This is an Invitation for Bids (IFB) package issued by the Colorado Division of Parks and Wildlife for the James M Robb Colorado River State Park Island Acres Wastewater Improvements project (C26CR1). The project scope includes removal and replacement of an existing submersible pump lift station with a new above-ground lift station package, wet well and grinder system, removal and replacement of aeration basin and evaporation lagoon liners, and associated site work. The bid schedule contains 23 line items including mobilization, construction surveying, demolition, lift station installation, grinder system installation, liner installation (aeration basin at 1,520 square yards and evaporation lagoon at 6,200 square yards), cattail plantings, site restoration, and time-and-equipment provisions for various equipment categories. The mandatory pre-bid conference is scheduled for November 30, 2026 at 11:00 AM at the project site (1055 Interstate 70, Palisade, Colorado 81520). Written questions are due by December 4, 2026 at 3:00 PM. Sealed bids must be received by December 15, 2026 at 10:00 AM. The Notice of Award is tentatively scheduled for December 18, 2026, with a Notice to Proceed on January 1, 2027. The contract term is 90 calendar days from the Notice to Proceed, with substantial completion required by April 1, 2027 for campground and facility spring reopening.

A five percent bid bond, certified check, or cashier's check is required for all bids of $50,000 or more. Performance and material and labor bonds at 100 percent of the contract price are required when the bid equals or exceeds $150,000. Colorado prevailing wage rates apply to this project exceeding $500,000 as outlined in Appendix A. At least eighty percent of the work must be performed by Colorado labor, with written justification required if this percentage cannot be met. Service Disabled Veteran-Owned Small Business (SDVOSB) entities registered and verified with the U.S. Department of Veterans Affairs may receive a five percent bid preference on price. Resident bidder preferences apply per C.R.S. 24-103-906. The project is not subject to Davis-Bacon wage rates but requires compliance with Colorado prevailing wage statutes and the LCPTracker cloud-based labor compliance and certified payroll application. Insurance requirements include workers' compensation, commercial general liability ($1,000,000 combined single limit), automobile liability ($1,000,000), and pollution liability ($1,000,000 each occurrence and aggregate). Liquidated damages are set at $500 per calendar day for work remaining incomplete after the contract time expires. The contractor must demonstrate qualification through three similar projects completed within the past five years involving lift station and synthetic membrane liner installations for wastewater applications.

View the file

Other files

File Type Posted
Addendum_1_IFB1_2027_45.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

James M Robb CO River SP - Island Acres - Wastewater Improvements

BIDDING AND CONTRACT INFORMATION

PROJECT NO. C26CR1

IFB1: 2027*45

MANDATORY PRE-BID CONFERENCE: November 30, 2026 at 11:00 AM

BID OPENING: December 15, 2026 at 10:00 AM

TABLE OF CONTENTS

C26CR1

BIDDING AND CONTRACT INFORMATION Starting Page

Invitation for Bids Bid Schedule Measurement and Payment Instructions to Bidders Contractor’s Qualifications and References

SPECIFICATIONS

Section 02050 – Mobilization Section 02070 – Demolition and Removal Section 02200 – Earthwork Section 02510 – Crusher Fines Surfacing Section 02577 – Fiberglass Wet Wells Section 02778 – Lagoon Liner System Section 02921 – Finish Grading and Soil Preparation Section 02934 – Seeding and Mulching Section 03200 – Concrete Reinforcement Section 03300 – Cast In Place Structural Concrete Section 11330 – Sewage Grinders Section 15150 – Packaged Lift Stations

CONSTRUCTION DRAWINGS

01 – Cover Sheet 02 – Site Map - Existing 03 – Site Map - Proposed 04 – Site Map – Lift Station 05 – Proposed Lift Station Details 06 – Site Map – Aeration Basin 07 – Aeration Basin Grading Plan 08 – Aeration Basin Details 09 – Site Map – Evaporation Lagoon 10 – Evaporation Lagoon Plan and Profile 11 – Evaporation Lagoon Details

APPENDICES

Appendix A ...................................... Prevailing Wage Determination for Mesa County, CO

Appendix B ........................... 1995 Design Drawings for Island Acres Wastewater Treatment

Appendix C ................................................ General Conditions for Capital Construction

Appendix D ................................................................. Sample Construction Contract

END OF TABLE OF CONTENTS

INVITATION FOR BIDS

The Colorado Division of Parks and Wildlife is accepting sealed bids for the removal and replacement of the existing submersible pump lift station with a new above ground lift station package, wet well and grinder, removal and replacement of aeration basin liners and evaporation lagoon liners, and associated site work.

Sealed bids will be received by Colorado Parks and Wildlife, 711 Independent Ave, Grand Junction, CO 81505 until December 15, 2026 at 10:00 AM, after which the bids will then be made public.

Bids shall be submitted using the form provided in the project specifications. On-line bid submittals are NOT accepted.

A five-percent (5%) Bid Bond, certified check, or cashier’s check is required with bid proposals of $50,000.00 or more.

Mandatory Pre-bid conference: November 30, 2026 at 11:00 AM at the project site. Meet at the Lift Station.

Project Address: James M Robb - CO River State Park - Island Acres 1055 Interstate 70 Palisade, CO, 81520 Mesa County

Project Coordinates: Latitude: 39° 10' 18" N Longitude: 108° 17' 44" W View Google Map Location – GOOGLE MAPS LINK

Contractor Questions: All questions related to the project shall be submitted via e-mail to the Project Manager, Eric Blake at eric.blake@state.co.us. The deadline for questions is December 4, 2026 at 3:00 PM. Questions submitted after the deadline will not be addressed. All questions and answers will be posted as solicitation amendments on the Vendor Self Service (VSS) website. Bidders may not automatically be notified of the existence of a modification or addendum. It is the responsibility of the bidder to check the VSS website periodically to see if any modifications have been issued. Failure to retrieve such modifications and include their provisions in your bid response may result in your bid being deemed non-responsive.

