Reconstruction of Mill Road from US 20 to 0. 2 miles north of US 20 and construction of Service Rd
Solicitation number
64V52
Issued by
Rock Island County, Illinois

About this file

This is a Notice to Bidders and Special Provisions document issued by the Illinois Department of Transportation (IDOT) for Contract No. 64V52, a federal-aid construction project in Winnebago County. The project involves the reconstruction of Mill Road from US 20 to 0.2 miles north of US 20, construction of a new Service Road 0.3 miles west of Mill Road, and reconstruction of Cemetery Loop Road. Work includes pavement removal and replacement with hot-mix asphalt (HMA) and Portland cement concrete (PCC) curb and gutter on Mill Road, HMA pavement with aggregate shoulders on Service Drive, and HMA pavement on Cemetery Loop Road, along with associated earthwork, drainage, traffic control, erosion control, and landscaping. Electronic bids must be submitted to the iCX system by 12:00 p.m. on July 31, 2026. The project has multiple interim completion dates: Winter Shutdown configuration by November 19, 2026, Stage A completion by May 14, 2027, and Stage B completion by June 16, 2027, with a final completion date of June 30, 2027, plus 30 working days for cleanup and punch list items. Coordination with adjacent IDOT Contracts 64R72, 64R71, 64C24, 64R15, and a Tollway project is required due to overlapping construction limits.

The contract will be awarded to the lowest responsive and responsible bidder. Liquidated damages of $6,775 per calendar day apply for failure to meet interim or final completion dates. The project involves complex coordination with multiple utility relocations, including work by AT&T, ComEd, Comcast, Syndeo, Frontier, and Nicor Gas, with specific utility contacts provided. Critical provisions include traffic control staging on US 20 and Mill Road, requirements for winter shutdown configuration maintenance, temporary pavement marking during winter months, PCC automatic batching equipment with computerized batch tracking, and quality control/quality assurance reporting for concrete. The project is funded through federal-aid (STP-KFG9(946)) and state construction funds. Regulated substances management applies at multiple identified work areas with specific contamination parameters. The contractor must maintain local access to Cherry Valley Cemetery and Service Drive throughout construction and coordinate with emergency response agencies, school districts, and municipalities regarding traffic changes.

View the file

Other files

File Type Posted
ILDOT 64V52.33.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting July 31, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 64V52 WINNEBAGO County Section 6RS Route FAP 525 Project STP-KFG9(946) District 2 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

July 31, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 64V52 WINNEBAGO County Section 6RS Project STP-KFG9(946) Route FAP 525 District 2 Construction Funds

0.31 miles of reconstruction of Mill Road from US 20 to 0.2 miles north of US 20 and construction of Service Rd 0.3 miles west of Mill Road. The project also consists of the reconstruction of the Cemetery Loop Rd.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

FAP Route 525 (Old Mill Rd. & Service Rd.)

Section 6RS Winnebago County

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS and frequently used RECURRING SPECIAL

PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment………………………………………………………………………………... 1 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches …………………………………………………………………………….. 6 406 Hot-Mix Asphalt Binder and Surface Course ……………………………………………………………. 7 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures ……………………………………………………………………………… 12 509 Metal Railings 522 Retaining Walls …………………………………………………………………………………………….. 14 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers ……………………………………………………………………………………………….. 44 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains ……………………………………………………. 52 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal ……………………………………………………………… 54 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection ……………………………………………………………….. 57 781 Raised Reflective Pavement Markers ……………………………………………………………………. 59 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain …………………………………………………………………………... 74 1042 Precast Concrete Products ……………………………………………………………………………….. 75 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment ……………………………………………………………………………

Section 6RS

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 X Additional State Requirements for Federal-Aid Construction Contracts 2 X Subletting of Contracts (Federal-Aid Contracts)

3 X EEO

4 Specific EEO Responsibilities Non Federal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos HMA Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 X Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 X Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 X Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 X Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 X Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays

Section 6RS i

TABLE OF CONTENTS

LOCATION OF PROJECT

DESCRIPTION OF PROJECT

COMPLETION DATE PLUS WORKING DAYS

START DATE – STAGE A

INTERIM COMPLETION DATE – WINTER SHUTDOWN 2026

INTERIM COMPLETION DATE – STAGE A

INTERIM COMPLETION DATE – STAGE B

FAILURE TO COMPLETE THE WORK ON TIME

COORDINATION WITH ADJACENT AND/ OR OVERLAPPING CONTRACTS

COOPERATION BETWEEN CONTRACTORS

AVAILABILITY OF ELECTRONIC FILES

3D MODEL – CONTRACTOR SUPPLIED

CRITICAL PATH SCHEDULE – TYPE B

MAINTENANCE OF ROADWAYS

STATUS OF UTILITIES (D2)

PCC AUTOMATIC BATCHING EQUIPMENT

PCC QC/QA ELECTRONIC REPORTS SUBMITTAL

TRAFFIC CONTROL PLAN

MAXIMUM DROP-OFFS BETWEEN ADJACENT LANES

TEMPORARY LINEAR DELINEATOR PANELS

WORK ZONE PAVEMENT MARKING AND REMOVAL

SEEDING, CLASS 4A AND 5

MOWING

BOX CULVERT END SECTIONS

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES

GROOVING FOR RECESSED PAVEMENT MARKING, LETTERS AND SYMBOLS

STABILIZED CONSTRUCTION ENTRANCE

DRAINAGE STRUCTURES TO BE ADJUSTED

STORM SEWER (WATER MAIN REQUIREMENTS)

