- HMA Resurfacing on George Street from North Avenue (IL 64 to the North Village Limit of Melrose Park
- Solicitation number
- 61M63
- Issued by
- Cook County, Illinois
About this file
This is a Notice to Bidders and Specifications document issued by the Illinois Department of Transportation (IDOT) for Contract No. 61M63, a construction project in Cook County involving the Village of Melrose Park. The project consists of hot mix asphalt surface removal, curb and gutter replacement, sidewalk and driveway improvements, storm sewer and drainage structure installation, 12-inch ductile iron water main installation, HMA binder and surface courses, pavement markings, and parkway restoration on George Street from North Avenue (IL 64) to the north village limit (CN Railroad), totaling 3,305 feet (0.626 miles). Electronic bids must be submitted to the iCX system prior to 12:00 p.m. on September 18, 2026, at which time bids will be publicly opened. The project is staged into four construction phases to maintain traffic flow and business access, with anticipated completion by October 31, 2027. Construction activities are limited to 7 a.m. to 7 p.m. Monday through Friday, 8 a.m. to 5 p.m. on Saturdays, and 10 a.m. to 5 p.m. on Sundays and holidays per Village Ordinance No. 959.
The contract will be awarded to the lowest responsive and responsible bidder in accordance with IDOT specifications, standard provisions, supplemental specifications, and recurring special provisions. Utility adjustments by NICOR, ComEd, and Crosstown Fiber are required during the pre-stage and will take approximately 50 days total. The contractor assumes responsibility for normal maintenance of roadways within the project limits, must maintain pedestrian and emergency vehicle access throughout construction, and is responsible for traffic control and protection. All excavations must be backfilled or plated over at the end of each workday. The project is funded as a District 1 Construction project and is subject to federal-aid requirements, including compliance with prevailing wage, EEO, and DBE participation provisions. The contractor must submit payroll records, maintain quality assurance protocols for concrete and hot-mix asphalt, and coordinate with utility companies and the Village throughout construction.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Letting September 18, 2026
Notice to Bidders, Specifications and Proposal
Contract No. 61M63 COOK County Section 24-00145-00-CH (Melrose Park) Route FAU 1672 (George Street) Project B765-682 () District 1 Construction Funds
Prepared by F
Checked by
(Printed by authority of the State of Illinois)
NOTICE TO BIDDERS
1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.
September 18, 2026 at which time the bids will be publicly opened from the iCX SecureVault.
2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the
Invitation for Bids as:
Contract No. 61M63 COOK County Section 24-00145-00-CH (Melrose Park) Project B765-682 () Route FAU 1672 (George Street) District 1 Construction Funds
HMA resurfacing on George Street from North Avenue (IL 64 to the north village limit of Melrose Park.
Includes curb & gutter, sidewalk, water main installation and pavement markings.
3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.
(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.
4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.
By Order of the Illinois Department of Transportation
Gia Biagi, Secretary
CONTRACT 61M63
INDEX
FOR
SUPPLEMENTAL SPECIFICATIONS
AND RECURRING SPECIAL PROVISIONS
Adopted January 1, 2026
This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.
ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)
SUPPLEMENTAL SPECIFICATIONS
Std. Spec. Sec. Page No.
109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires
1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment
RECURRING SPECIAL PROVISIONS
The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:
CHECK SHEET # PAGE NO.
1 Additional State Requirements for Federal-Aid Construction Contracts 2 Subletting of Contracts (Federal-Aid Contracts)
3 EEO
4 Specific EEO Responsibilities Non Federal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos HMA Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 Construction Layout Stakes
10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays
LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS
Table of Contents
CHECK SHEET # PAGE NO.
LRS 1 Reserved LRS 2 Furnished Excavation LRS 3 Work Zone Traffic Control Surveillance LRS 4 Flaggers in Work Zones LRS 5 Contract Claims LRS 6 Bidding Requirements and Conditions for Contract Proposals LRS 7 Bidding Requirements and Conditions for Material Proposals LRS 8 Reserved LRS 9 Bituminous Surface Treatments LRS 10 Reserved LRS 11 Employment Practices LRS 12 Wages of Employees on Public Works LRS 13 Selection of Labor LRS 14 Paving Brick and Concrete Paver Pavements and Sidewalks LRS 15 Partial Payments LRS 16 Protests on Local Lettings LRS 17 Substance Abuse Prevention Program LRS 18 Multigrade Cold Mix Asphalt LRS 19 Reflective Crack Control Treatment
TABLE OF CONTENTS
ITEM PAGE
i
LOCATION OF PROJECT ---------------------------------------------------------------------------------------------------------------------------------- 1 DESCRIPTION OF PROJECT ----------------------------------------------------------------------------------------------------------------------------- 1 PROJECT STAGING AND LOCAL ACCESS --------------------------------------------------------------------------------------------------------- 1 LIMITATION OF OPERATIONS --------------------------------------------------------------------------------------------------------------------------- 3 MAINTENANCE OF ROADWAYS (D1) ----------------------------------------------------------------------------------------------------------------- 3 STATUS OF UTILITIES (D-1) ------------------------------------------------------------------------------------------------------------------------------ 3 UTILITIES TO BE ADJUSTED ---------------------------------------------------------------------------------------------------------------------------- 3 UTILITIES TO BE WATCHED AND PROTECTED--------------------------------------------------------------------------------------------------- 5 OPEN EXCAVATIONS--------------------------------------------------------------------------------------------------------------------------------------- 7 SHEETING AND SHORING -------------------------------------------------------------------------------------------------------------------------------- 