- Construction of a Single Span PPC Deck Beam Bridge Carrying Farrell Rd. over Spring Creek
- Solicitation number
- 61M06
- Issued by
- Will County, Illinois
About this file
Contract Summary
This is a Notice to Bidders and specifications document from the Illinois Department of Transportation (IDOT) for Contract No. 61M06, a construction project in Will County involving the City of Joliet. The project consists of removing an existing single-span concrete deck beam bridge carrying Farrell Road over Spring Creek and replacing it with a single-span precast prestressed concrete (PPC) deck beam structure on pile bent abutments. Additional work includes approximately 400 feet of full-depth hot-mix asphalt (HMA) pavement reconstruction, earthwork, pipe culverts, guardrail installation, and incidental work. The project is located 550 feet north of U.S. Route 6 and extends north for 450 feet (0.085 miles) in Joliet Township and New Lenox Township. Electronic bids must be submitted to the iCX system by 12:00 p.m. on November 6, 2026, at which time bids will be publicly opened. The contract completion date is August 2, 2027, with contractors allowed 15 working days after that date for cleanup and punch list items. The contract will be awarded to the lowest responsive and responsible bidder; IDOT reserves the right to reject any or all proposals and to re-advertise the project.
The project includes substantial utility coordination requirements, with Nicor Gas requiring approximately 10 days for gas line relocation beginning in September 2026. Farrell Road will be closed to all traffic for the duration of construction. Special provisions address traffic control and protection, including the requirement for two changeable message signs positioned two weeks before construction begins. The project involves compliance with extensive NPDES stormwater requirements, wetland protection measures, and erosion control practices including perimeter erosion barriers, ditch checks, inlet protection, temporary seeding, and mulch. The contract includes stringent Hot-Mix Asphalt specifications requiring mixture design verification, Hamburg wheel and I-FIT testing, quality control management by certified technicians, and specific quality assurance protocols. Funding sources include federal-aid funds, requiring contractors to meet federal certifications and compliance requirements related to prevailing wages, employment practices, and Disadvantaged Business Enterprise (DBE) participation. No incumbent information is provided in the contract documents.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Letting November 6, 2026
Notice to Bidders, Specifications and Proposal
Contract No. 61M06 WILL County Section 21-00542-00-BR (Joliet) Route FAU 366 (Farrell Road) Project UUU5-053 () District 1 Construction Funds
Prepared by F
Checked by
(Printed by authority of the State of Illinois)
NOTICE TO BIDDERS
1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.
November 6, 2026 at which time the bids will be publicly opened from the iCX SecureVault.
2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the
Invitation for Bids as:
Contract No. 61M06 WILL County Section 21-00542-00-BR (Joliet) Project UUU5-053 () Route FAU 366 (Farrell Road) District 1 Construction Funds
Construction of a single span PPC deck beam bridge carrying Farrell Rd. over Spring Creek in the city of Joliet. Additional work includes full-depth HMA pavement reconstruction, pipe culverts, guardrail and other required work.
3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.
(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.
4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.
By Order of the Illinois Department of Transportation
Gia Biagi, Secretary
CONTRACT 61M06
INDEX
FOR
SUPPLEMENTAL SPECIFICATIONS
AND RECURRING SPECIAL PROVISIONS
Adopted January 1, 2026
This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.
ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)
SUPPLEMENTAL SPECIFICATIONS
Std. Spec. Sec. Page No.
109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires
1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment
RECURRING SPECIAL PROVISIONS
The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:
CHECK SHEET # PAGE NO.
1 Additional State Requirements for Federal-Aid Construction Contracts 2 Subletting of Contracts (Federal-Aid Contracts)
3 EEO
4 Specific EEO Responsibilities Non Federal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos HMA Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 Construction Layout Stakes
10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays
LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS
Table of Contents
CHECK SHEET # PAGE NO.
LRS 1 Reserved LRS 2 Furnished Excavation LRS 3 Work Zone Traffic Control Surveillance LRS 4 Flaggers in Work Zones LRS 5 Contract Claims LRS 6 Bidding Requirements and Conditions for Contract Proposals LRS 7 Bidding Requirements and Conditions for Material Proposals LRS 8 Reserved LRS 9 Bituminous Surface Treatments LRS 10 Reserved LRS 11 Employment Practices LRS 12 Wages of Employees on Public Works LRS 13 Selection of Labor LRS 14 Paving Brick and Concrete Paver Pavements and Sidewalks LRS 15 Partial Payments LRS 16 Protests on Local Lettings LRS 17 Substance Abuse Prevention Program LRS 18 Multigrade Cold Mix Asphalt LRS 19 Reflective Crack Control Treatment i
Farrell Road over Spring Creek Section No. 21-00542-00-BR
City of Joliet
TABLE OF CONTENTS
LOCATION OF PROJECT
PROJECT DESCRIPTION
STATUS OF UTILITIES (D-1)
TRAFFIC CONTROL PLAN
TRAFFIC CONTROL AND PROTECTION (ARTERIALS) (D-1)
CHANGEABLE MESSAGE SIGN
COMPLETION DATE PLUS WORKING DAYS (D-1)
CONTROLLED LOW-STRENGTH MATERIAL
PIPE CULVERT REMOVAL
REMOVAL OF EXISTING STRUCTURES
STEEL RAILING, TYPE SM (SPECIAL)
TREE REMOVAL AND FORESTRY WORK RESTRICTIONS – ENDANGERED SPECIES ACT
WASHOUT BASIN
(D-1) EMBANKMENT I
(D-1) FRICTION AGGREGATE
(D-1) HOT-MIX ASPHALT – MIXTURE DESIGN VERIFICATION AND PRODUCTION
(D-1) HOT-MIX ASPHALT BINDER AND SURFACE COURSE
(D-1) MAINTENANCE OF ROADWAYS
(D-1) MINERALIZED CARBON DIOXIDE CONCRETE
(D-1) PUBLIC CONVENIENCE AND SAFETY
(D-1) TEMPORARY TRAFFIC SIGNAL TIMIING
AVAILABLE REPORTS
LR 107-4
LR 1030-2
SWPPP
USACOE PERMIT
WILL-SOUTH COOK SWCD APPROVAL
IDOT REGULATORY FLOODWAY PERMIT
WILL-SOUTH COOK SWCD EROSION CONTROL DETAILS
BDE SPECIAL PROVISIONS
The following special provisions indicated by an “X” are applicable to this contract. An * indicates a new or revised special provision for the letting.
File Name Pg. Special Provision Title Effective Revised 80099 Accessible Pedestrian Signals (APS) April 1, 2003 Jan. 1, 2022 _ 80274 56 Aggregate Subgrade Improvement April 1, 2012 April 1, 2022 80192 Automated Flagger Assistance Device Jan. 1, 2008 April 1, 2023 80173 Bituminous Materials Cost Adjustments Nov. 2, 2006 Aug. 1, 2017 80426 Bituminous Surface Treatment with Fog Seal Jan. 1, 2020 April 1, 2026 80475 Bridge Deck Concrete Overlays Jan. 1, 2026 80241 Bridge Demolition Debris July 1, 2009
5053I Building Removal Sept. 1, 1990 Aug. 1, 2022 5026I Building Removal with Asbestos Abatement Sept. 1, 1990 Aug. 1, 2022
80460 59 Cement, Finely Divided Minerals, Admixtures, Concrete, and Mortar Jan. 1, 2025 Jan. 1, 2026 80384 76 Compensable Delay Costs June 2, 2017 April 1, 2019 80198 Completion Date (via calendar days) April 1, 2008 80199 Completion Date (via calendar days) Plus Working Days April 1, 2008 80461 Concrete Barrier Jan. 1, 2025 80453 Concrete Sealer Nov. 1, 2023 80261 80 Construction Air Quality – Diesel Retrofit June 1, 2010 Jan. 1, 2025 80476 Deck Slab Repair Jan. 1, 2026
* 80029 82 Disadvantaged Business Enterprise Participation Sept. 1, 2000 July 2, 2026
* 80486 Engineer’s Field Office Nov. 1, 2026 80467 86 Erosion Control Blanket Aug. 1, 2025 80229 Fuel Cost Adjustment April 1, 2009 Aug. 1, 2017 80452 Full Lane Sealant Waterproofing System Nov. 1, 2023 80433 Green Preformed Thermoplastic Pavement Markings Jan. 1, 2021 Jan. 1, 2022 80471 89 Guardrail Nov. 1, 2025 80472 High Friction Surface Treatment Nov. 1, 2025 80456 Hot-Mix Asphalt Jan. 1, 2024 April 1, 2026 80446 Hot-Mix Asphalt – Longitudinal Joint Sealant Nov. 1, 2022 Aug. 1, 2023 80438 Illinois Works Apprenticeship Initiative – State Funded Contracts June 2, 2021 April 2, 2024 80483 Inlet Filters April 1, 2026 80477 Longitudinal Tining Jan. 1, 2026 July 1, 2026 80450 Mechanically Stabilized Earth Retaining Walls Aug. 1, 2023 Aug. 1, 2025 80478 Modified Longitudinal Construction Joint Jan. 1, 2026 80464 90 Pavement Marking April 1, 2025 Nov. 1, 2025 80468 Pavement Patching Aug. 1, 2025 80441 91 Performance Graded Asphalt Binder Jan 1, 2023 April 1, 2026 80459 Preformed Plastic Pavement Marking June 2, 2024 3426I Railroad Protective Liability Insurance Dec. 1, 1986 Jan. 1, 2022 80473 Raised Reflective Pavement Markers Nov. 1, 2025 80455 97 Removal and Disposal of Regulated Substances Jan. 1, 2024 April 1, 2026 80474 Residential Driveway Temporary Signal Nov. 1, 2025 80445 99 Seeding Nov. 1, 2022 July 1, 2026
* 80457 105 Short Term and Temporary Pavement Markings April 1, 2024 Nov. 1, 2026 80462 109 Sign Panels and Appurtenances Jan. 1, 2025 Jan. 1, 2026 80479 Sinusoidal Rumble Strips Jan. 1, 2026 80469 Slope Wall Aug. 1, 2025 80448 111 Source of Supply and Quality Requirements Jan. 2, 2023 Jan. 1, 2026 80340 Speed Display Trailer April 2, 2014 Jan. 1, 2022 80127 Steel Cost Adjustment April 2, 2004 Nov. 1, 2025 80480 Structural Repair of Concrete Jan. 1, 2026 80397 113 Subcontractor and DBE Payment Reporting April 2, 2018 80391 114 Subcontractor Mobilization Payments Nov. 2, 2017 April 1, 2019
File Name Pg. Special Provision Title Effective Revised 80463 115 Submission of Bidders List Information Jan. 2, 2025 Mar. 2, 2025 80482 116 Submission of Payroll Records – Federal Aid Contract April 1, 2026 80437 Submission of Payroll Records – State Contract April 1, 2021 April 1, 2026 80435 Surface Testing of Pavements – IRI Jan. 1, 2021 Jan. 1, 2023 80465 118 Surveying Services April 1, 2025 80481 Temporary Concrete Barrier Jan. 1, 2026 80466 Temporary Rumble Strips April 1, 2025 80484 Tolerance in Thickness for Continuously Reinforced PCC Pavement July 1, 2026 80470 Traffic Signal Backplate Aug. 1, 2025 20338 Training Special Provisions Oct. 15, 1975 Sept. 2, 2021 80429 Ultra-Thin Bonded Wearing Course April 1, 2020 Jan. 1, 2022
* 80439 119 Vehicle and Equipment Warning Lights Nov. 1, 2021 Nov. 1, 2026 80458 120 Waterproofing Membrane System Aug. 1, 2024 80302 121 Weekly DBE Trucking Reports June 2, 2012 Jan. 2, 2025 80454 Wood Sign Support Nov. 1, 2023 80427 122 Work Zone Traffic Control Devices Mar. 2, 2020 Jan. 1, 2026 80485 125 Work Zone Width Restriction July 1, 2026 80071 Working Days Jan. 1, 2002
Section No. 21-00542-00-BR
City of Joliet
STATE OF ILLINOIS
SPECIAL PROVISIONS
The following Special Provisions supplement the “Standard Specifications for Road and Bridge Construction, Adopted January 1, 2022”, the latest edition of the “Manual on Uniform Traffic Control Devices for Streets and Highways”, and the “Manual of Test Procedures for Materials” in effect on the date of invitation for bids; and the “Supplemental Specifications and Recurring Special Provisions”, adopted January 1, 2026 and as indicated on the Check Sheet included herein, which apply to and govern the construction of: Farrell Road over Spring Creek, Section No. 21-00542-00- BR, Contract No. 61M06, Project No. UUU5(053), in the City of Joliet, Will County, Illinois and in case of conflict with any part, or parts, of said Specifications, the said Special Provisions shall take precedence and shall govern.
Route: Farrell Road Section: 21-00542-00-BR Project No.: UUU5(053)
Contract No.: 61M06
LOCATION OF PROJECT
This project is located in Section 1 of Township 35 North, Range 10 East of the Joliet Township and in Section 6 of Township 35 North, Range 11 East of the New Lenox Township, both of the 3rd Principal Meridian in Will County. The project begins along Farrell Road, 550 feet north of U.S.
Route 6 and extends north for 450 feet (0.085 miles).
PROJECT DESCRIPTION
This project consists of removing the existing single span concrete deck beam structure on concrete abutments carrying Farrell Road over Spring Creek and replacing with a single span PPC deck beam structure on pile bent abutments. Also included is approximately 400 feet of roadway work consisting of full depth HMA pavement reconstruction, earthwork, pipe culverts, guardrail and all other incidental and collateral work necessary to complete the project as shown on the plans and described herein.
City of Joliet
STATUS OF UTILITIES (D-1)
Effective: June 1, 2016 Revised: April 1, 2025
Utility companies and/or municipal owners located within the construction limits of this project have provided the following information regarding their facilities and the proposed improvements. The tables below contain a description of specific conflicts to be resolved and/or facilities which will require some action on the part of the Department’s contractor to proceed with work. Each table entry includes an identification of the action necessary and, if applicable, the estimated duration required for the resolution.
UTILITIES TO BE ADJUSTED
Conflicts noted below have been identified by following the suggested staging plan included in the contract. The company has been notified of all conflicts and will be required to obtain the necessary permits to complete their work; in some instances, resolution will be a function of the construction staging. The responsible agency must relocate, or complete new installations as noted below; this work has been deemed necessary to be complete for the Department’s contractor to then work in the stage under which the item has been listed.
Pre-Stage
STAGE /
LOCATION
TYPE DESCRIPTION
RESPONSIBLE
AGENCY
DURATION OF TIME
Farrell Road Sta. 115+25 to Sta.
119+75 RT
4” Gas Line
4” gas line is buried along entire west side of Farrel Road within the project limits.
Nicor has confirmed the gas line is in conflict with the guardrail and roadway embankment. Nicor is currently designing relocation plans for the gas line.
Nicor Gas
Per coordination with Nicor, estimated start of relocation is beginning of
September 2026.
The estimated number of days for relocation/installation is 10 days.
Pre-Stage: __10__ Days Total Installation
City of Joliet
The following contact information is what was used during the preparation of the plans as provided by the Agency/Company responsible for resolution of the conflict.
Agency/Company Responsible to
Resolve Conflict
Name of contact Phone E-mail address
AT&T Steven Pesola 815-412-5255 Sp9653@att.com ComEd Joseph Milani 708-208-9758 Joseph.milani@ComEd.com
Nicor Gas Diego Serapio 224-457-5785 dserapio@southernco.com Verizon Joe Chaney 312-617-2131 Joe.chaney@verizon.com
City of Joliet Jose Garcia Jgarcia2@joliet.gov
UTILITIES TO BE WATCHED AND PROTECTED
The areas of concern noted below have been identified by following the suggested staging plan included for the contract. The information provided is not a comprehensive list of all remaining utilities, but those which during coordination were identified as ones which might require the Department’s contractor to take into consideration when making the determination of the means and methods that would be required to construct the proposed improvement. In some instances, the contractor will be responsible to notify the owner in advance of the work to take place so necessary staffing on the owner’s part can be secured.
Pre-Stage
STAGE / LOCATION TYPE DESCRIPTION OWNER
Farrell Road Sta. 115+43 LT Sta. 116+39 LT Sta. 116+97 LT Sta. 118+40 LT Sta. 119+17 LT
Pole Aerial Lines
The contractor is alerted that AT&T has relocated their fiber optic cable to the relocated ComEd poles. The existing fiber optic along the west side of Farrell Road has been abandoned.
With relocation completed, there are no longer conflicts with the proposed improvements. However, power poles and the aerial lines should be protected by the Contractor during construction.
AT&T
Farrell Road Sta. 115+43 LT Sta. 116+39 LT Sta. 116+97 LT Sta. 118+40 LT Sta. 119+17 LT
Poles Aerial Lines
The contractor is alerted that ComEd has power poles and aerial lines along the entire east side of the project limits.
With relocation completed, there are no longer conflicts with the proposed improvements. However, power poles and the aerial lines should be protected by the Contractor during construction.
ComEd
City of Joliet
Farrell Road Sta. 115+25 to Sta.
119+75 LT
Buried Fiber Optic Cable
The contractor is alerted that there is a 2” buried fiber optic cable along entire east side of Farrell Road as shown in the plans.
There are no conflicts with the proposed improvement if constructed to plan. However, location of the fiber optic cable should be watched once the JULIE locate is completed prior to beginning of construction.
Verizon
Farrell Road Sta. 115+25 to Sta.
119+75 LT
Water Main
The contractor is alerted that there is a 16” water main along entire east side of Farrell Road within the project limits.
There are no conflicts with the proposed improvement. However, location of the water main should be watched once the JULIE locate is completed prior to beginning of construction.
The following contact information is what was used during the preparation of the plans as provided by the owner of the facility.
Agency/Company Responsible to
Resolve Conflict
Name of contact Phone E-mail address
AT&T Steven Pesola 815-412-5255 Sp9653@att.com
ComEd Joseph Milani 708-208-9758 Joseph.milani@ComEd.com Nicor Gas Diego Serapio 224-457-5785 dserapio@southernco.com Verizon Joe Chaney 312-617-2131 Joe.chaney@verizon.com
City of Joliet Jose Garcia Jgarcia2@joliet.gov
The above represents the best information available to the Department and is included for the convenience of the bidder. The days required for conflict resolution should be considered in the bid as this information has also been factored into the timeline identified for the project when setting the completion date. The applicable portions of the Standard Specifications for Road and Bridge Construction shall apply.
Estimated duration of time provided above for the first conflicts identified will begin on the date of the executed contract regardless of the status of the utility relocations. The responsible agencies will be working toward resolving subsequent conflicts in conjunction with contractor activities in the number of days noted.
City of Joliet
The estimated relocation duration must be part of the progress schedule submitted by the contractor.
A utility kickoff meeting will be scheduled between the Department, the Department’s contractor, and the utility companies when necessary.
Please note, the marking of underground facilities does not absolve the contractor of their responsibility to repair or replace any facilities damaged during construction at their expense.
TRAFFIC CONTROL PLAN
Traffic control shall be according to the applicable sections of the Standard Specifications, the Supplemental Specifications, the “Illinois Manual on Uniform Traffic Control Devices for Streets and Highways”, any special details and Highway Standards contained in the plans, and the Special Provisions contained herein.
Contractor shall contact District 1 Bureau of Traffic, the City of Joliet, Joliet Township and the Will County Division of Transportation 72 hours before starting work (All entities involved with detour).
Special attention is called to Article 107.09, 107.14 and Section 701 of the Standard Specifications and the following Highway Standards, Details, Quality Standard for Work Zone Traffic Control Devices, Recurring Special Provisions and Special Provisions contained herein, relating to traffic control:
STANDARDS: 701101-05, 701301-04, 701311-03, 701901-11, BLR 21-9, BLR 22-7
DETAILS: Detour Plan, TC-10, TC-13, TC-21
RECURRING SPECIAL PROVISION: Check Sheet #’s LRS3
SPECIAL PROVISIONS: Traffic Control and Protection (Arterials) Maintenance of Roadways Changeable Message Sign Public Convenience and Safety (D-1) Work Zone Traffic Control Devices (BDE) Work Zone Width Restriction (BDE) Vehicle Equipment Warning Lights (BDE)
Traffic: Farrell Road will be closed to all traffic for the duration of construction.
TRAFFIC CONTROL AND PROTECTION (ARTERIALS) (D-1)
Effective: February 1, 1996 Revised: March 1, 2011
Specific traffic control plan details and Special Provisions have been prepared for this contract. This work shall include all labor, materials, transportation, handling and incidental work necessary to
City of Joliet furnish, install, maintain and remove all traffic control devices required as indicated in the plans and as approved by the Engineer.
When traffic is to be directed over a detour route, the Contractor shall furnish, erect, maintain and remove all applicable traffic control devices along the detour route according to the details shown in the plans.
Method of Measurement: All traffic control (except temporary pavement markings) indicated on the traffic control plan details and specified in the Special Provisions will be measured for payment on a lump sum basis.
Basis of Payment: All traffic control and protection will be paid for at the contract lump sum price for
TRAFFIC CONTROL AND PROTECTION (SPECIAL).
Temporary pavement markings will be paid for separately unless shown on a Standard.
CHANGEABLE MESSAGE SIGN
Description: This work shall consist of providing all labor, equipment and materials necessary for the furnishing and maintaining of two (2) CHANGEABLE MESSAGE SIGNS.
Additionally, the two (2) CHANGEABLE MESSAGE SIGNS will be required to be in place and operational two (2) weeks prior to the beginning of construction at locations determined by the Engineer. The Engineer will provide the message to the Contractor to be used for these two weeks
Method of Measurement: This work will be measured for payment by calendar-month.
Basis of Payment: This work shall be paid for at the contract unit price per sign per calendar-month for CHANGEABLE MESSAGE SIGN.
COMPLETION DATE PLUS WORKING DAYS (D-1)
Effective: September 30, 1985 Revised: January 1, 2007
Revise Article 108.05 (b) of the Standard Specifications as follows:
"When a completion date plus working days is specified, the Contractor shall complete all contract items and safely open all roadways to traffic by 11:59 PM on August 2, 2027, except as specified herein.
The Contractor will be allowed to complete all clean-up work and punch list items within 15 working days after the completion date for opening the roadway to traffic. Under extenuating circumstances the Engineer may direct that certain items of work, not affecting the safe opening of the roadway to traffic, may be completed within the working days allowed for clean up work and punch list items. Temporary lane closures for this work may be allowed at the discretion of the Engineer.
City of Joliet
Article 108.09 or the Special Provision for “Failure to Complete the Work on Time”, if included in this contract, shall apply to both the completion date and the number of working days.
CONTROLLED LOW-STRENGTH MATERIAL
Description: The structure excavation area behind the proposed abutments along the width of the cap shall be filled with Controlled Low-Strength Material placed as dictated in the project plans, these special provisions, the Standard Specifications for Road and Bridge Construction, and to the satisfaction of the Engineer. The pay limits for this item shall be from the back of abutment to 2’-0” away from the back of abutment (pay limits of Structure Excavation). In addition, this material shall be placed from the bottom of abutment cap to the bottom of the proposed aggregate subgrade improvement.
Method of Measurement: This work will be measured for payment per cubic yard.
Basis of Payment: Placement of the material will be paid for at the contract unit price per cubic yard for CONTROLLED LOW-STRENGTH MATERIAL, which price shall be payment in full for furnishing all material, labor, and equipment required for this item as specified and to the satisfaction of the Engineer. Any additional Controlled Low-Strength Material required for fill behind the abutment due to over excavation shall be provided at no additional cost.
PIPE CULVERT REMOVAL
Description: This work shall consist of removing existing pipe culverts at locations shown in the plans and disposing of the pipe culverts outside the right-of-way in accordance with Section 501 of the Standard Specifications. The existing end sections associated with the pipe culverts shall be removed and disposed in conjunction with the pipe culverts.
Method of Measurement: Removal of existing pipe culverts will be measured for payment in place, in feet along the invert of the culvert. The measured length will not include the end section.
Basis of Payment: Removal of existing pipe culverts will be paid for at the contract unit price per foot for PIPE CULVERT REMOVAL. The removal of existing end sections will not be paid for separately, but shall be considered included in the cost of PIPE CULVERT REMOVAL.
REMOVAL OF EXISTING STRUCTURES
Description: This work shall be done in accordance with Art. 501.04 of the Standard Specifications for Road and Bridge Construction and will consist of providing all labor, equipment and materials for the removing and disposing of the existing single span structure carrying Farrell Road over Spring Creek. The existing structure is 51’-0” back to back abutments, 36’-0” out to out and has no skew.
The plans include four (4) sheets of existing structure plans which are included on a “FOR INFORMATION ONLY” basis.
City of Joliet
Method of Measurement: This work will be measured for payment by each.
Basis of Payment: This work will be paid for at the contract unit price per each for REMOVAL OF
EXISTING STRUCTURES.
STEEL RAILING, TYPE SM (SPECIAL)
Description: This item shall consist of the placement of Steel Railing in accordance with the applicable portions of Section 509 of the Standard Specifications for Road and Bridge Construction and the plan details.
Method of Measurement: This work will be measured for payment in place in feet. The length measured will be the overall length along the bottom longitudinal railing member through all posts and gaps.
Basis of Payment: Placement of this steel bridge rail will be paid for at the contract unit price per foot for STEEL RAILING, TYPE SM (SPECIAL), which price shall be payment in full for furnishing all material, labor, and equipment required for this item as specified and to the satisfaction of the Engineer.
TREE REMOVAL AND FORESTRY WORK RESTRICTIONS – ENDANGERED SPECIES ACT
This work shall be according to Section 201 of the Standard Specifications, except shall only be allowed from October 1 through March 31.
Work includes tree pruning and tree limb removal of live or dead branches, clearcutting, selective clearing, and the removal of live or dead trees measuring 3 inches (3”) in diameter or greater at a point of 4.5 feet (4.5’) above the highest ground level at the base of the tree.
Work that is considered hazardous or a safety concern can be removed any time during the calendar year with written approval by the Engineer.
No additional compensation or extension of time will be allowed to comply with these restrictions.
WASHOUT BASIN
Description: This item shall consist of constructing and maintaining a washout basin for concrete trucks and other construction vehicles.
Requirements: This work shall include general maintenance and removal of all construction debris.
Basis of Payment: This item will be paid for at the contract unit price per lump sum for WASHOUT
BASIN.
City of Joliet
(D-1) EMBANKMENT I
Effective: March 1, 2011 Revised: November 1, 2013
Description. This work shall be according to Section 205 of the Standard Specifications except for the following.
Material. All material shall be approved by the District Geotechnical Engineer. The proposed material must meet the following requirements.
a) The laboratory Standard Dry Density shall be a minimum of 90 lb/cu ft (1450 kg/cu m) when determined according to AASHTO T 99 (Method C).
b) The organic content shall be less than ten percent determined according to AASHTO T 194 (Wet Combustion).
c) Soils which demonstrate the following properties shall be restricted to the interior of the embankment and shall be covered on both the sides and top of the embankment by a minimum of 3 ft (900 mm) of soil not considered detrimental in terms of erosion potential or excess volume change.
1) A grain size distribution with less than 35 percent passing the number 75 um (#200) sieve.
2) A plasticity index (Pl) of less than 12.
3) A liquid limit (LL) in excess of 50.
d) Reclaimed asphalt shall not be used within the ground water table or as a fill if ground water is present.
e) The RAP used shall be according to the current Bureau of Materials and Physical Research Policy Memorandum, “Reclaimed Asphalt Pavement (RAP) for Aggregate Applications”.
Gradation deleterious count shall not exceed 10% of total RAP and 5% of other by total weight.
CONSTRUCTION REQUIREMENTS
Samples. Embankment material shall be sampled, tested, and approved before use. The contractor shall identify embankment sources, and provide equipment as the Engineer requires, for the collection of samples from those sources. Samples will be furnished to the Geotechnical Engineer a minimum of three weeks prior to use in order that laboratory tests for approval and compaction can be performed. Embankment material placement cannot begin until tests are completed and approval given.
Placing Material. In addition to Article 202.03, broken concrete, reclaimed asphalt with no expansive aggregate, or uncontaminated dirt and sand generated from construction or demolition activities shall
City of Joliet be placed in 6 inches (150 mm) lifts and disked with the underlying lift until a uniform homogenous material is formed. This process also applies to the overlaying lifts. The disk must have a minimum blade diameter of 24 inches (600 mm).
When embankments are to be constructed on hillsides or existing slopes that are steeper than 3H:1V, steps shall be keyed into the existing slope by stepping and benching as shown in the plans or as directed by the engineer.
Compaction. Soils classification for moisture content control will be determined by the Soils Inspector using visual field examination techniques and the IDH Textural Classification Chart.
When tested for density in place each lift shall have a maximum moisture content as follows.
a) A maximum of 110 percent of the optimum moisture for all forms of clay soils.
b) A maximum of 105 percent of the optimum moisture for all forms of clay loam soils.
Stability. The requirement for embankment stability in Article 205.04 will be measured with a Dynamic Cone Penetrometer (DCP) according to the test method in the IDOT Geotechnical Manual.
The penetration rate must be equal or less than 1.5 inches (38 mm) per blow.
Basis of Payment. This work will not be paid separately but will be considered as included in the various items of excavation.
(D-1) FRICTION AGGREGATE
Effective: January 1, 2011 Revised: December 1, 2021
Revise Article 1004.03(a) of the Standard Specifications to read:
“1004.03 Coarse Aggregate for Hot-Mix Asphalt (HMA). The aggregate shall be according to Article 1004.01 and the following.
(a) Description. The coarse aggregate for HMA shall be according to the following table.
City of Joliet
Use Mixture Aggregates Allowed
Class A Seal or Cover Allowed Alone or in Combination 5/:
Gravel Crushed Gravel Carbonate Crushed Stone Crystalline Crushed Stone Crushed Sandstone Crushed Slag (ACBF) Crushed Steel Slag Crushed Concrete
HMA
Low ESAL
Stabilized Subbase or Shoulders
Allowed Alone or in Combination 5/:
Gravel Crushed Gravel Carbonate Crushed Stone Crystalline Crushed Stone Crushed Sandstone Crushed Slag (ACBF) Crushed Steel Slag1/
Crushed Concrete
HMA
High ESAL Low ESAL
Binder
IL-19.0
or IL-19.0L
SMA Binder
Allowed Alone or in Combination 5/ 6/:
Crushed Gravel Carbonate Crushed Stone2/ Crystalline Crushed Stone Crushed Sandstone Crushed Slag (ACBF) Crushed Concrete3/
HMA
High ESAL Low ESAL
C Surface and Binder
IL-9.5
IL-9.5FG
or IL-9.5L
Allowed Alone or in Combination 5/:
Crushed Gravel Carbonate Crushed Stone2/ Crystalline Crushed Stone Crushed Sandstone Crushed Slag (ACBF) Crushed Steel Slag4/ Crushed Concrete3/
HMA
High ESAL
D Surface and Binder
IL-9.5
or IL-9.5FG
Allowed Alone or in Combination 5/:
Crushed Gravel Carbonate Crushed Stone (other than Limestone)2/ Crystalline Crushed Stone Crushed Sandstone Crushed Slag (ACBF) Crushed Steel Slag4/
City of Joliet
Other Combinations Allowed:
Up to... With...
25% Limestone Dolomite
50% Limestone Any Mixture D aggregate other than Dolomite
75% Limestone Crushed Slag (ACBF) or Crushed Sandstone
HMA
High ESAL
E Surface
IL-9.5
SMA
Ndesign 80 Surface
Allowed Alone or in Combination 5/ 6/:
Crushed Gravel
Crystalline Crushed Stone Crushed Sandstone Crushed Slag (ACBF) Crushed Steel Slag
No Limestone.
Up to... With...
50% Dolomite2/ Any Mixture E aggregate
75% Dolomite2/ Crushed Sandstone, Crushed Slag (ACBF), Crushed Steel Slag, or Crystalline Crushed Stone
75% Crushed Gravel2/
Crushed Sandstone, Crystalline Crushed Stone, Crushed Slag (ACBF), or Crushed Steel Slag
HMA
High ESAL
F Surface
IL-9.5
SMA
Ndesign 80 Surface
Allowed Alone or in Combination 5/ 6/:
Crystalline Crushed Stone Crushed Sandstone Crushed Slag (ACBF) Crushed Steel Slag No Limestone.
City of Joliet
Up to... With...
50% Crushed Gravel2/ or Dolomite2/
Crushed Sandstone, Crushed Slag (ACBF), Crushed Steel Slag, or Crystalline Crushed Stone
1/ Crushed steel slag allowed in shoulder surface only.
2/ Carbonate crushed stone (limestone) and/or crushed gravel shall not be used in SMA
Ndesign 80.
3/ Crushed concrete will not be permitted in SMA mixes.
4/ Crushed steel slag shall not be used as binder.
5/ When combinations of aggregates are used, the blend percent measurements shall be by volume.”
6/ Combining different types of aggregate will not be permitted in SMA Ndesign 80.”
(D-1) HOT-MIX ASPHALT – MIXTURE DESIGN VERIFICATION AND PRODUCTION
Effective: January 1, 2019 Revised: January 1, 2026
Add to Article 1030.05 (d)(3) of the Standard Specifications to read:
“ During mixture design, prepared samples shall be submitted to the District laboratory by the Contractor for verification testing. The required testing, number and size of prepared samples submitted, shall be according to the following tables.
High ESAL – Required Samples for Verification Testing
Mixture Hamburg Wheel and I-FIT Testing 1/ 2/
Binder total of 3 - 160 mm tall bricks
Surface total of 4 - 160 mm tall bricks
Low ESAL – Required Samples for Verification Testing
Mixture I-FIT Testing 1/ 2/
Binder 1 - 160 mm tall brick
Surface 2 - 160 mm tall bricks
City of Joliet
1/ The compacted gyratory bricks for Hamburg wheel and I-FIT testing shall be
7.5 ± 0.5 percent air voids.
2/ If the Contractor does not possess the equipment to prepare the 160 mm tall brick(s), twice as many 115 mm tall compacted gyratory bricks will be acceptable.
In the Supplemental Specifications, replace the addition of the paragraph between the third and fourth paragraphs of Article 1030.10 with the following:
“When a test strip is not required, each HMA mixture shall still be sampled on the first day of production: I-FIT and Hamburg wheel testing for High ESAL; I-FIT testing for Low ESAL. Within two working days after sampling the mixture, the Contractor shall deliver gyratory cylinders to the District laboratory for Department verification testing. The High ESAL mixture test results shall meet the requirements of Articles 1030.05(d)(3) and 1030.05(d)(4). The Low ESAL mixture test results shall meet the requirements of Article 1030.05(d)(4). The required number and size of prepared samples submitted for the Hamburg wheel and I-FIT testing shall be according to the “High ESAL - Required Samples for Verification Testing” table in Article 1030.05(d)(3) above.”
Replace the eleventh paragraph of Article 1030.10 of the Standard Specifications with the following:
“ If an initial Hamburg wheel or I-FIT test fails to meet the requirements of Article 1030.05(d), the Department will verify the results by testing the retained gyratory cylinders. Upon notification by the Engineer of a Hamburg wheel or I-FIT test failure on the retained gyratory cylinders, the Contractor shall substitute an approved mix design, submit a new mix design for mix verification testing according to Article 1030.05(d), or pave 250 tons with or without an adjustment and resample for Department Hamburg wheel and I-FIT testing as directed by the Engineer. Paving may continue as long as all other mixture criteria is being met. If Hamburg wheel or I-FIT tests on the resampled HMA fail, production of the affected mixture shall cease and the Contractor shall substitute an approved mix design or submit a new mix design for mix verification testing according to Article 1030.05(d).”
Add the following to the end of Article 1030.10 of the Standard Specifications to read:
“Mixture sampled during first day of production shall include approximately 60 lb (27 kg) of additional material for the Department to conduct Hamburg wheel testing and approximately 80 lb (36 kg) of additional material for the Department to conduct I-FIT testing. Within two working days after sampling, the Contractor shall deliver prepared samples to the District laboratory for verification testing. The required number and size of prepared samples submitted for the Hamburg wheel and I-FIT testing shall be according to the “High ESAL - Required Samples for Verification Testing” table in Article 1030.05(d)(3) above.”
(D-1) HOT-MIX ASPHALT BINDER AND SURFACE COURSE
Effective: November 1, 2019 Revised: April 1, 2026
Add the following to the end of Article 406.06(c) of the Standard Specifications:
City of Joliet
“ The amount of HMA binder course placed shall be limited to that which can be surfaced during the same construction season.”
Revise the fifteenth through eighteenth paragraphs of Article 406.14 of the Standard Specifications to read:
“ The mixture used in constructing acceptable HMA test strips will be paid for at the contract unit price. Unacceptable HMA test strips shall be removed and replaced at no additional cost to the Department.”
Revise Article 1004.03(c) to read:
“(c) Gradation. The coarse aggregate gradations shall be as listed in the following table.
Use Size/Application Gradation No.
Class A-1, A-2, & A-3 3/8 in. (10 mm) Seal CA 16 or CA 20
Class A-1 1/2 in. (13 mm) Seal CA 15
Class A-2 & A-3 Cover Coat CA 14
HMA High ESAL
IL-19.0;
Stabilized Subbase IL-19.0
CA 11 1/
SMA 12.5 2/ CA 134/, CA 14, or CA 16
SMA 9.5 2/ CA 133/4/ or CA 163/
IL-9.5 CA 16, CM 134/
IL-9.5FG CA 16
HMA Low ESAL
IL-19.0L CA 11 1/
IL-9.5L CA 16
1/ CA 16 or CA 13 may be blended with the CA 11.
2/ The coarse aggregates used shall be capable of being combined with the fine aggregates and mineral filler to meet the approved mix design and the mix requirements noted herein.
3/ The specified coarse aggregate gradations may be blended.
4/ CA 13 shall be 100 percent passing the 1/2 in. (12.5mm) sieve.”
Revise Article 1004.03(e) of the Standard Specifications to read:
“(e) Absorption. For SMA the coarse aggregate shall also have water absorption ≤ 2.0 percent.”
City of Joliet
Revise the “High ESAL” portion of the table in Article 1030.01 to read:
“High ESAL Binder Courses
IL-19.0, IL-9.5, IL-9.5FG, IL-4.75,
SMA 12.5, SMA 9.5
Stabilized Subbase IL-19.0
Surface Courses
IL-9.5, IL-9.5FG,
SMA 12.5, SMA 9.5”
Revise Note 2. and add Note 6 to Article 1030.02 of the Standard Specifications to read:
“Item Article/Section
(g)Performance Graded Asphalt Binder (Note 6) 1032
(h) Fibers (Note 2)
Note 2. A stabilizing additive such as cellulose or mineral fiber shall be added to the SMA mixture according to Illinois Modified AASHTO M 325. The stabilizing additive shall meet the Fiber Quality Requirements listed in Illinois Modified AASHTO M 325. Prior to approval and use of fibers, the Contractor shall submit a notarized certification by the producer of these materials stating they meet these requirements. Reclaimed Asphalt Shingles (RAS) may be used in Stone Matrix Asphalt (SMA) mixtures designed with an SBA polymer modifier as a fiber additive if the mix design with RAS included meets AASHTO T305 requirements. The RAS shall be from a certified source that produces either Type I or Type 2. Material shall meet requirements noted herein and the actual dosage rate will be determined by the Engineer.
Note 6. The asphalt binder shall be an SBS PG 76-28 when the SMA is used on a full-depth asphalt pavement and SBS PG 76-22 when used as an overlay, except where modified herein. The asphalt binder shall be a SBS PG 76-22 for IL-4.75, except where modified herein..”
Revise table in Article 1030.05(a) of the Standard Specifications to read:
“MIXTURE COMPOSITION (% PASSING) 1/
Sieve Size
IL-19.0 mm SMA 12.5 SMA 9.5 IL-9.5mm IL-9.5FG IL-4.75 mm min max min max min max min max min max min max
City of Joliet
1 1/2 in (37.5 mm)
1 in.
(25 mm) 100
3/4 in.
(19 mm) 90 100 100
1/2 in.
(12.5 mm) 75 89 80 100 100 100 100 100
3/8 in.
(9.5 mm) 65 90 100 90 100 90 100 100
#4 (4.75 mm) 40 60 20 30 36 50 34 69 60 756/ 90 100
#8 (2.36 mm) 20 42 16 24 4/ 16 324/ 34 5/ 52 2/ 45 606/ 70 90
#16 (1.18 mm) 15 30 10 32 25 40 50 65
#30 (600 m) 12 16 12 18 15 30
#50 (300 m) 6 15 4 15 8 15 15 30
#100 (150 m) 4 9 3 10 6 10 10 18
#200 (75 m) 3.0 6.0 7.0 9.0 3/ 7.5 9.5 3/ 4.0 6.0 4.0 6.5 7.0 9.0 3/
#635 (20 m)
≤ 3.0 ≤ 3.0
Ratio Dust/Asphalt Binder
1.0 1.5 1.5 1.0
1.0 1.0
1/ Based on percent of total aggregate weight.
2/ The mixture composition shall not exceed 44 percent passing the #8 (2.36 mm) sieve for surface courses with Ndesign = 90.
3/ Additional minus No. 200 (0.075 mm) material required by the mix design shall be mineral filler, unless otherwise approved by the Engineer.
4/ When establishing the Adjusted Job Mix Formula (AJMF) the percent passing the #8
(2.36 mm) sieve shall not be adjusted above the percentage stated on the table.
5/ When establishing the Adjusted Job Mix Formula (AJMF) the percent passing the #8
(2.36 mm) sieve shall not be adjusted below 34 percent.
6/ When the mixture is used as a binder, the maximum shall be increased by 0.5 percent passing.”
Revise Article 1030.05(b) of the Standard Specifications to read:
(b) Volumetric Requirements. The target value for the air voids of the HMA shall be 4.0 percent, for IL-4.75 and SMA mixtures it shall be 3.5 percent and for Stabilized Subbase it shall be
3.0 percent at the design number of gyrations. The voids in the mineral aggregate (VMA) and
City of Joliet voids filled with asphalt binder (VFA) of the HMA design shall be based on the nominal maximum size of the aggregate in the mix and shall conform to the following requirements.
Voids in the Mineral Aggregate (VMA), % Minimum for Ndesign
Mix Design 30 50 70 80 90
IL-19.0 13.5 13.5 13.5
IL-9.5 15.0 15.0
IL-9.5FG 15.0 15.0
IL-4.751/ 18.5
SMA-12.51/2/5/ 17.03//16.04/
SMA-9.51/2/5/ 17.03//16.04/
IL-19.0L 13.5
IL-9.5L 15.0
1/ Maximum draindown shall be 0.3 percent according to Illinois Modified
AASHTO T 305.
2/ The draindown shall be determined at the JMF asphalt binder content at the mixing temperature plus 30°F.
3/ Applies when specific gravity of coarse aggregate is ≥ 2.760.
4/ Applies when specific gravity of coarse aggregate is < 2.760.
5/ For surface course, the coarse aggregate can be crushed steel slag, crystalline crushed stone or crushed sandstone. For binder course, coarse aggregate shall be crushed stone (dolomite), crushed gravel, crystalline crushed stone, or crushed sandstone”
Revise the last paragraph of Article 1102.01 (a) (5) of the Standard Specifications to read:
“IL-4.75 and Stone Matrix Asphalt (SMA) mixtures which contain aggregate having absorptions greater than or equal to 2.0 percent, or which contain steal slag sand, shall have minimum surge bin storage plus haul time of 1.5 hours.”
Revise the first and second paragraphs of Articles 1030.06(c)(2) of the Standard Specifications to read:
“(2) Personnel. The Contractor shall provide a QC Manager who shall have overall responsibility and authority for quality control. This individual shall maintain active certification as a Hot-Mix Asphalt Level II technician.
In addition to the QC Manager, the Contractor shall provide sufficient personnel to perform the required visual inspections, sampling, testing, and documentation in a timely manner.
City of Joliet
Mix designs shall be developed by personnel with an active certification as a Hot-Mix Asphalt Level III technician. Technicians performing mix design testing and plant sampling/testing shall maintain active certification as a Hot-Mix Asphalt Level I technician.
The Contractor may provide a technician trainee who has successfully completed the Department’s “Hot-Mix Asphalt Trainee Course” to assist in the activities completed by a Hot-Mix Asphalt Level I technician for a period of one year after the course completion date. The Contractor may also provide a Gradation Technician who has successfully completed the Department's "Gradation Technician Course" to run gradation tests only under the supervision of a Hot-Mix Asphalt Level II Technician. The Contractor shall provide a Hot-Mix Asphalt Density Tester who has successfully completed the Department's "Nuclear Density Testing” course to run all nuclear density tests on the job site.”
Add Article 1030.06(d)(3) to the Standard Specifications to read:
“(3) The Contractor shall take possession of any Department unused backup or dispute resolution HMA mixture samples or density specimens upon notification by the Engineer. The Contractor shall collect the HMA mixture samples or density specimens from the location designated by the Engineer and may add these materials to RAP stockpiles according to Section 1031.”
Revise the second paragraph of Articles 1030.07(a)(11) and 1030.08(a)(9) of the Standard Specifications to read:
“When establishing the target density, the HMA maximum theoretical specific gravity (Gmm) will be based on the running average of four available Department test results for that project. If less than four Gmm test results are available, an average of all available Department test results for that project will be used. The initial Gmm will be the last available Department test result from a QMP project. If there is no available Department test result from a QMP project, the Department mix design verification test result will be used as the initial Gmm.”
Revise the Quality Control Limits table in Article 1030.09(c) to read:
CONTROL LIMITS
Parameter
IL-19.0, IL-9.5,
IL-9.5FG, IL-19.0L,
IL-9.5L
SMA-12.5,
SMA-9.5
IL-4.75
Individual Test
Moving Avg. of 4
Individual Test
Moving Avg. of 4
Individual Test
Moving Avg. of 4
% Passing: 1/ 1/2 in. (12.5 mm) ± 6 % ± 4 % ± 6 % ± 4 % 3/8 in. (9.5mm) ± 4 % ± 3 % # 4 (4.75 mm) ± 5 % ± 4 % ± 5 % ± 4 % # 8 (2.36 mm) ± 5 % ± 3 % ± 4 % ± 2 % # 16 (1.18 mm) ± 4 % ± 2 % ± 4 % ± 3 % # 30 (600 µm) ± 4 % ± 2.5 % ± 4 % ± 2.5 %
City of Joliet
Total Dust Content # 200 (75 µm) ± 1.5 % ± 1.0 % ± 1.5 % ± 1.0 %
Asphalt Binder Content
± 0.3 % ± 0.2 % ± 0.2 % ± 0.1 % ± 0.3 % ± 0.2 %
Air Voids 2/ ± 1.2 % ± 1.0 % ± 1.2 % ± 1.0 % ± 1.2 % ± 1.0 %
Field VMA 3/ -0.7 % -0.5 % -0.7 % -0.5 % -0.7 % -0.5 %
1/ Based on washed ignition oven or solvent extraction gradation.
2/ The air voids target shall be 3.2 to 4.8 percent.
3/ Allowable limit below minimum design VMA requirement.
Revise Article 1030.09(g)(1) of the Supplemental Specifications with the following:
“(1) The Contractor shall sample approximately 200 lb (91 kg) of mix as required for the
Department’s random mixture verification tests according to Article 1030.09(h)(1).”
Revise Article 1030.09(g)(2) of the Standard Specifications to read:
“(2) The Contractor shall complete split verification sample tests listed in the Limits of Precision table in Article 1030.09(h)(1).”
Revise the second sentence of Article 1030.09(h)(1) of the Supplemental Specifications with the following:
“The random verification mixture sampling interval will be a maximum of 3,000 tons
(2,720 metric tons). The Engineer will randomly identify one sample per interval, with a minimum of one sample per mix. If the remaining mix quantity is 600 tons (544 metric tons) or less, the quantity will be combined with the previous interval in the Engineer’s random sample identification. If the required tonnage of a mixture for a single pay item is less than 250 tons (225 metric tons) in total, the Engineer will waive mixture verification sampling and testing.”
Revise the third paragraph of Article 1030.09(h)(1) of the Standard Specifications to read:
“If comparisons of the mixture verification test results are outside the above limits of precision, the Department will verify the results by testing the retained split sample.
The retest results will replace all the original results.”
In the Supplemental Specifications, replace the revision for the end of the third paragraph of…