TEMPORARY PAVEMENT

TEMPORARY TRAFFIC SIGNAL TIMING

Section 6RS ii

CONSTRUCTION LAYOUT SPECIAL UTILIZING GPS EQUIPMENT

WASHOUT BASIN

BOX CULVERT REMOVAL

GEOTECHNICAL REINFORCEMENT

MAINTENANCE MOWING

TEMPORARY PAVEMENT REMOVAL

REMOVE CONCRETE BOX CULVERT END SECTION

TRAVERSABLE PIPE GRATE (SPECIAL)

TEMPORARY DRAINAGE CONNECTION

ENGINEER’S FIELD OFFICE, TYPE A (SPECIAL)

REMOVE AND REINSTALL SIGN PANEL

MAINTENANCE OF EXISTING TEMPORARY TRAFFIC SIGNAL INSTALLATION

REMOVE EXISTING TEMPORARY TRAFFIC SIGNAL EQUIPMENT

MODIFY TEMPORARY TRAFFIC SIGNAL EQUIPMENT

CONNECTION TO EXISTING DRAINAGE STRUCTURE

AGGREGATE SUBGRADE IMPROVEMENT (BDE)

AUTOMATED FLAGGER ASSISTANCE DEVICES (BDE)

BITUMINOUS MATERIALS COST ADJUSTMENTS (BDE)

CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE) ..

COMPENSABLE DELAY COSTS (BDE)

CONCRETE BARRIER (BDE)

DISADVANTAGED BUSINESS ENTERPRISE PARTICIPATION (BDE)

EROSION CONTROL BLANKET (BDE)

HOT-MIX ASPHALT (BDE)

HOT-MIX ASPHALT – LONGITUDINAL JOINT SEALANT (BDE)

INLET FILTERS

PAVEMENT MARKING (BDE)

PAVEMENT PATCHING (BDE)

PERFORMANCE GRADED ASPHALT BINDER (BDE)

PREFORMED PLASTIC PAVEMENT MARKING (BDE)

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)

SEEDING (BDE)

SHORT TERM AND TEMPORARY PAVEMENT MARKINGS (BDE)

Section 6RS iii

SIGN PANELS AND APPURTENANCES (BDE)

SOURCE OF SUPPLY AND QUALITY REQUIREMENTS (BDE)

SUBCONTRACTOR AND DBE PAYMENT REPORTING (BDE)

SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)

SUBMISSION OF BIDDERS LIST INFORMATION (BDE)

SUBMISSION OF PAYROLL RECORDS – FEDERAL AID CONTRACT (BDE)

SURFACE TESTING OF PAVEMENTS – IRI (BDE)

SURVEYING SERVICES (BDE)

TEMPORARY CONCRETE BARRIER (BDE)

TRAINING SPECIAL PROVISIONS (BDE)

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING SPECIAL PROVISION . 108

VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)

WEEKLY DBE TRUCKING REPORTS (BDE)

WOOD SIGN SUPPORT (BDE)

WORK ZONE TRAFFIC CONTROL DEVICES (BDE)

WORK ZONE WIDTH RESTRICTION (BDE)

SWPPP

Section 6RS

STATE OF ILLINOIS

SPECIAL PROVISIONS

The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction," adopted January 1 2022, the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways," and the "Manual of Test Procedures for Materials" in effect on the date of invitation for bids, and the Supplemental Specifications and Recurring Special Provisions indicated on the Check Sheet included herein which apply to and govern the construction of FAP Route 525 (Old Mill Rd. & Service Rd.), Project STP-KFG9(946), Section 6RS, Winnebago County, Contract No. 64V52 and in case of conflict with any part or parts of said Specifications, the said Special Provisions shall take precedence and shall govern.

LOCATION OF PROJECT

This project location is at US 20 (FAP 525) and Old Mill Rd (M 5150), approximately 0.6 miles east of the I-39/Harrison Avenue/US 20 interchange on US 20, T43N, R2E, section 36 in Rockford Township, and T44N, R2E, section 1 in Cherry Valley Township, in Winnebago County, IL.

DESCRIPTION OF PROJECT

This project consists of the reconstruction of Mill Road from US 20 to 0.2 miles north of US 20 and construction of Service Rd 0.3 miles west of Mill Road. The project also consists of the reconstruction of the Cemetery Loop Road.

Improvements consist of, but are not limited, to the following:

• Mill Road o Pavement removal o Shoulder removal o Curb and gutter removal o HMA pavement o PCC curb and gutter

• Service Dr o Pavement removal o Aggregate shoulders

• Cemetery Loop Rd o Entrance removals

The project also includes earthwork, ditch grading, traffic control, temporary traffic signals, erosion and sediment control, landscaping, pavement marking, signing, removal and proposed drainage, subsurface drainage and other associated items necessary to complete the project as shown in the Plans and described herein.

Section 6RS

COMPLETION DATE PLUS WORKING DAYS

Revise Article 108.05(b) of the Standard Specifications to read:

“(b) Completion Date Plus Working Days. When a completion date plus working days is specified, the Contractor shall complete all contract items to safely open all roadways to traffic by 11:59 p.m.

on or prior to Wednesday, June 30, 2027 , except as specified herein.

