Replacement of Bridge Carrying 15th Avenue of Rock River
Solicitation number
85802
Issued by
Rock Island County, Illinois

About this file

This file is a Notice to Bidders and Specifications document issued by the Illinois Department of Transportation (IDOT) for Contract No. 85802, a bridge replacement project in Winnebago County, Illinois, specifically for the City of Rockford. The project involves the replacement of the 15th Avenue bridge carrying traffic over the Rock River, along with reconstruction of approaches, installation of bridge lighting, traffic signal modernization, sidewalk improvements, water main replacement, and landscaping. Construction limits extend from Illinois Route 2 to 390 feet west of Orange Street, with additional work on Nelson Boulevard and Blackhawk Park. Electronic bids must be submitted to the iCX system by 12:00 p.m. on November 6, 2026, at which time bids will be publicly opened. The contract completion date is October 31, 2028, with fifteen working days allotted for cleanup, punch list items, and landscaping. The contractor must abide by the City of Rockford Construction Noise Ordinance and comply with working hour restrictions, with certain commercial and industrial areas potentially requiring work outside standard hours upon engineer approval.

The contract will be awarded to the lowest responsive and responsible bidder in conformity with departmental terms and conditions. The project is subject to multiple special provisions including temporary traffic signal installation, water main relocation, storm sewer construction, and traffic control requirements. Significant utility coordination is required, with water main work spanning approximately 356 calendar days across multiple construction stages. The contractor assumes all risk of damage to work and property and is responsible for notification to residents, coordination with third-party utilities, and compliance with Army Corps of Engineers Nationwide Permit No. 14 requirements, including prohibitions on in-stream work from April 1 through July 31 and tree clearing restrictions from April 1 through September 30. The project is federally funded in part, requiring compliance with federal-aid construction contract certifications and EEO requirements. Winter shutdown provisions require traffic configuration changes by November 18, 2027, with restrictions on through-lane closures on Illinois Route 2 during winter months, and the contractor must maintain temporary pavement markings, provide snow removal around traffic control devices, and ensure a temporary eight-foot-wide bicycle path throughout construction.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting November 6, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 85802 WINNEBAGO County Section 19-00631-00-BR (Rockford) Route FAU 5082 (15th Avenue) Project 8NNV-597 () District 2 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

November 6, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 85802 WINNEBAGO County Section 19-00631-00-BR (Rockford) Project 8NNV-597 () Route FAU 5082 (15th Avenue) District 2 Construction Funds

Replacement of the bridge carrying 15th Ave. over the Rock River in the city of Rockford. Additional work consists of the reconstruction of the approaches, bridge lighting, traffic signals, sidewalk, water main replacement and landscaping.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

CONTRACT 85802

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 Additional State Requirements for Federal-Aid Construction Contracts 2 Subletting of Contracts (Federal-Aid Contracts)

3 EEO

4 Specific EEO Responsibilities Non Federal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos HMA Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays

LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS

Table of Contents

CHECK SHEET # PAGE NO.

LRS 1 Reserved LRS 2 Furnished Excavation LRS 3 Work Zone Traffic Control Surveillance LRS 4 Flaggers in Work Zones LRS 5 Contract Claims LRS 6 Bidding Requirements and Conditions for Contract Proposals LRS 7 Bidding Requirements and Conditions for Material Proposals LRS 8 Reserved LRS 9 Bituminous Surface Treatments LRS 10 Reserved LRS 11 Employment Practices LRS 12 Wages of Employees on Public Works LRS 13 Selection of Labor LRS 14 Paving Brick and Concrete Paver Pavements and Sidewalks LRS 15 Partial Payments LRS 16 Protests on Local Lettings LRS 17 Substance Abuse Prevention Program LRS 18 Multigrade Cold Mix Asphalt LRS 19 Reflective Crack Control Treatment

15th Avenue Bridge Replacement West Street to Orange Street

Section 19-00631-00-BR City of Rockford i

INDEX OF SPECIAL PROVISIONS

GENERAL PROVISIONS

LOCATION OF PROJECT

DESCRIPTION OF PROJECT

COMPLETION DATE PLUS WORKING DAYS

WORKING HOURS

CONTROL OF WORK

SCHEDULING OF WORK

PROTECTION OF PERSONS AND PROPERTY

EXAMINATION OF THE PROJECT SITE

CONSTRUCTION SEAMS

LANE CLOSURE DURATION – COMPLETION DATE (VIA CALENDAR DAYS)

PERMITS AND NOTICES

DEPARTMENT OF THE ARMY CORPS OF ENGINEERS PERMIT

WORK IN RIGHT OF WAY

AVAILABLE REPORTS

STATUS OF UTILITIES

EXISTING UTILITY REMOVAL COORDINATION

EXISTING UTILITIES AND DRAINAGE STRUCTURES LOCATIONS

PROPER BACKFILLING

CONCRETE FOUNDATIONS

SAWCUTTING

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES

ROADWAY SPECIAL PROVISIONS

TRAFFIC CONTROL PLAN

MAINTENANCE OF DRIVEWAYS

STABILIZED CONSTRUCTION ENTRANCE

TEMPORARY ACCESS

WASHOUT BASIN

TEMPORARY CHAIN LINK FENCE

DEWATERING

SIGN REMOVAL

TRAFFIC SIGNAL SPECIAL PROVISIONS

TRAFFIC SIGNAL PAINTING

TEMPORARY TRAFFIC SIGNAL INSTALLATION

RELOCATE EXISTING EMERGENCY VEHICLE PRIORITY SYSTEM

REMOVE EXISTING TRAFFIC SIGNAL EQUIPMENT

RELOCATE VIDEO VEHICLE DETECTION SYSTEM

TEMPORARY TRAFFIC SIGNAL TIMING

LIGHTING SPECIAL PROVISIONS

JUNCTION BOX, SPECIAL

ROADWAY LUMINAIRE, LED, OUTPUT DESIGNATION E

TEMPORARY LUMINAIRE, LED, ROADWAY

RELOCATE EXISTING LUMINAIRE

LUMINAIRE SAFETY CABLE ASSEMBLY

BRIDGE PROVISIONS

PARAPET RAILING (SPECIAL)