7 CURING AND PROTECTION ------------------------------------------------------------------------------------------------------------------------------ 7 CURB AND GUTTER TRANSITIONS ------------------------------------------------------------------------------------------------------------------- 7 AGGREGATE BEDDING FOR CONCRETE WORK ------------------------------------------------------------------------------------------------ 8 INLET FILTERS------------------------------------------------------------------------------------------------------------------------------------------------ 8 MAINTENANCE OF EXISTING DRAINAGE STRUCTURES ------------------------------------------------------------------------------------- 9 EARTH EXCAVATION --------------------------------------------------------------------------------------------------------------------------------------- 9 HOT-MIX ASPHALT SURFACE REMOVAL, 4” ------------------------------------------------------------------------------------------------------ 9 HOT-MIX ASPHALT SURFACE REMOVAL – BUTT JOINT ------------------------------------------------------------------------------------ 11 INCIDENTAL HOT-MIX ASPHALT SURFACING -------------------------------------------------------------------------------------------------- 11 HOT-MIX ASPHALT SURFACE REMOVAL (SPECIAL) ----------------------------------------------------------------------------------------- 12 PROTECTIVE COAT --------------------------------------------------------------------------------------------------------------------------------------- 12 DETECTABLE WARNINGS ------------------------------------------------------------------------------------------------------------------------------ 13 PAVEMENT REMOVAL (SPECIAL) ------------------------------------------------------------------------------------------------------------------- 13 DRIVEWAY PAVEMENT REMOVAL ------------------------------------------------------------------------------------------------------------------ 14 COMBINATION CURB AND GUTTER REMOVAL ------------------------------------------------------------------------------------------------ 14 TOPSOIL FURNISH AND PLACE, 3” ----------------------------------------------------------------------------------------------------------------- 15 SIDEWALK REMOVAL ----------------------------------------------------------------------------------------------------------------------------------- 15 DUCTILE IRON WATER MAIN -------------------------------------------------------------------------------------------------------------------------- 16 WATER VALVES -------------------------------------------------------------------------------------------------------------------------------------------- 17 VALVE BOX -------------------------------------------------------------------------------------------------------------------------------------------------- 17 FIRE HYDRANTS TO BE REMOVED ----------------------------------------------------------------------------------------------------------------- 17 FIRE HYDRANT WITH AUXILIARY VALVE AND VALVE BOX ------------------------------------------------------------------------------- 18 FRAMES AND LIDS TO BE ADJUSTED ------------------------------------------------------------------------------------------------------------- 19 MANHOLES TO BE RECONSTRUCTED ------------------------------------------------------------------------------------------------------------ 20 FRAMES AND LIDS, TYPE I ----------------------------------------------------------------------------------------------------------------------------- 20 CATCH BASINS, MANHOLES, VALVE VAULTS, TYPE A, TYPE 1 FRAME, LID ------------------------------------------------------- 22 COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.12 (MODIFIED) --------------------------------------------------------- 23 COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.12 (SPECIAL) ----------------------------------------------------------- 24 PORTLAND CEMENT CONCRETE DRIVEWAY PAVEMENT, 8” ---------------------------------------------------------------------------- 24 AGGREGATE SURFACE COURSE FOR TEMPORARY ACCESS (D1) -------------------------------------------------------------------- 25 TRAFFIC CONTROL PLAN (D1) ----------------------------------------------------------------------------------------------------------------------- 26 ii
TRAFFIC CONTROL AND PROTECTION (ARTERIALS) (D1)--------------------------------------------------------------------------------- 27 SIGN REMOVAL -------------------------------------------------------------------------------------------------------------------------------------------- 28 DRAINAGE STRUCTURE TO BE REMOVED ------------------------------------------------------------------------------------------------------ 29 DUST CONTROL WATERING--------------------------------------------------------------------------------------------------------------------------- 29 TEMPORARY INFORMATION SIGNING ------------------------------------------------------------------------------------------------------------- 30 DUCTILE IRON WATER MAIN FITTINGS ----------------------------------------------------------------------------------------------------------- 31 WATER MAIN CONNECTION/DISCONNECTION (SHUTDOWN) ---------------------------------------------------------------------------- 31 RESTRICTED DEPTH CATCH BASINS, MANHOLES, TYPE 1 FRAME, LID ------------------------------------------------------------- 32 PRESSURE TESTING AND DISINFECTION -------------------------------------------------------------------------------------------------------- 33 RESTRAINED JOINT -------------------------------------------------------------------------------------------------------------------------------------- 34 SANITARY SEWER PVC, 6”----------------------------------------------------------------------------------------------------------------------------- 34 STORM SEWERS, CLASS B, TYPE 2 ---------------------------------------------------------------------------------------------------------------- 35 STORM SEWERS, CLASS A, TYPE 2 ---------------------------------------------------------------------------------------------------------------- 35 STORM SEWERS, DUCTILE IRON -------------------------------------------------------------------------------------------------------------------- 36 REMOVE EXISTING VALVE AND VAULT ----------------------------------------------------------------------------------------------------------- 36 SUPPLEMENTAL WATERING -------------------------------------------------------------------------------------------------------------------------- 37 EXPLORATORY EXCAVATION ------------------------------------------------------------------------------------------------------------------------ 38 VALVE VAULTS, TYPE A, 4’-DIAMETER, TYPE 1 FRAME, CLOSED LID ---------------------------------------------------------------- 38 RAILROAD TRACK REMOVAL------------------------------------------------------------------------------------------------------------------------- 39 COILABLE NON-METALLIC CONDUIT -------------------------------------------------------------------------------------------------------------- 40 TRENCH BACKFILL --------------------------------------------------------------------------------------------------------------------------------------- 40 PRESSURE CONNECTION, 12”X12” ----------------------------------------------------------------------------------------------------------------- 41 24” x 8” PVC SEWER SERVICE CONNECTION -------------------------------------------------------------------------------------------------- 42 36” x 8” PVC SEWER SERVICE CONNECTION -------------------------------------------------------------------------------------------------- 43 PUBLIC CONVENIENCE AND SAFETY (D1) ------------------------------------------------------------------------------------------------------- 43 ADJUSTMENTS AND RECONSTRUCTIONS (D1) ------------------------------------------------------------------------------------------------ 44 DRAINAGE AND INLET PROTECTION UNDER TRAFFIC (D-1) ----------------------------------------------------------------------------- 45 FRICTION AGGREGATE (D1)--------------------------------------------------------------------------------------------------------------------------- 47 HOT-MIX ASPHALT – MIXTURE DESIGN VERIFICATION AND PRODUCTION (D-1) ------------------------------------------------- 49 HOT-MIX ASPHALT BINDER AND SURFACE COURSE (D1) -------------------------------------------------------------------------------- 50 MINERALIZED CARBON DIOXIDE CONCRETE (D-1)------------------------------------------------------------------------------------------- 59 SIGN SHOP DRAWING SUBMITTAL ----------------------------------------------------------------------------------------------------------------- 60 REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (PROJECT SPECIFIC) ----------------------------------------------- 60 TRAFFIC SIGNAL GENERAL REQUIREMENTS -------------------------------------------------------------------------------------------------- 62 ELECTRIC CABLE ----------------------------------------------------------------------------------------------------------------------------------------- 77 CONCRETE FOUNDATIONS ---------------------------------------------------------------------------------------------------------------------------- 77 RELOCATE EXISTING TRAFFIC SIGNAL EQUIPMENT ---------------------------------------------------------------------------------------- 77 REMOVE EXISTING TRAFFIC SIGNAL EQUIPMENT ------------------------------------------------------------------------------------------- 78 TEMPORARY TRAFFIC SIGNAL TIMING ----------------------------------------------------------------------------------------------------------- 79 FAILURE TO COMPLETE PLANT CARE AND ESTABLISHMENT WORK ON TIME--------------------------------------------------- 79 REBUILD EXISTING HANDHOLE---------------------------------------------------------------------------------------------------------------------- 80 iii
MODIFY EXISTING CONTROLLER CABINET ----------------------------------------------------------------------------------------------------- 81 GENERAL ELECTRICAL REQUIREMENTS -------------------------------------------------------------------------------------------------------- 82 MAINTENANCE OF LIGHTING SYSTEM ------------------------------------------------------------------------------------------------------------ 99 WIRE AND CABLE --------------------------------------------------------------------------------------------------------------------------------------- 102 UNIT DUCT ------------------------------------------------------------------------------------------------------------------------------------------------- 103 ELECTRIC SERVICE INSTALLATION AND CONNECTION --------------------------------------------------------------------------------- 105 UNDERGROUND RACEWAYS ----------------------------------------------------------------------------------------------------------------------- 106 ROADWAY LUMINAIRE, LED------------------------------------------------------------------------------------------------------------------------- 107 LIGHT POLE BREAKAWAY DEVICE --------------------------------------------------------------------------------------------------------------- 116 PROTECTION OF EXISTING TREES --------------------------------------------------------------------------------------------------------------- 119 TEMPORARY SIDEWALK------------------------------------------------------------------------------------------------------------------------------ 122 FRAMES AND LIDS TO BE ADJUSTED (SPECIAL) ------------------------------------------------------------------------------------------- 123 CONCRETE TRUCK WASHOUT --------------------------------------------------------------------------------------------------------------------- 123 INDUSTRIAL WATER MAIN CONNECTION ------------------------------------------------------------------------------------------------------ 124 UNIT DUCT FOR LIGHTING --------------------------------------------------------------------------------------------------------------------------- 124 COMPLETION DATE PLUS WORKING DAYS (D1) -------------------------------------------------------------------------------------------- 125 AVAILABLE REPORTS --------------------------------------------------------------------------------------------------------------------------------- 126 IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING SPECIAL PROVISION -------------------------------------- 127
LR107-4 SPECIAL PROVISION FOR INSURANCE
LR1030-2 LOCAL QUALITY ASSURANCE/QUALITY MANAGEMENT QC/QA
IEPA PUBLIC WATER SUPPLY CONSTRUCTION PERMIT
IEPA NPDES PERMIT
MWRD NOTIFICATION AND REQUEST FOR INSPECTION (NRI)
CANADIAN NATIONAL RIGHT OF ENTRY INFORMATION
LPC 663 IEPA UNCONTAMINATED SOIL CERTIFICATION
BDE SPECIAL PROVISIONS
The following special provisions indicated by an “X” are applicable to this contract. An * indicates a new or revised special provision for the letting.