Plans and specifications are available for all bidders on the web at: www.colorado.gov/vss

The following is a tentative project schedule, which will be revised and expanded by the selected Contractor and submitted to the Project Manager for review:

MANDATORY PRE-BID CONFERENCE November 30, 2026 at 11:00 AM

WRITTEN QUESTIONS DUE December 4, 2026 at 3:00 PM

BID OPENING December 15, 2026 at 10:00 AM

NOTICE OF AWARD December 18, 2026 (Tentative)

NOTICE TO PROCEED January 1, 2027 (Tentative)

SUBSTANTIAL COMPLETION April 1, 2027 https://maps.app.goo.gl/zmvFYnX4nrzBPWVa8 http://www.colorado.gov/vss

BID SCHEDULE

DEPARTMENT OF NATURAL RESOURCES

COLORADO PARKS AND WILDLIFE

STATE OF COLORADO

Proposes to furnish all labor, equipment, materials, and incidentals needed to complete the James M Robb CO River SP - Island Acres - Wastewater Improvements. The work shall be completed in 90 calendar days from the date of the Notice to Proceed. We have read and made, the “Instructions to Bidders”, the “General Conditions for Capital Construction”, the Written Specifications, and the Construction Drawings part of this bid.

Technical Specifications related to construction materials and methods for work embraced under this Contract shall consist of references to, but not limited to, the Colorado Department of Transportation Most Current Standard Specifications for Roads and Bridge Construction.

Special attention should be given to these references and revisions noted within.

UNITS: LS= lump sum, SY= square yard, CY= cubic yard, TON= tons, HR = hours

Service Disabled Veteran Owned Small Business Statement (SDVOSB): The undersigned bidder shall certify by checking below that the corporation, partnership, or sole proprietorship IS or IS NOT claiming a 5% bid preference in accordance with C.R.S. 24-103-211. SDVOSB certification must be included with your bid.

Is: Is Not:

Colorado Labor: The undersigned bidder shall certify by indicating the percentage of Colorado labor of the total workforce to be utilized for this project in accordance with C.R.S. 8-17-101.

Colorado Labor shall be employed to perform at least 80% of the work on a public works project greater that $500,000.00. A written justification for not meeting this percentage must be included with your bid.

% of Colorado Labor: ___________

Addendum Inclusion Statement: The undersigned bidder shall certify by listing below that all Addenda have been considered and included as part of the Contractor’s proposal. The Addendum numbers that the Contractor has included as part of his proposal shall be listed in the space provided.

Addenda:

Base Bid: Furnish and install all materials and labor for the completion of the Base Bid Improvements per the Construction Drawings and Specifications.

Base Bid Items: Quant ity

Unit Unit Cost Total Item Cost

1. Mobilization 1 LS $ $

2. Construction Surveying 1 LS $ $

3. Demolition and Site Preparation 1 LS $ $

4. Construction Access Improvements 1 LS $ $

5. Remove and Replace Existing 5-ft Fiberglass Wet Well

1 LS $ $

6. Furnish & Install New Above Ground Lift Station with Bypass Piping, Complete

1 LS $ $

7. Furnish & Install New Sewage Grinder with Controller and Mounting and Retrieval Systems, Complete

1 LS $ $

8. Sludge Removal & Disposal from Aeration Basin & Wet Well

1 LS $ $

9. Strip, Stockpile, and Re-spread Topsoil 3,100 CY $ $

10. Salvage, Stockpile, and Place Cobble 112 CY $ $

11. Excavation and Placement at Proposed Berm Location

1,285 CY $ $

12. Excavation and Haul-Off of Excess Topsoil with Testing

550 CY $ $

13. Import & Install Liner Bedding Material 2,700 TON $ $

14. Install New Liner Aeration Basin 1,520 SY $ $

15. Install New Liner Evaporation Lagoon 6,200 SY $ $

16. Cattail Plantings Evaporation Lagoon 2,950 SY $ $

17. Site Restoration, Seeding, Mulching, and Cleanup

1 LS $ $

18. Excavator 80 HR $ $

19. Grader 80 HR $ $

20. Loader 80 HR $ $

21. Tandem Dump Truck 80 HR $ $

22. Skid Steer Loader 80 HR $ $

23. Laborer 160 HR $ $

Total Base Bid AMOUNT _$______________________

Total Base Bid AMOUNT:(PLEASE WRITE OUT BID AMOUNT)

DOLLARS

(A Corporate Signature Block)

Company Name

A Corporation

Date , 20

Colorado VSS Vendor ID# (if available) _____________________________________

By President Attested to by Secretary

(A Partnership Signature Block) A limited partnership of , general partner;

doing business as (dba)

Company Name

Colorado VSS Vendor ID# (if available) _____________________________________ by General Partner

(A Sole Proprietorship Signature Block) A Sole Proprietorship of (dba)

Colorado VSS Vendor ID# (if available) _____________________________________ by Owner

MEASUREMENT AND PAYMENT

The following descriptions delineate the Work, materials, and how measurements of completed Work will be made and paid for, for each bid item in the Bid Schedule. The Bidder is to read these definitions and price their proposal accordingly.

