About this file

This is a Notice to Bidders and contract specification document issued by the Illinois Department of Transportation (IDOT) for the reconstruction of the I-57 and IL 16 interchange east of Mattoon in Coles County under Contract No. 74435, Project NHPP-BR-CFS0(030). The project involves converting the existing cloverleaf interchange to a raindrop diamond configuration, including removal and replacement of I-57 structures over IL 16, removal of I-57 structures over the Lincoln Prairie Grass Trail with replacement by cast-in-place box culvert, and comprehensive ancillary work encompassing pavement patching, milling, HMA resurfacing, full-depth HMA and PCC pavement, shoulders, curb and gutter, PCC sidewalk, medians, storm sewer systems, pipe and precast box culverts, guardrails, pavement markings, sign installation, fiber optic cable systems, CCTV dome cameras, communications vaults, and ADA-compliant pedestrian facilities. The project geographic limits span I-57 from 0.5 miles south to 1 mile north of IL 16, and IL 16 from just east of Swords Drive to just west of Lerna Road. Electronic bids must be submitted to the iCX-Integrated Contractors Exchange system by 12:00 p.m. on September 18, 2026, with the contract award proceeding to the lowest responsive and responsible bidder. The project is staged with intermediate completion dates of November 15, 2027 (Pre-Stage), November 15, 2028 (Stage 1), and November 15, 2029 (Stage 2), with overall project completion by November 15, 2030, followed by 15 guaranteed working days for cleanup and punch list items.

This is a Federal-aid NHPP construction contract subject to prevailing wage standards, EEO compliance requirements, and a Project Labor Agreement. Specific ramp and roadway closures are restricted to defined calendar day limits, with liquidated damages assessed under Article 108.09 of the Standard Specifications for each additional day roadways remain closed beyond specified reopening dates. No lane closures utilizing traffic control will be permitted between November 15 and March 1 of any year. The contractor must coordinate with concurrent Contract 74650 for bridge superstructure work within overlapping project limits and cooperate with the City of Mattoon's proposed solar-powered lighting system conversion for the Lincoln Prairie Grass Trail structure. The contract includes comprehensive special provisions addressing traffic control staging, ADA curb ramps and pedestrian facilities compliant with PROWAG guidelines, fiber optic cable installation with specific testing and splicing requirements, CCTV dome camera systems with detailed specifications, communications vault installation, and various removal and construction items. IDOT reserves the right to reject any or all proposals and determine responsibility at the time of award.

View the file

Other files

File Type Posted
Reconstructing the I-57 and IL 16 Interchange.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting September 18, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 74435 COLES County Section (15-22HB-4)BR(15-22)R Route FAI 57 Project NHPP-BR-CFS0(030) District 7 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

September 18, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 74435 COLES County Section (15-22HB-4)BR(15-22)R Project NHPP-BR-CFS0(030) Route FAI 57 District 7 Construction Funds

Reconstructing the I-57 and IL 16 interchange located east of Mattoon from a cloverleaf to a raindrop diamond configuration.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

FAI ROUTE 57 (I-57)

PROJECT NHPP-0CFS0(30)

SECTION (15-22HB-4)BR (15-22)R

COLES COUNTY

CONTRACT NO. 74435

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

SECTION (15-22HB-4)BR (15-22)R

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 X Additional State Requirements for Federal-Aid Construction Contracts 2 X Subletting of Contracts (Federal-Aid Contracts)

3 X EEO

4 Specific EEO Responsibilities Nonfederal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos Hot-Mix Asphalt Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 X Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 X Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays

SECTION (15-22HB-4)BR (15-22)R

i

TABLE OF CONTENTS

LOCATION OF PROJECT

DESCRIPTION OF PROJECT

COMPLETION DATE PLUS GUARANTEED WORKING DAYS

INTERIM COMPLETION DATES

TRAFFIC CONTROL PLAN

TRAFFIC CONTROL AND PROTECTION, STANDARD 701423 (SPECIAL)

NOTIFICATION OF ROAD CLOSURE

ROAD CLOSURES

ADA CURB RAMPS

AGGREGATE SHOULDERS

APPROACH SLAB REMOVAL

BORROW AREAS, USE AREAS, AND/OR WASTE AREAS

CAT 5 ETHERNET CABLE

CHANGEABLE MESSAGE SIGNS

COMBINATION CONCRETE CURB AND GUTTER, TYPE M (SPECIAL)

COMMUNICATIONS VAULT

CLASS BS AGGREGATE OPTIMIZATION

CLASS SI CONCRETE (OUTLET), SPECIAL

CLOSED CIRCUIT TELEVISION CABINET

CLOSED-CIRCUIT TELEVISION DOME CAMERA, IP BASED

CONCRETE ANCHORS

CONCRETE HEADWALL REMOVAL (SPECIAL)

CONCRETE MEDIAN, TYPE SM (DOWELLED)

COOPERATION BETWEEN CONTRACTORS

DETOUR SIGNING

EMBANKMENT

FIBER OPTIC CABLE 24 FIBERS, SINGLE MODE

FIBER OPTIC UTILITY MARKERS

FUSION SPLICING OF FIBER OPTIC CABLES

GUARD POSTS

GUARD POST REMOVAL

HMA SURFACE REMOVAL

HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH

INCIDENTAL HOT-MIX ASPHALT SURFACING

SECTION (15-22HB-4)BR (15-22)R

ii

LIGHT POLE, GALVANIZED STEEL, 50 FT. M.H., TENON MOUNT

LINEAR DELINEATION PANELS

MEDIAN INLET BOX REMOVAL

OUTLET PROTECTOR

PAVEMENT PATCHING STANDARD 442201

PEDESTRIAN PUSH-BUTTON POST

PIPE DRAIN REMOVAL

PIPE UNDERDRAINS 6” (MODIFIED)

PIPE UNDERDRAIN OUTLET EXTENSION FOR 6” PIPE

PIPE UNDERDRAIN REMOVAL (SPECIAL)