The Contractor will be allowed _30_ working days after the completion date for opening the roadway to traffic to complete clean-up work, ground mount signs on breakaway steel posts work, and punch list items. Miscellaneous items may be completed within the working days allowed for clean-up work and punch list items if approved by the Engineer. Temporary lane closures for this work (adhering to the restrictions set forth in the TRAFFIC CONTROL PLAN) may be allowed at the discretion of the Engineer.”

START DATE – STAGE A

The Contractor shall not place the traffic configuration for Stage A on or before 12:01AM Monday, March 15, 2027 or before the completion of the south leg of Mill Road by Contract 64R72. The completion of the south leg of Mill Road is scheduled for November 19, 2026. These work restrictions will be valid in order for traffic staging to align with Contract 64R72 construction.

The work associated with Stage A may start before March 15, 2027, if coordinated with adjacent contract 64R72 and approved by Operations. Work in Stage A configuration will only be permitted prior to March 15, 2027 after the completion of the south leg of Mill Road by Contract 64R72.

Traffic must be placed in the Winter Configuration prior to the date listed in INTERIM

COMPLETION DATE – WINTER SHUTDOWN 2026.

Prestage construction may be started before this start date.

INTERIM COMPLETION DATE – WINTER SHUTDOWN 2026

The Winter Stage traffic configuration shall be in place on or before 11:59 PM Thursday, November 19, 2026. These Winter Shutdown work restrictions will be valid in order to complete the work per the specifications. Work may start on or after 12:01AM Monday, March 15, 2027.

Work may start before March 15, 2027, if approved by Operations.

The work associated with the Winter Shutdown shall be per the Special Provision for TRAFFIC CONTROL PLAN Winter Shutdown.

Section 6RS

INTERIM COMPLETION DATE – STAGE A

The Contractor shall complete all required work associated with Stage A on or before 11:59 PM Friday, May 14, 2027 to allow Stage D of the 64R72 Contract to be implemented.

The work associated with the Stage A construction shall include (but is not limited to):

• North Mill Road full depth pavement, concrete curb and gutter, drainage, and safety features

After the INTERIM COMPLETION DATE – STAGE A, an additional 5 Working Days will be allowed to complete all other remaining clean-up work and punch list items required for Stage A completion which do not impact Stage D of Contract 64R72.

INTERIM COMPLETION DATE – STAGE B

The Contractor shall complete all required work associated with Stage B on or before 11:59 PM Wednesday, June 16, 2027 to allow Stage D-2 of the 64R72 Contract to be implemented.

The work associated with the Stage B construction shall include:

• North Mill Road full depth pavement, concrete curb and gutter, drainage, and safety features

After the INTERIM COMPLETION DATE – STAGE B, an additional 5 Working Days will be allowed to complete all other remaining clean-up work and punch list items required for Stage B completion which do not impact Stage D-2 of Contract 64R72.

FAILURE TO COMPLETE THE WORK ON TIME

Should the Contractor fail to complete the work on or before the interim completion date as specified in the Special Provisions for the staged traffic configuration for START DATE – STAGE A, or WINTER SHUTDOWN 2026, or INTERIM COMPLETION DATE – STAGE A, or INTERIM COMPLETION DATE – STAGE B or within such extended time as may have been allowed by the Department, the Contractor shall be liable to the Department in the amount of SIX THOUSAND SEVEN HUNDRED SEVENTY FIVE DOLLARS ($6,775), not as a penalty but as liquidated damages, for each calendar day overrun in the contract time or such extended time as may have been allowed. Such damages may be deducted by the Department for any monies due to the Contractor.

In fixing the damages set herein, the desire is to establish a certain mode of calculation for the work because the Department’s actual loss in the event of delay, cannot be predetermined, would be difficult of ascertainment, and a matter of argument and unprofitable litigation. This said mode is an equitable rule for measurement of the Department’s actual loss and fairly takes into account the loss of use of the roadway if the project is delayed in completion. The Department shall not be required to provide any actual loss in order to recover these liquidated damages provided herein, as said damages are very difficult to ascertain. Furthermore, no provisions of this clause shall be construed as a penalty, as such is not the intention of the parties.

Section 6RS

A calendar day is every day on the calendar and starts at 12:00 midnight and ends at the following 12:00 midnight, twenty-four hours later.

COORDINATION WITH ADJACENT AND/ OR OVERLAPPING CONTRACTS

This contract abuts and/ or overlaps with other concurrent and future Illinois Department of Transportation (IDOT) and Illinois Tollway Contracts as listed below.

Each contract includes work items requiring close coordination between the various Contractors regarding the sequence and timing for execution of work items in accordance with Article 105.08 of the Standards Specifications and as herein noted.

This contract also includes critical work items that affect the future staging of traffic and/ or the completion dates of other contracts. Each of the contracts depends on certain portions of the work to be completed by others in order to complete the program on schedule. These critical items along with their completion dates are listed herein.

The following paragraph shall be added to the beginning of Article 105.08. “The Contractor shall identify such work items (including the critical items listed in the Contract and these Special Provisions) at the beginning of the contract and coordinate the sequence and timing for their execution and completion with the other Contractors through the Engineer. All of these work items shall be identified as separate line items in the Contractor’s proposed Construction Progress Schedule. Additional compensation or the extension of contract time will not be allowed for the progress of the work items affected by the lack of such coordination by the Contractor”.