File Name Pg. Special Provision Title Effective Revised 80099 Accessible Pedestrian Signals (APS) April 1, 2003 Jan. 1, 2022 _ 80274 Aggregate Subgrade Improvement April 1, 2012 April 1, 2022 80192 Automated Flagger Assistance Device Jan. 1, 2008 April 1, 2023 80173 Bituminous Materials Cost Adjustments Nov. 2, 2006 Aug. 1, 2017 80426 Bituminous Surface Treatment with Fog Seal Jan. 1, 2020 April 1, 2026 80475 Bridge Deck Concrete Overlays Jan. 1, 2026 80241 Bridge Demolition Debris July 1, 2009
5053I Building Removal Sept. 1, 1990 Aug. 1, 2022 5026I Building Removal with Asbestos Abatement Sept. 1, 1990 Aug. 1, 2022
80460 143 Cement, Finely Divided Minerals, Admixtures, Concrete, and Mortar Jan. 1, 2025 Jan. 1, 2026 80384 160 Compensable Delay Costs June 2, 2017 April 1, 2019 80198 Completion Date (via calendar days) April 1, 2008 80199 Completion Date (via calendar days) Plus Working Days April 1, 2008 80461 Concrete Barrier Jan. 1, 2025 80453 Concrete Sealer Nov. 1, 2023 80261 164 Construction Air Quality – Diesel Retrofit June 1, 2010 Jan. 1, 2025 80476 Deck Slab Repair Jan. 1, 2026
* 80029 166 Disadvantaged Business Enterprise Participation Sept. 1, 2000 July 2, 2026 80467 Erosion Control Blanket Aug. 1, 2025 80229 Fuel Cost Adjustment April 1, 2009 Aug. 1, 2017 80452 Full Lane Sealant Waterproofing System Nov. 1, 2023 80433 Green Preformed Thermoplastic Pavement Markings Jan. 1, 2021 Jan. 1, 2022 80471 Guardrail Nov. 1, 2025 80472 High Friction Surface Treatment Nov. 1, 2025 80456 Hot-Mix Asphalt Jan. 1, 2024 April 1, 2026 80446 Hot-Mix Asphalt – Longitudinal Joint Sealant Nov. 1, 2022 Aug. 1, 2023 80438 Illinois Works Apprenticeship Initiative – State Funded Contracts June 2, 2021 April 2, 2024 80483 170 Inlet Filters April 1, 2026
* 80477 Longitudinal Tining Jan. 1, 2026 July 1, 2026 80450 Mechanically Stabilized Earth Retaining Walls Aug. 1, 2023 Aug. 1, 2025 80478 Modified Longitudinal Construction Joint Jan. 1, 2026 80464 172 Pavement Marking April 1, 2025 Nov. 1, 2025 80468 173 Pavement Patching Aug. 1, 2025 80441 174 Performance Graded Asphalt Binder Jan 1, 2023 April 1, 2026 80459 Preformed Plastic Pavement Marking June 2, 2024 3426I 180 Railroad Protective Liability Insurance Dec. 1, 1986 Jan. 1, 2022 80473 181 Raised Reflective Pavement Markers Nov. 1, 2025 80455 182 Removal and Disposal of Regulated Substances Jan. 1, 2024 April 1, 2026 80474 Residential Driveway Temporary Signal Nov. 1, 2025
* 80445 Seeding Nov. 1, 2022 July 1, 2026 80457 184 Short Term and Temporary Pavement Markings April 1, 2024 April 2, 2024 80462 188 Sign Panels and Appurtenances Jan. 1, 2025 Jan. 1, 2026 80479 Sinusoidal Rumble Strips Jan. 1, 2026 80469 Slope Wall Aug. 1, 2025 80448 190 Source of Supply and Quality Requirements Jan. 2, 2023 Jan. 1, 2026 80340 Speed Display Trailer April 2, 2014 Jan. 1, 2022 80127 Steel Cost Adjustment April 2, 2004 Nov. 1, 2025 80480 Structural Repair of Concrete Jan. 1, 2026 80397 192 Subcontractor and DBE Payment Reporting April 2, 2018 80391 193 Subcontractor Mobilization Payments Nov. 2, 2017 April 1, 2019 80463 194 Submission of Bidders List Information Jan. 2, 2025 Mar. 2, 2025
File Name Pg. Special Provision Title Effective Revised 80482 195 Submission of Payroll Records – Federal Aid Contract April 1, 2026 80437 Submission of Payroll Records – State Contract April 1, 2021 April 1, 2026 80435 Surface Testing of Pavements – IRI Jan. 1, 2021 Jan. 1, 2023 80465 197 Surveying Services April 1, 2025 80481 198 Temporary Concrete Barrier Jan. 1, 2026 80466 Temporary Rumble Strips April 1, 2025
* 80484 Tolerance in Thickness for Continuously Reinforced PCC Pavement July 1, 2026 80470 Traffic Signal Backplate Aug. 1, 2025 20338 199 Training Special Provisions Oct. 15, 1975 Sept. 2, 2021 80429 Ultra-Thin Bonded Wearing Course April 1, 2020 Jan. 1, 2022 80439 202 Vehicle and Equipment Warning Lights Nov. 1, 2021 Nov. 1, 2022 80458 Waterproofing Membrane System Aug. 1, 2024 80302 203 Weekly DBE Trucking Reports June 2, 2012 Jan. 2, 2025 80454 Wood Sign Support Nov. 1, 2023 80427 204 Work Zone Traffic Control Devices Mar. 2, 2020 Jan. 1, 2026
* 80485 207 Work Zone Width Restriction July 1, 2026 80071 Working Days Jan. 1, 2002
GEORGE STREET
JOB NUMBER: C-91-127-25
SECTION NO. 24-00145-00-CH
VILLAGE OF MELROSE PARK
COOK COUNTY
STATE OF ILLINOIS
SPECIAL PROVISIONS
The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction", adopted January 1, 2022, herein referred to as the Standard Specifications, the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways", and the "Manual of Test Procedures of Materials" in effect on the date of invitation of bids, and the Supplemental Specification and Recurring Special Provisions indicated on the Check Sheet included here in which apply to and govern the construction of the above named section, and in case of conflict with any parts, or parts of said Specifications, the said Special Provisions shall take precedence and shall govern the construction of:
GEORGE STREET
JOB NUMBER C-91-127-25
SECTION NO. 24-00145-00-CH
VILLAGE OF MELROSE PARK
COOK COUNTY
CONTRACT NO. 61M63
LOCATION OF PROJECT
The project is located on George Street beginning at North Avenue (IL 64) (Station 1+40) and ending at the north Village limit (CN Railroad) (Station 34+45) for a total net length of 3,305 feet (0.626 miles) within the Village of Melrose Park in Cook County, Illinois.