PRECAST CONCRETE BOX CULVERTS 8’ X 4’ SP

PREFORMED THERMOPLASTIC PAVEMENT MARKING SHIELD

PROTECTING OR RESETTING SURVEY MARKERS

REAL-TIME TRAFFIC CONTROL SYSTEM

RECOVERABLE DELINEATORS

RECTANGULAR RAPID FLASHING BEACON ASSEMBLY (COMPLETE)

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES

REMOVAL OF EXISTING SIGN LIGHTING UNIT WITH NO SALVAGE

REMOVAL OF EXISTING STRUCTURE (SPECIAL)

REMOVAL OF TOWER FOUNDATION

REMOVE EXISTING WEATHER STATION

REMOVE INLET BOX

ROCKFILL – REPLACEMENT

SLOTTED DRAIN 12” WITH 6” SLOT

STAMPED COLORED PORTLAND CEMENT CONCRETE MEDIAN SURFACE

STAMPED COLORED PORTLAND CEMENT CONCRETE PAVEMENT 9” (JOINTED)

STATUS OF UTILITIES TO BE ADJUSTED

SURFACE REMOVAL, VARIABLE DEPTH (SPECIAL)

SYSTEM IMPLEMENTATION, EQUIPMENT INTEGRATION AND SUPPORT

TERMINATION OF FIBER OPTIC CABLES WITH FUSION SPLICED ST CONNECTORS

TEMPORARY RAISED PAVEMENT MARKER

TEMPORARY RUMBLE STRIPS (SPECIAL)

TEMPORARY TRAFFIC SIGNAL INSTALLATION

TRAFFIC BARRIER TERMINALS

WOVEN WIRE FENCE REMOVAL

DIAMOND GRINDING AND SURFACE TESTING BRIDGE SECTIONS

SLIPFORM PARAPET

SECTION (15-22HB-4)BR (15-22)R

iii

BRIDGE DECK CONSTRUCTION

BRIDGE DECK GROOVING (LONGITUDINAL)

MEMBRANE WATERPROOFING SYSTEM FOR BURIED STRUCTURES

METALLIZING OF STRUCTURAL STEEL

DRILLED SHAFTS

PREFORMED PAVEMENT JOINT SEAL

BITUMINOUS MATERIALS COST ADJUSTMENTS (BDE)

CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)

COMPENSABLE DELAY COSTS (BDE)

CONCRETE BARRIER (BDE)

CONCRETE SEALER (BDE)

DECK SLAB REPAIR

EROSION CONTROL BLANKET (BDE)

DISADVANTAGED BUSINESS ENTERPRISE PARTICIPATION (BDE)

FUEL COST ADJUSTMENT (BDE)

GUARDRAIL (BDE)

HOT-MIX ASPHALT (BDE)

HOT-MIX ASPHALT – LONGITUDINAL JOINT SEALANT (BDE)

LONGITUDINAL TINING (BDE)

PAVEMENT MARKING (BDE)

PAVEMENT PATCHING (BDE)

PERFORMANCE GRADED ASPHALT BINDER (BDE)

PREFORMED PLASTIC PAVEMENT MARKING (BDE)

RAISED REFLECTIVE PAVEMENT MARKERS (BDE)

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)

SEEDING (BDE)

SHORT TERM AND TEMPORARY PAVEMENT MARKINGS (BDE)

SIGN PANELS AND APPURTENANCES (BDE)

SLOPE WALL (BDE)

SOURCE OF SUPPLY AND QUALITY REQUIREMENTS (BDE)

SPEED DISPLAY TRAILER (BDE)

STEEL COST ADJUSTMENT (BDE)

SUBCONTRACTOR AND DBE PAYMENT REPORTING (BDE)

SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)

SUBMISSION OF BIDDERS LIST INFORMATION (BDE)

SUBMISSION OF PAYROLL RECORDS – FEDERAL AID CONTRACT (BDE)

SURFACE TESTING OF PAVEMENTS – IRI (BDE)

SECTION (15-22HB-4)BR (15-22)R

iv

SURVEYING SERVICES (BDE)

TEMPORARY CONCRETE BARRIER (BDE)

TRAINING SPECIAL PROVISIONS (BDE)

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING SPECIAL PROVISION

VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)

WOOD SIGN SUPPORT (BDE)

WEEKLY DBE TRUCKING REPORTS (BDE)

WORK ZONE TRAFFIC CONTROL DEVICES (BDE)

WORK ZONE WIDTH RESTRICTION (BDE)

PROJECT LABOR AGREEMENT

STORM WATER POLLUTION PREVENTION PLAN

SECTION (15-22HB-4)BR (15-22)R

STATE OF ILLINOIS

SPECIAL PROVISIONS

The following Special Provisions supplement the “Standard Specifications for Road and Bridge Construction, Adopted January 1, 2022”, the latest edition of the “Manual on Uniform Traffic Control Devices for Streets and Highways”, and the “Manual of Test Procedures for Materials” in effect on the date of invitation for bids, and the “Supplemental Specifications and Recurring Special Provisions” indicated on the Check Sheet included herein, which apply to and govern the construction of FAI Route 57 (I-57), Project NHPP-0CFS0(30), Section (15-22HB-4)BR (15-22)R, Coles County, Contract No. 74435, and in case of conflict with any part, or parts, of said Specifications, the said Special Provisions shall take precedence and shall govern.

FAI Route 57 (I-57) Project NHPP-0CFS0(30)

Section (15-22HB-4)BR (15-22)R Coles County

Contract No. 74435

LOCATION OF PROJECT

This project is located on I-57 at the I-57 interchange with IL 16, east of Mattoon in Coles County.

Work on I-57 begins 0.5 miles south of IL 16 and continues to 1 mile north of IL 16. Work on IL 16 begins just east of Swords Dr. and ends just west of Lerna Road.

DESCRIPTION OF PROJECT

This project consists of reconstructing the interchange configuration from a cloverleaf to a raindrop diamond. The reconstruction includes the removal and replacement of the I-57 structures over IL 16, removal of the I-57 structures over the Lincoln Prairie Grass Trail, and replacement of those structures with a cast-in-place box culvert. Additional work includes pavement patching, milling, HMA resurfacing, HMA pavement (full-depth), PCC pavement, shoulders, curb and gutter, PCC sidewalk, medians, storm sewer, pipe culverts, precast box culverts, guardrail, guardrail shoulder stabilization, pavement marking, signs, pavement removal, paved shoulder removal, drainage structure removals, earth excavation, seeding, and any other work necessary to complete this section.