The adjacent and/or overlapping Contracts will be:

• I-39 Reconstruction Contracts:

o IDOT Contract 64C24 (I-39 Mainline) o IDOT Contract 64R71 (Harrison Avenue) o IDOT Contract 64R72 (US 20)

• Other Adjacent Contracts:

o IDOT Contract 64R15 (FAP 525 (US 20) Hot-Mix Asphalt Resurfacing) o Tollway Project Wheeler/Ispen Road

No adjustments will be made for delay or suspension of the work due to the fault of the Contractor in coordinating project schedule, staging and work items with adjacent Contracts.

Some of the Contracts noted above may have detours implemented. The anticipated seasons or timeframe of the detours are listed below:

• 64C24 o No detours anticipated

• 64R71 o No detours anticipated

• 64R15 o No known detours

Section 6RS

• 64R72 o No known detours

• Tollway Project Wheeler/Ispen Road o No known detours

The list below indicates all such items of the work which have specific completion dates. It is essential that the Contractor responsible for the work complete these items on or before the date indicated so that other contracts may plan and execute their work accordingly.

Interim Completion Dates and Coordination with Adjacent Contract 64R71 The construction limits for Contract 64V52 and Contract 64R71 may overlap, however, it is anticipated that this Contract will be completed prior to the start of the 64V52 contract.

Contract 64R71 is scheduled to be completed and open to traffic by Friday, November 21, 2025 (plus an additional 30 Working Days for cleanup and punch list).

Interim Completion Dates and Coordination with Adjacent Contract 64C24 The construction limits for Contract 64V52 and Contract 64C24 will overlap. Regular coordination between the two contracts will be required in order to minimize/eliminate conflicts in traffic staging, and to maximize safety of both the traveling public and of the respective work zones along US 20 and Mill Road.

Coordination with Adjacent Contract 64R15 The construction limits for Contract 64R72 and Contract 64R15 may overlap. It is anticipated that Contract 64R15 will begin during the 2025 Construction Season. The 64R15 asphalt overlay work will be approximately 0.4 miles east of Mill Road.

Coordination between the two contracts may be required to minimize/eliminate conflicts in traffic staging, and to maximize safety of both the traveling public and of the respective work zones.

Coordination with Adjacent Contract 64R72 Contract 64R72 was on the February 2026 Letting, with the start of work anticipated to commence in Spring 2026. Therefore, the construction limits for Contract 64V52 and Contract 64R72 will overlap. The Contractor shall coordinate with the Department and make MOT and construction activity modifications to accommodate the planned work as needed. The cost for coordination, modifications required to the MOT and construction activities, shall be included in the cost of Mobilization. Contract Dates for adjacent Contract 64R72 include:

• Start Date (64R72 Stage 1 & Stage A): April 13,2026

• Interim Completion Date (Stage 1B-1 & Stage A-2): July 2, 2026 The sidewalk along the west side of Mill Rd and shared-use paths in the southwest and northwest quadrants of Mill Rd and US 20 shall be completed

• Winter Shutdown: November 19, 2026 to March 15, 2027. The south leg of Mill Rd construction through and including Stage B-2 shall be completed and Winter Stage traffic configuration shall be in place

• Interim Completion Date (Stage D-2): June 30, 2027. The northeast quadrant of Mill Rd US 20, Stage D-2 work as shown in the plans, shall be completed.

• Completion Date: October 15, 2027 (plus 30 working days)

Section 6RS

Coordination with Adjacent Tollway Wheeler/Ispen Road Contract The construction limits for Contract 64R72 and the Tollway Contract are not anticipated to overlap.

This contract is anticipated to begin construction in 2026.

Shared Access and Work Area When necessary for proper prosecution of work, each Contractor shall permit the other access through the overlapping construction areas and the use of any access or haul roads constructed by others.

When necessary for the proper prosecution of work, each Contractor shall permit the other to work within predetermined areas of overlapping construction work areas for a predetermined duration. The Contractor working within the adjacent overlapping construction work areas will be responsible for cleaning the work area upon completion and leaving the work area in a suitable condition, including application of temporary erosion control measures as required, to the satisfaction of both Engineers. Examples of work requiring occupation of overlapping work areas include (but are not limited to): Earth Excavation/ Grading, Landscaping, Maintenance of Erosion Control Items.

Any damages resulting from the shared use of access facilities or overlapping work area shall be repaired by the Contractor which caused the damage at his own expense and at no additional cost to the Contract.

Basis of Payment. All expenses incurred by the Contractor by reason of compliance with these requirements, unless noted otherwise, shall be considered as included in and completely covered by the contract unit prices for the various items included in the contract.

COOPERATION BETWEEN CONTRACTORS

Contract 64V52 will be required to coordinate with 64R72. The Resident Engineers of both contracts and a minimum of one representative from each Contractor shall conduct a joint meeting to discuss completed 64R72 work and planned construction sequencing of the 64V52 contract at the start of the 64V52 contract. Following the initial meeting, regular coordination between the two contracts will be required in order to minimize/eliminate conflicts in traffic staging, and to maximize safety of both the traveling public and of the respective work zones along Mill Road, Service Drive, and Cemetery Loop Road. The Department may require the Contractor to attend additional coordination meetings at a time and location determined by the Department.

The cooperation between work under Contract 64V52 and Contract 64R72 is essential due to the adjacent limits of construction and shared maintenance of traffic responsibilities along US 20 and Mill Rd. All traffic staging configurations and changes to staging along US 20 and Mill Rd shall be coordinated between the contractors performing the work for 64V52 and 64R72. The Contractor shall make no claims against the Department for additional compensation due to delays due to the 64R72 Contract.