Bid Item 1 – Mobilization This bid item includes the mobilization of personnel, equipment and supplies at the project site in preparation for the Work, as well as the establishment and maintenance for the duration of the Contract of the Contractor’s sanitary facilities, protective fencing and barricades not included elsewhere, necessary facilities, and all other costs incurred or labor and operations which must be performed prior to beginning the other items under the Contract. This item shall include any costs for required bonding of this project. This item shall also include marshalling, disassembly and security of all items indicated on the Construction Drawings or Specifications or installed as part of mobilization and demobilization from the site. Payment will be made in two installments: the first 60% will be paid on the first month’s pay estimate, and the remaining 40% after the final cleanup has been completed and approved.

Bid Item 2 – Construction Surveying This bid item includes establishing and maintaining all horizontal and vertical control, setting reference stakes, clearing limits, layout stakes, batter boards, and all other construction staking required for the project. The work shall be done under the supervision of a registered professional land surveyor (P.L.S.) registered in the State of Colorado. This bid item covers all aspects of the construction staking associated with the project, including buildings, sitework, roads, parking lots, and utilities. As-built drawings required to document construction shall be considered a requirement of this bid item. Measuring and surveying for payment quantities and the calculations and documentation required for construction quantities are also included. Progress payments will be made periodically based on an estimated completed percentage of the lump sum bid price.

Bid Item 3 – Demolition and Site Preparation This bid item includes all labor, materials, and equipment required to demolish and appropriately dispose of items identified for removal, demolition, and disposal within the limits of work. Items include but are not limited to:

• Existing submersible pumps, piping, fittings, rails, and controls, including the pumping and disposal of any sewage in the wet well;

• Existing (2) layers of liners at the Aeration Basin;

• Existing (2) layers of liners at the Evaporation Lagoon; and

• Concrete flatwork, wooden fencing, and other items required in preparation for the above ground lift station concrete pad

The handling, transportation, cleaning, and disposal of sewage/sludge/biosolids shall be performed in accordance with all federal, state, and local laws, regulations, and standards.

Payment will be made at the lump sum bid price.

This bid item also includes the temporary removal of aeration basin equipment as needed to perform work, and gate/fence sections at the aeration basin and along the construction access route. The unit contract price includes all labor, material, equipment, and disposal fees for completion of the work in accordance with the Drawings and Specifications. Payment will be made at the lump sum bid price.

Bid Item 4 – Construction Access Improvements This bid item includes all labor, materials, equipment, and incidental costs connected with performing improvements to existing site conditions to accommodate temporary construction access. This bid item includes but is not limited to: furnishing, importing, and installing aggregate base course as needed for construction equipment access, furnishing and installing metal plate(s) or other temporary measures for the protection of existing infrastructure. A full description of the contractor’s proposed construction access improvements shall be detailed in the ‘Construction Control Plan’ submittal and approved by CPW prior to any work. Payment will be made at the LUMP SUM bid price.

Bid Item 5 – Remove and Replace Existing 5-ft Fiberglass Wet Well This bid item includes all material, labor, equipment, and incidental costs connected with planning, demolition, submittals, transportation, handling, storage, excavation, hauling, disposal, and installation of new -ft fiberglass wet well. This bid item also includes but is not limited to: the disconnection and re-connection of piping from the existing wet well to the new wet well, backfilling, and compacting within the limits of work as noted on the plans of a 5’ diameter FRP wet well. Measurement and Payment for this bid item will be made upon completion and acceptance of the completed wet well, complete and ready to use, at the LUMP SUM bid price.

Bid Item 6 – Furnish and Install New Above Ground Lift Station with Bypass Piping, Complete This bid item includes all labor, materials, equipment, independent testing services, and incidental costs connected with furnishing and installing a pre-engineered above ground pump system, complete and ready to use, as shown on the plans and described in the specifications.

This bid item also includes all required submittals, certifications, permits, inspections, demonstrations and trainings to CPW personnel. Also included in this line item is the furnishing and installation of the concrete pad including reinforcement steel, formwork, inspections, testing, and all other costs connected with the concrete pad. This bid item also includes all required electrical services and connections to the existing electrical service panel and physical connections to the existing PVC sanitary sewer and force main pipe. Additionally, this line item shall include any and all bypass piping requirements (pumps, pipes, hoses, storage tanks if necessary) to maintain lift station functionality during Park operations if installed after April 1.

Payment will be made at the LUMP SUM bid price for the completely installed, tested, and approved lift station complete and ready to use.

Bid Item 7 – Furnish and Install New Sewage Grinder with Controller and Mounting and Retrieval Systems, Complete This bid item includes all labor, materials, submittals, equipment, and incidental costs connected with furnishing and installing a solids reduction sewage grinder system, complete and ready to use, as shown on the plans and described in the specifications. This bid item includes but is not limited to: furnishing and installing the solids reduction grinder, the controller system, and the wet well mounting and retrieval system as shown on the plans and described in the specifications. Also included are all required electrical services to connect the grinder and controller system to the existing electrical service panel and physical connections and hardware. Payment will be made at the LUMP SUM bid price for the completely installed, tested, and approved sewage grinder, controller, and mounting and retrieval system complete and ready to use.

Bid Item 8 – Sludge Removal and Disposal from Aeration Basin and Wet Well

This bid item includes all material, labor, equipment, and incidental costs connected with the removal, handling, and disposal of sludge from the aeration basin and wet well. The handling, transportation, cleaning, and disposal of sludge shall be performed in accordance with all federal, state, and local laws, regulations, and standards. Payment will be made at the LUMP SUM bid price.

Bid Item 9 – Strip, Stockpile, and Re-spread Topsoil This bid item includes all material, labor, equipment, and incidental costs connected with the removal, handling, transportation, and staging of topsoil from the Evaporation Lagoon.

