IFB_250017_Fac_Mods_at_SA_BB_Ops_-_Memo_to_CAMM_-_Lic,_Time,_LD's_09-09-2025.pdf

PDF 142 KB Posted

Attached to
IFB 250017 Facility Modifications at Santa Ana Bus Base Operations Building
Solicitation number
250017
Issued by
Orange County, California

About this file

This is an interoffice memorandum from the State of California's Facilities Engineering department dated September 9, 2025, regarding IFB 250017 for facility modifications at the Santa Ana Bus Base Operations Building. The project, identified under Requisition #035570, involves modifications to the operations building at the Santa Ana Bus Base facility. The contract is structured with a 180 calendar day performance period for completion of the facility modifications work.

Bidders must hold a valid State of California Class B General Building Contractor license and either possess valid State of California C-6, C-8, and C-15 Specialty Contractor licenses or subcontract with licensed specialty contractors holding these classifications. The liquidated damages rate is set at $300 per calendar day, calculated based on two hours of daily Project Manager oversight at a rate of $150 per hour. This assessment reflects the state's anticipated management burden throughout the contract performance period.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INTEROFFICE MEMO

September 9, 2025

To: Josie Mellen – Senior Contract Administrator (CAMM)

From: Eric Torres, Sr. Project Manager, Cap. Pgms. – Facilities Eng. E.T.

Subject: IFB 250017 Facility Modifications at Santa Ana Bus Base Operations

Building. Requisition # 035570.

• Valid State of California Contractor’s License classification requirements are as follows:

o Bidders will be required to hold a valid State of California Class B General Building Contractor license, and either

▪ hold valid State of California C-6, C-8, and C-15 Specialty Contractor license, or

▪ subcontract to valid State of California C-6, C-8, and C-15 Specialty Contractor licensed contractor(s).

• Contract Time period is 180 calendar days.

• The liquidated damages for the above subject project are $300 per calendar day, the basis for which is two (2) hours of staff time for the Project Manager per day (2 Hours X $150 = $300.00).

Thank you.

File details come from the government source that posted it. Updated .