IFB_24C314004_ADDENDUM_1.pdf
PDF 124 KB Posted
- Solicitation number
- 0000033910
- Issued by
- Sacramento County, San Diego City, California
About this file
This is Addendum #1 to IFB #24C314004 issued by the California Highway Patrol (CHP) for ceiling mounted heater replacement services at the Golden Gate Air Operations Unit in Napa, CA. The scope of work involves replacing five existing ceiling mounted gas hangar heater units that are no longer effectively heating the space. The contractor must possess valid C-20 Warm-Air Heating, Ventilating and Air Conditioning Contractor and C-36 Plumbing Contractors licenses (or C-20 with C-36 subcontractor). Work must be performed between 8:00 AM and 5:00 PM Monday through Friday, with a 30-day completion timeline from project start date.
The contractor must provide a 100% payment bond and is responsible for removing existing units, installing five new Energy Star rated commercial grade heaters and compatible thermostats, obtaining required permits, providing staff training, furnishing operation manuals, and warranting work for one year. The contractor must seek any available public utility rebates and pass cost savings to CHP. All equipment and installation must comply with California Code of Regulations Title 24, Part 6 requirements. The work location is at 3500 Airport Road, Napa, CA 94558.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IFB_24C314004.pdf | ||
| 24C314004_SUMMARY_OF_QUESTIONS_AND_ANSWERS.docx | DOCX document | |
| 24C314004_ADDENDUM_2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF CALIFORNIA HIGHWAY PATROL
January 27, 2025 Page 1 of 1
ADDENDUM NUMBER 1
TO
INVITATION FOR BID - NUMBER 24C314004
CEILING MOUNTED HEATER REPLACEMENT SERVICES
CALIFORNIA HIGHWAY PATROL
GOLDEN GATE AIR OPERATIONS UNIT
Addendum #1 changes the IFB as follows:
1. IFB, Proposed Agreement:
Exhibit A, is replaced in its entirety.
A COPY OF THIS ADDENDUM, IN ITS ENTIRETY, MUST BE INCLUDED WITH YOUR IFB. FAILURE
TO DO SO MAY RENDER YOUR BID NON-RESPONSIVE.
If you have any questions, contact Tessa Gomez Contract Services Unit at (916) 843-3613.
Department of California Highway Patrol and TBD Upon Award
Agreement #24C314004
EXHIBIT A
(Standard Agreement)
SCOPE OF WORK
1. Contractor agrees to provide to the Department of California Highway Patrol (CHP)
Golden Gate Air Operations Unit, the services described herein: furnish all supplies, materials, tools, equipment, labor, personnel, and supervision; pay all taxes, insurance, bonds, license and permit fees, and all other direct and indirect costs necessary to provide Ceiling Heater Replacement Services as set forth in this Agreement.
A. License Requirement/Certification: Contractor must possess a valid C-20, Warm-
Air Heating, Ventilating and Air Conditioning Contractor and C-36, Plumbing Contractors License, California Contractor’s State License Board Specialty License OR valid C-20 license with C-36 subcontractor.
B. Contractor shall provide a Payment Bond equal to 100 percent of the value of the Agreement. Contractor shall complete State of California Standard 807, in duplicate, and submit prior to execution of Agreement.
2. The services shall be performed at:
Department of California Highway Patrol Golden Gate Air Operations Unit 3500 Airport Road Napa, CA 94558
3. The services shall be provided during:
All work shall be performed between the hours of 8:00 a.m. and 5:00 p.m., Monday through Friday, unless other arrangements are approved by the CHP on-site contact.
4. The project representatives during the term of this Agreement will be:
STATE AGENCY
CONTRACTOR
TBD Upon Award
SECTION/UNIT
Facilities Section
SECTION/UNIT
ATTENTION
Mauricio Castro, Facilities Coordinator
ATTENTION
ADDRESS
601 N. 7th Street, Sacramento, CA 95811
ADDRESS
TELEPHONE NUMBER
(916) 843-3800
Facilities301@chp.ca.gov
TELEPHONE NUMBER
Agreement #24C314004
SCOPE OF WORK (Continued)
5. General:
The California Highway Patrol (CHP) is in need of replacing five (5) ceiling mounted gas hangar heater units at its Golden Gate Air Operations Area Unit. The existing five
(5) gas hangar heating units are no longer effectively heating the space and must be replaced. This Agreement is under the jurisdiction of CHP, who will execute the contract documents, coordinate with Contractor as necessary, and conduct inspections to ensure that the work is performed in strict accordance with the specifications. No deviations from the Scope of Work will be permitted without concurrence and prior authorization from the CHP Facilities Coordinator or designee.
A. Remove and dispose of the five (5) existing ceiling mounted gas heating units according to federal, state, and local regulations.
B. Install five (5) like for like new commercial grade Energy Star rated ceiling mounted gas heating units including parts, fittings, and rebuild kits to connect to the existing piping if needed.
C. Replace and install five (5) new like for like commercial grade Energy Star rated thermostats including parts and fittings that connect and are compatible with new heater units.
D. Where applicable, Contractor is to seek any public utility rebates and pass the cost savings on to the California Highway Patrol.
E. Contractor shall start-up and test units to ensure proper operation and to make any adjustments needed.
F. Contractor shall provide on-site training to CHP staff on the operation and functions of the newly installed heating units.
G. Contractor shall provide two copies of Operation and Maintenance Manuals to the CHP on-site contact.
H. Contractor is responsible for obtaining any permits required for the installation of the heating units.
I. Contractor shall remove all debris, including packaging materials from the jobsite on a daily basis.
J. Contractor shall warranty work for a period of one year after installation and provide manufacturer’s warranty on equipment installed.
Agreement #24C314004
SCOPE OF WORK (Continued)
K. Contractor has thirty (30) days from the project start date to complete the project. If more time is needed the Facilities Analyst will be contacted.
L. The replacement equipment and installation must be compliant with the
California Code of Regulations, Title 24, Part 6, regulations..
| 24C314004 ADDENDUM 1 |
| 24C314004 EXHIBITS |
File details come from the government source that posted it. Updated .