Payment will be made at the unit price for CUBIC YARDS of topsoil stockpiled striped, stockpiled, and spread over newly installed liner as demonstrated by the Contractor’s independent surveyor.

Bid Item 10 – Salvage, Stockpile, and Place Cobble This bid item includes all material, labor, equipment, and incidental costs connected with the removal, handling, transportation, staging, and placement of cobble from the Evaporation Lagoon at locations shown on the drawings. Contractor shall take all measures necessary to ensure protection of the existing effluent PVC pipe including but not limited to: requiring only small equipment or hand placement of cobble near the pipe. A pre- and post-placement pipe inspection shall be performed by the Contractor and the CPW Project Manager. Payment will be made at the unit price for CUBIC YARDS of cobble salvaged, stockpiled, and reinstalled as demonstrated by the Contractor’s independent surveyor.

Bid Item 11 – Excavation and Placement at Proposed Berm Location This bid item includes all material, labor, equipment, and all incidental costs connected with the excavation, grading, handling, transportation, placement, and compaction of excess excavated material from the Aeration Basin and the Evaporation Lagoon as shown on the plans and approved by the CPW Project Manager. Excavations shall be made to the locations and elevations shown on the drawings. Measurement for this bid item will be based on excavated and graded volumes to the locations and elevations shown on the plans based on in-situ conditions. Payment will be made at the contract unit price for CUBIC YARDS of material. Construction survey exhibits and volume calculations are required to accompany the pay applications.

Bid Item 12 – Excavation and Haul-Off of Excess Topsoil with Testing This bid item includes all material, labor, equipment, independent testing services, and all incidental costs connected with the excavation, testing, handling, transportation, and disposal fees for excess topsoil material from the Evaporation Lagoon as shown on the plans and approved by the CPW Project Manager. Contractor shall assume excess topsoil will be considered a Class A biosolid per CDPHE Regulation 64. Contractor shall provide independent testing services if required by the disposal landfill. Measurement and payment for this bid item will be based on CUBIC YARDS of material hauled-off from the site and disposed of, with load tickets and disposal receipts required with pay application.

Bid Item 13 – Import and Install Liner Bedding Material This bid item includes all material, labor, equipment, and incidental costs connected with importing and installing liner bedding material as noted on the plans and specifications. This bid item includes subgrade preparation, grading, and placement of the imported bedding.

Bedding material shall be free of rocks and organic material no greater than 3” in diameter, moisture treated and compacted to 95% of standard proctor density. Measurement for this item will be based on load tickets delivered to the site, and paid based on the contract unit price in TONS. Load tickets shall be submitted by the Contractor with the pay application.

Bid Item 14 – Install New Liner Aeration Basin This bid item includes all material, labor, equipment, independent testing services, and incidental costs connected with installing a new liner at the aeration basin as noted on the plans and specifications. Installation of liner penetrations, testing and verification of seaming, leak testing, and compaction of liner trenches are considered incidental to the work and will not be paid separately. Upon delivery and appropriate storage of the liner material on site, 20% of this bid item will be paid based solely on “Materials On Hand” at the job site.

Measurement and payment for this bid item will be based on the SQUARE YARDS of liner placed, based on quantities from the Contractor’s independent surveyor.

Bid Item 15 – Install New Liner Evaporation Lagoon This bid item includes all material, labor, equipment, independent testing services, and incidental costs connected with installing a new liner at the Evaporation Lagoon as noted on the plans and specifications. Installation of liner penetrations, testing and verification of seaming, leak testing, and compaction of liner trenches are considered incidental to the work and will not be paid separately. Upon delivery and appropriate storage of the liner material on site, 20% of this bid item will be paid based solely on “Materials On Hand” at the job site.

Measurement and payment for this bid item will be based on the SQUARE YARDS of liner placed, based on quantities from the Contractor’s independent surveyor.

Bid Item 16 – Cattail Plantings Evaporation Lagoon This bid item includes all material, labor, equipment, independent testing services, and incidental costs connected with furnishing and installing cattail plantings at the Evaporation Lagoon. Payment will be made on the SQUARE YARDS of cattails installed based on quantities from the Contractor’s independent surveyor.

Bid Item 17 – Site Restoration, Seeding, Mulching, and Cleanup This bid item includes all material, labor, equipment, independent testing services, and incidental costs connected with restoring the site following construction to pre-project conditions and elevations, including but not limited to: ripping/decompaction and seeding/mulching all disturbed areas, removing any temporary construction access items, finish grading, and regarding and resurfacing gravel pedestrian trail access roads (if applicable). Payment will be made at the LUMP SUM bid price after the restoration, cleanup, and seeding/mulching has been approved by the CPW Project Manager.

Bid Items 18 - 22: Time & Equipment These bid items will only apply to additional construction requests by the Project Manager that are not included in other bid items. Payment will be made at the contract unit price for the number of HOURS operated or worked and includes operator, fuel, labor, tools and all support necessary for operation. A total of two hours for mobilization/demobilization will be paid on each piece of equipment requested not already located at the job site. The number of hours to be paid under these items will be discussed and agreed to in advance by the Contractor and the Project Manager. Bid Item pricing shall be based on the following types of equipment:

Bid Item 18: Excavator – Cat 330D series or equivalent

Bid Item 19: Grader – Cat 140M series or equivalent

Bid Item 20: Loader– Cat 950H series or equivalent

Bid Item 21: Tandem Dump Truck

Bid Item 22: Skid-Steer Loader – Cat 226B series or equivalent

Bid Item 23: Laborer

As a footnote to the bid items, the following items have NOT been included as specific pay items and ARE to be considered incidental to the construction for which they are required:

• Testing

• State electrical permits and inspections

• Water, watering, and dust control

• Dewatering

• Temporary facilities and utilities

• Traffic control

• Barricades and other required safety provisions

This concludes the bid items listed in the proposal. The only payments made under this contract are for the bid items listed herein, and no additional payments will be made to the Contractor for work specified or shown in these Contract Documents. If any discrepancies exist, the Contractor shall notify the Project Manager in writing, requesting clarification.

