The document is a City of Sanford Solicitation Tabulation Sheet for the Groveview Lift Station Improvements project (IFB 24/25-23), opened on June 5, 2025, at 2:00 P.M. local time. The solicitation involves comprehensive lift station renovation and infrastructure improvements, including demolition of existing facilities, installation of new wet wells, pumps, piping, electrical systems, and associated site work. Seven vendors submitted detailed bids: Carr & Collier, Cathcart Construction, ClearWater Solutions, Danus Utilities, Prime Construction Group, Sanpik, and US Water Services.

The total bid prices range from $1,060,098.89 (Cathcart Construction) to $1,357,660.00 (Prime Construction Group), with most vendors' proposals falling between $1.1 and $1.2 million. The bid includes line-item pricing for various project components such as mobilization, demolition, site work, pumping systems, piping, electrical infrastructure, and site accessories. A note on the document indicates a correction was needed due to a discrepancy with Sanpik's lump sum bid. The solicitation is subject to the City of Sanford's terms and conditions, with all additional terms submitted by bidders requiring prior approval through the bid addenda process.

View the file

Other files for this state and local contract opportunity

Other files attached to Groveview Pump Station Improvements, newest first.
File Type Posted
800197898_PP_Bond_Form.pdf PDF
IFB_24_25-23_Approved_Agenda.pdf PDF
IFB_24_25-23_Approved_Agenda.pdf PDF
Notice_of_Intent_to_Award.pdf PDF
Bid_Tabulation_-_Groveview_Pump_Station_Improvements.pdf PDF
Bid_Tabulation_-_Groveview_Pump_Station_Improvements.pdf PDF
Bid_Tabulation_-_Groveview_Pump_Station_Improvements.pdf PDF
IFB_24_25_23_Bid_Tabulation_UPDATED.pdf PDF
IFB_24_25_23_Bid_Tabulation_UPDATED.pdf PDF
IFB_24_25-23_Tabulation.pdf.pdf PDF
IFB_24_25-23_Tabulation.pdf.pdf PDF
6.12.25_Opening.pdf PDF
6.12.25_Opening.pdf PDF
IFB_24_25_23_Adedendum_3.pdf PDF
IFB_24_25_23_Adedendum_3.pdf PDF
IFB_24_25_23_Adedendum_3.pdf PDF
IFB_24_25_23_Adedendum_3.pdf PDF
IFB_24_25_23_Addedum_2.pdf PDF
IFB_24_25_23_Addedum_2.pdf PDF
IFB_24_25_23_Addedum_2.pdf PDF
IFB_24_25_23_Addedum_2.pdf PDF
IFB_24_25_23_Addedum_1.pdf PDF
IFB_24_25_23_Addedum_1.pdf PDF
IFB_24_25_23_Addedum_1.pdf PDF
IFB_24_25_23_Addedum_1.pdf PDF
IFB_24_25_23_Addedum_1.pdf PDF
IFB_24_25_23_Addedum_1.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Project_Manual.pdf PDF
Order_ID_7800421.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
Order_ID_7800421.pdf PDF
Order_ID_7800421.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Project_Manual.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
Order_ID_7800421.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Project_Manual.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
Order_ID_7800421.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Project_Manual.pdf PDF
Order_ID_7800421.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Project_Manual.pdf PDF
Order_ID_7800421.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Project_Manual.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Plans.pdf PDF
IFB_24-25-23_Groveview_Pump_Station_Improvements_-_Project_Manual.pdf PDF
Order_ID_7800421.pdf PDF
Show all 50

Groveview Pump Station Improvements has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Sanford Solicitation Tabulation Sheet Form Finance Department | Purchasing Division IFB 24/25-23 300 N Park Ave Groveview Lift Station Improvements Sanford, FL 32771 June 5, 2025 Telephone: (407) 688-5030 2:00 P.M. Local Time

Email: Maria.green@sanfordfl.gov

VENDOR NAME→

Carr & Collier Cathcart

Construction ClearWater

Solutions Danus Utilities Prime Construction

Group Sanpik US Water Services

Solicitation Evaluation Category ↓

Mobilization/Demolitization

$110,000.00 $50,493.75 $100,930.96 $120,000.00 $125,000.00 $78,000.00 $45,561.00

General Requirements (Indemnification, Bonds, Preconstruction Video, Record Drawings, Site Layout & Survey)

$15,470.00 $27,791.50 $32,228.16 $60,000.00 $65,000.00 $78,000.00 $43,187.00

Erosion and Sedimentation Control

$1,000.00 $2,003.13 $5,942.66 $6,000.00 $5,000.00 $2,000.00 $6,739.00

Clearing and Grubbing

$8,000.00 $92,680.44 $17,192.95 $60,000.00 $15,000.00 $20,000.00 $11,217.00

Site Work (Grading and Restoration)

$4,000.00 $14,523.73 $13,898.03 $50,000.00 $40,000.00 $5,000.00 $27,054.00

Temporary Bypass Pumping During Construction

$33,000.00 $5,256.25 $52,304.03 $22,500.00 $35,000.00 $16,000.00 $27,443.00

Demolish Existing Lift Station (Salvage Items as Required, Complete Building Demolition, removal of walls and stabs to

$12,000.00 $24,150.01 $43,877.74 $33,000.00 $45,000.00 $30,000.00 $56,490.00

Remove and Dispose of Existing Force Main

$4,060.00 $4,156.04 $19,601.10 $5,800.00 $5,800.00 $2,030.00 $20,416.00

Solicitation Number:

Solicitation Title Solicitation Opening Date:

Solicitation Opening Time:

PUR-F-231 1 Rev. 03/2016

VENDOR NAME→

Carr & Collier Cathcart

Construction ClearWater

Solutions Danus Utilities Prime Construction

Group Sanpik US Water Services

Take Out of Service (Fully Grout) Existing Gravity Main

$3,060.00 $9,137.50 $4,959.90 $4,500.00 $1,800.00 $270.00 $5,616.00

Remove and Dispose of Existing Electrical Equipment

$6,000.00 $9,375.00 $7,156.59 $3,500.00 $10,000.00 $13,500.00 $23,821.00

Convert Existing Wet Well Into Manhole

$14,000.00 $28,643.76 $21,092.20 $16,000.00 $12,500.00 $16,000.00 $19,299.00

Furnish and Install New Wet Well, Valve Vault, Hatches and Accessories

$227,000.00 $169,316.74 $164,923.61 $252,000.00 $295,355.00 $197,000.00 $177,864.00

Furnish and Install 6" D.1. Pipe and Fittings from Wet Well Pumps through Valve Vault (Including Check Valves, Emergency Pump Out, Plug Valves, Accessories, Ending at (and Including) the Wye Outside the Valve Vault)

$188,000.00 $70,312.50 $97,143.63 $55,000.00 $20,000.00 $101,000.00 $107,275.00

Furnish and Install New Submersible Pumps with Base Pedestal and Plate, Guide Rails, Brackets, Float Switches

$205,000.00 $189,751.25 $133,539.11 $127,000.00 $369,750.00 $155,000.00 $134,456.00

Install Diesel Driven Bypass Pump and Accessories

$7,000.00 $12,025.01 $9,046.73 $35,000.00 $10,000.00 $17,000.00 $17,951.00

Furnish and Install New 6-inch PVC Force Main

$5,025.00 $16,279.68 $17,291.10 $8,000.00 $3,000.00 $1,350.00 $15,795.00

Furnish and Install New 10-inch Gravity Sewer Main

$10,035.00 $6,790.61 $41,532.12 $30,000.00 $4,500.00 $2,187.00 $9,126.00

Furnish and Install New 12-inch Gravity Sewer Main

$31,050.00 $11,587.74 $68,286.24 $70,000.00 $27,000.00 $21,114.00 $29,430.00

Furnish And Install Sanitary Manholes 4- Feet Diameter (+8' Depth)

$49,000.00 $35,461.12 $55,680.59 $22,500.00 $20,255.00 $18,000.00 $20,907.00

Modify Existing Sanitary Manhole $11,000.00 $12,259.38 $12,180.28 $2,500.00 $8,500.00 $5,700.00 $6,407.00

PUR-F-231 2 Rev. 03/2016

VENDOR NAME→

Carr & Collier Cathcart

Construction ClearWater

Solutions Danus Utilities Prime Construction

Group Sanpik US Water Services

Connect to Existing Force Main $8,000.00 $16,891.25 $11,170.01 $8,000.00 $6,500.00 $6,000.00 $14,334.00

Furnish and Install New Equipment Rack and Components, Electrical and Controls, New Power Feed, New Tower and Antenna, Coordination with FPL, P itti

$164,000.00 $145,312.50 $133,780.11 $180,000.00 $197,500.00 $290,000.00 $216,518.00

Furnish and Install Light Pole Assembly and Lighting

$18,000.00 $70,312.50 $10,390.78 $7,500.00 $5,500.00 $3,375.00 $11,399.00

Furnish and Install Lift Station Concrete (8")

$16,000.00 $19,962.50 $17,574.44 $16,000.00 $20,200.00 $23,000.00 $25,066.00

Furnish and Install Chain Link Fence and 1 Gate (Including Barb Wire Attachment) (6' Fence Plus Attachment)

$13,000.00 $15,625.00 $18,548.88 $16,000.00 $9,500.00 $14,000.00 $17,449.00

TOTAL BID LUMP SUM PRICE AS

SUBMITTED

$1,162,700.00 $1,060,098.89 $1,110,271.95 $1,210,800.00 $1,357,660.00 $1,115,526.00 $1,090,820.00

OPENED BY: Maria A. Green VERIFIED BY: Marisol Ordoñez

NOTE: Correction due to discrepancy with Sanpik Lump Sum

Rules: All bids accepted by City of Sanford are subject to the City's terms and conditions and any and all additional terms and conditions submitted by the bidders are rejected and shall have no force and effect unless receiving prior consideration and approval of the City in the form of Addenda to this bid.