SECTION (15-22HB-4)BR (15-22)R

COMPLETION DATE PLUS GUARANTEED WORKING DAYS

The Contractor shall complete all contract items and safely open all roadways to traffic by November 15, 2030, except as specified herein. The Contractor will be allowed to complete all clean-up work and punch list items within 15 guaranteed working days after the completion date for opening the roadway to traffic.

Under extenuating circumstances, the Engineer may direct that certain items of work, not affecting the safe opening of the roadway to traffic, may be completed within the guaranteed working days allowed for clean-up work and punch list items. Temporary lane closures for this work may be allowed at the discretion of the Engineer.

Article 108.09 of the Standard Specifications or the Failure to Complete the Work on Time special provision, if included in this contract, shall apply to both the completion date and the number of working days.

INTERIM COMPLETION DATES

The Contractor shall complete all contract items for pre-stage construction and safely open all roadways to traffic by November 15, 2027. The Contractor will be allowed to complete all clean-up work and punch list items within ten guaranteed working days after the completion date for opening the roadway to traffic.

The Contractor shall complete all contract items for stage 1 construction and safely open all roadways to traffic by November 15, 2028. The Contractor will be allowed to complete all clean-up work and punch list items within ten guaranteed working days after the completion date for opening the roadway to traffic.

The Contractor shall complete all contract items for stage 2 construction and safely open all roadways to traffic by November 15, 2029. The Contractor will be allowed to complete all clean-up work and punch list items within ten guaranteed working days after the completion date for opening the roadway to traffic.

Under extenuating circumstances, the Engineer may direct that certain items of work, not affecting the safe opening of the roadway to traffic, may be completed within the guaranteed working days allowed for clean-up work and punch list items. Temporary lane closures for this work may be allowed at the discretion of the Engineer.

Article 108.09 of the Standard Specifications, or the Failure to Complete the Work on Time special provision, if included in this contract, shall apply to both the interim completion date and the number of working days.

SECTION (15-22HB-4)BR (15-22)R

TRAFFIC CONTROL PLAN

Traffic control shall be in accordance with the applicable sections of the Standard Specifications for Road and Bridge Construction, the applicable guidelines contained in the Illinois Manual on Uniform Traffic Control Devices for Streets and Highways, these special provisions, and any other special details and highway standards contained herein and in the plans.

Special attention is called to Articles 107.09, 107.14, and 107.15 of the Standard Specifications for Road and Bridge Construction, the following highway standards and special details relating to traffic control, and these special provisions.

Highway Standards:

701101 701106 701400 701401 701402 701406 701411 701421 701422 701423 701426 701428 701451 701456 701801 701901

Traffic control standards shall be applied as directed by the Engineer and the following suggested applications:

Standard 701401: This standard is applicable for installing temporary concrete barrier on I-57 and completing proposed interstate ramp pavements during stage 3 when crossovers are no longer in use.

Standard 701402: This standard is applicable for interstate bridge repairs.

Standard 701406: This standard is applicable for HMA shoulder removal and replacement along I-57.

Standard 701411: This standard is applicable for HMA shoulder removal and replacement along I-57 at the ramp terminals.

Standard 701421: This standard is applicable for HMA shoulder removal and replacement and earthwork adjacent to IL 16.

Standard 701422: This standard is applicable for temporary ramp construction, raindrop construction, PCC median construction, HMA surface removal, paving operations, removal of the crossovers and pavement removal on IL 16.

Standard 701423: This standard is applicable for stage construction of precast box culverts underneath IL 16.

Standard 701426: This standard is applicable for the application of pavement markings.

Standard 701451: This standard is applicable for ramp closures during I-57 bridge repairs and ramp closures during removal and replacement of the I-57 structures over the Lincoln Prairie Grass Trail. This standard shall be utilized with marked route detours.

SECTION (15-22HB-4)BR (15-22)R

Standard 701456: This standard is applicable for HMA shoulder removal and replacement on the existing ramps and for lane closures on the proposed ramps during stage construction of the raindrop.

Standard 701801: This standard is applicable for the Lincoln Prairie Grass Trail during removal and replacement of the trail pavement and the construction of the proposed cast-in-place box culvert for the trail. This standard is also applicable to the proposed shared-use path during the path’s construction and the construction of the raindrop and proposed ramps.

Bridge Width Restriction Signs: The Contractor shall furnish and install the following signs to advise motorists of the width restriction created by the stage construction bridge work. The W12- I103 signs shall be installed on posts or skids, unless otherwise specified, at the locations listed below:

• Two each, along SB I-57, just north of Exit 192, with 1 Mile

• One each, along SB Exit 192 on-ramp, with 1 Mile

• Two each along SB I-57, just north of Exit 203, with 12 Miles

• One each, along SB Exit 203 on-ramp, with 12 Miles

• Two each along NB I-57, just south of Exit 190, with ½ Mile

• One each, along both NB Exit 190 on-ramps, with ½ Mile

• Two each along NB I-57, just south of Exit 184, with 6 Miles

• One each, along NB Exit 184 on-ramp, with 6 Miles

• One each, along EB IL 16, just east of the US 45 (Lake Land Blvd.) intersection, with 2

Miles

• One each, along EB IL 16, just east of Logan St. intersection, with 1 Mile

• One each, along WB IL 16, just west of IL 130 intersection, with 8 Miles

• Two each, along WB IL 16, just west of Douglas St. intersection, with 6 Miles

• Two each, along WB IL 16, just west of Lerna Road intersection, with 500 FT

• Pre-Stage C Bridge Width Restriction Sign: 12’-6” (NB I-57)

• Stage 1 Bridge Width Restriction Sign: 16’-6” (NB I-57) and 17’-0” (SB I-57)

• Stage 2 Bridge Width Restriction Sign: 17’-0” (NB I-57) and 16’-6” (SB I-57)

• Pre-Stage 3B Bridge Width Restriction Sign: 12’-6” (WB IL 16)

• Pre-Stage 3C Bridge Width Restriction Sign: 14’-6” (WB IL 16)

• Pre-Stage 3D Bridge Width Restriction Sign: 13’-6” (EB IL 16)

• Pre-Stage 3E Bridge Width Restriction Sign: 12’-6” (EB IL 16)

• Stage 3A Bridge Width Restriction Sign: 15’-6” (WB IL 16) and 15’-10” (EB IL 16)

• Stage 3B Bridge Width Restriction Sign: 14’-6” (WB IL 16) and 14’-6” (EB IL 16)

The Engineer shall approve the exact locations of all proposed signs and barricades prior to installation. Installation shall be in accordance with Standard 701901.