END OF SECTION

INSTRUCTIONS TO BIDDERS

PROJECT: James M Robb CO River SP - Island Acres - Wastewater Improvements

PROJECT NO: C26CR1

1. Bidders must review the plans and specifications, construction site and conditions in their entirety, and determine the problems that may be encountered in performing the work.

The bidder shall include any costs associated with his/her findings in the prices quoted in the proposal. Documents will be available on the State of Colorado VSS website www.colorado.gov/vss. No additional copies of the drawings and specifications will be provided by the Division of Parks and Wildlife at any time before or after the bid opening.

2. All work must conform to the requirements stated in the “General Conditions for Capital Construction”.

3. All questions concerning this project shall be in writing directed to the Project Manager identified in the Invitation for Bids. The Invitation for Bids also identifies important dates and deadlines for this project.

4. BID SCHEDULE:

A. The bidder shall include on the signature page, their Vendor ID (if available) obtained from registration on the Colorado VSS website.

B. The bidder shall complete the Minority Business, Service Disabled Veteran Owned Small Business and Colorado Labor statements as well as acknowledge addendum(s) on the first page of the Bid Schedule.

C. All bid items shall include a unit and extended price or the bid will be disqualified. The bidder shall write in words and numerically the total base bid and add/alternate (if applicable) amounts on the included Bid Schedule. If conflicts exist between the written words and the numerical amount, the actual line item unit cost shall take precedence.

D. The Bid Schedule shall be signed manually in ink:

1) If the bidder is a corporation, use the corporate signature block, insert the name of the state in which the company was incorporated, and include the Employer Identification Number (E.I.N.) in the appropriate spaces. The bid must be signed by an officer (President or Vice President), and the title indicated. The signature of the officer shall be attested to by the Secretary and properly sealed. Cross out incorrect titles and insert correct ones, if necessary.

2) If the bidder is a partnership, use the partnership signature block. Cross out the word "Limited" if the partnership is a general one. Print each partner's name and note the proportion of the partnership that each partner has. The majority or general partner must sign the proposal. The same person must sign the contract, if awarded. Print the company name in the appropriate space.

3) If the bidder is a proprietorship, use the sole proprietorship signature block, print in the owner's name, Social Security number, and the business name in the blanks provided, and the owner signs the owner blank.

5. BID BOND: A bid bond is required for all competitive sealed bids when the price exceeds

$50,000. A bid guarantee in an amount not less than five percent (5%) of the total bid price must be submitted in the form of a firm commitment, such as a bid bond, bank money order, certified check or cashier's check. Checks or money orders should be made payable to the Treasurer, State of Colorado. An irrevocable letter of credit is not acceptable as a bid guarantee. Failure to furnish a bid guarantee in the proper form and amount by the time set for opening of bids may be cause for rejection of the bid.

6. PERFORMANCE BOND, LABOR AND MATERIAL BOND: The successful bidder shall furnish a bond in the amount of 100% of the contract price for performance and for material and labor payment when bid is equal to or exceeds $150,000. The bond shall be executed on the standard State of Colorado form. The State requests that the Surety and Contractor leave the date of the Contract found on the first page of each bond form, blank and we will ‘pen’ in the date after the Controller executes the Contract. These bonds will be submitted along with the standard State Agreement form within 10 days of the "Notice of Award."

7. VENDOR BOND ASSISTANCE: Any vendors that need support responding to solicitations may contact the Colorado Supplier Diversity Navigator at the Statewide Equity Office of Supplier Diversity dhr.colorado.gov/statewide-equity-office/supplier-diversity. Services provided include assistance with responding to solicitations, interpretation of solicitation documents, technical assistance referrals, availability of resources, and bond assistance under the Construction Statewide Bond Assistance Program dhr.colorado.gov/statewide-equity-office/supplier-diversity/construction-and-bond-assistance, through which eligible contractors can apply for assistance in securing the required bonding. The office can be reached during normal business hours by calling 303-866-5765 or emailing DPA_SupplierDiversityHelp@state.co.us.

8. RESIDENT BIDDER PREFERENCE: When a contract for commodities or services is to be awarded to a bidder (projects >$500,000), a resident bidder shall be allowed a preference against a nonresident bidder equal to the preference given or required by the state in which the nonresident bidder is a resident. (§24-103-906 C.R.S.) A resident bidder is authorized to transact business in the State of Colorado, maintains a place of business in Colorado and pays unemployment compensation taxes.

9. SERVICE DISABLED VETERAN OWNED SMALL BUSINESSES (SDVOSB’s): SDVOSB’s, who are incorporated or organized in Colorado or maintain a place of business or have an office in Colorado and who are officially registered and verified as a SDVOSB by the Center for Veteran Enterprise within the U.S. Department of Veterans Affairs. (www.vip.vetbiz.gov), may receive a 5% preference on their bid. This preference applies only to the price, and the SDVOSB’s must still meet all other qualifications required in the bid. SDVOSB’s claiming this preference shall submit documentation of SDVOSB certification Issued through the U.S. Department of Veterans Affairs in their response to the solicitation. Bid submissions without this documentation will not be given a preference.