STEEL RAILING REMOVAL

Section 19-00631-00-BR ii

REMOVE AND RELOCATE EXISTING PLAQUE

CONCRETE BRIDGE RAILING (SPECIAL)

DRILL AND GROUT DOWEL BARS

WATERMAIN PROVISIONS

WATER DISTRIBUTION SYSTEM – CITY OF ROCKFORD

REQUIREMENTS FOR WATER MAIN VALVE SHUT OFF

REQUIREMENTS FOR UNSCHEDULED (EMERGENCY) WATER MAIN VALVE SHUT OFF

DUCTILE IRON WATER MAIN, 16”, 6”

FIRE HYDRANTS TO BE REMOVED

FIRE HYDRANT WITH AUXILIARY VALVE AND VALVE BOX

CONNECT TO EXISTING 6” WATER MAIN, 16” WATER MAIN

EXPANSION JOINT (WATER MAIN)

STEEL CASING

WATER MAIN 16", SPECIAL

WATER MAIN INSULATION

DRAINAGE SPECIAL PROVISIONS

PROPOSED STORM SEWER CONNECTION TO EXISTING MANHOLE

MANHOLES, TYPE A, WITH SPECIAL FRAME AND GRATE

INLETS, SPECIAL, NO. 1

INLETS, SPECIAL, NO. 2

PROPOSED MANHOLE/CATCH BASIN CONNECTION OVER EXISTING STORM SEWER

SANITARY MANHOLES TO BE ADJUSTED WITH NEW TYPE 1 FRAME, CLOSED LID

REMOVAL OF OLD CASTINGS

USACE PERMIT, TRANSFER OF PERMIT VERIFICATION, COMPLETED WORK CERTIFICATION

SWPP BDE 2342 AND CONTRACTOR CERTIFICATION STATEMENT 2342A

IEPA LPC 663

INSURANCE (LR 107-4)

CONSTRUCTION AND MAINTENANCE SIGNS

LOCAL QUALITY ASSURANCE/QUALITY MANAGEMENT QC/QA

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING

BDE SPECIAL PROVISIONS

The following special provisions indicated by an “X” are applicable to this contract. An * indicates a new or revised special provision for the letting.

File Name Pg. Special Provision Title Effective Revised 80099 91 Accessible Pedestrian Signals (APS) April 1, 2003 Jan. 1, 2022 _ 80274 93 Aggregate Subgrade Improvement April 1, 2012 April 1, 2022 80192 Automated Flagger Assistance Device Jan. 1, 2008 April 1, 2023 80173 Bituminous Materials Cost Adjustments Nov. 2, 2006 Aug. 1, 2017 80426 Bituminous Surface Treatment with Fog Seal Jan. 1, 2020 April 1, 2026 80475 Bridge Deck Concrete Overlays Jan. 1, 2026 80241 Bridge Demolition Debris July 1, 2009

5053I Building Removal Sept. 1, 1990 Aug. 1, 2022 5026I Building Removal with Asbestos Abatement Sept. 1, 1990 Aug. 1, 2022

80460 96 Cement, Finely Divided Minerals, Admixtures, Concrete, and Mortar Jan. 1, 2025 Jan. 1, 2026 80384 113 Compensable Delay Costs June 2, 2017 April 1, 2019 80198 Completion Date (via calendar days) April 1, 2008 80199 Completion Date (via calendar days) Plus Working Days April 1, 2008 80461 Concrete Barrier Jan. 1, 2025 80453 117 Concrete Sealer Nov. 1, 2023 80261 Construction Air Quality – Diesel Retrofit June 1, 2010 Jan. 1, 2025 80476 Deck Slab Repair Jan. 1, 2026

* 80029 118 Disadvantaged Business Enterprise Participation Sept. 1, 2000 July 2, 2026

* 80486 Engineer’s Field Office Nov. 1, 2026 80467 122 Erosion Control Blanket Aug. 1, 2025 80229 125 Fuel Cost Adjustment April 1, 2009 Aug. 1, 2017 80452 Full Lane Sealant Waterproofing System Nov. 1, 2023 80433 Green Preformed Thermoplastic Pavement Markings Jan. 1, 2021 Jan. 1, 2022 80471 Guardrail Nov. 1, 2025 80472 High Friction Surface Treatment Nov. 1, 2025 80456 128 Hot-Mix Asphalt Jan. 1, 2024 April 1, 2026 80446 132 Hot-Mix Asphalt – Longitudinal Joint Sealant Nov. 1, 2022 Aug. 1, 2023 80438 Illinois Works Apprenticeship Initiative – State Funded Contracts June 2, 2021 April 2, 2024 80483 Inlet Filters April 1, 2026 80477 134 Longitudinal Tining Jan. 1, 2026 July 1, 2026 80450 Mechanically Stabilized Earth Retaining Walls Aug. 1, 2023 Aug. 1, 2025 80478 Modified Longitudinal Construction Joint Jan. 1, 2026 80464 136 Pavement Marking April 1, 2025 Nov. 1, 2025 80468 Pavement Patching Aug. 1, 2025 80441 137 Performance Graded Asphalt Binder Jan 1, 2023 April 1, 2026 80459 Preformed Plastic Pavement Marking June 2, 2024 3426I Railroad Protective Liability Insurance Dec. 1, 1986 Jan. 1, 2022 80473 Raised Reflective Pavement Markers Nov. 1, 2025 80455 143 Removal and Disposal of Regulated Substances Jan. 1, 2024 April 1, 2026 80474 Residential Driveway Temporary Signal Nov. 1, 2025 80445 145 Seeding Nov. 1, 2022 July 1, 2026