The signs shall be furnished by the Contractor and shall conform to the dimensions and text as shown on the drawing included herein. When the width displayed on the signs must be changed as determined by the Engineer for the second stage of construction, materials to modify the signs shall be furnished and installed by the Contractor. The Contractor shall be responsible for the

SECTION (15-22HB-4)BR (15-22)R

maintenance of the barricades and signs during the life of the project. The Contractor shall ensure the continual visibility of these signs is maintained and not obstructed by vegetation or other obstacles.

The signs shall be promptly removed when the restriction is no longer in effect.

The cost of furnishing, installing, maintaining and removing width restriction signs and wing barricades will be included in the cost for Traffic Control and Protection (Special).

SECTION (15-22HB-4)BR (15-22)R

TRAFFIC CONTROL AND PROTECTION, STANDARD 701423 (SPECIAL)

This work shall conform to Section 701 of the Standard Specifications, Standard 701423, and as modified herein. The type II barricades, drums, or vertical barricades with steady burn mono-directional lighting shall be extended beyond the end of the temporary concrete barrier as shown on the pre-stage 3C work area and traffic control staging plan. The temporary pavement marking tape for the left and right edge lines shall be extended to the end of the traffic control devices.

This work will be paid for at the contract unit price per EACH for TRAFFIC CONTROL AND

PROTECTION, STANDARD 701423 (SPECIAL).

TRAFFIC CONTROL AND PROTECTION, (SPECIAL)

This work shall consist of furnishing, installation, maintenance, and removal of work zone traffic control and protection. This work shall conform to Section 701 of the Standard Specifications and as specified herein.

Stages 1 & 2: For these stages the traffic control and protection (special) shall apply to interstate route I-57. Standards 701400 and 701416 shall be followed except as modified on the Traffic Control and Protection (Special) Stages 1 & 2 (I-57) detail shown in the plans. This detail shows how to incorporate Standards 701411 into 701416. The temporary pavement markings shown on the highway standards and plan details shall be included in the cost of the traffic control and protection, (special). No lane closures utilizing traffic control and protection, (special) shall be allowed between November 15 and March 1 of any year.

Stages 3A & 3B: For these stages the traffic control and protection (special) shall apply to state route IL 16. Standards 701400 and 701416 shall be followed except as modified on the Traffic Control and Protection (Special) Stage 3A (IL 16), the Staging Plans Stage 3A Traffic Control, the Traffic Control and Protection (Special) Stage 3B (IL 16) and the Staging Plans Stage 3B details shown in the plans. These details show how to incorporate Standards 701411 into 701416 and how to modify the taper and tangent lengths for the lower speeds on IL 16. The temporary pavement markings shown on the highway standards and plan details shall be included in the cost of the traffic control and protection, (special). No lane closures utilizing traffic control and protection, (special) shall be allowed between November 15 and March 1 of any year.

The temporary yield sign shown on the Staging Plans Stage 3B sheets will be paid for separately as Sign Panel – Type 1 and Wood Sign Support.

Stage 3D: For this stage the traffic control and protection (special) shall apply to the raindrop section of state route IL 16. The left turn lanes at the ends of the raindrop shall be closed using drums with steady burn monodirectional lights as shown on the Staging Plans Stage 3D Traffic Control details.

This work will be paid for at the contract unit price per each for TRAFFIC CONTROL AND

PROTECTION (SPECIAL).

SECTION (15-22HB-4)BR (15-22)R

NOTIFICATION OF ROAD CLOSURE

The Contractor shall notify the Engineer a minimum of 21 days prior to a road closure. The Engineer will in turn notify the District Bureau of Operations – Traffic Unit of the impending closure.

This will allow time for the Engineer to contact emergency services (police, fire, ambulance, etc.).

The Contractor will not be allowed to close the road without the 21 day notice, and failure to provide proper notice will delay the road closure. Delays caused by failure to provide the required notice shall not be considered justification for a change in the completion date.

ROAD CLOSURES

Pre-Stage: The Lincoln Prairie Grass Trail shall be closed during construction of SN 015-2026.

The closure of the trail shall not exceed 75 calendar days. Two changeable message signs, one at each approach of the trail, shall be in place seven calendar days prior to the closure of the trail to inform the public of the impending closure. The message to be displayed will be determined by the Engineer.

Stage 1: Existing Ramp F (SB I-57 exit ramp) along with the NW temporary ramp and existing Ramp D (SB I-57 entrance ramp) along with the SW temporary ramp shall be closed during the removal of existing SN 015-0051, the replacement of the structure with embankment and new HMA pavement, and the construction of the proposed ramp A and D terminals adjacent to I-57.

The closure of these ramps shall not exceed 60 calendar days.

Stage 2: Existing Ramp B (NB I-57 exit ramp) along with the SE temporary ramp and existing Ramp H (NB I-57 entrance ramp) along with the NE temporary ramp shall be closed during the removal of existing SN 015-0052, the replacement of the structure with embankment and new HMA pavement, and the construction of the proposed ramp B and C terminals adjacent to I-57.

The closure of these ramps shall not exceed 60 calendar days.

Stage 3A: Existing Ramp H (NB I-57 entrance ramp) shall be closed during the removal of an existing pipe culvert beneath the pavement, construction of temporary storm sewer beneath the pavement, and class D pavement patching. The ramp closure shall not exceed three calendar days.