10. COLORADO LABOR: Colorado Labor shall be employed to perform at least eighty percent (80%) of the work on a public works project (>$500,000) per CRS 8-17-101. BIDS/CORE notice to require bidder to indicate 80% Colorado labor in bid or proposal and provide written justification if the 80% Colorado labor is not included in the bid. The justification is a requirement of the bid or proposal submittal. State Agency shall waive the 80% requirement and post justification on its web site; if there is reasonable evidence to demonstrate insufficient Colorado labor to perform the work and, if compliance with the 80% would create an undue burden that would substantially prevent a project from proceeding to completion.

Posting of the agency’s written waiver should include but not be limited to contractor’s justification for insufficient available Colorado labor and the agency’s determination that there is an undue burden negatively impacting the project schedule, budget/appropriation, quality/standards of care or any other specific requirement of the project due to compliance with the 80% Colorado labor requirement. The posting of rational should be made on the date of the award and remain for not less than thirty (30) calendar days in a conspicuous web site https://dhr.colorado.gov/statewide-equity-office/supplier-diversity https://dhr.colorado.gov/statewide-equity-office/supplier-diversity/construction-and-bond-assistance https://dhr.colorado.gov/statewide-equity-office/supplier-diversity/construction-and-bond-assistance mailto:DPA_SupplierDiversityHelp@state.co.us http://www.vip.vetbiz.gov/ location of the state agency under the title – “Reporting Requirements for Public Projects as per HB13-1292”.

11. FINAL REPORTING FOR IRON, STEEL, OR RELATED MANUFACTURED ITEMS: This requirement only applies when a contract for a public works project is to be awarded to a bidder (projects >$500,000), for a project that does not receive any federal moneys. At the completion of the project, the Contractor shall provide an accounting of the value and origin of the five most costly manufactured goods incorporated into the project. For the purposes of this reporting, “manufactured goods” contain over fifty percent iron or steel content when it is delivered to the job site for installation. If all the manufacturing processes for the final product take place in the United States, the product shall be considered as originating there.

12. SUBMITTAL OF BID: The completed Bid must be received by the deadline identified in the Invitation for Bid. You must include as part of your bid the following items:

A. Provide completed Bid Schedule as described above.

B. Provide Bid Bond (if required) as described above.

C. SDVOSB certification issued through the U.S Department of Veterans Affairs (if applicable).

D. Colorado Labor Justification if not using 80% Colorado Labor (if applicable).

E. Contractor’s Qualifications and References Statement.

This information is to be enclosed in a sealed envelope marked "SEALED BID". Include the bid opening date and time.

The envelope shall be addressed to:

ATTN: ERIC BLAKE

NORTHWEST REGIONAL OFFICE

COLORADO PARKS AND WILDLIFE

711 INDEPENDENT AVENUE

GRAND JUNCTION, COLORADO 81505

Bidders Name and Address should appear in the Upper Left Corner of the envelope.

13. METHOD OF AWARD: The lowest responsible bid, taking into account the Colorado resident bidder preference provision of Colorado Law, will be determined by and the purchase order or contract will be issued, to the extent that the total dollar amount is within available funds to finance the construction. If all bids exceed such amount, the right is reserved to reject all bids. The Division of Parks and Wildlife reserves the right to reject any or all proposals, to waive informalities, and to accept any proposal deemed desirable.

Additive alternates will be used in determining the lowest responsible bidder within the amount available to finance the contract, added in the numeric order listed. An equal number of alternates shall be added to the base bid of each bidder within funds available to finance the contract for purposes of determining the lowest responsible bidder.

The bidder must be registered to do business in the State of Colorado with the Secretary of State www.sos.state.co.us. A Certificate of Good Standing will be required to process the Agreement.

http://www.sos.state.co.us/

If Federal funds are utilized for this project, the contract cannot be awarded to a contractor which has been disbarred or suspended or is otherwise excluded from or ineligible for participation in federal assistance programs. The excluded parties list can be found at the following web site: https://www.sam.gov/

14. UNIT COST: The price quoted in the proposal shall include the costs of labor, materials, equipment, and incidentals required to provide a fully complete and functioning unit as shown and described in the plans and specifications. The price stated in the proposal shall be complete, and represent total payment for each item in the proposal. No additional payment will be made for the work presented in the proposal.

15. INSURANCE: The successful bidder will be required to submit proof of insurance at the time of executing the agreement. Proof of insurance must be submitted on certificates showing the minimum coverage amounts.

A. The Contractor is required to procure and maintain at all times during the term of this contract the insurance coverage listed below:

1) Workers’ Compensation and Employer’s Liability Insurance, as required by state statute, including occupational disease, covering all of contractor or subcontractor employees acting within the course and scope of their employment.

2) Commercial General Liability Insurance written on ISO occurrence form CG 00 01 10/93 or equivalent, covering premises operations, fire damage, independent contractors, products and completed operations, blanket contractual liability, personal injury, and advertising liability with minimum limits as follows:

a. $1,000,000 combined single limit written on an occurrence basis;

b. $1,000,000 general aggregate;

c. $1,000,000 products and completed operations aggregate; and

d. $50,000 any one fire.

e. If any aggregate limit is reduced below $1,000,000 because of claims made or paid, the contractor shall immediately obtain additional insurance to restore the full aggregate limit and furnish to the State a certificate or other document satisfactory to the State showing compliance with this provision.

3) Automobile Liability Insurance covering any auto (including owned, hired and non-owned autos) with a minimum limit as follows: $1,000,000 each accident combined single limit.

