IFB_24_25_23_Bid_Tabulation_UPDATED.pdf
PDF 236 KB Posted
- Attached to
- Groveview Pump Station Improvements State and local contract opportunity
- Solicitation number
- IFB 24/25-23
- Issued by
- Seminole County, Florida
About this file
The document is a Solicitation Tabulation Sheet for the City of Sanford's Finance Department Purchasing Division, specifically for Invitation for Bid (IFB) 24/25-23 regarding the Groveview Lift Station Improvements project. The solicitation was opened on June 5, 2025, at 2:00 P.M. local time, with six vendors submitting bids: Carr & Collier, Cathcart Construction, ClearWater Solutions, Danus Utilities, Prime Construction Group, Sanpik, and US Water Services. The project involves comprehensive lift station improvements, including demolition of the existing above-ground station, installation of a new submersible pump station, construction of a junction manhole, force and gravity mains, electrical controls, equipment, and an emergency diesel bypass pump.
The bid tabulation sheet provides a detailed breakdown of costs for various project components, with total bid lump sum prices ranging from $1,060,098.89 (Cathcart Construction) to $1,357,660.00 (Prime Construction Group). The lowest bidder was Cathcart Construction at $1,060,098.89, while the highest was Prime Construction Group at $1,357,660.00. A note indicates a correction was needed due to a discrepancy with Sanpik's lump sum bid. The document follows the City of Sanford's standard bidding rules, which state that all bids are subject to the city's terms and conditions, and any additional terms submitted by bidders are rejected unless previously approved through addenda.
View the file
Other files for this state and local contract opportunity
Show all 50
Groveview Pump Station Improvements has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Sanford Solicitation Tabulation Sheet Form Finance Department | Purchasing Division IFB 24/25-23 300 N Park Ave Groveview Lift Station Improvements Sanford, FL 32771 June 5, 2025 Telephone: (407) 688-5030 2:00 P.M. Local Time
Email: Maria.green@sanfordfl.gov
VENDOR NAME→
Carr & Collier Cathcart
Construction ClearWater
Solutions Danus Utilities Prime Construction
Group Sanpik US Water Services
Solicitation Evaluation Category ↓
Mobilization/Demolitization
$110,000.00 $50,493.75 $100,930.96 $120,000.00 $125,000.00 $78,000.00 $45,561.00
General Requirements (Indemnification, Bonds, Preconstruction Video, Record Drawings, Site Layout & Survey)
$15,470.00 $27,791.50 $32,228.16 $60,000.00 $65,000.00 $78,000.00 $43,187.00
Erosion and Sedimentation Control
$1,000.00 $2,003.13 $5,942.66 $6,000.00 $5,000.00 $2,000.00 $6,739.00
Clearing and Grubbing
$8,000.00 $92,680.44 $17,192.95 $60,000.00 $15,000.00 $20,000.00 $11,217.00
Site Work (Grading and Restoration)
$4,000.00 $14,523.73 $13,898.03 $50,000.00 $40,000.00 $5,000.00 $27,054.00
Temporary Bypass Pumping During Construction
$33,000.00 $5,256.25 $52,304.03 $22,500.00 $35,000.00 $16,000.00 $27,443.00
Demolish Existing Lift Station (Salvage Items as Required, Complete Building Demolition, removal of walls and stabs to
$12,000.00 $24,150.01 $43,877.74 $33,000.00 $45,000.00 $30,000.00 $56,490.00
Remove and Dispose of Existing Force Main
$4,060.00 $4,156.04 $19,601.10 $5,800.00 $5,800.00 $2,030.00 $20,416.00
Solicitation Number:
Solicitation Title Solicitation Opening Date:
Solicitation Opening Time:
PUR-F-231 1 Rev. 03/2016
VENDOR NAME→
Carr & Collier Cathcart
Construction ClearWater
Solutions Danus Utilities Prime Construction
Group Sanpik US Water Services
Take Out of Service (Fully Grout) Existing Gravity Main
$3,060.00 $9,137.50 $4,959.90 $4,500.00 $1,800.00 $270.00 $5,616.00
Remove and Dispose of Existing Electrical Equipment
$6,000.00 $9,375.00 $7,156.59 $3,500.00 $10,000.00 $13,500.00 $23,821.00
Convert Existing Wet Well Into Manhole
$14,000.00 $28,643.76 $21,092.20 $16,000.00 $12,500.00 $16,000.00 $19,299.00
Furnish and Install New Wet Well, Valve Vault, Hatches and Accessories
$227,000.00 $169,316.74 $164,923.61 $252,000.00 $295,355.00 $197,000.00 $177,864.00
Furnish and Install 6" D.1. Pipe and Fittings from Wet Well Pumps through Valve Vault (Including Check Valves, Emergency Pump Out, Plug Valves, Accessories, Ending at (and Including) the Wye Outside the Valve Vault)
$188,000.00 $70,312.50 $97,143.63 $55,000.00 $20,000.00 $101,000.00 $107,275.00
Furnish and Install New Submersible Pumps with Base Pedestal and Plate, Guide Rails, Brackets, Float Switches
$205,000.00 $189,751.25 $133,539.11 $127,000.00 $369,750.00 $155,000.00 $134,456.00
Install Diesel Driven Bypass Pump and Accessories
$7,000.00 $12,025.01 $9,046.73 $35,000.00 $10,000.00 $17,000.00 $17,951.00
Furnish and Install New 6-inch PVC Force Main
$5,025.00 $16,279.68 $17,291.10 $8,000.00 $3,000.00 $1,350.00 $15,795.00
Furnish and Install New 10-inch Gravity Sewer Main
$10,035.00 $6,790.61 $41,532.12 $30,000.00 $4,500.00 $2,187.00 $9,126.00
Furnish and Install New 12-inch Gravity Sewer Main
$31,050.00 $11,587.74 $68,286.24 $70,000.00 $27,000.00 $21,114.00 $29,430.00
Furnish And Install Sanitary Manholes 4- Feet Diameter (+8' Depth)
$49,000.00 $35,461.12 $55,680.59 $22,500.00 $20,255.00 $18,000.00 $20,907.00
Modify Existing Sanitary Manhole $11,000.00 $12,259.38 $12,180.28 $2,500.00 $8,500.00 $5,700.00 $6,407.00
PUR-F-231 2 Rev. 03/2016
VENDOR NAME→
Carr & Collier Cathcart
Construction ClearWater
Solutions Danus Utilities Prime Construction
Group Sanpik US Water Services
Connect to Existing Force Main $8,000.00 $16,891.25 $11,170.01 $8,000.00 $6,500.00 $6,000.00 $14,334.00
Furnish and Install New Equipment Rack and Components, Electrical and Controls, New Power Feed, New Tower and Antenna, Coordination with FPL, P itti
$164,000.00 $145,312.50 $133,780.11 $180,000.00 $197,500.00 $290,000.00 $216,518.00
Furnish and Install Light Pole Assembly and Lighting
$18,000.00 $70,312.50 $10,390.78 $7,500.00 $5,500.00 $3,375.00 $11,399.00
Furnish and Install Lift Station Concrete (8")
$16,000.00 $19,962.50 $17,574.44 $16,000.00 $20,200.00 $23,000.00 $25,066.00
Furnish and Install Chain Link Fence and 1 Gate (Including Barb Wire Attachment) (6' Fence Plus Attachment)
$13,000.00 $15,625.00 $18,548.88 $16,000.00 $9,500.00 $14,000.00 $17,449.00
TOTAL BID LUMP SUM PRICE AS
SUBMITTED
$1,162,700.00 $1,060,098.89 $1,110,271.95 $1,210,800.00 $1,357,660.00 $1,115,526.00 $1,090,820.00
OPENED BY: Maria A. Green VERIFIED BY: Marisol Ordoñez
NOTE: Correction due to discrepancy with Sanpik Lump Sum
Rules: All bids accepted by City of Sanford are subject to the City's terms and conditions and any and all additional terms and conditions submitted by the bidders are rejected and shall have no force and effect unless receiving prior consideration and approval of the City in the form of Addenda to this bid.
PUR-F-231 3 Rev. 03/2016
Sheet1
File details come from the government source that posted it. Updated .