* 80457 151 Short Term and Temporary Pavement Markings April 1, 2024 Nov. 1, 2026 80462 155 Sign Panels and Appurtenances Jan. 1, 2025 Jan. 1, 2026 80479 Sinusoidal Rumble Strips Jan. 1, 2026 80469 Slope Wall Aug. 1, 2025 80448 157 Source of Supply and Quality Requirements Jan. 2, 2023 Jan. 1, 2026 80340 Speed Display Trailer April 2, 2014 Jan. 1, 2022 80127 159 Steel Cost Adjustment April 2, 2004 Nov. 1, 2025 80480 Structural Repair of Concrete Jan. 1, 2026 80397 161 Subcontractor and DBE Payment Reporting April 2, 2018 80391 162 Subcontractor Mobilization Payments Nov. 2, 2017 April 1, 2019

File Name Pg. Special Provision Title Effective Revised 80463 163 Submission of Bidders List Information Jan. 2, 2025 Mar. 2, 2025 80482 164 Submission of Payroll Records – Federal Aid Contract April 1, 2026 80437 Submission of Payroll Records – State Contract April 1, 2021 April 1, 2026 80435 Surface Testing of Pavements – IRI Jan. 1, 2021 Jan. 1, 2023 80465 166 Surveying Services April 1, 2025 80481 167 Temporary Concrete Barrier Jan. 1, 2026 80466 Temporary Rumble Strips April 1, 2025 80484 Tolerance in Thickness for Continuously Reinforced PCC Pavement July 1, 2026 80470 168 Traffic Signal Backplate Aug. 1, 2025 20338 169 Training Special Provisions Oct. 15, 1975 Sept. 2, 2021 80429 Ultra-Thin Bonded Wearing Course April 1, 2020 Jan. 1, 2022

* 80439 172 Vehicle and Equipment Warning Lights Nov. 1, 2021 Nov. 1, 2026 80458 Waterproofing Membrane System Aug. 1, 2024 80302 173 Weekly DBE Trucking Reports June 2, 2012 Jan. 2, 2025 80454 Wood Sign Support Nov. 1, 2023 80427 174 Work Zone Traffic Control Devices Mar. 2, 2020 Jan. 1, 2026 80485 177 Work Zone Width Restriction July 1, 2026 80071 Working Days Jan. 1, 2002

GUIDE BRIDGE SPECIAL PROVISION INDEX/CHECK SHEET

Effective as of the: January 16, 2026 Letting

An * indicates a new or revised special provision.

Pg

√ File Name Title Effective Revised

*GBSP 4 Polymer Modified Portland Cement Mortar June 7, 1994 Oct 17, 2025 GBSP 13 High-Load Multi-Rotational Bearings Oct 13, 1988 June 28, 2024 GBSP 14 Jack and Remove Existing Bearings April 20, 1994 April 13, 2018 GBSP 16 Jacking Existing Superstructure Jan 11, 1993 April 13, 2018 GBSP 18 Modular Expansion Joint May 19, 1994 Oct 27, 2023 GBSP 21 Cleaning and Painting Contact Surface Areas of Existing Steel

Structures June 30, 2003 Oct 23, 2020

*GBSP 25 Cleaning and Painting Existing Steel Structures Oct 2, 2001 Oct 17, 2025 GBSP 26 Containment and Disposal of Lead Paint Cleaning Residues Oct 2, 2001 Apr 22, 2016 GBSP 33 Pedestrian Truss Superstructure Jan 13, 1998 Oct 27, 2023 *GBSP 34 Concrete Wearing Surface June 23, 1994 Oct 17, 2025 GBSP 45 Bridge Deck Thin Polymer Overlay May 7, 1997 June 28, 2024 178 GBSP 55 Erection of Curved Steel Structures June 1, 2007 GBSP 59 Diamond Grinding and Surface Testing Bridge Sections Dec 6, 2004 April 15, 2022 GBSP 60 Containment and Disposal of Non-Lead Paint Cleaning

Residues Nov 25, 2004 Apr 22, 2016

GBSP 61 Slipform Parapet June 1, 2007 April 15, 2022 GBSP 67 Structural Assessment Reports for Contractor’s Means and

Methods Mar 6, 2009 Oct 5, 2015

GBSP 71 Aggregate Column Ground Improvement Jan 15, 2009 Oct 15, 2011 179 GBSP 78 Bridge Deck Construction Oct 22, 2013 Dec 21, 2016 GBSP 79 Bridge Deck Grooving (Longitudinal) Dec 29, 2014 Mar 29, 2017 GBSP 81 Membrane Waterproofing for Buried Structures Oct 4, 2016 March 1, 2019 GBSP 82 Metallizing of Structural Steel Oct 4, 2016 Oct 20, 2017 GBSP 83 Hot Dip Galvanizing for Structural Steel Oct 4, 2016 June 28, 2024 GBSP 85 Micropiles Apr 19, 1996 Oct 23, 2020 GBSP 86 Drilled Shafts Oct 5, 2015 Oct 27, 2023 GBSP 87 Lightweight Cellular Concrete Fill Nov 11, 2001 Apr 1, 2016 GBSP 88 Corrugated Structural Plate Structures Apr 22, 2016 April 13, 2018 GBSP 89 Preformed Pavement Joint Seal Oct 4, 2016 March 24, 2023 GBSP 90 Three Sided Precast Concrete Structure (Special) Dec 21, 2016 March 22, 2024 GBSP 91 Crosshole Sonic Logging Testing of Drilled Shafts Apr 20, 2016 March 24, 2023 GBSP 92 Thermal Integrity Profile Testing of Drilled Shafts Apr 20, 2016 March 24, 2023 GBSP 93 Preformed Bridge Joint Seal Dec 21, 2016 June 28, 2024 GBSP 94 Warranty for Cleaning and Painting Steel Structures Mar 3, 2000 Nov 24, 2004 GBSP 96 Erection of Bridge Girders Over or Adjacent to Railroads Aug 9, 2019 GBSP 97 Folded/Formed PVC Pipeliner April 15, 2022 GBSP 98 Cured-in-Place Pipe Liner April 15, 2022 GBSP 99 Spray-Applied Pipe Liner April 15, 2022 181 GBSP 100 Bar Splicers, Headed Reinforcement Sept 2, 2022 Oct 27, 2023 *GBSP 101 Noise Abatement Wall, Ground Wall Dec 9, 2022 Oct 17, 2025 *GBSP 102 Noise Abatement Wall, Structure Mounted Dec 9, 2022 Oct 17, 2025 GBSP 103 Noise Abatement Wall Anchor Rod Assembly Dec 9, 2022