4) Pollution liability policy with minimum limits of $1,000,000 each occurrence and $1,000,000 Annual Aggregate covering any environmental damage caused by the contractor or subcontractor during the Work with the State included as an additionally insured party.

B. The State of Colorado shall be named as an Additional Insured on the Commercial General Liability, Automobile Liability, policy insurance certificates and Colorado Parks and Wildlife must be named as the certificate holder for all coverages 1-3 noted above (leases and construction contracts will require the additional insured coverage for completed operations on endorsements CG 2010 11/85, CG 2037, or equivalent). Coverage required of the contract will be primary over any insurance or self-insurance program carried by the State of Colorado.

C. The Insurance shall include provisions preventing cancellation or non-renewal without at least 45 days prior notice to the State by certified mail.

D. The Insurance shall include a waiver of subrogation for all coverages.

E. The contractor will require all insurance policies in any way related to the contract and secured and maintained by the contractor to include clauses stating that each carrier will waive all rights of recovery, under subrogation or otherwise, against the State of Colorado, its agencies, institutions, organizations, officers, agents, employees and https://www.sam.gov/ volunteers.

F. All policies evidencing the insurance coverage required hereunder shall be issued by insurance companies satisfactory to the State. No later than 15 days prior to the expiration date of any such coverage, the contractor shall deliver the State certificates of insurance evidencing renewals thereof.

16. If the successful bidder, upon acceptance of his bid by the OWNER, fails to execute such further contractual documents, and give such bond(s) (including any necessary coinsurance or reinsurance agreements) as may be required within ten (10) days after receipt of the Notice of Award, the contract may be terminated for default. In such event the CONTRACTOR shall be liable for any cost of procuring the work which exceeds the amount of his bid, and the bid guarantee shall be available toward offsetting such difference.

17. The bidder is not to give any information concerning his proposal to any other bidder or receive any information concerning another proposal.

18. SALES TAX: The Division of Parks and Wildlife is exempt from paying Colorado sales tax.

Any materials and supplies purchased for this contract are exempt. The Contractor will need to obtain an exemption number from the Department of Revenue for this project and each subcontractor is required to obtain one under the general contractor.

19. QUANTITIES: Quantities stated in the bid schedule and construction documents are estimates only and may increase or decrease during construction. The contractor will perform the required quantity of work based on the unit prices stated in the Bid Schedule except as provided in Section 4.2 of the "General Conditions for Capital Construction."

20. WORK STOPPAGE: Work stoppage is a possibility. The contractor must request all shutdowns or stoppages in writing. If a shutdown is granted, the Division will pay for only work that has been totally completed. No advanced payment of mobilization will be made.

21. CONSTRUCTION SCHEDULE: The Contractor shall submit a written project schedule and supporting data to the Project Manager as soon as possible after the receipt of the Notice of Award. The schedule shall describe key milestones and duration of project activities.

The supporting data for the schedule shall include a complete list of anticipated submittals and due dates, and the key ordering and delivery lead times. The Contractor shall schedule the sequence of construction to consider the delivery of long lead-time items. It shall be the Contractor's responsibility to notify the Project Manager of any problem in conforming to the Contract Documents, Specifications, and Construction Drawings for any element of the proposed improvements prior to its construction.

22. WORK SCHEDULE: The Contractor shall provide the Project Manager for review and acceptance, and prior to the commencement of any Work, a breakdown of the Contract cost proposal into values representing the various distinct stages, or units of the whole project, as a basis for making partial and final payments. Stages or specialty items shall be described in terms of a percentage to the whole. The schedule of values shall be shown on a proposed time line estimating the actual Work schedule. The schedule shall indicate starting and completion dates for the various stages of Work and shall be in a format acceptable to the Project Manager.

23. SCHEDULE OF VALUES: Submit typed schedule of values on AIA Form G703, or a similar typewritten format on white 8-1/2" x 11" paper. Use the Table of Contents of these Contract Documents as a basis of format. Identify each line item with number and title of the

Specification section. The schedule of values shall aggregate the total contract amount, and be divided so as to facilitate payments to subcontractors and suppliers. Upon request by the Project Manager, support values given with data that will substantiate their correctness. The schedule, when approved by the Project Manager, will be used as a basis for the Contractor's application for payment. Break down installed costs into delivered costs of products and total installed costs with overhead and profit. Provide a summary of the cost and origin of the five most costly manufactured items containing more than fifty percent iron or steel to be installed on the project. Revise the schedule to list change orders for each application for payment.

24. SCHEDULE OF SUBCONTRACTORS, MAJOR EQUIPMENT AND MATERIALS SUPPLIERS: The

Contractor shall provide the Owner, prior to the commencement of any Work, a detailed listing of subcontractors and major equipment and materials suppliers indicating their name, address, description of service or equipment and materials being provided, if they are a woman owned or minority owned business enterprise (WBE/MBE), and their vested monetary interest in the contract. The Contractor shall not award any Work to a subcontractor, transfer or assign any portion of the Contract Work, without the written approval of the Owner. Records shall be maintained throughout the duration of the Contract and periodically submitted at the time the Contractor submits progress payment applications. The Owner will use these records to verify the Contractor’s level of indebtedness prior to making final payment.

25. DIVISION APPROVAL OF INDEPENDENT TESTING LABORATORY AND SURVEYOR: The

Contractor shall submit the name and qualifications of the independent testing laboratory and the registered land surveyor to the Project Manager as soon as possible after the receipt of the Notice of Award. The Division may request personal interviews, and retains the right to reject the proposed candidates without reservation. If a candidate is rejected, the Contractor shall provide an alternative that is acceptable, and work shall not begin until approval is obtained.