DESCRIPTION OF PROJECT
This work consists of the hot mix asphalt surface removal; removal and replacement of curb and gutter, driveway aprons, and sidewalk; installation of storm sewer and drainage structures; installation of a 12” ductile iron water main, hot-mix asphalt (HMA) binder & surface, pavement marking, restoring disturbed parkways with topsoil and sod and all other appurtenant work necessary to complete the project as shown on the plans and described herein.
PROJECT STAGING AND LOCAL ACCESS
During the construction of the project George Street will remain accessible to businesses needing to enter their driveways, as well as emergency vehicles. The construction is planned to be broken up into four stages. Southbound George Street traffic will be detoured around the site for the duration of the project. The Contractor will be required to adhere to the following staging plan:
Stage 0 Construction – During this stage, temporary sidewalk and sidewalk ramps will be constructed necessary to maintain pedestrian access during Stage 1. Both northbound and southbound George Street traffic will be maintained with all work occurring outside the limits of the existing roadway.
Stage 1 Construction - During this stage, the underground improvements, surface milling and binder installation, concrete improvements, traffic signal work, and parkway restoration shall be constructed on the west side of George Street. Northbound traffic will be allowed on the east side of George Street from North Avenue to Armitage Avenue utilizing a temporary pavement that shall be constructed before Stage 1. Southbound traffic will not be allowed from North Avenue to Armitage Avenue and will have to follow the detour to access North Avenue. Two-way traffic will be permitted north of Armitage Avenue. Temporary southbound traffic road closures, traffic control, and temporary pavement markings will be necessary to construct these improvements as shown on the plans.
SECTION NO. 24-00145-00-CH
VILLAGE OF MELROSE PARK
Storm sewer installation shall be completed before water main installation to avoid water main conflicts with proposed sewers. Storm sewer laterals that cross the northbound lane shall be constructed during this stage with flagging operations to maintain northbound traffic with minimum traffic impacts. At the end of the construction day, trenches that cross the George Street northbound lane shall be capped with hot mix asphalt binder. The hot mix asphalt will be included in the cost for TEMPORARY PAVEMENT.
Temporary access to businesses shall be maintained. Various commercial driveways shall be completed in stages to maintain access. Access to driveways will be interrupted at various times and interruptions shall be coordinated with businesses 48 hours in advance of any work that will impact driveway access. Once driveway access has been removed, the contractor shall restore access in 10 calendar days with new concrete improvements. The gap between the new curb and the existing pavement shall be filled with concrete that is set four and a quarter inch (4 1/4”) below the curb edge of pavement and shall then be capped with temporary aggregate to restore access to properties. Temporary aggregate will be paid under the TEMPORARY ACCESS (COMMERCIAL ENTRANCE) item. During underground improvements, all access to driveways is to be restored at the end of the day. On-street parking will be prohibited during this stage.
The contractor will be required to remove or bag any non-applicable existing signage during this stage.
It is anticipated that multiple construction crews will be needed to work simultaneously on different parts of the project to complete stage 1 and the project overall, within the contract working days.
Stage 2 Construction - During this stage, service drive removal and restoration, pavement widening construction, surface milling and binder installation, concrete improvements, lighting improvements, traffic signal work, and parkway restoration will be constructed on the east side of George Street. Northbound traffic will be allowed on the west side of George Street from North Avenue to Armitage Avenue. Southbound traffic will not be allowed from North Avenue to Armitage Avenue and will have to follow the detour to access North Avenue. Two-way traffic will be allowed north of Armitage Avenue. Temporary southbound traffic road closures, temporary pavement markings, and traffic control will be necessary to construct these improvements as shown on the plans.