The Department reserves the right to have work performed by other Contractors and by Department forces and to permit public utility companies and others to perform work during the progress and within the limits of or adjacent to the work. The Contractor shall conduct its work in a respective manner and shall cooperate with such other parties to cause as little interference as possible with such other work and as the Department may also direct. If there is a difference of

Section 6RS opinion as to the respective rights of the Contractor and others doing work within the limits of or adjacent to the work, the Engineer will decide the order and coordination of the work. The Engineer’s decision shall be final and binding on the Contractor. The Contractor shall make no claims against the Department for additional compensation due to delays or other conditions created by the operations of such other parties.

The Contractor is advised that certain operations will involve coordination with Department personnel and Contractors currently performing work on or adjacent to this project for the Department and other agencies. The Contractor shall cooperate to the fullest extent with the Department and the Contractors working on adjacent projects in compliance with Articles 105.07 and 105.08. Any inconveniences or delays caused by the Contractor in complying with this requirement shall be considered incidental to the contract and no additional compensation will be allowed.

The Department and the Engineer shall be notified in writing by the Contractor at least 48 hours prior to the start of any operation requiring cooperating with others. All other agencies, unless otherwise noted, will be notified in writing by the Contractor ten (10) days prior to the start of any such operation. The Contractor shall make no claims against the Department for additional compensation due to delays or other conditions created by the operations of such other parties.

AVAILABILITY OF ELECTRONIC FILES

Effective 10/16 Revised 1/29/25

Electronic files of this project will be made available to the Contractor after the contract has been awarded. This information will be provided upon request in a Bentley CONNECT Platform software format ONLY. If data is required in other formats, it will be your responsibility to make these conversions. The Contractor shall coordinate obtaining electronic files through the Project Engineer. If there is a conflict between the electronic files and the printed contract plans and documents, the printed contract plans and documents shall take precedence over the electronic files. The Contractor shall accept all risk associated with using the electronic files and shall hold the Department harmless for any errors or omissions in the electronic files and the data contained therein. Errors or delays resulting from the use of the electronic files by the Contractor shall not result in an extension of time for any interim or final completion date or shall not be considered cause for additional compensation. The Contractor shall not use, share, or distribute these electronic files except for the purpose of constructing this contract. Any claims by third parties due to use or errors shall be the sole responsibility of the Contractor. The Contractor shall include this disclaimer with the transfer of these electronic files to any other parties and shall include appropriate language binding them to similar responsibilities.

3D MODEL – CONTRACTOR SUPPLIED

Effective 10/29/25

If the Contractor develops a 3D model of the project site, then it shall be provided to the Resident Engineer. 3D models developed by the Contractor shall be provided to the Resident Engineer at no additional cost to the Department.

Section 6RS

CRITICAL PATH SCHEDULE – TYPE B

Effective: September 27, 2024

Description

This work shall consist of preparing, revising, and updating a detailed progress schedule based upon the Critical Path Method (CPM). This work shall also consist of performing time impact analysis of the progress schedule based upon the various revisions and update as they occur.

General

Revise the first and second paragraphs of Article 108.02 of the Standard Specifications to read:

“After the award of the contract and prior to starting of work, the Contractor shall submit to the Engineer a satisfactory progress schedule, which shall show the proposed sequence of work, including traffic control and staging, and how the Contractor proposes to complete the various items of work within the number of working days setup in the contract or on or before the completion date specified in the contract. Additionally, the Contractor shall submit an updated progress schedule on the first Monday of each month and as deemed necessary by the Engineer.

The progress schedule shall be the intended work schedule and shall be used to plan, organize, and execute the work; record and report actual performance and progress, and forecast remaining work.

The progress schedule shall be used as a basis for establishing the controlling item of the construction operations and for checking the progress of all work under the contract. The controlling item shall be defined as the item which must be completed either partially or completely to permit continuation of progress. It shall be the responsibility of the Contractor to show the intended rate of production for each controlling item listed on the schedule during the period such item is controlling.”

Revise the fifth paragraph of Article 108.02 of the Standard Specifications to read:

“No payment under this contract will be made until a progress schedule has been submitted for approval. Payment may be withheld until a satisfactory schedule has been submitted and approved. If the Contractor deviates from the current approved progress schedule by not following the logical sequence of the critical path, payment will be withheld until a revised progress schedule is submitted and approved by the Engineer. Payment may be withheld if scheduled updated progress schedules are not submitted as required.”

Revise the first paragraph of Article 108.03 of the Standard Specifications to read:

“Time is of the essence in this contract. The Contractor shall begin the work to be performed under the contract not later than ten days after the execution of the contract by the Department, unless otherwise provided in the contract. The work shall be prosecuted in such a manner and with such a supply of materials, equipment and labor as is considered necessary to ensure its completion according to the time specified in the contract.

Section 6RS

Requirements

The progress schedule shall be developed using a project management software approved by the Engineer. The progress schedule submitted shall be a Gantt chart with a tabular data report for each activity and accompanied by a narrative report.

