantenergy.com/cleanenergy/whatyoucando/customerinterconnection
Construction will be carried out in a safe and effective manner that maintains protection of the landfill and landfill infrastructure. Site access during construction must be maintained for W&R staff. Equipment used must not compromise the integrity of the landfill infrastructure. W&R will allow for construction to be carried out by Firm selected subcontractor.
All construction work must be done in accordance with Wisconsin Statute 111.321 and Chapter 19 of the Dane
County Code of Ordinances as not to discriminate on the basis of age, race, ethnicity, religion, color, gender, disability, marital status, sexual orientation, national origin, cultural differences, ancestry, physical appearance, arrest record or conviction record, military participation or membership in the national guard, state defense for or any other reserve component of the military forces of the United States, or political beliefs. The Firm, prior to construction, shall file an Affirmative Action Plan in accord with Chapter 19 of the Dane County Code of
Ordinances.
Stormwater and Erosion Control Permit Where applicable, Firm will be responsible for preparing and submitting a WDNR Construction Site Stormwater
Permit, via a Notification of Intent (NOI) and subsequent application. The NOI and application will require erosion control and stormwater management plans.
Where applicable, Firm will be responsible for preparing and submitting a Dane County Erosion Control Permit, via an Erosion Control and Shoreland Erosion Control application.
Solar Array Commissioning
At substantial completion, W&R will schedule a construction inspection meeting. Firm must attend and provide a written punch-list to W&R. The punch-list must contain items found not to be complete, in need of correction, replacement or otherwise not in accordance with the Construction Documents. Firm must perform or witness and document functional testing. Firm must provide W&R with the results of the functional testing and provide recommendations for corrective measures where systems do not meet design intent.
Firm will be responsible for completing all required commissioning tests as required by WPL. A copy of all commissioning tests and final WPL commissioning approval will be sent to W&R
Record Documentation Firm will provide a set of Construction Documents, on which daily records of changes and deviations will be recorded. At completion of the project, the Firm will submit its marked-up documents and surveying records.
Based on these marked up documents, Firm will revise the original documents, including the electronic files, showing changes in the work made during the construction process to produce a set of Record Drawings.
This work must be completed and submitted to W&R within ninety (90) calendar days of substantial completion.
The consequences of addenda, change orders and other circumstances known by the Firm to have caused change must be included in the production of the Record
Solar Array Operation
Firm will be responsible for the operation of the Verona Landfill Solar Array, once constructed and fully commissioned.
Firm will create an Operation Plan which will include the following at minimum:
▪ Array ownership background and summary https://dnr.wisconsin.gov/topic/Stormwater/construction https://dnr.wisconsin.gov/topic/Stormwater/construction https://lwrd.danecounty.gov/permits-applications
▪ Site Contacts
▪ Site security and access plan
▪ Emergency Response Plan
▪ Ownership and transfer procedure for environmental attributes
▪ Annual operations report and quarterly operations meeting schedule
▪ Solar array maintenance plan
▪ Prairie maintenance plan
▪ Utility usage and agreements
▪ Copy of utility interconnection agreement
▪ Any other relevant considerations during the life of the solar array
Subsection 5.2.2 – Required Meetings
Project Kick-off Meeting: This meeting will be used to discuss roles and responsibilities, expectations, project challenges and opportunities, and overall timeline for completing the project.
Monthly design development meetings: These meetings will be held monthly for the duration of the project. These meetings will be with pertinent Firm staff and W&R staff. These meetings will act as review meetings for drafts of deliverables, timeline update, and the venue for any other communication needs that arise during the project.
Relevant topics for these meeting include solar sizing, permitting applications, interconnection agreement, complete design review, and permit review.
Pre-Construction Meeting: This meeting will allow Firm and W&R to coordinate construction schedule, submittal review timelines, critical path items, and discuss any potential challenges for construction. This meeting will occur prior to construction.
Biweekly Construction Progress Meetings: This meeting will allow Firm, and W&R to ensure timely completion of construction work, address any questions, and coordinate upcoming activities. Monthly design meetings will no longer be necessary after the start of construction.
Substantial Completion Inspection Meeting: This will walk through the entire construction project in order to develop a project close-out punch-list. This will be done with W&R.
Quarterly Operations Meetings: These meetings will be used to provide quarterly updates on the operation of the solar array, any issues causing variances in generation or interconnection, and a summary of the electrical and environmental attribute generation from the past quarter. These will occur during the duration of the lease and will not begin until commissioning is complete.
Subsection 5.2.3 – Deliverables
Provide Solar Sizing and Preliminary Design (5.2.1).
Provide negotiated and completed agreement on a Land Lease for the closed Verona Landfill.
Provide Solar Array Construction Drawings (5.2.1).
Complete and provide copies of Interconnect Agreement, Rezoning Permit(s), and Closure Plan Modification
Approval (5.2.1).
Complete commissioning and verification of constructed solar array (5.2.2).
Provide a Solar Array Operation Plan. Assume one (1) review iteration with one (1) week review by W&R (5.2.2).
Provide an annual report and quarterly transfer of Environmental Attributes to the County (5.2.2).
Subsection 5.2.4 – Pricing Cost proposals for solar design, construction, and operation shall be presented in the form of a business plan that at a minimum includes Category 2 scope of work. W&R is accustomed to business arrangements with unique pricing and ownership options and encourages responses that minimize capital and/or operating cost, and maximize return to the County. Similar arrangements include the Yahara Solar Project.
https://www.danecounty.gov/PressDetail/11003
6. RFP Response Requirements & Evaluation Criteria
Proposers are to submit the following information in their proposal, in five (5) clearly distinct sections, as outlined below. Proposers may choose to respond to one or both of the categories.
Section 1: Description of planning and design techniques to be used in approaching the project. Close attention will be paid to the Proposer’s knowledge and understanding of the following where applicable for each category:
• Assessment techniques for closed landfill infrastructure conditions.
• Available technology for upgrades of landfill facilities and infrastructure.
• Landfill stormwater design and infrastructure.
• Landfill gas collection and use systems.
• Landfill leachate collection systems.
• Creativity and innovation of proposed beneficial use of landfill gas.
• Maximum solar photovoltaic production potential of available space.
• Stormwater requirements of solar array installations in the state of Wisconsin.
• Site security and safety.
• Federal, state, and local statutes, regulations and codes for solar installations greater than 1MW.
Section 2: Description of Proposer’s qualifications, experience, organization and resources. Description must include, where applicable for each category:
• Experience with, or involvement in designing landfills.
• Experience with, or involvement in management of closed landfills.
• Resumés describing the professional affiliations, educational and work experiences for each of the key staff (including consultants) that will be assigned to this project; these key staff must retain project involvement and oversight throughout the course of the project.
• Experience with, or involvement in developing large-scale solar photovoltaic systems in the past (1MW or larger).
• Experience with negotiating and executing interconnection agreements with utilities in the past. Please provide any relevant examples associated with Proposer’s experience.
• Resumés describing the professional affiliations, educational and work experiences for each of the key staff (including consultants) that would be assigned to this project; these key staff must retain project involvement and oversight throughout the course of the project.
• A project organizational chart, listing key staff and consultants, that will maintain involvement over the course of the project.
Section 3: Indicate a tentative timetable (in the form of a Gantt chart or similar chart) for each phase of the project, using a theoretical start date of May 1st, 2025. Include proposed deadlines for listed deliverables, such as
Sizing and Preliminary Design. An estimated the Milestone Worksheet is included as Attachment G.
Section 4: Pricing Proposal or proposed business plan for share of revenue and environmental attributes
Section 5: Clearly state any limitations Proposer wishes to include and detail any conditions that you may have with the example service agreement (Attachment A) or the example Land Lease (Attachment B). Example DA or
MOUs may be supplied under supplemental documents.
No. Evaluation Criteria Scoring Method Weight (Points)
1. Approach to Project and Planning Process 0-100 Points 25 (25% of Total)
2. Relative Experience and Project Personnel 0-100 Points 30 (30% of Total)
3. Cost/Rebate Proposal 0-100 Points 30 (30% of Total)
4. Timeline 0-100 Points 10 (10% of Total)
5. Limitations 0-100 Points 5 (5% of Total)
7. Pricing Proposal
BASE FEE - CATEGORY 1: LANDFILL INFRASTRUCTURE UPDATES
The Base Fees must include all costs necessary to perform the work, including but not limited to, meetings, data gathering, design, processing, subcontractors, reproducing and mailing submittals, and other work as outlined in each Phase.
Line Item Description Unit of Measure Unit Cost No Bid
1 Category 1 Scope of Work (5.1) Fixed Fee
BASE FEE - SOLAR DESIGN, CONSTRUCTION, AND OPERATIONS
The Base Fees must include all costs necessary to perform the work, including but not limited to, meetings, data gathering, design, processing, subcontractors, reproducing and mailing submittals, and other work as outlined in each Phase.
Line Item Description Unit of Measure Unit Cost No Bid
2 Category 2 Scope of Work (5.2):
Please upload business plan under supplement pricing information.
Fixed Fee
8. Proposer Questionnaire & Uploads
8.1. Contact Information
Fill out the required contact information:
8.1.1. Contact Name*
*Response required
8.1.2. Contact Title*
*Response required
8.1.3. Company Name*
*Response required
8.1.4. Company Address*
*Response required
8.1.5. Contact Telephone Number*
*Response required
8.1.6. Contact Email Address*
*Response required
8.2. RFP Addenda
8.2.1. Proposer has reviewed and acknowledges all Addenda. *
☐ Yes
☐ No
*Response required
8.3. Question and Answer (Q&A)
8.3.1. Proposes has reviewed and acknowledges all Q&A. *
☐ Yes
☐ No
*Response required
8.4. Proposer Information
8.4.1. Fair Labor Practices Certification*
Has your company been found by the National Labor Relations Board ("NLRB") or the Wisconsin Employment
Relations Commission ("WERC") to have violated any statute or regulation regarding labor standards or relations in the seven years prior to the date this bid submission is signed?
If yes is answered, a copy of any relevant information regarding such violation is required to be uploaded with your bid submission as part of Supplemental Material.
Additional information about the NLRB and WERC can be found using the following links:
www.nlrb.gov and http://werc.wi.gov.
http://www.nlrb.gov/ http://werc.wi.gov/
☐ No, our company has NOT been found by the NLRB or the WERC to have violated any statute or regulation regarding labor standards or relations in the seven years prior to the date this bid submission is signed.
☐ Yes, our company HAS been found by the NLRB or the WERC to have violated any statute or regulation regarding labor standards or relations in the seven years prior to the date this bid submission is signed.
*Response required
8.4.2. W-9*
Please upload your company's W9 form.
NOTE: The W9 is required to be signed within the past 12 months
*Response required
8.5. RFP Document Uploads
8.5.1. RFP Response Document- Upload your Proposal*
Please upload your RFP Response Document.
Please DO NOT include the Pricing Proposal in this section.
*Response required
8.5.2. RFP Response Document-Supplemental Document Upload
Upload any additional or required information documents that supplement this RFP.
8.5.3. RFP Pricing Proposal*
Please upload your Pricing Proposal in this section.
*Response required
8.5.4. RFP Pricing Proposal – Additional Documents
Please upload any documents providing further clarification of the submitted Pricing Proposal. At a minimum, provide a Rate Schedule. Rates must be maintained, with no increase, until December 31, 2026.
8…