26. CONSTRUCTION CONTROL PLAN: A traffic, excavation, and construction access control plan shall be submitted by the Contractor and approved by the Owner prior to the commencement of work. The disruption to project area visitors shall be kept to a minimum.

The plan shall take into consideration all users, including motorists, cyclists, and pedestrians. The Contractor shall provide all lights, signs, barricades, flagmen, or other devices necessary to provide for public safety in accordance with the current United States Department of Transportation’s Manual of Uniform Traffic Control Devices.

27. STORMWATER MANAGEMENT PLAN: This project will disturb more than 1 acre of ground, so a State stormwater control permit is required. The Contractor must submit a copy of the permit certification and the Stormwater Management Plan to the Owner for approval prior to the commencement of Work. The plan shall describe how the work shall remain in substantial compliance with the requirements of the Stormwater Management Program of the State Health Department, and Specification Section 02279.

28. Colorado Parks and Wildlife shall not be obligated or liable for any cost incurred by any company or individual reviewing this proposed project or prior to the issuance of a contract approved by the Controller of the State of Colorado or such assistant as he may designate.

Any and all costs, to review the project, inspect the proposed construction site, prepare and or submit bids will be the sole responsibility of the bidder.

29. A submission in response to the solicitation acknowledges acceptance by the proposer of all unaltered terms and conditions, as set forth herein. Any proposed exception taken to the State’s Terms and Conditions must be clearly and thoroughly identified and supported and acceptable alternatives must be proposed. Failure to do so shall be deemed a waiver of any rights to subsequently raise exception and/or request modification, except as outlined or specified in this solicitation. Submission of exceptions does not guarantee their acceptance, however, and such submittal will be taken into consideration during proposal review and scoring by the evaluation team. The state reserves the right to reject any changes suggested to PO or Contact terms and conditions and award to the next most advantageous qualified responsive vendor.

30. PROTESTED SOLICITATIONS AND AWARDS: An aggrieved party may file a protest concerning a material issues(s), at any phase of solicitation, including but not limited to, specifications, award or a disclosure of information marked confidential in the bid. The protest shall be submitted via email to the DNR Procurement Official as noted below within ten (10) business days after such aggrieved person knows, or should have known, of the facts giving rise thereto. Reference CRS 24-109-102, as amended, and Procurement Rule R-24-109-102-01, et seq.

DNR Procurement Official: Ion Cotsapas, ion.cotsapas@state.co.us

The written protest shall include, as a minimum, the following:

A. The name and address of the protestor;

B. Appropriate identification of the procurement by bid or award number;

C. A statement of the reasons for the protest, and any available exhibits, evidence, or documents substantiating the protest.

31. ACH/EFT PAYMENTS: Contractors are highly encouraged to consider signing up for ACH/EFT payments. ACH/EFT payments provide the advantage of ensuring quick and secure payments for the goods and services that vendors provide to the State. ACH/EFT payments help avoid the unnecessary, and sometimes inevitable delays in mail, and the possibility of lost warrants which will further delay vendor payment. DNR’s goal is to pay vendors as soon as possible - signing up for the ACH/EFT is an important step in making this happen. For additional information about signing up for ACH/EFT payments, please contact the Project Manager identified in the Invitation for Bids.

32. In accordance with procurement code and CRS 24-103-904 titled “Purchasing Preference for Environmentally Preferable Products”, bidders responding to this solicitation may seek to qualify for the preference and governmental bodies conducting this solicitation shall award a contract to a bidder who offers environmentally preferable products subject to the condition in the code and procurement rules.

33. ALTERNATIVE PRODUCTS: Certain materials and equipment have been specified by manufacturers’ trade names. This was done to establish the minimum quality and type of product desired. Alternatives to the manufacturers’ products may be used if the Project Manager determines they are equal. The Award will be based on the products identified in the plans.

34. DAVIS-BACON WAGE LAW: The subject Project is not a Federal prevailing wage rate project so Davis-Bacon Wage Rates do not apply. The State of Colorado prevailing wage requirements do apply; see below.

mailto:ion.cotsapas@state.co.us

35. PREVAILING WAGES: A public construction project in the amount of five hundred thousand dollars or more shall be subject to the State prevailing wage rate, of the regular, holiday, and overtime wages paid and the general prevailing payments on behalf of employees to lawful welfare, pension, vacation, apprentice training, and educational funds in the State, for each employee needed to execute the contract. Payments to the funds must constitute an ordinary business expense deduction for federal income tax purposes by contractors and subcontractors. Contractors are required to pay their employees at weekly intervals and shall comply with the enforcement provisions of C.R.S. §24-92-209. Contractors awarded a project of this size will be required to utilize the LCPTracker cloud-based labor compliance and certified payroll application. Upon award, the Contractor will need to return a completed copy of this form for LCPTracker enrollment:

https://drive.google.com/file/d/13Xvu5GttmOerEViwQsXlnbVI40YwsllD/view.

The applicable prevailing wages for this project are attached in Appendix A. Please review the “Special Considerations for Public Projects” section of the Contract Sample for additional details regarding compliance with the prevailing wages statutes.

36. NOTICE OF CONTRACTOR’S SETTLEMENT: a Final Settlement will be advertised via electronic media on the Colorado VSS website at www.colorado.gov/vss.

37. CONTRACT CLOSE OUT: Final Payment Statement: In addition to submittals required by the conditions of the Contract, provide submittals required by governing authorities and submit a final statement of accounting giving total adjusted Contract Sum, previous payments and sum remaining due.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .