IFB_24_25-23_Grovieview_Pump_Station_Improvement_NOA.pdf

PDF 581 KB Posted

Attached to
Groveview Pump Station Improvements State and local contract opportunity
Solicitation number
IFB 24/25-23
Issued by
Seminole County, Florida

About this file

This is a Notice of Award issued by the City of Sanford, Florida for the Groveview Pump Station Improvements project (IFB 24/25-23). The project encompasses the demolition of an existing above-ground pump station and its replacement with a new submersible pump station, including construction of one junction manhole, installation of force and gravity mains to redirect flow, implementation of electrical controls and equipment, and integration of an emergency diesel by-pass pump. Sealed bids were due on May 22, 2025 at 2:00 P.M. local time, with all contractor questions required by May 15, 2025. The award was issued on September 16-17, 2025, with the Notice of Award signed by Craig Radzak, Assistant City Manager, on behalf of the City of Sanford. The successful contractor must execute the Agreement and furnish required Performance Bond, Payment Bond, and certificates of insurance within fourteen calendar days from receipt of the Notice of Award. The anticipated contract duration is 270 calendar days from the Notice to Proceed.

The winning bid was accepted in the amount of $1,034,481. The award was made to the lowest responsive and responsible bidder, with the City of Sanford reserving the right to waive formalities and reject any or all bids. The project requires compliance with Florida Department of Environmental Protection regulations and precise utility coordination with existing municipal sanitary sewer infrastructure, including integration with an 8-foot diameter wet well and 6-inch force mains. Bidders were required to demonstrate proper licensing, professional qualifications, and ability to meet stringent insurance and bonding requirements. The procurement encouraged participation from Minority/Women-owned Business Enterprises (M/WBE), though no specific incumbent vendor was identified for this replacement infrastructure project.

View the file

Other files for this state and local contract opportunity

Other files attached to Groveview Pump Station Improvements, newest first.
File Type Posted
800197898_PP_Bond_Form.pdf PDF
IFB_24_25-23_Approved_Agenda.pdf PDF
IFB_24_25-23_Approved_Agenda.pdf PDF
Notice_of_Intent_to_Award.pdf PDF
Bid_Tabulation_-_Groveview_Pump_Station_Improvements.pdf PDF
Bid_Tabulation_-_Groveview_Pump_Station_Improvements.pdf PDF
Bid_Tabulation_-_Groveview_Pump_Station_Improvements.pdf PDF
IFB_24_25_23_Bid_Tabulation_UPDATED.pdf PDF
IFB_24_25_23_Bid_Tabulation_UPDATED.pdf PDF
IFB_24_25_23_Bid_Tabulation_UPDATED.pdf PDF
IFB_24_25-23_Tabulation.pdf.pdf PDF
IFB_24_25-23_Tabulation.pdf.pdf PDF
6.12.25_Opening.pdf PDF
6.12.25_Opening.pdf PDF
IFB_24_25_23_Adedendum_3.pdf PDF
IFB_24_25_23_Adedendum_3.pdf PDF
IFB_24_25_23_Adedendum_3.pdf PDF
IFB_24_25_23_Adedendum_3.pdf PDF
IFB_24_25_23_Addedum_2.pdf PDF
IFB_24_25_23_Addedum_2.pdf PDF
IFB_24_25_23_Addedum_2.pdf PDF
IFB_24_25_23_Addedum_2.pdf PDF
IFB_24_25_23_Addedum_1.pdf PDF
IFB_24_25_23_Addedum_1.pdf PDF
IFB_24_25_23_Addedum_1.pdf PDF
IFB_24_25_23_Addedum_1.pdf PDF
IFB_24_25_23_Addedum_1.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Project_Manual.pdf PDF
Order_ID_7800421.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Project_Manual.pdf PDF
Order_ID_7800421.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Project_Manual.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Project_Manual.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
Order_ID_7800421.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Project_Manual.pdf PDF
Order_ID_7800421.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
Order_ID_7800421.pdf PDF
Order_ID_7800421.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Project_Manual.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
Order_ID_7800421.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Project_Manual.pdf PDF
Order_ID_7800421.pdf PDF
Show all 50

Groveview Pump Station Improvements has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Groveview Pump Station Improvements NOTICE OF AWARD 00510-1

SECTION 00510

NOTICE OF AWARD FORM

To:

Project Name and Bid No.: Groveview Pump Station Improvements IFB 24/25-23

The OWNER has considered the BID submitted by you, dated May 22, 2025 for the above described WORK in response to the Invitation for Bids and Bidding Documents.

You are hereby notified that your BID has been accepted for BID items in the amount of $1,034,481 .

You are required by the Instructions to Bidder to execute the Agreement and furnish the required CONTRACTOR's Performance Bond, Payment Bond, and certificates of insurance within fourteen (14) calendar days from the date of this Notice to you. If you fail to execute said Agreement and to furnish said Bonds and insurance within fourteen (14) calendar days from receipt of this Notice, said OWNER will be entitled to consider all your rights arising out of the OWNER's acceptance of your BID as abandoned and as a forfeiture of your BID BOND. The OWNER will be entitled to such other rights as may be granted by law.

You are required to return an acknowledged copy of this NOTICE OF AWARD to the OWNER.

Dated this day of , .

OWNER:

(Name of OWNER)

By (Signature)

(Printed Name and Title)

ACCEPTANCE OF NOTICE

Receipt and acceptance of the above NOTICE OF AWARD is hereby acknowledged by this day of , .

By

Printed Name and Title

END OF SECTION

16th September 2025

City of Sanford

Craig Radzak, Assistant City Manager

Matthew Sands - President

Matthew Sands 17th September 2025

Amy Stevenson Corporate Seal

Amy Stevenson Sticky Note Accepted set by Amy Stevenson

Amy Stevenson Sticky Note Completed set by Amy Stevenson

Amy Stevenson M.S Signature

Amy Stevenson Sticky Note Accepted set by Amy Stevenson

File details come from the government source that posted it. Updated .