Stage 3B: Existing Ramp B (NB I-57 exit ramp) and D (SB I-57 entrance ramp) shall be permanently closed in this stage to complete the proposed Ramp C and D pavements. The number of days from the closure of the existing ramps to the opening of the proposed ramps shall not exceed 45 calendar days.

Stage 3E: Existing Ramp F (SB I-57 exit ramp) shall be permanently closed in this stage to complete the proposed Ramp A pavement. The number of days from the closure of the existing ramps to the opening of the proposed ramps shall not exceed 45 calendar days.

Stage 3F: Existing Ramp H (NB I-57 entrance ramp) shall be permanently closed in this stage to complete the proposed Ramp B pavement. The number of days from the closure of the existing ramps to the opening of the proposed ramps shall not exceed 45 calendar days.

SECTION (15-22HB-4)BR (15-22)R

Failure to safely open the above roadways on or before the specified calendar days will result in the Contractor paying liquidated damages for each additional calendar day the roadway remains closed. The liquidated damages will be assessed per Article 108.09 of the Standard Specifications.

ADA CURB RAMPS

This work shall consist of constructing a PCC sidewalk in accordance with Section 424 and Section 606 of the Standard Specifications except as described herein. All pedestrian facilities and shared use paths on this project must be constructed according to Public Rights-of-Way Accessibility Guidelines (PROWAG). The appropriate pedestrian ramp details for each quadrant are included in the plans. The Engineer may provide additional details to those provided in the plans that meet the PROWAG guidelines as the need arises and field conditions dictate.

Pedestrian facilities must be constructed to meet the following criteria:

Pedestrian Access Routes (PAR) must be constructed to meet the following:

• 5 feet typical width (4 feet minimum)

• A maximum cross slope of 2.0%. (1.5% preferred)

• Vertical discontinuities must be less than 0.25 inches.

• Must provide positive drainage to prevent ponding and maintain existing drainage flow patterns unless indicated otherwise in the plans.

• All grade breaks shall be constructed perpendicular to the path of travel.

Landings are part of the PAR and must be constructed to meet the following:

• 5 feet by 5 feet typical (4 feet by 4 feet minimum)

• Maximum slope of 2.0% in all directions. (1.5% preferred)

• Required at all locations where the PAR changes directions.

• Must be connected to the PAR

To ensure that the pedestrian facilities are constructed in compliance with PROWAG, the Contractor shall follow the construction sequence at each quadrant:

(1) The Contractor shall use the appropriate ramp details in the plans to determine if the removal limits for the sidewalk and curb and gutter are adequate.

(2) The Contractor shall verify the proposed curb flow lines will provide positive drainage as well as maintain existing drainage patterns including existing gutter flows. The curb and gutter shall be constructed as detailed in the plans with a defined flow line and no vertical discontinuities in the PAR.

(3) All landings/turning spaces shall be formed and placed separately in an independent concrete pour prior to placement of curb ramps and sidewalk. All necessary subgrade preparation for the entire quadrant shall be done before the landings/turning spaces are constructed. Tie bars will be required as shown in the plan detail. The tie bars will not be paid for separately.

(4) After the landings have been constructed, the Contractor will be allowed to form and pour the remaining curb ramps/sidewalks.

SECTION (15-22HB-4)BR (15-22)R

(5) If at any time the Contractor determines that the requirements of PROWAG cannot be met, the Contractor shall meet with the Engineer to determine the best solution. Once the Engineer and the Contractor reach agreement on how to proceed, the Contractor may proceed with the curb ramp/sidewalk pour.

The Contractor may confer with the Engineer for guidance in laying out the proposed work, but it will be the Contractor's responsibility to ensure the proposed work meets all the requirements of this special provision. This layout includes, but is not limited to, placement of grade breaks, curb transitions, gutter flow lines, truncated dome placement, crosswalk marking placement, flares, landing limits, and ramp limits. Any inspection or checking of the Contractor’s layout and the acceptance of any part of it shall not relieve the Contractor of their responsibility to secure proper dimensions, grades, and elevations. It is important that the Contractor layout this work properly to achieve the construction of a compliant pedestrian facility.

Sidewalk joints shall be placed according to Section 424.06 of the Standard Specifications. A sidewalk joint will be required at all grade breaks within the PAR. The top grade break of walkable flares shall require a visual joint to indicate a change in grade. The Contractor shall have the option of providing saw cuts to construct all sidewalk and gutter joints within the PAR.

If the Contractor constructs any pedestrian or shared-use trail facilities that are not per plan, do not meet PROWAG, or do not follow the agreed upon resolution between the Engineer and the Contractor; the Contractor will be responsible for correcting the deficient facilities with no compensation paid for the corrective work.

Tie bars are required for the landings as shown on the plan detail. They shall be #4 bars 30” in length.

This work will not be paid for separately but shall be considered included in the cost for Portland Cement Concrete Sidewalk, of the thickness specified and for Combination Concrete Curb and Gutter, of the type specified.

AGGREGATE SHOULDERS

Aggregate shoulder shall be constructed according to Section 481 of the Standard Specifications and as revised herein.

481.02 Materials. Revise to read:

Item Article/Section

(a) Coarse Aggregate 1004.04

(b) RAP Material (Note 1) 1031

Revise the first paragraph of 1004.04 (a) to read:

The coarse aggregate shall be crushed stone or crushed concrete.

Revise Note 1 to read:

SECTION (15-22HB-4)BR (15-22)R

Note 1. Reclaimed asphalt pavement (RAP) may be used as aggregate wedge shoulders Type B if a safety shoulder is present. The use of RAP will be excluded within city limits.

APPROACH SLAB REMOVAL

Description. This work shall consist of the complete removal of the existing approach slab as shown in the plans. All pavement and appurtenances within the limits of the approach slab shall be removed. This includes, but not limited to, PCC pavement, HMA overlays, reinforcement, curbs, inlets, stabilized subbase, approach footing (sleeper slab), connector pavement, and expansion joint material adjacent to the approach slab. Approach slab removal shall be performed in accordance with Section 440 and Article 442.05(a) of the Standard Specifications.

Method of Measurement. Approach slab removal will be measured for payment in place, and the area computed in square yards.