A. Format

The electronic schedule format shall contain the following on each page printed:

• Project Name

• Project Title: Contract number

• Company Name: Contractor’s name

• Type and edition of software

• Submittal date

• Number/Version: Original or update number

• Planning Unit: Calendar Days or Working Days

• Start Date of contract work

• Milestone Completion Date(s) as specified in contract documents

• Page number

B. Target Schedule Development

1. The Contractor shall take account in the schedule for any critical closure periods and limitations of operations specified in Article 107.09 of the Standard Specifications or the contract documents

C. Schedule Updates

1. All updates shall be plotted against the Target Schedule. The Contractor shall not make any changes to the original duration, activity relationships or constraints, and shall not add or delete activities, or alter the Target Schedule’s logic when updating the schedule.

2. The updated information will include the original schedule detail and the following additional information:

• Actual start dates

• Actual finish dates

• Activity percent completion

• Remaining duration of activities in progress

• Identified or highlighted critical activities

3. The Engineer shall withhold progress payments if the Contractor does not submit scheduled updates as required.

Section 6RS

4. Upon receipt of the updated CPM progress schedule, the Engineer will review the schedule for conformance with the Contract Documents and degree of detail. The Engineer, within 14 calendar days after receipt of the updated CPM progress schedule and supporting documents, will approve or reject it with written comments. If the updated CPM progress schedule is rejected, the Contractor must submit a revised updated CPM progress schedule within seven calendar days after the date of rejection.

5. The updated progress schedule must accurately represent the Project’s current status.

D. Schedule Revisions

Revisions to the Target Schedule may be initiated by a proposal by the Contractor or by direction from the Engineer.

1. Contractor Changes to the Target Schedule.

The Contractor shall comply with the following requirements regarding proposed changes to the Target Schedule:

• If the Contractor proposes to make any changes in the Target Schedule, the Contractor shall notify the Engineer in writing, stating the reasons for the change, identifying each changed activity (including duration and interrelationships between activities) and providing a submittal including compact discs and printed copies of the proposed revised schedule. Every effort must be made by the Contractor to retain the original Activity ID numbers.

• The Engineer has the authority to approve or reject the proposed change(s) in the

Target Schedule and shall do so in writing within 14 calendar days after receipt of the Contractor’s submittal. If the Engineer approves the change in the Target Schedule, all future monthly updates will be plotted against the new Target Schedule.

• If the Engineer approves a portion of the change to the Target Schedule, the

Contractor shall submit a revised schedule incorporating such change(s) within seven calendar days after the partial approval along with a written description of the change(s) to the schedule.

2. Engineer Changes to the Target Schedule The Engineer may direct the Contractor to revise the approved baseline CPM progress schedule. Reasons for such direction may include, are limited to the following: (1) changes in the work, (2) re-phasing of the Project or any phase, (3) a change in the duration of the Project or phase, and (4) acceleration of the Project or phase.

• The Engineer will direct the Contractor to provide a revised CPM schedule in writing.

• The Contractor shall submit the revised CPM progress schedule within ten calendar days of receipt of the Engineer’s written direction.

Section 6RS

• The Engineer has the authority, in its sole discretion, to approve or reject the revised CPM progress schedule and will do so in writing within fourteen calendar days after receipt of the Contractor’s submittal If the Engineer approves the revised CPM progress schedule, such schedule will be designated the new “Target Schedule”.

• If the Engineer approves a portion of the change to the Target Schedule, the

Contractor shall submit a revised schedule incorporating such change(s) within seven calendar days after the partial approval along with a written description of the change(s) to the schedule.

E. Schedule Presentation (Gantt Chart)

1. The following shall be included for each activity in the graphic part of the schedule in the Gantt chart format:

• Activity identification numbers

• Description of the work activity o Maximum 45 characters o Usage of percentage numbers shall not be permitted in the description o Multiple activities with the same description shall include a location as part of the description

• Duration of the work activity in whole days o Must be contiguous and not interruptible o Include production rates

• Sequence and interdependence of work activities o Sequence shall not violate the schedule logic

• Critical path to milestone and contract completion o Only one (1) controlling item shall be designated at any point in time on the schedule

2. Work activities shall be broken down such that each activity encompasses a single operation or tightly-integrated operations in a single, contiguous and continuous area of the project. Each activity shall have a duration of not more than 20 working days, except for non-work type activities (such as mobilization), unless otherwise approved by the Engineer.

3. Include the following dates:

• Start/End for each stage of construction

• Milestones identified in the contract

• Document Submittals o Shop drawings, etc.

• Work activities

• Equipment, Access, Installation

4. Calculate total float as finish float. Calculate the schedule using retained logic. Do not sequester float by calendar manipulations or extended duration. Float is not for the exclusive use or benefit of either the Department or the Contractor.

5. Include a legend defining all abbreviations, terms, and symbols used

Review and Approval Process

The Contractor shall electronically submit the progress schedule to the Engineer for review in both its original file format and in pdf format.

Section 6RS

The Engineer will notify the Contractor in writing, within 14 calendar days after receiving any progress schedule submittal or resubmittal, if the schedule is approved or if any corrections or revisions are required. If corrections or revisions are required to the progress schedule, the Contractor shall submit the revised progress schedule to the Engineer within 7 calendar days after receiving the Engineer’s request for corrections or revisions.

Submittals that are required to be revised and resubmitted shall have the revisions clouded or annotated to designate revisions.