Temporary access to businesses shall be maintained. Various commercial driveways will be completed in stages to maintain access. Access to driveways will be interrupted at various times and interruptions shall be coordinated with businesses 48 hours in advance of any work that will impact driveway access. Once driveway access has been removed, the contractor shall restore access within 10 calendar days with new concrete improvements. The gap between the new curb and the existing pavement shall be filled with concrete that is set four and one quarter inches (4 1/4”) below the curb edge of pavement and shall then be capped with temporary aggregate to restore access to properties. During underground improvements, all access to driveways is to be restored by the end of the day. On-street parking will be prohibited during this stage. The contractor will be required to remove or bag any non-applicable existing signage during this stage.
Any work required on the west side of George Street during this stage will utilize flagging operations to maintain northbound traffic with minimum traffic impacts.
SECTION NO. 24-00145-00-CH
VILLAGE OF MELROSE PARK
It is anticipated that multiple construction crews will be needed to work simultaneously on different parts of the project to complete stage 2 and the project overall, within the contract working days.
Stage 3 Construction – During this stage, two-way traffic will be allowed on George Street. Work completed during this stage will utilize flagging operations to maintain two-way traffic. This stage will consist of frame and lid adjustments within the roadway pavement, pouring concrete around those frames, final parkway restoration, paving the final hot-mix asphalt surface course for the entire length of the project, and pavement markings. Frame and lid adjustments shall be completed in stages to always allow for two-way traffic.
LIMITATION OF OPERATIONS
Per Village Ordinance No. 959, construction activities shall occur between 7am and 7pm Monday through Friday, 8am and 5pm on Saturdays, and 10am and 5pm on Sundays and holidays.
Contractors shall schedule work in such a manner to accommodate weather dependent items and specialty items in accordance with the overall desired completion date of October 31, 2027.
Furthermore, cut sheets for proprietary items with long lead-times shall be submitted for review as soon as the contract is executed.
MAINTENANCE OF ROADWAYS (D1)
Effective: September 30, 1985 Revised: November 1, 1996
Beginning on the date that work begins on this project, the Contractor shall assume responsibility for normal maintenance of all existing roadways within the limits of the improvement. This normal maintenance shall include all repair work deemed necessary by the Engineer but shall not include snow removal operations. Traffic control and protection for maintenance of roadways will be provided by the Contractor as required by the Engineer.
If items of work have not been provided in the contract, or otherwise specified for payment, such items, including the accompanying traffic control and protection required by the Engineer, will be paid for in accordance with Article 109.04 of the Standard Specifications.
STATUS OF UTILITIES (D-1)
Effective: June 1, 2016 Revised: January 1, 2020
Utility companies and/or municipal owners located within the construction limits of this project have provided the following information regarding their facilities and the proposed improvements. The tables below contain a description of specific conflicts to be resolved and/or facilities which will require some action on the part of the Department’s contractor to proceed with work. Each table entry includes an identification of the action necessary and, if applicable, the estimated duration required for the resolution.
UTILITIES TO BE ADJUSTED
Conflicts noted below have been identified by following the suggested staging plan included in the contract. The company has been notified of all conflicts and will be required to obtain the necessary permits to complete their work; in some instances, resolution will be a function of the construction staging. The responsible agency must relocate, or complete new installations as noted below; this
SECTION NO. 24-00145-00-CH
VILLAGE OF MELROSE PARK
work has been deemed necessary to be complete for the Department’s contractor to then work in the stage under which the item has been listed.
Pre-Stage
STAGE /
LOCATION TYPE DESCRIPTION RESPONSIBLE
AGENCY
DURATION OF
TIME
Station 1+95 Gas Line Existing Gas Main to be adjusted NICOR 10 Day Installation
Station 2+50 Gas Line Existing Gas Main to be adjusted NICOR 10 Day Installation
Station 14+93 Gas Line Existing Gas Main to be adjusted NICOR 10 Day Installation
Station 14+00 Utility Pole Existing Utility Pole at Bloomingdale ComEd 10 Day Installation
Station 1+55 Communications Existing Handhole to be adjusted Crosstown Fiber 10 Day Installation
Stage 1 No conflicts to be resolved.
Stage 2 No conflicts to be resolved.
Pre-Stage:___50__ Days Total Installation Stage 1: ____0____ Days Total Installation Stage 2: ____0 __ Days Total Installation
The following contact information is what was used during the preparation of the plans as provided by the Agency/Company responsible for resolution of the conflict.
SECTION NO. 24-00145-00-CH
VILLAGE OF MELROSE PARK
Agency/Company Responsible to Resolve
Conflict Name of Contact Phone E-mail address
Nicor
Karey Johnson 224-471-9356 gasmaps@southernco.com karejohn@southernco.com
Crosstown Fiber Thomas Philbin 773-910-7065 tphilbin@crosstownfiber.com
ComEd Lisa Argast 708-277-8511 PlanSubmittalsandMapRequests @exeloncorp.com
UTILITIES TO BE WATCHED AND PROTECTED
The areas of concern noted below have been identified by following the suggested staging plan included for the contract. The information provided is not a comprehensive list of all remaining utilities, but those which during coordination were identified as ones which might require the Department’s contractor to take into consideration when making the determination of the means and methods that would be required to construct the proposed improvement. In some instances, the contractor will be responsible to notify the owner in advance of the work to take place so necessary staffing on the owner’s part can be secured.
Stage 1 through 2
STAGE /
LOCATION TYPE DESCRIPTION OWNER Action
Station 1+40 and Station 34+45
Overhead Lines
Existing Overhead wire lines that cross George Street
ComEd, AT&T
Contractor shall be attentive and work carefully when construction equipment is near overhead lines.
Station 2+36, 3+66, 4+44, 4+81, 6+86, 6+96, 8+73, 9+27, 11+58, 12+77, 13+38, 15+84, 17+64, 19+46, 22+80, 26+28, 27+85, and 29+49
Utility Poles Existing Utility Poles along George Street ComEd Temporary bracing is required.
Station 12+70 Underground Lines
Existing Underground wire line that crosses George Street
ComEd
Contractor shall be attentive and work carefully when construction equipment is near underground lines.
SECTION NO. 24-00145-00-CH
VILLAGE OF MELROSE PARK
The above represents the best information available to the Department and is included for the convenience of the bidder. The days required for conflict resolution should be considered in the bid as this information has also been factored into the timeline identified for the project when setting the completion date. The applicable portions of the Standard Specifications for Road and Bridge Construction shall apply.
Estimated duration of time provided above for the first conflicts identified will begin on the date of the executed contract regardless of the status of the utility relocations. The responsible agencies will be working toward resolving subsequent conflicts in conjunction with contractor activities in the number of days noted.
The estimated relocation duration must be part of the progress schedule submitted by the contractor. A utility kickoff meeting will be scheduled between the Department, the Department’s contractor and the utility companies when necessary. The Department’s contractor is responsible for contacting J.U.L.I.E.
prior to all excavation work.
Agency/Company Responsible to
Resolve Conflict
Name of contact
Address Phone E-mail address
AT&T Tim Lapointe
1000 Commerce Drive, 2nd Floor Oak Brook, IL 60523
(630) 573-5687 Tl0695@att.com
Comcast Martha Gieras
688 Industrial Drive, Elmhurst, IL 60126
(224) 229-5862
Martha_Gieras@comcast.c om
ComEd Lisa
Argast
3 Lincoln Centre, Suite 600 Oakbrook Terrace, IL, 60181
(708) 277-8511
PlanSubmittalsandMapReq uests@exeloncorp.com
Nicor Karey
Johnson
1844 Ferry Rd, Naperville, IL 60563 (224)
471-9356 gasmaps@southernco.com karejohn@southernco.com
Verizon John Buher
(630) 675-3794 john.buher@verizon.com
Crosstown Fiber Thomas Philbin
333 Butterfield Road, Suite 120, Lombard, IL 60148
(773) 910-7065 tphilbin@crosstownfiber.co m
AT&T Tim Lapointe
1000 Commerce Drive, 2nd Floor Oak Brook, IL 60523
(630) 573-5687 Tl0695@att.com
SECTION NO. 24-00145-00-CH
VILLAGE OF MELROSE PARK
OPEN EXCAVATIONS
Leaving any excavation open overnight will not be allowed on this project. The Contractor will be responsible for completely backfilling or plating over of all excavations at the end of each day. If the excavations are backfilled, they shall be filled with an aggregate meeting the gradation of CA-6. The material will be compacted sufficiently to prevent rutting or settlement of material under traffic loads. If plates are used, they shall be of sufficient thickness to support vehicular loads and they shall extend a minimum of nine inches (9”) beyond the limits of the excavation on all sides. If the plates are to be left over the weekend, the edges of the plates shall be cushioned with a bituminous mixture in areas where vehicular traffic will cross the plates. Steel Plate Ahead signs (W8-24(O), 48") to be installed prior to any steel plate.
Excavations deeper than 36" along George Street or 24" near North Avenue will not be allowed within 8 feet of an open traffic lane unless shielded by a temporary longitudinal barrier.
The costs for providing the aggregate, plates, signs and bituminous mixture will not be paid for directly but shall be considered included in the cost of the excavation work required for the various contract items.
SHEETING AND SHORING
Any sheeting or shoring required for the underground utility improvements or other construction elements requiring relatively deep excavations shall be included in the cost of the particular the underground utility pay item and no additional compensation will be allowed for any supplemental work associated with the maintenance of trench sides or other excavated areas.
CURING AND PROTECTION
After the concrete has been finished and the water sheen has disappeared from the surface of the concrete, the surface shall be sealed with membrane curing compound of a type approved by the Engineer. The seal shall be maintained for the specified curing period. The edges of the concrete shall also be sealed immediately after the forms are removed. In addition, all concrete placed during periods of cold weather shall be protected in accordance with Article 1020.13 of the Standard Specifications.
This work shall be considered included in the cost of the various concrete items in the Contract.
The work shall be under the charge and care of the Contractor until final acceptance by the Engineer as coordinated with the Village. The Contractor shall assume all responsibility for any injury or damage to the work from any cause whatsoever and he shall rebuild, repair or restore the damaged work at his own expense.
Basis of Payment: This item will not be paid for separately but will be included in the cost for the various concrete items in the Contract.
CURB AND GUTTER TRANSITIONS
Transitions from proposed curb and gutters to existing curb and gutters, and from 6” curb height to 4” curb height (and vice-a-versa) shall be done in ten (10) foot transitions unless directed by the Engineer.
Basis of Payment: This item will not be paid for separately but will be included in the cost for the various concrete items in the Contract.
SECTION NO. 24-00145-00-CH
VILLAGE OF MELROSE PARK
AGGREGATE BEDDING FOR CONCRETE WORK
New sidewalk and curb & gutter shall be placed on a minimum of two inches (2”) of compacted CA-6 stone bedding. New 8” driveway pavement and 8” pavement shall be placed on a minimum of four inches (4”) of compacted CA-6 stone bedding. Additional aggregate required to adjust the existing elevation of the subgrade to the proposed elevation will be included in the cost of that pay item.
Basis of Payment: This item will not be paid for separately but will be included in the cost for the respective concrete items in the contract.
INLET FILTERS
This work shall consist of the furnishing, installation, and removal of a drainage structure inlet filter assembly, consisting of a frame and filter bag, to collect sediment in surface stormwater runoff at locations shown on the plans or as directed by the Engineer be in accordance with Section 280 of the Standard Specifications.
The Contractor shall inspect the work site and review the plans to determine the number and dimensions of the various types of drainage structure frames (circular and rectangular) into which the inlet filters will be installed prior to ordering materials.
The drainage structure inlet filter assembly shall be installed under the grate on the lip of the drainage structure frame with the fabric bag hanging down into the drainage structure.
The drainage structure inlet filter assembly shall remain in place until final removal of the assembly is directed by the Engineer. The drainage structure inlet filter assembly shall remain the property of the Contractor. Final removal of the assembly shall include the disposal of debris or silt that has accumulated in the filter bag at the time of final removal.
Cleaning of the filter bags shall be included in this item. The cleanings shall be performed weekly, or as needed to keep the bags from reaching 75% of their storage capacity, for the duration of the use of each drainage structure inlet filter assembly. The Engineer shall be the sole judge of the need for cleaning, based on the rate that debris and silt is collected at each location. Also included shall be the off-site disposal of the material which is removed from the bags.
A detail drawing in the plans depicts the drainage structure inlet filter assembly.
The drainage structure inlet filter assembly consists of a steel frame with a replaceable geotextile fabric bag attached with a steel band with locking cap that is suspended from the frame. A clean used bag and a used steel frame in good condition meeting the approval of the Engineer may be substituted for new materials.
Basis of Payment: The work will be paid for at the Contract unit price per EACH for INLET FILTERS.
SECTION NO. 24-00145-00-CH
VILLAGE OF MELROSE PARK
MAINTENANCE OF EXISTING DRAINAGE STRUCTURES
All loose material deposited in the flow line of gutters and drainage structures that obstructs the natural flow of water shall be removed at the close of each working day. At the conclusion of the construction operations, all drainage facilities shall be clean and free of all obstructions due to construction operations.
Basis of payment: This item will not be paid for separately but shall be included in the cost for the various sewer structures in the contract.
EARTH EXCAVATION
This item includes all of the excavating and grading work necessary on this Project to establish the subgrade elevations of the proposed sidewalks and proposed pavement widening within existing grass parkways along George Street.
The removal and disposal of all brush, rock, construction debris, hedges, trees of sizes less than 6” in diameter and other excess materials located within the roadway construction area of the Project’s improvements shall be included under this item.
Curb and gutter, sidewalk, and driveway removal are not paid for under this item but will be paid under their respective removal pay items.
Any excavation of the parkway which is required to give a uniform slope from the face of sidewalk to the top of the curb will also be paid for under this item. The payment for EARTH EXCAVATION will only be applicable where the proposed top of curb has been lowered substantially from the existing grade (three inches or greater), or where a uniform parkway slope is unattainable through the basic grading operations of topsoil placement. The proposed sodding and topsoil volume will be subtracted from the volume to be measured for payment. Any excavation and grading of the parkway where the top of curb has not been lowered by three inches or greater shall be included in the cost for TOPSOIL FURNISH AND PLACE, 3”.
Basis of Payment: This work will be paid for at the Contract unit price per Cubic Yard for EARTH
EXCAVATION.
HOT-MIX ASPHALT SURFACE REMOVAL, 4”
All work and materials furnished under this item shall be in accordance with Section 440 of the “Standard Specifications for Road and Bridge Construction”, except as modified, amended or clarified by this Special Provision.
This item includes the removal of the existing asphalt surface necessary to provide the profile of the proposed pavement cross section on all streets to be resurfaced. The depth of the material removed will vary from zero to four inches (0”- 4”) or as directed by the Engineer, depending on the thickness of the existing asphalt overlay and the proposed cross section. The above work shall be done after the proposed curb and gutter and the concrete “wedge” have been constructed and properly cured.
At the edge of pavement of streets to be resurfaced, the asphalt surface and possibly some of the existing base course shall be milled to a depth of 4 1/4 inches, allowing for a total asphalt thickness of 4-1/2 inches (4 1/4 inches plus a 1/4 inch reveal). Any concrete, brick, or stone milling necessary to meet these specifications shall be included in the cost of this pay item.
Sufficient milling or grinding passes shall be made over the existing pavement so that all irregularities and high spots are eliminated from the pavement’s surface before it is overlaid with new material. All
SECTION NO. 24-00145-00-CH
VILLAGE OF MELROSE PARK
asphalt surface removal at the butt joints is included in this item, and butt joints shall be saw-cut after placement of the HMA binder and no more than twenty-four (24) hours prior to the placement of the hot-mix asphalt surface course.
Following the bituminous surface removal operation, and prior to placing the HMA binder, the Engineer will inspect the milled surface or base course by proof-rolling and determine the locations and extents of any areas to be patched. The Contractor shall provide the use of a loaded semi-tractor dump truck and driver for the purpose of proof-rolling the pavement.