Basis of Payment. This work will be paid for at the contract unit price per SQUARE YARD for

APPROACH SLAB REMOVAL.

BORROW AREAS, USE AREAS, AND/OR WASTE AREAS

Effective: November, 2009 Revised: April 3, 2018

In addition to the provisions contained in Article 107.22 of the Standard Specifications, the Contractor shall submit all required documents to the District electronically. All photos shall be in color.

CAT 5 ETHERNET CABLE

This work shall be in accordance with Sections 873, 1076, and 1088 of the Standard Specifications, except as modified herein. This work shall consist of furnishing and installing an outdoor rated CAT 5E cable in conduits, handholes, and poles.

The cable shall be rated for outdoor use and conform to the following specifications:

• Outdoor CMX rated jacket (climate/oil resistant jacket)

• UV resistant outer jacket material (PVC-UV, UV stabilized)

• Outer jacket ripcord

• Designed for outdoor above- ground or conduit duct applications

• Cat 5E rated to 350MHz (great for 10/100 or even 1000mbps gigabit Ethernet)

• Meets TIA/EIA 568b.2 standard

• Shielded twist pair

• 4 pairs, 8 conductors

• 24AWG, solid core copper

• UL 444 ANSI TIA/EIA-568.2 ISO/IEC 11801

• RoHS compliant

SECTION (15-22HB-4)BR (15-22)R

• Shielded

Basis of Payment: This work will be paid for at the contract unit price per FOOT for CAT 5

ETHERNET CABLE.

CHANGEABLE MESSAGE SIGNS

This work shall be completed in accordance with Section 701 of the Standard Specifications, the Supplemental Specifications, and the following additional requirements. The changeable message signs to be installed under this item are to be used as advanced notification of the impending work, advanced notification of the closure of the Lincoln Prairie Grass Trail, and for providing additional messages to the traveling public during road closures. The Engineer will determine the messages to be displayed.

Four changeable message signs shall be required for the advanced notification of impending work of this project, one for each approach to the project on I-57 and on IL 16. The Engineer will determine the exact locations of the changeable message signs.

The changeable message signs for advanced notification of this project shall be in place a minimum of 14 days directly prior to the commencement of work that requires a lane closure. The Contractor will not be permitted to have any lane closures without the 14 day notice using the changeable message signs, unless approved by the Engineer. Delays caused by failure to provide the required notice shall not be considered justification for a change in the working days allowed on the contract.

The maximum pay for the advanced notification changeable message signs is 14 calendar days per message sign. If the Contractor delays their start date, the message signs shall remain in place until lane closures are necessary and work commences. No payment will be made for any days beyond the 14 day maximum.

COMBINATION CONCRETE CURB AND GUTTER, TYPE M (SPECIAL)

This work consists of the construction of a mountable combination concrete curb and gutter. The combination concrete curb and gutter, type M (special) shall be constructed according to Section 606 of the Standard Specifications and per the dimensions shown on the detail in the plans.

The work will be paid for at the contract unit price per FOOT for COMBINATION CONCRETE

CURB AND GUTTER, TYPE M (SPECIAL).

SECTION (15-22HB-4)BR (15-22)R

COMMUNICATIONS VAULT

This work shall be in accordance with Sections 814 and 1088 of the Standard Specifications except as modified herein. This work shall consist of furnishing and installing a communications vault constructed of polymer concrete.

The following items are approved for use: Hubbel, Quazite, Part Numbers: PG2436HA00 (Cover) and PG2436BA30 (Box) or approved equal:

The communications vault and lid shall conform to the following specifications:

Cover:

• Material: polymer concrete

• Nominal Dimensions: 24” W x 36 L”

• Gasketed, heavy duty lid with two bolts

• Design/Test Load: 15,000/22,500 lb

• ANSI Tier: 15

Box

• Material: polymer concrete

• Nominal Dimensions: 24” W x 36” L x 30” D

• Open bottom

• Design/Test Load: 22,500/33,750 lb

• ANSI Tier: 22

The location of the handhole shall be excavated so that the top of the handhole is set flush with the sidewalk or paved surface. When installed in earth shoulder away from the pavement edge, the top surface of the handhole shall be 1 in. above the finished grade. The excavation shall be deep enough to accommodate the depth of the box and French drain.

The French drain shall be constructed underneath the proposed handhole according to Article

601.06 and in accordance with Standard 814001.

The conduits shall enter the vault at 24” minimum and the Contractor shall install 6 inches of CA 5 or CA 7 in the bottom of the vault.`

The Contractor shall submit testing reports to verify that the communications vaults and lids meet the requirements of ANSI Tier 15 and ANSI Tier 22 loading.

The fiber optic locating cable shall be continuous and accessible on the outside of each communication vault. The Contractor shall utilize appropriate corrosion resistant hardware (stainless steel) and connections to the locating wire. The Contractor shall submit material and installation methods to the Department for review.

Basis of Payment: This work will be paid for at the contract unit price per EACH for

COMMUNICATIONS VAULT.

SECTION (15-22HB-4)BR (15-22)R

CLASS BS AGGREGATE OPTIMIZATION

For superstructure construction, class BS concrete shall contain a blend of two or more coarse aggregate sizes blended in accordance with Article 1004.02(d). The blended aggregate will consist of CA-7 or CA-11 with CA-13, CA-14, or CA-16. The blended coarse aggregate gradation shall have a minimum of 45% passing the 1/2 in. (12.5 mm) sieve and a maximum of 60% passing the 1/2 in. (12.5 mm) at the discretion of the Engineer.

The cost of compliance with this requirement shall be considered included in the cost of Concrete Superstructures.

CLASS SI CONCRETE (OUTLET), SPECIAL

This work consists of the construction of concrete outlets as detailed and at locations shown in the plans, as directed by the Engineer, and in accordance with the applicable portions of Section 606 of the Standard Specifications. Excavation and backfill required for this work will not be measured for payment.

This work will be paid for at the contract unit price per CUBIC YARD for CLASS SI CONCRETE

(OUTLET), SPECIAL.

