This is a Notice to Bidders and Specifications document issued by the Illinois Department of Transportation (IDOT) for Contract No. 72639, a construction project spanning Adams and Pike Counties. The project consists of 9.8 miles of shoulder repair work on I-72 from I-172 to 0.9 miles east of IL 96 and on I-172 from I-72 to 0.9 miles south of IL 57, with a gross length of 8.98 miles and net length of 8.48 miles. The work includes HMA surface removal, HMA shoulder resurfacing, HMA shoulder widening at emergency median crossovers, pavement markings, and all associated work for completion. Electronic bids must be submitted to the iCX system (Integrated Contractors Exchange) by 12:00 p.m. on June 12, 2026, at which time bids will be publicly opened. The contract will be awarded to the lowest responsive and responsible bidder in compliance with all Department terms and conditions. Contractors are required to coordinate with District 6 Bureau of Operations at least 72 hours in advance of work and three weeks prior to implementing traffic control. Specific ramp closures are limited to daytime operations (9:00 a.m. to 3:30 p.m., Monday through Friday) with a maximum of three closures each. At least one lane in each direction on both highways must remain open to traffic at all times. Working day contracts shall be completed by June 30, 2027, except for off-pavement and cleanup work.

The contract is funded through National Highway Performance Program (NHPP) construction funds. Compensation includes bituminous materials cost adjustments based on fluctuations in the Bituminous Price Index, applicable when there is a difference exceeding five percent between the index price at letting and the month work is performed. Costs for anti-strip additives for HMA mixtures with crushed gravel or sandstone coarse aggregate must be included in unit bid prices. The contractor may request a delayed start within ten days after bid opening, subject to Department approval, with the understanding that such approval does not extend the project completion deadline. The specification document incorporates supplemental specifications and recurring special provisions effective January 1, 2026, including requirements for traffic control standards, environmental compliance, concrete and material specifications, and federal-aid contract provisions. The project is subject to prevailing wage requirements, Equal Employment Opportunity (EEO) obligations, and federal labor standards for any federally funded portions.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting June 12, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 72639 ADAMS-PIKE Counties Section (1-2)SR, (75-1)SR-1 Route FAI 72, FAI 172 Project NHPP-VI6W(201) District 6 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

June 12, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 72639 ADAMS-PIKE Counties Section (1-2)SR, (75-1)SR-1 Project NHPP-VI6W(201) Route FAI 72, FAI 172 District 6 Construction Funds

9.8 miles of shoulder repair on I-72 from I-172 to 0.9 miles east of IL 96 and on I-172 from I-72 to 0.9 miles south of IL 57.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

FAI ROUTES 72 AND 172, (I-72 AND I-172)

PROJECT NHPP-VI6W(201)

SECTION (1-2)SR, (75-1)SR-1

ADAMS AND PIKE COUNTIES

CONTRACT NO. 72639

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

SECTION (1-2)SR, (75-1)SR-1

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 X Additional State Requirements for Federal-Aid Construction Contracts 2 X Subletting of Contracts (Federal-Aid Contracts)

3 X EEO

4 Specific EEO Responsibilities Nonfederal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos Hot-Mix Asphalt Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 X Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays

SECTION (1-2)SR, (75-1)SR-1

i

TABLE OF CONTENTS

LOCATION OF PROJECT

DESCRIPTION OF PROJECT

TRAFFIC CONTROL PLAN

STATUS OF UTILITIES TO BE ADJUSTED

UNDERGROUND FACILITIES – DEPARTMENT OWNED

DELAYED START

NOTIFICATION PRIOR TO RAMP CLOSURES

DETOUR SIGNING

HMA ANTI-STRIP ADDITIVE REQUIREMENTS

HOT-MIX ASPHALT SHOULDER REMOVAL AND REPLACEMENT

CLEANING UNDERDRAIN OUTLETS

OUTLET MARKER

AUTOMATED FLAGGER ASSISTANCE DEVICES (BDE)

BITUMINOUS MATERIALS COST ADJUSTMENTS (BDE)

CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)

COMPENSABLE DELAY COSTS (BDE)

FUEL COST ADJUSTMENT (BDE)

HOT-MIX ASPHALT (BDE)

PAVEMENT MARKING (BDE)

PERFORMANCE GRADED ASPHALT BINDER (BDE)

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)

SEEDING (BDE)