Acceptance or approval of any progress schedule by the Engineer shall not be construed to imply approval of any particular method of construction, sequence of construction, any implied or stated rate of production. Acceptance will not act as a waiver of the obligation of the Contractor to complete the work in accordance with the contract proposal, plans and specifications, modify any rights or obligations of the Department as set forth in the contract, nor imply any obligation of a third party. Acceptance shall not be construed to modify or amend the contract or the time limit(s) therein. Acceptance shall not relieve the Contractor of the responsibility for the accuracy of any of the information included on the schedule. Failure of the Contractor to include in the schedule any element of work required for the performance of the contract, any sequence of work required by the contract, or any known or anticipated condition affecting the work shall not excuse the Contractor from completing all work required within the time limit(s) specified in the contract notwithstanding acceptance of the schedule by the Engineer.

Basis of Payment

This work will not be paid for separately, but shall be included in the cost for MOBILIZATION.

MAINTENANCE OF ROADWAYS

Effective: June 26, 2003 Revised: April 4, 2023

Beginning on the date that work begins on this project, the Contractor shall assume responsibility for normal maintenance of all existing roadways within the limits of the improvement. This normal maintenance shall include all repair work such as patching, intermittent resurfacing, sign maintenance, and shoulder work deemed necessary by the Engineer, but shall not include snow removal operations. Traffic control and protection for maintenance of roadways will be provided by the Contractor as required by the Engineer.

If items of work have not been provided in the contract, or otherwise specified for payment, such items, including the accompanying traffic control and protection required by the Engineer, will be paid for in accordance with Article 109.04 of the Standard Specifications.

STATUS OF UTILITIES (D2)

Utility companies and/or municipal owners located within the construction limits of this project have provided the following information regarding their facilities and the proposed improvements.

The tables below contain a description of specific conflicts to be resolved and/or facilities which will require some action on the part of the Department’s contractor to proceed with work. Each

Section 6RS table entry includes an identification of the action necessary and, if applicable, the estimated duration required for the resolution.

This represents the best information available to the Department and is included for the convenience of the bidder. The applicable portions of the Standard Specifications for Road and Bridge Construction shall apply.

The contractor may schedule a utility kickoff meeting and utility progress meetings between the Department, the Department’s contractor and the utility companies when necessary. The Department’s contractor is responsible for contacting J.U.L.I.E. prior to all excavation work.

UTILITIES TO BE ADJUSTED

The responsible agency must relocate or complete new installations as noted below for the Department’s contractor to then work in the said location:

OWNER TYPE DESCRIPTION LOCATION NOTES

AT&T Communication UG & OH fiber optic

N side of Service Rd; W side of Mill Rd north of Service Rd.

Relocation permit is pending R/W clear, work can commence work following ComEd’s relocation.

ComEd Electric Poles & OH lines

Poles in SE & NE quad US 20/Mill; W side of Mill Rd north of US 20

Relocation permitted, work in progress.

Comcast Communication UG fiber optic

N side of Service Rd; W side of Mill Rd south of Service Rd.

Relocation permitted, work in progress.

Syndeo Communication UG fiber optic

N side of Service Rd; W side of Mill Rd south of Service Rd.

Relocation permit pending

Frontier Communication UG copper cable

E side of Mill Rd north of US 20; W side of Mill Rd south of US 20; N side of Service Rd.

Relocation permit pending

Nicor Gas UG gas main

E side of Mill Rd north of Service Rd;

W side of Mill Rd south of Service Rd;

N side of Service Rd.

Relocation permit pending

Village of Cherry Valley Water main Abandoned in place

E side of Mill Rd north & south of US

See Attachment A for water main as-builts. The water

Section 6RS main north of 400+50 dead ends at 408+50 with no services and will be cut, capped, and abandoned in place.

The contractor may remove and scrap/salvage the main and the casing pipe under US 20 as needed. If the abandoned fire hydrant at 408+50 rt gets removed, please set it aside and contact the Village to pick it up.

Table information is up to date as of 1/28/26.

UTILITIES TO BE WATCHED AND PROTECTED

The areas of concern noted below have been identified, in addition to those noted on the plans, as utility facilities not being relocated for this contract. The information provided is not a comprehensive list of all remaining utilities, but those which during coordination were identified as ones which might require the Department’s contractor to take into consideration when making the determination of the means and methods that would be required to construct the proposed improvement. In some noted instances, the contractor will be responsible to notify the owner in advance of the work to take place so necessary staffing on the owner’s part can be secured.

LOCATION OWNER TYPE DESCRIPTION NOTES

Drainage str.

L303 (500+00 lt) AT&T Communication UG fiber optic

Existing facility runs along ROW line here.

407+20, 80’ rt ComEd & Frontier

Electric & communication

Pole, pedestal, post-mounted equipment

Existing above-ground fixtures to remain in place.

Contact utility to vertically adjust to new grade if needed.

Table information is up to date as of 1/28/26.

Section 6RS

UTILITY CONTACT INFORMATION

The following contact information is provided by the utilities specifically for this project:

Company Name of contact

Phone E-mail address Notes

AT&T Michael Wassom

(847) 345-mw3549@att.com AT&T project #

RE2122-3

ComEd Paul Casperson (630) 234-

Paul.casperson@comed.com ComEd project #

H27421ROC

Comcast Tom Yuccas (815) 509-thomas_yuccas@cable.comcast.com

Village of Cherry Valley

Andy Wesseln (815) 580-awesseln@cherryvalley.org

Syndeo Dan Halverson (815) 739-danh@syndeonetwork.com Company formerly known as Dekalb Fiber Optic

Frontier Paulo Javier (309) 820-

Paulo.t.javier@ftr.com

Nicor Karey Johnson (630) 388-karejohn@southernco.com Nicor project # N19325

AT&T

Legacy (fiber optic)

Ken Caudill (consultant KCI Technologies)

(240) 215-

Ken.caudill@kci.com No conflict: FO in SE corner of Mill & State, not in project limits

Four Rivers Sanitation Auth.