CLOSED CIRCUIT TELEVISION CABINET

Description. This work consists of furnishing and installing a pole mounted equipment cabinet and peripheral equipment at locations indicated in the plans. These cabinets will be utilized to house critical electrical, optical, and communications equipment as defined in other contract pay items.

Materials. Materials shall be in accordance with the following specifications.

The equipment cabinet shall conform to the details shown on the plan sheet. Equipment cabinets shall be mounted and anchored on the poles and structures at locations indicated in the plans. In addition, all mounting hardware and brackets required to install the equipment cabinet on the pole shall be stainless steel and provided by the Contractor. The mounting heights and pole diameters shall be as specified by the Engineer.

The cabinet shall be a NEMA 3R single door enclosure, constructed from .125” thick aluminum, with nominal outside dimensions of 18” (H) x 14” (W) x 10” (D). The cabinet shall have a natural finish.

The cabinet shall be furnished with a slam lock, neoprene door gasket, vent slots, continuous stainless steel door hinge, and all stainless-steel hardware. The cabinet shall also have a Corbin #2 dead bolt lock or skeleton key. The key shall be removable in the lock position only. Two keys shall be supplied for each lock, and all equipment cabinet locks shall be keyed the same.

SECTION (15-22HB-4)BR (15-22)R

All cables shall be labeled utilizing marking tags.

The cabinet shall be equipped with a main power panel as shown on the cabinet plan detail sheet.

The power panel shall include one 15A main breaker, power terminal blocks, and one 6 outlet power strip with integral surge protection. The power panel shall include a plexi-glass safety shield that covers the power panel.

Power Strip. The cabinet power strip shall have a minimum of six outlets and integral surge suppression that meets or exceeds the following minimum specifications:

• Let Through Voltage: <85 Volts

• Operating Voltage: 120VAC, 50/60H

• UL Suppressed Voltage Rating: 330V

• Energy Rating: 320J

• Peak Current NM/CM: 13k Amps NM, 13k Amps CM

• EMI/RFI Noise Filtration: >25-60dB

The power strip shall be wired directly to the protected power terminals on the cabinet surge arrestor.

Construction Requirements. The Contractor shall prepare and submit shop drawings that detail all the components to be supplied, along with associated mounting hardware for the pole mounted equipment cabinet. The shop drawings must be approved by the Engineer prior installation of the completed cabinet in the field.

The Engineer reserves the right to inspect and/or factory test any completed cabinet assemblies prior to shipment of the material to the project site. Any deviances from these specifications that are identified during such testing shall be corrected prior to delivery of the assembly to the project site.

The AC power service to be run to the equipment cabinet shall be terminated. In addition, the cabinet shall be connected to an adequate ground following the Standard Specifications.

The Contractor shall terminate any inbound and outbound fiber optic, telephone, or wireless antenna leads in the equipment cabinet as shown in the plans. The Contractor shall terminate any twisted pair communication cable on the termination panel in the equipment cabinet as shown in the plans. Lugs shall be installed at the end of each conductor suitable for connection to the barrier terminal blocks.

Method of Measurement. This item shall be measured for payment by each pole mounted equipment cabinet in-place.

Basis of Payment. This work will be paid for at the contract unit price per EACH for CLOSED

CIRCUIT TELEVISION CABINET.

SECTION (15-22HB-4)BR (15-22)R

CLOSED-CIRCUIT TELEVISION DOME CAMERA, IP BASED

Description. This work shall consist of furnishing and installing an integrated closed-circuit television (CCTV) dome camera assembly, camera brackets, and all other items required for installation and operation. This assembly shall contain all components identified herein and shall be configured as indicated on the plan sheets.

Materials. The CCTV camera shall be an Axis Model Q6075-E “or approved equal” dome camera assembly for integration into the existing District 7 ITS system. The Contractor shall provide all materials required to install the proposed camera on the proposed light pole structure as shown on the plan sheets. The Contractor shall submit catalog cut sheets to the Department for all items (mounting brackets, hardware, etc.) that will be utilized for review prior to commencing work.

The Department will program the cameras.

The camera shall meet or exceed the following specifications:

Camera

• Video:

o 60 Hz (NTSC), 50 Hz (PAL)

• Image Sensor:

1/2.8” progressive scan CMOS

• Lens:

• 4.44–142.6 mm, F1.6–4.41 o Horizontal angle of view: 62.8°–2.23° o Vertical angle of view: 36.8°–1.3° o Autofocus, auto-iris

• Day And Night:

Automatically removable infrared-cut filter

• Minimum Illumination:

o Color: 0.3 lux at 30 IRE F1.6 o B/W: 0.03 lux at 30 IRE F1.6 o Color: 0.5 lux at 50 IRE F1.6 o B/W: 0.04 lux at 50 IRE F1.6

• Shutter Time: Ntsc:

1/33000 s to 1/3 s with 50 Hz o 1/33000 s to 1/4 s with 60 Hz

• Pan/Tilt/Zoom:

Pan: 360° endless, 0.05° - 450°/s o Tilt: 220°, 0.05°-450°/s o 32x optical zoom and 12x digital zoom, total 384x zoom E-flip, 256 preset positions, Tour recording, Guard tour, Control queue, On-screen directional indicator, Set new pan 0°,Adjustable zoom speed

Video

• Video Compression:

SECTION (15-22HB-4)BR (15-22)R

• H.264 (MPEG-4 Part 10/AVC), Motion JPEG

• Resolutions:

• HDTV 1080p 1920x1080 to 320x180 o HDTV 720p 1280x720 to 320x180

• Frame Rate (H.264):

• Up to 60/50 fps (60/50 Hz) in HDTV 720p o Up to 30/25 fps (60/50 Hz) in HDTV 1080p

• Video Streaming:

o Multiple, individually configurable streams in H.264 and Motion JPEG, Axis’ Zipstream technology, Controllable frame rate and bandwidth, VBR/MBR H.264

• Image Setting:

o Manual shutter time, compression, color, brightness, sharpness, white balance, exposure control, exposure zones, fine tuning of behavior at low light, rotation: 0°, 180°, text and image overlay, 32 individual 3D privacy masks, image freeze on PTZ, automatic defog, backlight compensation

