Industry Day Questions and Answers - Little Goose Spare Transformers for Lower Snake River Plants - 12.18.2024.pdf
PDF 145 KB Posted
- Solicitation number
- Not on record
About this file
This is a Questions and Answers document from an Industry Day held on December 18, 2024, for Little Goose Spare Transformers for Lower Snake River Plants, managed by the US Army Corps of Engineers Walla Walla District. The document covers key discussions about four transformer units requiring mineral oil, with an anticipated four-year lead time for delivery.
Key details include delivery and assembly flexibility, with transformers allowed to be delivered individually or together via barge, and assembly work permitted up to 24 hours per day with prior approval. The contract will be Firm Fixed Price with Economic Price Adjustment, with concerns raised about potential tariff impacts on overseas manufacturers. The government indicated they cannot recommend specific manufacturers and will research Buy American Act and Trade Agreements Act requirements. Industry representatives requested at least 90 days for proposal submission instead of the standard 30 days. The transformer pads will be ready by delivery date, with assembly occurring in an off-site storage yard to minimize impact on dam operations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
T1/T2 Industry Day
Questions from Industry
Question 1 – Lead Time
Industry: What is the value of lead time in terms of consideration?
Government: We anticipate a four year lead time for delivery. Additionally - if the Government choses to evaluate delivery schedule as a factor, the criterion for evaluation will be broken out within the solicitation evaluation factors.
Question 2 – Delivery/Assembly
Industry: Is there delivery flexibility specifically on the assembly side. Is the expectation that as soon as 2 transformers are delivered that they are immediately dressed out or can we deliver all 4 and then dress them out? How much flexibility do you have on delivery timing and dress out timing?
Government: CLIN structure anticipated is per transformer so as they are completed, you can deliver them. If it is more cost effective to ship them all at the same time, as long as you meet the target delivery then we are unconcerned. We can support receiving them with a staggered shipping schedule as long as there is coordination.
Industry: We anticipate delivery on a barge to the site which gives us a little more flexibility. We will have to look at this from a risk perspective.
Government: Pads will be ready by the delivery date. May need to consider how you would get the transformers from the barge to the trailer.
Question 3 – Delivery/Assembly
Industry: In terms of site specifications - 7 days a week 12 hours a day, 24 hours are normal when working assembly/processing. Is that acceptable?
Government: Typically, that is what we do at the projects. Sometimes there are projects that say no. The storage yard is off site of the dam, and we would have to have construction personnel to support outside of working hours but that isn’t unheard of. Impact on dam will be minimal.
Industry: Contracting and operations aren’t always on the same page. Approval of KO will be required.
So, need to iron out the directions definitively prior to project. Can’t have employees with downtime because it costs significant amounts of money.
Question 4 - Oil
Industry: Will these transformers use mineral oil?
Government: Yes, mineral oil units.
Question 5 - Tariffs
Industry: Most manufacturers are overseas and are concerned with tariffs. Prices could potentially skyrocket. Would this allow a change order? How is that handled?
Government: This is a valid concern considering the potential impacts. We will need to research this further and get back to you.
Question 6 - Manufacturers
Industry: Is there any information you can provide regarding manufacturers?
Government: We cannot recommend any particular manufacturer. We can’t speak to terminations within this field.
Industry: Have any manufacturers come out to demonstrate their product?
Government: The Government does not define the transformer manufacturers. The specific dimensional and equipment requirements for the specific transformers are specified in the Plans and Specifications.
No transformer manufacturers have demonstrated their services or capabilities to the U.S. Army Corps of
Engineers, or Walla Walla District. The Hydroelectric Design Center (HDC) has hosted device manufacturers such as temperature monitoring systems, bushings, and on-line dissolved gas analyzer manufacturers to provide training on these devices that are in service at the U.S. Army Corps of
Engineers’ hydroelectric dams. Also, during these training sessions, the device manufacturers have presented new advancements on their devices.
Industry Suggestion:
Proposal timeline – Please allow as much time at the beginning for proposal rather than giving 30 days and then continuing to provide extensions. Industry suggests initial window of at least 90 days for proposal submission.
Government Comments:
Per feedback from industry, four year lead time for delivery is standard. This action is Firm Fixed Price with Economic Price Adjustment.
Will have to research Buy American Act and/or Trade Agreements in DFARS Supplement to define our left and right limits. This action may be subject to both, and our solicitation will include the details.
Government will not address minor manufacturer process details during the bidder inquire process. These types of process or material changes are minor and will be addressed with the submittal process under a variation.