Section 19-00631-00-BR City of Rockford

STATE OF ILLINOIS

SPECIAL PROVISIONS

The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction", adopted January 1, 2022, the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways", the “Illinois Supplement to the Manual on Uniform Traffic Control Devices”, the "Manual of Test Procedures for Materials" in effect on the date of invitation for bids, and the "Supplemental Specifications and Recurring Special Provisions" indicated on the Check Sheet included herein which apply to and govern the replacement of the 15th Avenue Bridge over the Rock River (SN 101-6069), Section: 19-00631-00-BR, within the City of Rockford, in Winnebago County, and in case of conflict with any part, or parts, of said Specifications, the said Special Provisions shall take precedence and shall govern.

GENERAL PROVISIONS

LOCATION OF PROJECT

The construction limits for the 15th Avenue Bridge Replacement are approximately from Illinois Route 2 to 390-feet west of Orange Street. Pavement marking and restriping will be completed from West Street to Illinois Route 2. Construction limits for Illinois Route 2 are from 130-feet south and 100-feet north of 15th Avenue. The project includes reconstruction of Nelson Boulevard and Blackhawk Park / Marinelli Field. Construction limits for Nelson Boulevard are 105-feet south and 125-feet north of 15th Avenue.

DESCRIPTION OF PROJECT

The work consists of the replacement of the 15th Avenue over Rock River Bridge (SN# 101-6137). Other improvements include bridge lighting, traffic signal and ADA ramp modifications, tree removal, earth excavation, topsoil excavation and placement, seeding, storm sewer and drainage structures, erosion control, pavement removal, aggregate sub-grade, hot-mix asphalt base and surface courses, driveway pavement, PCC sidewalk, combination concrete curb and gutter, pavement markings, water main replacement, and traffic signal modernization with combination mast arms, as well as all incidental and collateral work necessary to complete the project as shown on the plans and described herein.

COMPLETION DATE PLUS WORKING DAYS

The Project has a Completion Date of October 31st, 2028. A total of fifteen working days will be allotted for clean-up work, punch list items, and landscaping.

Section 19-00631-00-BR

WORKING HOURS

This project is located within the City of Rockford, IL. The Contractor shall abide by the City of Rockford Construction Noise Ordinance (Sec. 17-6) for all work with the following exception. In certain areas (some commercial and/or industrial areas), the Contractor may be required to work outside of these hours. Ownership may waive specific requirements of the City of Rockford Construction Noise Ordinance on an individual case basis.

Contractor acknowledges that alterations to the construction sequencing and schedule may be required for coordination with any third-party utilities. Contractor shall be responsible for any necessary coordination with utility companies. Any delay to the contract caused directly or indirectly by third party utilities shall not be cause for adjustment to the contract sum.

The Contractor is responsible for preparing the initial schedule in the form of an activity on arrow diagram which shall include activity description and duration, two copies shall be submitted to the Engineer at the preconstruction meeting. The construction time, as determined by the schedule shall not exceed the specified contract time. The schedule shall be updated the first of each month, when there is a delay in completion of any critical activity, or when the contract is modified causing additions, deletion or revision of activities required.

If the Contractor wishes to work outside of these hours, they must obtain written approval from the Engineer as coordinated with the City of Rockford Division of Transportation.

City of Rockford Tim Hinkens – City Engineer 425 E. State Street Rockford, IL 61104

(779) 348-7647

CONTROL OF WORK.

No work shall be done by the Contractor until a pre-construction meeting has been held and until a 48 hour notice has been provided to the City’s Project Manager.

The Contractor and/or their sub-Contractor shall contact any resident prior to a temporary loss of access to their house a minimum of 48 hours but not more than 72 hours, prior to the commencement of these activities. The morning of the work, the Contractor will again be required to notify the residents door to door. The Contractor should provide information regarding the anticipated time that full access will be restored. Coordination between activities should allow for work to be done in a timely manner to permit access to the roadway.

Article 1.4.01 – Authority of Engineer The term “Engineer” in this provision is defined in the special provision above, which means City of Rockford.

Article 1.4.02 – Cooperation with Utilities The Contractor shall notify all utility owners of the proposed construction schedule, and shall coordinate construction operations with the utility owners so that relocation of utility lines and structures may proceed in an orderly manner. Notification shall be in writing with copies transmitted to the Engineer.

SCHEDULING OF WORK.

Contractor shall abide by the City of Rockford Construction Noise Ordinance (Sec. 17-6) for all work with the following exception. In certain areas (some commercial and/or industrial areas), the Contractor may be required to work outside of these hours.

Ownership may waive specific requirements of the City of Rockford Construction Noise Ordinance on an individual case basis.

Contractor acknowledges that alterations to the construction sequencing and schedule may be required for coordination with any third-party utilities. Contractor shall be responsible for any necessary coordination with utility companies. Any delay to the contract caused directly or indirectly by third party utilities shall not be cause for adjustment to the contract sum.

The Contractor is responsible for preparing the initial schedule in the form of an activity on arrow diagram which shall include activity description and duration, two copies shall be submitted to the Engineer at the preconstruction meeting. The construction time, as determined by the schedule shall not exceed the specified contract time. The schedule shall be updated the first of each month, when there is a delay in completion of any critical activity, or when the contract is modified causing additions, deletion or revision of activities required.

PROTECTION OF PERSONS AND PROPERTY.

The Contractor shall assume and bear all risk of damage to the work, and all risk of any accident(s), from whatsoever cause arising, until the work herein provided for shall be fully completed and accepted by the City.

Any damage to property outside of what has been asked in these specifications shall be restored to its original state or as directed by the Engineer, at the Contractor’s expense.

EXAMINATION OF THE PROJECT SITE.

Bidders should carefully examine the project site(s), to eliminate misconceptions, verify dimensions, elevations, working conditions, transportation and storage facilities. Bidders should give due consideration to same in preparing their proposals as no exceptions will be considered after awarding the contract; nor will the Contractor be entitled to any extra compensation for their failure to verify conditions at the site.

CONSTRUCTION SEAMS.

All paving seams (joints) shall be raked out and rolled according to Section 406 of the Standard Specifications and as directed by the Owner. No overlapping seams will be allowed.

LANE CLOSURE DURATION – COMPLETION DATE (VIA CALENDAR DAYS)

Extended duration lane closures will be required to complete the proposed improvements on Illinois Route 2 and the Blackhawk Park entrance during construction operations. The Contractor shall expedite/increase their work schedule and supplement work forces to complete the work as described within the allotted amount of calendar days.

Northbound Illinois Route 2

As shown on the Sequence of Construction plans, during Pre-stage construction operations, NB IL Route 2 will be reduced to one through lane through the project area to facilitate the construction of the watermain connection. The Pre-stage work for Illinois Route 2 requiring a NB lane closure shall be completed within 30 concurrent calendar days, measured from the day the lane closure is implemented.

As shown on the Sequence of Construction plans, during Stage 2 construction operations, NB IL Route 2 will be reduced to one through lane through the project area to facilitate the construction of bridge approach slab. The Stage 2 work for Illinois Route 2 requiring a NB lane closure shall be completed within 253 concurrent calendar days, measured from the day the lane closure is implemented. See additional requirements related to winter shut down in the TRAFFIC CONTROL PLAN.

Blackhawk Park

As shown on the Sequence of Construction plans, during Stage 1 construction operations, the intersection of 15th Avenue and the Blackhawk Park Entrance will be closed to traffic.

To accomplish the entrance reconstruction work, the Blackhawk Park Entrance may be closed for a maximum 60 concurrent calendar days, measured from the day the lane closure is implemented.

Prosecution and Progress

Prior to implementing any lane closures, the Contractor shall submit to the Engineer a separate progress schedule exclusively for the work on Illinois Route 2 that will require an extended duration lane closure for the work described in this special provision. The schedule shall be in accordance with Article 108.02 of the Standard Specifications.

Determinations and Extension of Contract Time shall be in accordance with Article 108.08 of the Standard Specifications.

Liquidated Damages shall be in accordance with Article 108.09 of the Standard Specifications.

PERMITS AND NOTICES.

The City of Rockford will issue permits for work on City property. When applicable, the Contractor is responsible for procuring permits from the Illinois Department of Transportation when working within the State Right of Way. City of Rockford permitting fees are waived for City projects.

DEPARTMENT OF THE ARMY CORPS OF ENGINEERS PERMIT

The construction of this project shall be performed in accordance with Nationwide Permit Number 14 issued under Section 404 of the Federal Clean Water Act as administered by the U.S. Army Corps of Engineers. The Nationwide Permit Conditions and General Conditions, including Section 401 Water Quality Certification Conditions, are included herein and must be complied with by the Contractor. Should the Contractor plan to undertake construction activities, which are not covered by the N.W.P., he shall obtain the necessary permit at his expense and present it to the Engineer prior to starting the work.

The following commitments have been made concerning the construction of the project:

1. No in stream work shall be conducted from April 1st through July 31st of any given year.

a. If rock jetties or caissons are to be used for the project they must be installed outside of these dates. However, work may occur from the platforms during these dates.

b. The contractor is prohibited from the use of explosives during demolition.

2. Trees three (3) inches or greater in diameter at breast height shall not be cleared from April 1st through September 30th of any given year.

The cost of complying with the Department of the Army Corps of Engineers permit(s) will not be paid for separately but shall be considered as incidental to Cofferdam Excavation.

WORK IN RIGHT OF WAY.

All work in the public right of way shall be done in accordance with Chapter 26 of the City of Rockford Code of Ordinances. The ordinances may be found on the City of Rockford website at: https://www.rockfordil.gov/378/Ordinances

It should be noted that information regarding the general ordinances published for the City of Rockford may be viewed, saved, or printed online at the Municipal Code Corporation website, and/or by contacting the Council Clerk by email or by phone at 779-348-7391.

The online code is actually only as current as the last supplement, which may not be posted for several months. Due to recent budgetary constraints, we have been unable to maintain the latest version of the Code of Ordinances online. For up-to-the-minute information, email the Council Clerk. Copies of the City of Rockford Code of Ordinances can also be found at the Rockford Public Library and Winnebago County Law Library.

AVAILABLE REPORTS

☐ No project specific reports were prepared.

When applicable, the following checked reports and record information is available for Bidders’ reference upon request:

☒ Record structural plans

☒ State Preliminary Site Investigation (PSI) by Huff & Huff, August 25, 2025

☒ Local Preliminary Site Investigation (PSI) by V3, March 31, 2026

☒ State Preliminary Environmental Site Assessment (PESA) by IDOT, January 13, 2021

☒ Local Preliminary Environmental Site Assessment (PESA) by CMT, June 22, ☒ Soils/Geotechnical Report Structural Geotechnical Report by GSG – October 30, 2023

☒ Boring Logs

☐ Pavement Cores

☒ Location Drainage Study (LDS)

☒ Hydraulic Report

☐ Noise Analysis

☒ Other: LPC 663 Test Results/Additional Information by V3, (not received yet)

Those seeking these reports should request access via email from:

Timothy Hinkens, P.E.

City Engineer City of Rockford, Illinois Department of Public Works Office: (779) 348-7647 Cell: (815) 218-2413 E-mail: Timothy.Hinkens@rockfordil.gov

STATUS OF UTILITIES

Utility companies and/or municipal owners located within the construction limits of this project have provided the following information regarding their facilities and the proposed improvements. The tables below contain a description of specific conflicts to be resolved and/or facilities which will require some action on the part of the Department’s contractor to proceed with work. Each table entry includes an identification of the action necessary and, if applicable, the estimated duration required for the resolution.

UTILITIES TO BE ADJUSTED

Conflicts noted below have been identified by following the suggested staging plan included in the contract. The company has been notified of all conflicts and will be required to obtain the necessary permits to complete their work; in some instances, resolution will be a function of the construction staging. The responsible agency must relocate, or complete new installations as noted below; this work has been deemed necessary to be complete for the Department’s contractor to then work in the stage under which the item has been listed.

Pre-Stage

STAGE /

LOCATION

TYPE DESCRIPTION

RESPONSIBLE

AGENCY

DURATION

OF

TIME

NB IL Route 2 Water main Shut off water main to rebuild with a new connection at valve.

contractor 30 cal days

Stage 1

STAGE /

LOCATION

TYPE DESCRIPTION

RESPONSIBLE

AGENCY

DURATION OF

TIME

15th Ave Bridge

Water Main Relocate Water main.

Hanging underneath the new bridge structure contractor ~ 356 cal days

Stage 2

LOCATION

TYPE DESCRIPTION

RESPONSIBLE

AGENCY

DURATION OF

TIME

15th Ave and Nelson Blvd intersection

Water Main

Connect new water main to existing water main. Turn on water main once reconnection is complete contractor ~ 356 cal days

Pre-Stage: 30 Days Total Installation

Stage 1: 356 Days Total Installation

Stage 2: 356 Days Total Installation

The following contact information is what was used during the preparation of the plans as provided by the Agency/Company responsible for resolution of the conflict.

Agency/Company Responsible to

Resolve Conflict

Name of contact Phone E-mail address

City of Rockford Matt Baillargeon Matt.baillargeon@rockfordil.gov

UTILITIES TO BE WATCHED AND PROTECTED

The areas of concern noted below have been identified by following the staging plan included for the contract. The information provided is not a comprehensive list of all remaining utilities, but those which during coordination were identified as ones which might require the Department’s contractor to take into consideration when making the determination of the means and methods that would be required to construct the proposed improvement. In some instances, the contractor will be responsible to notify the owner in advance of the work to take place so necessary staffing on the owner’s part can be secured.

Pre-Stage

LOCATION

TYPE DESCRIPTION OWNER

South of 15th Ave and IL

Rte 2 intersection

Telecommunications

Buried line that runs across IL route 2.

Approx 94’ south of geometry intersects

AT&T

Southbound lane IL Route 2 at 15th Ave intersection

Fiber network Underground fiber optic line that run north-south along IL RTE 2. Approx 30’ west of

IL RTE 2 centerline.

Bluebird Fiber

IL Route 2 at 15th Ave intersection Sanitary Sewer

15” VCP sanitary sewer pipe running south to north parallel to the IL Rte 2

Centerline. Approx 13’ east of centerline

Four Rivers

Sanitation Authority

Nelson Blvd and 15th Ave Intersection

Sanitary Sewer

Two (2) 72” RCP sanitary sewer lines running north to south across 15th avenue.

The two lines cross 15th avenue at stations, 167+21.33 and 167+56.84 approximately.

Four Rivers

Sanitation Authority

Nelson Blvd Sanitary Sewer

8” VCP sanitary sewer line running north along Nelson Blvd parallel to the centerline. Approx. 9’ west of centerline starting at station 315+19.60

Four Rivers

Sanitation Authority

IL Route 2 Gas line 6” Plastic; HDPE gasline parallel to the centerline approx. 2’ inside the ROW line on the west side of the road

Nicor Gas

15th Avenue Gas line 4” steel gasline parallel to the centerline approx. 27’ north. Or 11’ south of the EX- ROW line

Nicor Gas

Nelson Blvd Gas line 4” Plastic; HDPE gasline parallel to the centerline approx. 23’ east.

Nicor Gas

IL Route 2 Telecommunications Underground line that runs along IL Rte 2 on the west side of the roadway.

Stratus

Networks

LOCATION

TYPE DESCRIPTION OWNER

15th Avenue Electric

Aerial power lines running along the Northside of 15th ave on the east side of the bridge starting at sta. 167+77.45, (33.6’ LT of Centerline). Wire continues moving east

ComEd

The following contact information is what was used during the preparation of the plans as provided by the owner of the facility.

Agency/Company Responsible to

Resolve Conflict

Name of contact Phone E-mail address

Stratus Networks Tony Jordan 309-253-4374 tjordan@stratusnet.com AT&T n/a n/a G11629@ATT.com

USIC / ComEd Patricia Rodriguez 630-396-8225 patriciarodriguez@usicllc.com Bluebird Fiber Brian Art 847-650-1348 brian.art@bluebirdfiber.com

Comcast Martha Gieras 224-229-5862 martha.gieras@cable.comcast.com Nicor Gas Charles Parrott 630-388-3319 x2adiste@southernco.com

Four Rivers Sanitation Matt Campbell 815-387-7684 mcampbell@fourrivers.illinois.gov

The above represents the best information available to the Department and is included for the convenience of the bidder. The days required for conflict resolution should be considered in the bid as this information has also been factored into the timeline identified for the project when setting the completion date. The applicable portions of the Standard Specifications for Road and Bridge Construction shall apply.

Estimated duration of time provided above for the first conflicts identified will begin on the date of the executed contract regardless of the status of the utility relocations. The responsible agencies will be working toward resolving subsequent conflicts in conjunction with contractor activities in the number of days noted.

The estimated relocation duration must be part of the progress schedule submitted by the contractor. A utility kickoff meeting will be scheduled between the Department, the Department’s contractor, and the utility companies when necessary.

The contractor is responsible for contacting JULIE (or DIGGER within the City of Chicago) prior to any excavation work. Please note that IDOT electrical facilities are not part of the one-call locating services, such as JULIE or DIGGER.

If the contract requires the services of an electrical contractor, it is the contractor’s responsibility, at their own expense, to locate existing IDOT and/or local agency electrical facilities before commencing work. For contracts that do not require an electrical contractor, the contractor may request one free locate of IDOT electrical facilities by contacting the Department’s Electrical Maintenance Contractor and/or the appropriate local agency electrical maintenance contractor. Additional locate requests will be at the contractor’s expense.

For work on or near IDOT ROW on contracts without an electrical contractor, the Department’s Electrical Maintenance Contractor must be notified at least 72 hours in advance of the work by calling 773-287-7600 or emailing dispatch@meade100.com to arrange for the locating of underground electrical facilities.

Please note, the marking of underground facilities does not absolve the contractor of their responsibility to repair or replace any facilities damaged during construction at their expense.

EXISTING UTILITY REMOVAL COORDINATION

Existing utilities that have been or will be out-of-service and are located under or near the existing roadway pavement may need to be removed during stage construction. A utility coordination meeting shall be held 2 weeks prior to changing MOT stages to allow time for utilities to mobilize. The Contractor shall be responsible for the pavement removal and earthwork as depicted in the contract plans. The Contractor shall closely coordinate the construction activities with the utilities and their contractors. The Contractor’s schedule shall take into account the estimated duration for removals located in the Status of Utilities special provision.

EXISTING UTILITIES AND DRAINAGE STRUCTURES LOCATIONS.

Ownership does not guarantee the completeness or accuracy of the information shown on any plans regarding gas and water mains, sewers, inlets, buffalo boxes and power lines, poles or any other existing utilities or drainage structures. The Contractor shall make their own investigation to verify or determine the existence, nature and location of all utilities on the site that may interfere with construction before commencing work. The Contractor shall report to the Owner any omissions or differences in location from that shown on any project plans. Care should be taken while working near these utilities to prevent their damage.

PROPER BACKFILLING.

All trenches shall be backfilled, from the bottom of the trench to the centerline of the pipe, with granular backfill or approved native material. The backfill material shall be deposited in the trench for its full width on each side of the pipe simultaneously, distributed evenly by hand, carefully packing the backfill material under the haunches of the pipe and compacted by tamping.

All trenches shall be backfilled, from the centerline of the pipe to a depth of one (1) foot above the top of the pipe, with granular backfill or approved native material compacted by tamping. The contractor shall use special care in placing this portion of the backfill so as to avoid injuring or moving the pipes. Ag Lime materials will not be allowed for backfill material.

When the type of backfill is not indicated in the plans, or elsewhere specified, the trench shall be backfilled, from one (1) foot above the pipe to the finished grade, with native material, or other materials approved by the Engineer, in twelve (12) inch layers compacted by tamping.

Granular backfill material is required under pavements, curbs, driveways, or sidewalks planned to be constructed within one (1) year after backfill. The area requiring such granular backfill shall be indicated in the plans. Where the excavation is made through or within two (2) feet of permanent pavements, curbs, driveways, or sidewalks, or where such structures are undercut by the excavation, or where such structures may reasonably be expected to be constructed over or within two (2) feet of the excavation within one (1) year after backfilling, the entire backfill to the subgrade of the structures shall be made with granular backfill material, as approved by the Engineer, placed in six (6) inch layers, loose measurement, and compacted to not less than ninety-five (95) percent of standard laboratory density in accordance with the requirements of ASTM Standard D-698.

CONCRETE FOUNDATIONS

All drilled foundations listed under Class SI concrete in Table 1 of Article 1020.04 shall use Drilled Shaft (DS) concrete mix in lieu of Class SI concrete meeting the requirements of Section 1020 of the Standard Specifications.

SAWCUTTING

Work shall consist of sawing existing pavements to such a depth that when the pavement is removed, a clean neat edge will result with no spalling of the remaining pavement. Saw cutting shall be performed at all locations where pavement is removed and will be replaced. This work item shall be considered incidental to construction and no further compensation will be allowed.

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES

Description. This work shall consist of the removal and disposal of regulated substances according to Section 669 of the Standard Specifications as revised below.

Contract Specific Work Areas. For stationing, the lateral distance is measured from centerline and the farthest distance is the offset distance or construction limit, whichever is less.

The following contract specific work areas shall be monitored by the Environmental Firm for soil contamination and workers protection.

PESA Site 4013-COV-2 – Vacant Land, 1900-2000 Blocks oF S. Main Street, Rockford, Winnebago County, Illinois

• Station 370+10 to Station 371+78 (CL IL-2), 0 feet to 77 feet RT. The Engineer has determined this material from 0 to 1 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling parameters include: SVOCs, Iron, Manganese, and Mercury.

PESA Site 4013-COV-4 – Commercial Building, 2019-2021 S. Main Street, Rockford, Winnebago County, Illinois

• Station 370+10 to Station 370+75 (IL 2), 0 feet to 80 feet LT. The Engineer has determined this material from 0 to 1 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling parameters include: SVOCs and Manganese.

PESA Site 4013-COV-6 – Poor Clares Corpus Christi Monastery, 2111 S. Main Street, Rockford, Winnebago County, Illinois

• Station 369+37 to Station 370+10 (IL 2), 0 feet to 62 feet LT. The Engineer has determined this material from 0 to 1 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: SVOCs and Manganese.