• Wide Dynamic Range (WDR):

o Up to 120 dB depending on scene, highlight compensation

Network

• Security:

• Password protection, IP address filtering, HTTPSa encryption, IEEE 802.1Xa network access control, Digest authentication, User access log, Centralized Certificate Management

• Protocols:

• IPv4/v6, HTTP, HTTPSa, SSL/TLSa, QoS Layer 3 DiffServ, FTP, CIFS/SMB, SMTP, Bonjour, UPnPTM, SNMP v1/v2c/v3 (MIB-II), DNS, DynDNS, NTP, RTSP, RTP, SFTP, TCP, UDP, IGMP, RTCP, ICMP,DHCP, ARP, SOCKS, SSH, NTCIP

System Integration

• Application Prog

• Open API for software integration, including VAPIX®

• Interface

• AXIS Camera Application Platform; specifications at www.axis.com, AXIS Video

Hosting System (AVHS) with One-Click Connection, ONVIF Profile S, specification at www.onvif.org

• Analytics:

• Video motion detection, Autotracking, Active Gatekeeper

• Basic Analytics (not to be compared with third-party analytics): Object removed, Enter/Exit detector, Fence detector, Object Counter, Highlight compensation, Support for AXIS Camera

• Application Platform enabling installation of third-party applications, see www.axis.com/acap

• Event Triggers: Detectors: Live stream accessed, Video motion detection, Shock Detection, Object removed, Enter/Exit detector, Fence detector, Object counter;

Hardware: Fan, Network, Temperature, Casing Open; PTZ: Autotracking, Error, Moving, Ready, Preset Reached; Storage: Disruption, Recording; System: System Ready; Time:

• Recurrence, Use Schedule; Input signal: Manual trigger, Virtual Input

SECTION (15-22HB-4)BR (15-22)R

• Event Actions:

• Day/night mode, overlay text, video recording to edge storage,

• pre- and post-alarm video buffering, send SNMP trap

• PTZ: PTZ preset, start/stop guard tour

• File upload via FTP, SFTP, HTTP, HTTPS network share and

• Email; Notification via email, HTTP, HTTPS and TCP

• Data Streaming

• Event data

• Built In Installation Pixel Counter

• Aids

General

• Casing:

• IP66-, NEMA 4X- and IK10-rated

• Metal casing (aluminum), polycarbonate (PC) clear dome,

• sunshield (PC/ASA)

• Sustainability:

• PVC Ffree

• Memory:

• 512 MB RAM, 128 MB Flash

• Power Camera:

• Axis High PoE midspan 1–port: 100–240 V AC, max 74 W

• Camera consumption: typical 16 W, max 60 W

• Connectors:

• RJ45 10BASE-T/100BASE-TX PoE, RJ45 Push-pull Connector

• (IP66) included

• Edge Storage:

• Support for SD/SDHC/SDXC card

• Support for recording to dedicated network-attached storage

• (NAS); For SD card and NAS recommendations see www.axis.com

• Operating

• With 30 W midspan: -4 °F to 122 °F

• Conditions:

• With 60 W midspan: -58 °F to 122 °F

• Maximum temperature (intermittent): 140 °F

• Arctic Temperature Control: Start-up as low as -40 °F

• Humidity 10–100% RH (condensing)

• Approvals:

• EMC: EN 55022 Class A, EN 61000-3-2, EN 61000-3-3, EN 61000-6-1, EN 61000-6-

2, EN 55024, FCC Part 15 Subpart B Class A, ICES-003 Class A, VCCI Class A, RCM AS/NZS CISPR 22 Class A, KCC KN32 Class A, KN35

• Safety: IEC/EN/UL 60950-1, IEC/EN/UL 60950-22

• Environment: EN 50121-4, IEC 62236-4, IEC 60068-2-1, IEC 60068-2-2, IEC 60068-

2-6, IEC 60068-2-14, IEC 60068-2-27, IEC 60721-4-3, NEMA 250 Type 4X, IEC

60068-2-30, IEC 60068-2-60, IEC 60068-2-78, IEC/EN 60529 IP66, NEMA TS-2-2003

v02.06, Subsection 2.2.7, 2.2.8, 2.2.9; IEC 62262 IK10, ISO 4892-2

• Midspan: EN 60950-1, GS, UL, cUL, CE, FCC, VCCI, CB, KCC, UL-AR

SECTION (15-22HB-4)BR (15-22)R

• Weight:

• 8.2 lb.

• Included

• Axis High PoE 60 W midspan 1-port, RJ45 Push-pull Connector

• Accessories: (IP66), Sunshield, Installation Guide, Windows decoder 1-user license

• Video Management

• AXIS Camera Companion, AXIS Camera Station, Video

• Software:

• management software from Axis’ Application Development

• Partners available on www.axis.com/techsup/software

• Warranty:

• Axis 3-year warranty and AXIS Extended Warranty option

Environmental Enclosure/Housing. The environmental enclosure shall be designed to physically protect the integrated camera from the outdoor environment and moisture via a sealed enclosure.

If the option exists in the standard product line of the manufacturer, the assembly shall be supplied with an integral sun shield. The enclosure shall be fully water and weather resistant with a NEMA 4 rating or better.

The camera dome shall be constructed of distortion free acrylic or equivalent material that must not degrade from environmental conditions. The environmental housing shall include a camera mounting bracket. In addition, the environmental housing shall include a heater, blower, and power surge protector. An integral fitting compatible with a standard 1-1/2 in (38.1 mm) NPT pipe, suitable for outdoor pendant mounting shall also be provided.

The enclosure shall be equipped with a heater controlled by a thermostat. The heater shall turn n when the temperature within the enclosure falls below 40° F (4.4°C). The heater shall turn off when the temperature exceeds 60°F (15.6°C). The heater will minimize internal fogging of the dome faceplate when the assembly is operated in cold weather.

In addition, a fan shall be provided as part of the enclosure. The fan will provide airflow to ensure effective heating and to minimize condensation.

The enclosure shall be equipped with a hermetically sealed, weatherproof connector, located near the top for external interface with power, video, and control feeds.

CCTV Dome Camera Mounting Supports. The Contractor shall furnish and…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .