Questions and Answers.pdf

PDF 188 KB Posted

Attached to
FMC Devens - Replace Fire Alarm Panels
Solicitation number
IFBP02051200001
Issued by

View the file

Other files

File Type Posted
AMENDMENT 0002.pdf PDF
Devens Abstract.pdf PDF
AMENDMENT 0001.pdf PDF
Prebid Site Visit Minutes Sign In and Pictures.pdf PDF
2 - Solicitation Document 03212012.pdf PDF
3 - STATEMENT OF WORK.pdf PDF
1 - COVER LETTER.pdf PDF
6 - NCIC Form.pdf PDF
4 - DRAWING.pdf PDF
5 - Wage Rate MA01 01062012.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FMC DEVENS – REPLACE FIRE ALARM PANELS

PROJECT 2A1P QUESTIONS

SOLICITATION IFBP02051200001

The following questions were posed by a contractor for the above referenced solicitation:

SUBMITTED BY: R.B. ALLEN

1) The specifications calls for the breaking of a shield wire every 10 devices. There was no indication of shielded wiring in the building. Is this necessary?

CLARIFICATION: THIS REQUIREMENT WAS REMOVED IN AMENDMENT 0001 ISSUED 4/6/2012.

2) The specifications call for “Manufacturer” training. Is this on-site or at the manufacturers’ place of business?

CLARIFICATION: Operation training for line staff will be conducted on-site. Diagnostic training for Facilities staff will be held on-site as well.

3) The specification call for “verification” of the entire system upon completion. Is this meant to perform a 100% test on all of the systems upon completion?

CLARIFICATION: Yes, a 100% test is required.

4) During system “down-time” will a fire watch be provided?

CLARIFICATION: FMC Devens will provide fire watch at all times when required.

5) Upon removal of the existing equipment, is it the contractors’ responsibility to dispose of all the cabinets, batteries and assorted construction debris?

CLARIFICATION: FMC Devens will dispose of all old equipment, cabinets, batteries, debris, etc.

6) Some of the existing annunciators are flush mounted. Since the new annunciator is a different size box, would surface mount be acceptable?

CLARIFICATION: Surface mount boxes are acceptable, but the size will need to be provided to FMC Devens prior to installation to ensure that the new boxes will not encroach on the available width in passageways. If the surface mount boxes are too large another solution will have to be found.