This is an Industry Day presentation for the Little Goose Spare Transformers procurement by the U.S. Army Corps of Engineers Walla Walla District, scheduled for December 18, 2024. The project involves the design, manufacture, testing, delivery, site reassembly, and field testing of two types of Class II GSU Power Transformers: T1 Spare Transformers (two single-phase generator step-up transformers rated 164,000/244,900 kVA, 500kV high-voltage, 13.2 kV low-voltage) and T2 Spare Transformers (two single-phase generator step-up transformers rated 82,000/109,334 kVA, 500kV high-voltage, 13.2 kV low-voltage). Options include one additional T1 Transformer and one additional T2 Transformer.
The contract will be a Supply, Firm Fixed-Price with Economic Price Adjustment with a period of performance of 1,460 calendar days. Award will be made using Best Value Trade Off methodology. The target solicitation release date is March 2025 with award planned for July 2025. The transformers will be delivered to the Little Goose Lock and Dam Storage Yard. The presentation outlines the USACE project team, rules of engagement for industry communication, and CLIN structure for payment. Performance and payment bonds may be required. One-on-one sessions with industry were offered to discuss capabilities, lead times, shipping processes, teaming arrangements, risk factors, and cost considerations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INDUSTRY DAY
LITTLE GOOSE SPARE
TRANSFORMERS FOR
LOWER SNAKE RIVER
PLANTS
Brooke Moore/Kristin Hyde
Walla Walla District
December 18, 2024
• Introduction of USACE Personnel
• Schedule
• Rules of Engagement
• Project Overview
• Q&A
• One-on-One Sessions
AGENDA
USACE PERSONNEL INTRODUCTIONS
Name Position
Brooke Moore Contracting Officer
Alan Inglis/Kristin Hyde Contract Specialist
Greg Linklater Project Manager
Jack Bryson Chief of Tech at Little Goose Lock and Dam
Mark Pfeifer Technical Lead
Peter Kleine Senior Electrical Engineer (HDC)
Teresa Casper Generation Equipment Section Chief (HDC)
Randy Mallo Electrical Engineer (WW District)
Doug Newton BPA Large Capital Program Manager
SCHEDULE
Time Topic
0800-0900 Project Presentation
0930-1430 One-on-One Sessions
• Questions
• Questions welcome during the briefing both orally and through the chat feature.
• If preferred, submit questions in writing via email to Brooke Moore at brooke.n.moore@usace.army.mil and Kristin Hyde at kristin.a.hernandez@usace.army.mil.
• Proprietary Information
• Clearly identify any questions/information you consider proprietary.
• One-on-One Sessions
• Verbal answers are “Unofficial”.
RULES OF ENGAGEMENT
mailto:brooke.n.moore@usace.army.mil mailto:kristin.a.hernandez@usace.army.mil
• A consolidated list of questions and answers, as well as a copy of this PowerPoint, will be added to the notice on Sam.gov to communicate all official Government responses to non-proprietary questions.
• All items briefed today and discussed at the One-on-Ones are preliminary and are subject to final acquisition strategy and solicitation approval.
• All communications from potential offerors shall be sent to:
brooke.n.moore@usace.army.mil, kristin.a.hernandez@usace.army.mil and alan.n.inglis@usace.army.mil
• After the final solicitation is released/posted, communications are limited to the
Contracting Officer/Contract Specialist. All questions concerning this solicitation must be submitted through the Bidder Inquiry function in ProjNet.
RULES OF ENGAGEMENT (CONTINUED)
mailto:brooke.n.moore@usace.army.mil mailto:kristin.a.hernandez@usace.army.mil mailto:alan.n.inglis@usace.army.mil
PROJECT INFORMATION
Little Goose Spare Transformers for Lower Snake River Plants
PROJECT OVERVIEW
• Project Description: Design, manufacture, test, deliver (FOB to Little Goose Lock and Dam Storage Yard), site reassembly, and field testing of the following Class II GSU Power Transformers:
• T1 Spare Transformer: Two (2) single-phase generator step-up (GSU) power transformers, each rated164,000/244,900 kVA, 500kV high-voltage (H), 13.2 kV low-voltage(X&Y), Class ONAN/ONAF cooling.
– Option for One (1) additional T1 Transformer
• T2 Spare Transformer: Two (2) single-phase generator step-up (GSU) power transformers rated 82,000/109,334 kVA, 500kV high-voltage (H), 13.2 kV low-voltage(X&Y), Class ONAN/ONAF cooling.
– Option for One (1) additional T2 Transformer
• Contract type: Supply, Firm Fixed-Price with Economic Price Adjustment
• Period of Performance: 1,460 calendar days
• Acquisition Strategy: Best Value Trade Off
• Basis of Selection of Award: The anticipated award will be made to the responsible Offeror whose proposal conforms to the requirements of the solicitation, is fair and reasonable, and offers the best overall value to the Government, with appropriate consideration given to the selection factors as defined in the Solicitation.
• Access to Plans and Specifications: Not available at this time.
• Important Dates: (Subject to change)
• Target Solicitation Date: March 2025
• Target Award Date: July 2025
• Bonding: USACE is considering requiring a performance and payment bond for this project.
PROJECT OVERVIEW (CONTINUED)
• SECTION 01 22 00
• MEASUREMENT AND PAYMENT
• It is anticipated that payment will be made under the following CLIN Structure for each Transformer:
– CLIN 0001: Design, Manufacture and Factory Test two (2) T1 Transformers
– CLIN 0002: Deliver, Off-Load, Reassemble and Test two (2) T1Transformers
– CLIN 0003: Provide all Close Out Items for two (2) T1 Transformers
– CLIN 0004: Materials for two (2) T1 Transformers
– CLIN 0005: Design, Manufacture and Factory Test two (2) T2 Transformers
– CLIN 0006: Deliver, Off-Load, Reassemble and Test two (2) T2Transformers
– CLIN 0007: Provide all Close Out Items for two (2) T2 Transformers
– CLIN 0008: Materials for two (2) T2 Transformers
– Option CLIN 0009: Design, Manufacture and Factory Test one (1) T1Transformer
– Option CLIN 0010: Deliver, Off-Load, Reassemble and Test one (1) T1Transformer
– Option CLIN 0011: Provide all Close Out Items for one (1) T1 Transformer
– Option CLIN 0012: Materials for one (1) T1 Transformer
– Option CLIN 0013: Design, Manufacture and Factory Test one (1) T2 Transformer
– Option CLIN 0014: Deliver, Off-Load, Reassemble and Test one (1) T2Transformer
– Option CLIN 0015: Provide all Close Out Items for one (1) T2 Transformer
– Option CLIN 0016: Materials for one (1) T2 Transformer
MEASUREMENT AND PAYMENT
LAYDOWN AND OFFLOAD AREAS
The T1 and T2 Transformers will be delivered to the storage yard located at Little Goose Lock and Dam. Specific details will be provided in the Solicitation.
• Virtual sessions with registered firms and their teams.
• Questions/Recommendations from Industry are Highly Encouraged.
• Verbal dialog between Government and Industry, both during today’s open forum and one-on-one appointments, is unofficial.
• Official responses to questions requires submittal of questions in writing to the Government as outlined previously.
• The Government will share official responses to all industry questions via Sam.gov; however, the names of the industry representatives and their companies will not be published.
• Proprietary information will not be published if properly identified.
ONE-ON-ONE INFORMATION
1. What is your company’s bonding capability, and would this impact your ability to propose?
2. What is the current anticipated lead time for delivery?
3. Please briefly explain the expected shipping process from point of Transformer manufacture to the destination point of the Little Goose Storage Yard.
4. What percentage of the work is anticipated to be self-performed and what percentage of the work is anticipated to be subcontracted?
5. Would you have to team to successfully complete this project? And if so – do you already have a major subcontractor identified?
6. What do you identify as the high-risk elements in this project?
7. What can the Government do prior to issuing the solicitation to reduce uncertainty?
8. What do you think are the major cost drivers?
9. What things shouldn’t the Government mandate to keep costs down?
10. What should the Government mandate?
QUESTIONS FOR ONE-ON-ONE MEETINGS
Walla Walla District:
• Brooke Moore, Contracting Officer, brooke.n.moore@usace.army.mil
• Kristin Hyde, Contract Specialist, kristin.a.hernandez@usace.army.mil
• Alan Inglis, Contract Specialist, alan.n.inglis@usace.army.mil
Internet Links:
• https://sam.gov
• https://www.acquisition.gov (Federal Acquisition Regulation)
POINTS OF CONTACT
mailto:brooke.n.moore@usace.army.mil mailto:kristin.a.Hernandez@usace.army.mil mailto:alan.n.inglis@usace.army.mil https://www.acquisition.gov/ https://www.acquisition.gov/
If you have any additional questions and are not registered for a one-on-one session, please submit your question in writing per the directions on slides four and five. A consolidated list of questions and answers, as well as a copy of this PowerPoint, will be added to the notice on Sam.gov to communicate all official Government responses to non-proprietary questions.
Q&A
| Slide 1: Industry day Little Goose Spare Transformers for Lower Snake River Plants |
| Slide 2: agenda |
| Slide 3: USACE Personnel introductions |
| Slide 4: Schedule |
| Slide 5: Rules of engagement |
| Slide 6: Rules of engagement (continued) |
| Slide 7: Project information |
| Slide 8: PROJECT Overview |
| Slide 9: Project Overview (continued) |
| Slide 10: Measurement and payment |
| Slide 11: Laydown and offload areas |
| Slide 12: One-on-one information |
| Slide 13: Questions for One-on-one meetings |
| Slide 14: Points of Contact |
| Slide 15: Q&A |
File details come from the government source that posted it. Updated .