PESA Site 4013-COV-7 – Vacant Land, 2100-2200 Blocks of S. Main Street, Rockford, Winnebago County, Illinois

• Station 366+00 to Station 366+82 (IL 2), 0 feet to 72 feet RT. The Engineer has determined this material from 0 to 1 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(3). Contaminants of concern sampling parameters include: SVOCs.

Work Zones Three distinct OSHA HAZWOPER work zones (exclusion, decontamination, and support) shall apply to projects adjacent to or within sites with documented leaking underground storage tank (LUST) incidents, or sites under management in accordance with the requirements of the Site Remediation Program (SRP), Resource Conservation and Recovery Act (RCRA), or Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), or as deemed necessary. For this project, the work zones apply for the following ISGS PESA Sites: None

Additional information on the contract specific work areas listed above collected during the regulated substances due-diligence process is available through the District’s Environmental Studies Unit (DESU).

ROADWAY SPECIAL PROVISIONS

TRAFFIC CONTROL PLAN

Standards:

701101 701427 701601 701602 701611 701701 701801 701901

Details:

• Detour Plans

• Staging Plans

• District Standard WORK ZONE SIGN DETAILS (DIST STD. 34.1)

• District Standard TRAFFIC CONTROL TYPICAL WEAVE (DIST STD 39.1)

• District Standard TRAFFIC CONTROL FOR ROAD CLOSURE (DIST STD 40.1)

• District Standard TRAFFIC CONTROL AND PROTECTION AT TURN BAYS (TO

REMAIN OPEN TO TRAFFIC) (DIST STD 94.2)

General:

Where construction activities involve sidewalks on both sides of the street, the work shall be staged so that both sidewalks are not out of service at the same time.

Signs:

“BUMP” (W8-1(O)48) signs shall be installed as directed by the Engineer.

“UNEVEN LANES” W8-11(O)48 signs shall be installed at 1 mile intervals or as directed by the Engineer.

“LOW SHOULDER” W8-9(O)48 signs shall be installed at 1 mile intervals or as directed by the Engineer.

“NO PASSING ZONES NOT STRIPED NEXT ___ MILES” (G20-I 100(O)) signs shall be 60” x 36”.

When covering existing Department signs, no tape shall be used on the reflective portion of the sign. Contact the District sign shop for covering techniques.

Install a "TO ACTIVATE SIGNAL" sign below the “STOP HERE ON RED” sign. The detail of this sign is included in the plans.

The “ROAD CLOSED” sign on the Type III barricades shall be unobstructed and visible to traffic at all times. No equipment, debris, or other materials shall be stored within 20 feet of the first set of Type III barricades, unless approved by the Engineer.

Any plates or direct applied sheeting used to alter signs shall have the same sheeting as the base sign.

No more than one kind of alteration shall be used to alter a sign.

Any post stubs without a sign in place and visible shall have a reflector placed on each post.

Flaggers:

Flaggers shall comply with all requirements and signaling methods contained in the Department’s “Traffic Control Field Manual” current at the time of letting. The flagger equipment listed for flaggers employed by the Illinois Department of Transportation shall apply to all flaggers

When the mainline flagger is within 200 feet of an intersection, the sideroad flagger shall be required.

When the road is closed to through traffic and it is necessary to provide access for local traffic, all flaggers as shown on the applicable standards will be required. No reduction in the number of flaggers shall be allowed.

Pavement Marking:

All temporary pavement markings that will be operational during the winter months (December through March) shall be paint.

Short term pavement markings on a milled surface shall be paint.

District Standards Application:

Traffic Control for Road Closure: This work shall be done according to the Road Closure Standard and Section 701 of the Standard Specifications.

“ROAD CLOSED AHEAD” (W20-3(O)-48) with flasher and the appropriate arrow plate (W1-6(O)-36x18 or W1-7(O)-36x18) shall be required on all side roads within the limits of the mainline “ROAD CLOSED AHEAD” signs as shown in the plans.

15th Avenue shall be considered Condition I Major sideroad closures for signing as shown on the District Standard Traffic Control for Road Closure Detail.

The Contractor shall notify the Department via email at DOT.D2.TrafficNotice@illinois.gov. This request shall be submitted a minimum of three weeks (21 days) and no earlier than four weeks (28 days) prior to the anticipated closure date to allow the State adequate time to re-route oversized loads.

Signing and devices required to close the road, according to the Traffic Control for Road Closure detail and contained herein, shall be the responsibility of the Contractor. Detour signing required to detour traffic to alternate routes shall be the responsibility of the Contractor. The day the detour signing begins, the detour will be in effect when the Contractor has notified the Resident Engineer or personnel on the project. No detour shall be erected on Friday, Saturday or Sunday. The road shall not be closed until the detour signing is completely installed, verified, and ready to accept traffic.

The “ROAD CLOSED” sign on the Type III barricades shall be unobstructed and visible to traffic at all times. No equipment, debris, or other materials shall be stored within 20 feet of the first set of Type III barricades, unless approved by the Engineer.

The Contractor shall not drive around the outside of the Type III barricades, but shall relocate the barricades temporarily for access. When it is necessary for the barricades to be moved for access, the Contractor shall move the devices into the left lane and/or left shoulder area behind barricades that are to remain in place. At no time shall the barricades be turned parallel to traffic flow for access purposes.

If a path becomes evident around the outside of the barricades, the Contractor shall be required to place additional Type III barricades to prevent driving around the existing barricades. Additional barricades shall be included in the cost of applicable Traffic Control Standards

This work shall be paid for at the contract lump sum price for TRAFFIC CONTROL AND

PROTECTION, (SPECIAL).

Road Closure – Closures within Closures: The road closure shall be completed using Type III barricades in compliance with Standards 701901, and signing according to Traffic Control for Road Closure detail. Two flashers shall be installed above each Type III barricade. The "ROAD CLOSED" (R11-2) or “ROAD CLOSED TO THRU TRAFFIC” (R11-4) signs shall be placed as shown in Standard 701901.