(sewer)

Kyle Gruhn (815) 621-kgruhn@fourrivers.illinois.gov No conflict: MH in NW corner of Mill & State adjusted under 64R71

ATTACHMENTS

• Attachment A: Water main as-builts

PCC AUTOMATIC BATCHING EQUIPMENT

Effective: January 1, 2015 Revised: January 31, 2023

Portland cement concrete provided shall be produced from batch plants that conform to the requirements of Article 1103.03 (a) and (b) of the Standard Specifications for Road and Bridge Construction. Semi-automatic batching will not be allowed.

Plants shall have computerized batching interfaced with a printer. IDOT Producer Number, IDOT Design Number, Concrete Material Code, batch weights, aggregate mixtures, water added, amount of each admixture or additive, and percent variance from design shall be printed for each batch. Tickets shall state the actual water-cement ratio as batched, and the amount of water that can be added to the batch without exceeding the maximum water-cement ratio. Truck delivery tickets are still required as per Article 1020.11(a)(7) of the Standard Specifications.

Section 6RS

PCC QC/QA ELECTRONIC REPORTS SUBMITTAL

Effective: January 1, 2015 Revised: January 31, 2023

The Contractor’s QC personnel shall be responsible for electronically submitting the following reports to the Department: PRO and IND data for BMPR MI654 “Concrete Air, Slump, and Quantity,”; PRO data for BMPR MI655 “P.C. Concrete Strength,” and PRO data for BMPR MI504 “Aggregate Gradation” reports to the Department. The format for the electronic submittals shall be the QMP package reporting program, which will be provided by the Department. Microsoft Excel 2007 or newer and Microsoft Outlook is required for this program which shall be provided by the Contractor.

TRAFFIC CONTROL PLAN

Effective: January 14, 1999 Revised: January 13, 2017

Traffic Control shall be according to the applicable sections of the Standard Specifications for Road and Bridge Construction, the applicable guidelines contained in the National Manual on Uniform Traffic Control Devices for Streets and Highways, Illinois Supplement to the National Manual on Uniform Traffic Control Devices, these special provisions, and any special details and Highway Standards contained herein and in the Plans.

Special attention is called to Articles 107.09 and 107.14 of the Standard Specifications for Road and Bridge Construction and the following Highway Standards relating to traffic control along with the Bureau of Local Roads and Streets special provisions for the construction and maintenance of signs.

Standards:

701001 701006 701201 701206 701301 701306

701326 701331 701501 701701 701901 704001

Details:

• Staging Plans

• District Standard WORK ZONE SIGN DETAILS (DIST STD. 34.1)

• District Standard TRAFFIC CONTROL FOR ROAD CLOSURE (DIST STD. 40.1)

Signs:

When covering existing Department signs, no tape shall be used on the reflective portion of the sign. Contact the District sign shop for covering techniques.

Any plates or direct applied sheeting used to alter signs shall have the same sheeting as the base sign.

Section 6RS

No more than one kind of alteration shall be used to alter a sign.

Any post stubs without a sign in place and visible shall have a reflector placed on each post.

No bracing shall be allowed on post-mounted signs.

Flaggers:

Flaggers shall comply with all requirements and signaling methods contained in the Department’s “Traffic Control Field Manual” current at the time of letting. The flagger equipment listed for flaggers employed by the Illinois Department of Transportation shall apply to all flaggers.

In addition to the flaggers shown on applicable standards, on major sideroads, flaggers shall be required on all legs of the Mill Road & US 20 intersection.

When the mainline flagger is within 200 feet of an intersection, the sideroad flagger shall be required.

When the road is closed to through traffic and it is necessary to provide access for local traffic, all flaggers as shown on the applicable standards will be required. No reduction in the number of flaggers shall be allowed.

Pavement Marking:

All temporary pavement markings that will be operational during the winter months (December through March) shall be Paint.

Temporary pavement markings shall be paid for separately at the contract unit prices of specified temporary pavement marking items.

Changeable Message Signs:

A changeable message sign shall be in place for a minimum of 2 weeks (14 calendar days) prior to the start of work, for a stage switch, for a major change in traffic patterns, and prior to beginning construction. Locations for change in traffic patterns are to be determined by the engineer.

A changeable message sign shall be in place for a minimum of 1 week (7 calendar days) prior to nighttime full closures for overhead beam removal and/or setting and overhead sign truss placement or removal and sign installation or removal. Locations are to be determined by the Engineer. The message boards shall state location of work.

This work will be paid for at the Contract Unit Price per Calendar Day for Changeable Message Sign.

Highway Standards Application:

Traffic Control and Protection, Standard 701701:

This work shall be done according to Section 701 of the Standard Specifications and the Typical Application of Traffic Control Devices for Highway Construction, Standard 701701, and as specified herein.

Section 6RS

The “left” leg of the intersection shown on this standard also applies when the right turn lane is closed. When the right turn lane is closed, “RIGHT TURN LANE CLOSED AHEAD” shall be substituted for the LEFT TURN LANE CLOSED AHEAD” and the set up would be a mirror image to…