IFB_250139_Bid_Schedule.xlsx
XLSX spreadsheet 26 KB Posted
- Attached to
- HSIP- Various Signalized Locations- Tucson- FHWA
- Solicitation number
- 250139
- Issued by
- Pima County, Tucson City, Arizona
About this file
This is a Bid Schedule document for the City of Tucson, Arizona, regarding the Highway Safety Improvement Program (HSIP) project at various signalized locations, with federal funding from the Federal Highway Administration (FHWA). The project, identified by ADOT TRACS number T0493 01C, involves the installation of new signal heads and related infrastructure at nine intersections throughout Tucson. Work includes removal and relocation of existing signs and delineators, installation of traffic signal faces and mounting assemblies, conductors, control cabinets, pre-empt beacons, video detection cameras, luminaires, and associated electrical equipment. The pre-bid meeting is scheduled for August 4, 2025, at 11:00 am, with bids due on September 11, 2025, at 2:00 pm Arizona local time. The contract term is 180 calendar days.
The bid schedule contains over 50 line items with quantities specified for each component, including lump sum allowances for traffic signal general conductors ($90,000) and miscellaneous work ($135,000). Pricing is structured as a unit-price bid format where contractors provide pricing per unit, with the total construction cost to be calculated based on submitted bids. The project is federally funded and subject to Davis-Bacon wage rates, equal employment opportunity provisions, and Build America Buy America requirements. The estimated project value ranges from $1,000,000 to $5,000,000. Contractors must submit 10% bid security and provide performance and payment bonds for 100% of the contract amount. The Disadvantaged Business Enterprise (DBE) goal is 0.00%, though bidders are still required to make good faith efforts to include DBEs. Subcontractors with contract values exceeding $5,000 must be listed in the bid submission.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Tab
| CITY OF TUCSON | |||||
| BID SCHEDULE | |||||
| IFB# 250139 | |||||
| Various Signalized Locations- Tucson- FHWA | |||||
| TRACS# T0493 01C | |||||
| PLAN NUMBER: U-2025-005 | |||||
| ITEM NO. | ITEM DESCRIPTION | UNIT | QUANTITY | UNIT PRICE | AMOUNT |
| 2020034 | REMOVAL OF SIGNS AND DELINEATORS | L.S. | 1 | ||
| 2020039 | REMOVE AND RELOCATE SIGN | EACH | 17 | ||
| 2020205 | REMOVE AND SALVAGE TRAFFIC SIGNAL FACE | EACH | 87 | ||
| 6072001 | SIGN MOUNT ASSEMBLIES (FLAG MOUNTED) | EACH | 23 | ||
| 6080002 | REGULATORY,WARNING, OR MARKER SIGN PANEL W/TYPE II SHEET (TYPE XI) | S.F. | 174 | ||
| 6080051 | METRO STREET NAME SIGN WITH FLAG MOUNT | S.F. | 84 | ||
| 7010005 | TRAFFIC CONTROL | L.S. | 1 | ||
| 7010025 | FLASHING ARROW PANEL | EA/DAY |
tc={19A9B1A3-67D5-4602-BCD4-3CF621744EA6}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
| Dollar value allowance items for arrow panel, flaggers (include shadow truck in specs), 3 officers for 8 hours a day (just signal heads a day, additional work 2 to 3 days) | 32 | ||||||
| 7010027 | CHANGEABLE MESSAGE BOARD | EA/DAY | 36 | ||||
| 7010077 | FLAGGING SERVICES (UNIFORMED OFFICER) (OFF DUTY) | HOUR | 480 | ||||
| 7310050 | POLE (TYPE R) | EACH | 2 | ||||
| 7310420 | MAST ARM (40 FT.) (TAPERED) | EACH | 1 | ||||
| 7310425 | MAST ARM (45 FT.) (TAPERED) | EACH | 2 | ||||
| 7310535 | MAST ARM (20 FT.) (TAPERED) (LUMINAIRE) | EACH | 2 | ||||
| 7320601 | CONDUCTORS, SIGNAL/LIGHTING (29TH AND CRAYCROFT) | L.S. | 1 | ||||
| 7320602 | CONDUCTORS, SIGNAL/LIGHTING (29TH AND SWAN) | L.S. | 1 | ||||
| 7320604 | CONDUCTORS, SIGNAL/LIGHTING (GOLF LINKS AND SWAN) | L.S. | 1 | ||||
| 7320605 | CONDUCTORS, SIGNAL/LIGHTING (GRANT AND SWAN) | L.S. | 1 | ||||
| 7320606 | CONDUCTORS, SIGNAL/LIGHTING (RIVER AND HACIENDA DEL SOL) | L.S. | 1 | ||||
| 7320607 | CONDUCTORS, SIGNAL/LIGHTING (ROGER AND FLOWING WELLS) | L.S. | 1 | ||||
| 7320608 | CONDUCTORS, SIGNAL/LIGHTING (VALENCIA AND SANTA CLARA) | L.S. | 1 | ||||
| 7320609 | CONDUCTORS, SIGNAL/LIGHTING (VIA INGRESSO AND MISSION) | L.S. | 1 | ||||
| 7320610 | CONDUCTORS, SIGNAL/LIGHTING (WRIGHTSTOWN AND PANTANO) | L.S. | 1 | ||||
| 7320612 | TRAFFIC SIGNAL GENERAL CONDUCTORS ALLOWANCE | USD | 90,000 | $ 1.00 | $ 90,000 | ||
| 7320820 | BATTERY BACK UP POWER SYSTEM | EACH | 4 | ||||
| 7330044 | TRAFFIC SIGNAL FACE (TYPE F) (ALUMINUM HOUSING) | EACH | 19 | ||||
| 7330045 | TRAFFIC SIGNAL FACE (TYPE F) | EACH | 24 | ||||
| 7330055 | CONDUCTOR (NO. 6) (GREEN INSULATED) | L.F. | 1 | ||||
| 7330057 | CONDUCTOR (NO. 6) (GREEN INSULATED) | L.F. | 1 | ||||
| 7330058 | CONDUCTOR (NO. 6) (GREEN INSULATED) | L.F. | 2 | ||||
| 7330062 | CONDUCTOR (NO. 6) (GREEN INSULATED) | L.F. | 1 | ||||
| 7330063 | CONDUCTOR (NO. 6) (GREEN INSULATED) | L.F. | 1 | ||||
| 7330070 | TRAFFIC SIGNAL FACE (TYPE G) | EACH | 26 | ||||
| 7330086 | TRAFFIC SIGNAL FACE (TYPE G) (ALUMINUM HOUSING) | EACH | 18 | ||||
| 7330202 | TRAFFIC SIGNAL FACE (PEDESTRIAN) (COUNT DOWN) | EACH | 2 | ||||
| 7330315 | TRAFFIC SIGNAL MOUNTING ASSEMBLY (TYPE IV) | EACH | 7 | ||||
| 7330320 | TRAFFIC SIGNAL MOUNTING ASSEMBLY (TYPE V) | EACH | 11 | ||||
| 7330325 | TRAFFIC SIGNAL MOUNTING ASSEMBLY (TYPE VI) | EACH | 4 | ||||
| 7330330 | TRAFFIC SIGNAL MOUNTING ASSEMBLY (TYPE VII) | EACH | 11 | ||||
| 7330350 | TRAFFIC SIGNAL MOUNTING ASSEMBLY (TYPE XI) | EACH | 2 | ||||
| 7330370 | TRAFFIC SIGNAL MOUNTING ASSEMBLY (SKYBRAC) | EACH | 9 | ||||
| 7330500 | PRE-EMPT BEACON | EACH | 10 | ||||
| 7330510 | PRE-EMPT SENSOR | EACH | 10 | ||||
| 7340101 | CONTROL CABINET | EACH | 4 | ||||
| 7340260 | MMU2 SMART MONITOR | EACH | 3 | ||||
| 7350010 | VIDEO DETECTION CAMERA (RIVER/HACIENDA DEL SOL) | EACH | 1 | ||||
| 7360050 | LUMINAIRE (HORIZONTAL MOUNT) (LED) | EACH | 2 | ||||
| 7370200 | REMOVE AND SALVAGE OR REINSTALL ELECTRICAL EQUIPMENT | L.S. | 1 | ||||
| 9010001 | MOBILIZATION | L.S. | 1 | ||||
| 9240101 | MISCELLANEOUS WORK (MINOR ALTERATIONS IN DETAILS OF CONSTRUCTION) | USD | 135,000 | $ 1.00 | $ 135,000 | ||
| Total Construction Cost |
Dollar value allowance items for arrow panel, flaggers (include shadow truck in specs), 3 officers for 8 hours a day (just signal heads a day, additional work 2 to 3 days)
&"Arial,Bold"&10T0493 - VARIOUS SIGNALIZED LOCATIONS, TUCSON
HSIP FLASHING YELLOW ARROW IMPROVEMENTS
BID SCHEDULE
&"Arial,Regular"&8&F &"Arial,Regular"&8&P of &N
File details come from the government source that posted it. Updated .