SHORT TERM AND TEMPORARY PAVEMENT MARKINGS (BDE)

SIGN PANELS AND APPURTENANCES (BDE)

SOURCE OF SUPPLY AND QUALITY REQUIREMENTS (BDE)

SPEED DISPLAY TRAILER (BDE)

SUBCONTRACTOR AND DBE PAYMENT REPORTING (BDE)

SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)

SUBMISSION OF BIDDERS LIST INFORMATION (BDE)

SUBMISSION OF PAYROLL RECORDS – FEDERAL AID CONTRACT (BDE)

SURVEYING SERVICES (BDE)

TRAINING SPECIAL PROVISIONS (BDE)

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING SPECIAL PROVISION

VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)

SECTION (1-2)SR, (75-1)SR-1

ii

WORK ZONE TRAFFIC CONTROL DEVICES (BDE)

WORKING DAYS (BDE)

PROJECT LABOR AGREEMENT

SECTION (1-2)SR, (75-1)SR-1

STATE OF ILLINOIS

SPECIAL PROVISIONS

The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction, Adopted January 1, 2022", the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways", and the "Manual of Test Procedures for Materials" in effect on the date of invitation for bids, and the "Supplemental Specifications and Recurring Special Provisions" indicated on the Check Sheet included herein, which apply to and govern the construction of FAI Routes 72 and 172, (I-72 and I-172), Project NHPP-VI6W(201), Section (1- 2)SR, (75-1)SR-1, Adams and Pike Counties, Contract No. 72639, and in case of conflict with any part, or parts, of said Specifications, the said Special Provisions shall take precedence and shall govern.

FAI Routes 72 and 172, (I-72 and I-172) Project NHPP-VI6W(201)

Section (1-2)SR, (75-1)SR-1 Adams and Pike Counties

Contract No. 72639

LOCATION OF PROJECT

The project is located on I-72 from I-172 to 0.9 miles east of IL 96 and on I-172 from I-72 to 0.9 miles south of IL 57. The project has a gross length of 8.98 miles and a net length of 8.48 miles.

DESCRIPTION OF PROJECT

The project consists of HMA surface removal, HMA shoulder resurfacing, HMA shoulder widening at emergency median crossovers, pavement markings, and all other work necessary to complete the project.

TRAFFIC CONTROL PLAN

Effective: November 1, 1984 Revised: October 10, 2022

The following traffic control and protection will apply to this project:

Highway Standards:

701101 This standard will be used on multi-lane highways for all work activities within 24 inches and 15 ft. from the edge of pavement.

701106 This standard will be used on multi-lane highways for all work activities greater than 15 ft. from the edge of pavement.

SECTION (1-2)SR, (75-1)SR-1

701201 This standard will be used on 2 lane / 2 way traffic for construction activities such as resurfacing the IL 96 interchange ramps.

701400 This standard will be used any time a lane is closed on a freeway or expressway.

701401 This standard will be used any time a nighttime lane closure is required on a freeway or expressway due to work encroaching on a travel lane adjacent to the shoulder or on the shoulder within 24” of the edge of pavement. This standard is applicable for construction activities such as I-72 and I-172 shoulder resurfacing operations and shall be used in conjunction with Standard 701400.

701411 This standard will be used for all work activities involving freeway and expressway lane closures in close proximity to entrance and exit ramps. Each ramp, regardless of the number of setups required, shall be considered as one each.

701426 This standard will be used any time a lane closure is required on a freeway or expressway when any vehicle, equipment, workers, or their activities require stationary operations less than one hour or moving operations where the average speed is greater than 1 mph. This standard is applicable for construction activities such as I-72 and I-172 during pavement marking operations.

701451 This standard will be used for closing an interchange ramp to traffic. Ramp closures will be allowed for shoulder surface removal and HMA resurfacing operations.

701901 This standard describes all permissible traffic control devices that can be utilized with the above-mentioned traffic control standards.

Limitations Of Construction: The Contractor shall coordinate the items of work to keep hazards and traffic inconveniences to a minimum, as specified below.

1. The Contractor shall contact the District 6 Bureau of Operations, (217) 785-5306, at least 72 hours in advance of beginning work and three weeks prior to implementing any traffic control.

2. Changeable message sign(s) will be required for each direction of travel on I-72 and I-172 in which construction will occur. The sign(s) shall be placed and operating in advance of the project limits, in accordance with Standard 701400, two weeks prior to the start of work or any lane closure and/or ramp closure. As work continues, the sign(s) shall be relocated and operating in advance of the first operation requiring a lane closure.

3. All traffic control signs shall be new and meet current reflectivity standards. Remaining traffic control devices shall be new, or like new, equipped with new reflective sheeting at the time of use. The Engineer will be the sole judge of the condition of the devices.

4. In advance of each lane closure, the Contractor shall provide six “BE PREPARED TO STOP” (W3-4(O)48) signs. These signs shall be tripod mounted and placed at locations as designated by the Engineer, to provide adequate warning in advance of traffic back-ups. The signs will not be paid for separately but considered included in the contract unit bid prices for the traffic control and protection pay items.

5. Where construction operations require the construction of a temporary ramp, a "BUMP" sign(s) (W8-1(O)48) shall be used. The Contractor shall place the signs adjacent to the

SECTION (1-2)SR, (75-1)SR-1

temporary ramp or as directed by the Engineer. The signs shall remain in place until the temporary ramp is eliminated. The signs will not be paid for separately but considered included in the contract unit bid prices for the traffic control and protection pay items.

6. During construction, at least one lane of I-72 and I -172 shall remain open to traffic in each direction at all times.

7. A maximum 1 1/2” drop off will be allowed over night during ramp resurfacing operations.

Interchange Ramps: Interchange ramps shall be kept open to traffic and fully operational at all times during the construction of this project except as specified below.

The following I-72 ramps shall be temporarily closed utilizing Standard 701451 for HMA resurfacing operations:

• I-172 SB to I-72 WB (Exit 0): Ramp A

• I-72 EB to I-172 NB (Exit 4): Ramp B

• I-72 at IL 96 (Exit 10): Ramps A, B, C, and D

The Contractor shall provide a minimum of seven days of notice to the Engineer and District 6 Operations for all ramp closures. The Contractor shall provide additional changeable message signs seven-days prior to any proposed ramp closure. The changeable message signs shall be placed at locations specified below or as designated by the Engineer.

Only one ramp shall be closed at a time at the I-72 and I-172 trumpet interchange. Ramp closures shall be limited to one entrance ramp and one exit ramp at the IL 96 interchange.

The I-172 SB to I-72 WB (Exit 0) ramp closure shall be limited to daytime closures between 9:00 AM to 3:30 pm, Monday through Friday. Closures will be limited to three separate occasions.

The I-72 EB to I-172 NB (Exit 4) ramp closure shall also be limited to daytime closures between 9:00 AM to 3:30 pm, Monday through Friday. Closures will be limited to three separate occasions.

The I-72 at IL 96 (Exit 10) ramps shall also be limited to daytime closures between 9:00 AM to 3:30 pm, Monday through Friday. Closures will be limited to three separate occasions for each ramp.

Should the Contractor fail to have the ramps open on time, or exceed the number of allowable closures, the Contractor shall be liable to the department for liquidated damages in accordance with Article 108.09 of the Standard Specifications and any other additional special provisions which may be attached herein which supplements Article 108.09.

Interchange Ramp Closures:

Short-term closures for I-172 SB to I-72 WB

1. Ramp A (Exit 0): The Contractor shall furnish a changeable message sign on SB IL 57 north of the I-172 interchange, on I-172 SB north of the IL 57 interchange to display the following:

SECTION (1-2)SR, (75-1)SR-1

I-72 WB

EXIT 0

CLOSED

USE

I-72 EB

EXIT 10

FOLLOW

MARKED

DETOUR

The Contractor shall use Standard 701451 for the ramp closure and shall furnish an additional changeable message sign at the ramp closure as well.

Short-term closures at I-72 EB to I-172 NB:

1. Ramp B (Exit 4): The Contractor shall furnish a changeable message sign on I-72 EB west of the IL 106 interchange to display the following:

I-172 NB

EXIT 4

I-72 EB

FOLLOW

MARKED

DETOUR

Short-term closures at IL 96 interchange:

1. Ramp A (Exit 10): The Contractor shall furnish a changeable message sign on I-172 SB north of the I-72 trumpet interchange (Exit 0) to display the following:

SECTION (1-2)SR, (75-1)SR-1

IL 96

I-72 WB

EXIT 0

TO

IL 106

EXIT 1

The Contractor shall use TStandard 701451 for the ramp closure and shall furnish an additional message sign at the ramp closure as well.

2. Ramp C (Exit 4): The Contractor shall furnish a changeable message sign on I-72 WB east of the Barry Interchange (Exit 20) to display the following:

IL 96

EXIT 20

TO

IL 106

3. Ramps B & D (Exit 4): The Contractor shall furnish two changeable message signs for each direction of IL 96 to display the following:

I-72

RAMP

ALT

ROUTE

SECTION (1-2)SR, (75-1)SR-1

STATUS OF UTILITIES TO BE ADJUSTED

Reviewed: April 14, 2020

The following utilities are involved in this project. The utility companies have provided the estimated dates.

Name & Address of Utility Type Location Estimated Date of Relocation Completed

None Anticipated

The above represents the best information of the Department and is only included for the convenience of the bidder. The applicable provisions of Articles 105.07, 107.20, 107.37, 107.38, 107.39, 107.40, and 108.02 of the Standard Specifications shall apply.

The estimated utility relocation dates should be part of the progress schedule submitted by the Contractor. If any utility adjustments or relocations have not been completed by the above dates specified and when required by the Contractor's operations after these dates, the Contractor should notify the Engineer in writing. A request for an extension of time will be considered to the extent the Contractor's critical path schedule is affected.

UNDERGROUND FACILITIES – DEPARTMENT OWNED

Effective: February 1, 1996 Reviewed: September 20, 2024

The Contractor’s attention is directed to the presence of state-owned underground utilities within the limits of the proposed improvement. The Contractor shall notify the Illinois Department of Transportation, Bureau of Traffic Operations, a minimum of 72 hours in advance of work being done in the area at (217) 622-0608 to locate department owned underground facilities. The Illinois Department of Transportation is not a member of the Joint Utility Locating Information for Excavators (JULIE) system.

Any damage to the underground facilities, caused by the Contractor resulting from their failure to contact the Illinois Department of Transportation as specified above or from negligent operation, shall be repaired to the satisfaction of the Department at the Contractor’s expense, including temporary repairs which may be required to keep the facility operational while material is being obtained to make permanent repairs. Splicing of electric and fiber optic cables will not be allowed.

Electric cables shall be replaced from pole to pole or controller.

SECTION (1-2)SR, (75-1)SR-1

DELAYED START

Add the following after the first paragraph of Article 108.03 of the Standard Specifications:

"Contractors who are the apparent low bidder, may submit a written request for a delayed start within ten days after bid opening to the Regional Engineer. The request shall include specific reasons for the delayed start identifying a revised prosecution of work plan and a proposed progress schedule. The Regional Engineer will schedule a meeting with the Contractor within five working days after receipt of the delayed start request. At that time, schedules for the prosecution of work, exact starting dates, and preconstruction conference meeting dates shall be established. Consideration of a delayed start will not affect award decisions, or the procedures followed to execute awarded contracts.

By submission of a delayed start request, the Contractor understands and agrees that the granting of a delayed start shall not be reason for an extension of time to complete the contract, and that the decision to approve a delayed start for any or all contracts will reside with the Department, whose decision shall be final.

Working day contracts granted a delayed start shall be scheduled for completion, except for off-pavement and/or cleanup work, by June 30, 2027. However, upon starting a working day contract, working days will be charged according to Article 108.04 until the contract is complete.”

NOTIFICATION PRIOR TO RAMP CLOSURES

The Contractor shall notify the District’s Bureau of Operations and the individuals and organizations listed below at least seven days prior to any road and/or ramp closures.

Traffic Operations Engineer (Dist. 6) (217)-785-5306 Illinois State Police (Troop 6) (217)-285-2034 Adams County Engineer (217) 223-0614 Adams County Sheriff’s Department (217) 277-2202 Pike County Engineer (217)-285-4364 Pike County Sheriff’s Department (217)-285-4471

These agencies, organizations, and individuals shall also be notified when the road and/or ramps are re-opened to traffic and when the project is complete.

Changeable message signs will be placed at points located along IL 96, I-72, and I-172 ahead of the proposed ramp closures. The sign locations shall be according to the plans or as directed by the Engineer.

SECTION (1-2)SR, (75-1)SR-1

DETOUR SIGNING

Reviewed: April 14, 2020

Description. This work shall consist of furnishing, erecting, maintaining, covering, uncovering, and removing the detour signing as shown in the plans for the temporary ramp closure of

• I-172 SB to I-72 WB (Exit 0): Ramp A

• I-72 EB to I-172 NB (Exit 4): Ramp B

Materials. The materials used shall be in accordance with Section/Article 1090, 1091, 1006.29, and 1007.05 of the Standard Specifications.

Construction Requirements. The Contractor shall furnish and erect new detour signs at locations indicated in the plans. The signs shall be post mounted. Where it is possible, signs may be attached to existing posts or poles. The Contractor can contact District 6 Operations (Traffic) at

(217) 785-5306 for assistance in detour signing locations.

The signs are to be in place and uncovered prior to any road closure. When a detour is not in use, the detour signing shall be completely covered.

The signs and posts shall be removed when detours are no longer required. The Contractor shall return the area around the signs to its previous condition, at the Contractor’s expense. This may include seeding.

Method of Measurement. This work will be measured for payment on a lump sum basis and shall include furnishing, erecting, and maintaining detour route signs at locations indicated in the plans.

Basis of Payment. This work will be paid for at the contract unit price per LUMP SUM for DETOUR

SIGNING.

HMA ANTI-STRIP ADDITIVE REQUIREMENTS

HMA mixtures utilizing crushed gravel or sandstone coarse aggregate shall incorporate an anti-strip additive according to Article 1030.05(c). The additive shall be sufficient to achieve a TSR equal to 0.90 or greater for 6-inch specimens. If a liquid additive is used, the additive quantity shall be between 0.25% and 1.0% of the total weight of liquid asphalt. The mixture shall meet the minimum conditioned tensile strength requirements described in Article 1030.05(c).

The anti-strip additive product utilized for mix design verification shall be used for mixture production. A change in anti-strip additive product requires a reverification of the TSR and minimum conditioned tensile strength requirements prior to mixture production.

HMA mixtures having an ABR greater than 20% incorporating RAP/FRAP materials consisting of crushed gravel or sandstone coarse aggregate shall include an anti-strip additive. Where the RAP/FRAP materials requiring anti-strip were not included in the initial mix design verification, a new mix design is not required. However, a re-verification of the TSR and minimum conditioned tensile strength requirements is required prior to mixture production.

SECTION (1-2)SR, (75-1)SR-1

This work will not be measured for payment. The cost of furnishing and introducing anti-stripping additives in the HMA shall be in included in the contract unit price of the HMA item involved.

HOT-MIX ASPHALT SHOULDER REMOVAL AND REPLACEMENT

Description. This pay item is intended to remove and replace existing HMA shoulders in areas that have deteriorated due to construction activities associated with resurfacing paved shoulders at locations identified by the Engineer.

Construction Requirements. This work shall consist of removing and disposing the lower 4 inches of existing HMA shoulders at locations identified by the Engineer. Removal and disposal shall be according to Section 440 of the Standard Specifications.

This work shall also consist of replacing the lower 4 inches of HMA shoulders after HMA surface removal operations are complete. The replacement of the HMA shoulders shall be according to Section 482 of the Standard Specifications. The upper 4 inches of HMA shoulders will be paid for separately via HMA shoulders.

Method of Measurement. This work will be measured for payment in place, and the area computed in square yards.

Basis of Payment. This work will be paid for at the contract unit price per SQUARE YARD for

HOT-MIX ASPHALT SHOULDER REMOVAL AND REPLACEMENT.

CLEANING UNDERDRAIN OUTLETS

Revised: January 31, 2024

Description. This work shall consist of cleaning existing underdrain outlets and replacing missing rodent shields.

All existing underdrain outlets shall be cleaned unless otherwise directed by the Engineer. This cleaning shall include removing vegetation, sediment, or other debris from the existing headwall and outlet pipe. The cleaning shall also include reestablishing positive drainage from the outlet to the ditch where needed. The outlet pipe shall be flushed with water using a hose or other suitable equipment. The pipe shall be flushed a minimum distance of 10 feet beyond the pipe opening. The pressure of water introduced into the pipe shall not exceed 50 psi. All equipment used is subject to the approval of the Engineer. Headwalls and pipes damaged during cleaning shall be replaced as directed by the Engineer.

Any headwalls which are no longer properly attached to the drain shall be reconnected to the drain pipe using methods identified in Section 701 of the Standard Specifications. Damaged headwalls will be paid for according to Article 109.04 of the Standard Specifications as directed by the Engineer.

Existing outlets with an invert elevation below the existing ditch elevation do not require cleaning unless directed by the Engineer. If the contract includes separate work for ditch cleaning or regrading at the location of the outlet, the outlet should be cleaned after ditch work is complete.

SECTION (1-2)SR, (75-1)SR-1

Where rodent shields are not functioning or absent, they should be replaced according to Article

601.05 of the Standard Specifications. The Contractor shall submit a rodent shield design for approval of the Engineer prior to use.

Method of Measurement. This work will be measured for payment in place at each underdrain outlet cleaned.

Basis of Payment. This work will be paid for at the contract unit price per EACH for CLEANING

UNDERDRAIN OUTLETS.

OUTLET MARKER

Revised: April 14, 2020

Description. This work shall consist of marking the location of all existing pipe underdrain outlets within the limits of the project.

Materials. Materials shall meet the requirements of the following Articles of Section 1000 of the Standard Specifications:

Item Article/Section

(a) Modified Urethane Pavement Marking…………………………………...........................1095.09

Construction Requirements. Outlet markers, as detailed in the plans, shall be installed on the completed bituminous with painted pavement markings. Outlet markers shall be placed directly over all existing pipe underdrain outlet pipes. The outlet marker color shall be white. Installation shall be according to Article 780.06.

Method of Measurement. This work will be measured for payment in units of each at pipe underdrain outlet locations.

Basis of Payment. This work will be paid for at the contract unit price per EACH for OUTLET

MARKER.

SECTION (1-2)SR, (75-1)SR-1

AUTOMATED FLAGGER ASSISTANCE DEVICES (BDE)

Effective: January 1, 2008 Revised: April 1, 2023

Description. This work shall consist of furnishing and operating automated flagger assistance devices (AFADs) as part of the work zone traffic control and protection for two-lane highways where two-way traffic is maintained over one lane of pavement in segments where no sideroads or entrances require deployment of additional flaggers. Use of these devices shall be at the option of the Contractor.

Equipment. AFADs shall be the STOP/SLOW or Red/Yellow Lens type mounted on a trailer or moveable cart meeting the requirements of the MUTCD and NCHRP 350 or MASH 2016, Category 4.

General. AFADs shall be placed at each end of the traffic control, where a flagger is shown on the plans. The AFAD shall be setup within five degrees of vertical.

Flagger symbol signs as shown on the plans shall be replaced with “BE PREPARED TO STOP” signs when the AFAD is in operation.

Personal communication devices shall not be used to operate the AFAD.

Flagging Requirements. Flaggers and flagging requirements shall be according to Article 701.13 of the Standard Specifications and the following.

Each AFAD shall be operated by a flagger trained to operate the specific AFAD to be deployed.

A minimum of two flaggers shall be on site at all times during operation. Each flagger shall be positioned outside the lane of traffic and near each AFAD’s location.

Flagging equipment required for traditional flagging shall be available near each AFAD location in the event of AFAD equipment malfunction/failure.

For nighttime flagging, the AFAD and flagger shall be illuminated according to Article 701.13 of the Standard Specifications.

When not in use, AFADs will be considered non-operating equipment and shall be stored according to Article 701.11 of the Standard Specifications.

Basis of Payment. This work will not be paid for separately but shall be considered as included in the cost of the various traffic control items included in the contract.

SECTION (1-2)SR, (75-1)SR-1

BITUMINOUS MATERIALS COST ADJUSTMENTS (BDE)

Effective: November 2, 2006 Revised: August 1, 2017

Description. Bituminous material cost adjustments will be made to provide additional compensation to the Contractor, or credit to the Department, for fluctuations in the cost of bituminous materials when optioned by the Contractor. The bidder shall indicate with their bid whether or not this special provision will be part of the contract.

The adjustments shall apply to permanent and temporary hot-mix asphalt (HMA) mixtures, bituminous surface treatments (cover and seal coats), and preventative maintenance type surface treatments that are part of the original proposed construction, or added as extra work and paid for by agreed unit prices. The adjustments shall not apply to bituminous prime coats, tack coats, crack filling/sealing, joint filling/sealing, or extra work paid for at a lump sum price or by force account.

Method of Adjustment. Bituminous materials cost adjustments will be computed as follows.

CA = (BPIP - BPIL) x (%ACV / 100) x Q

Where: CA = Cost Adjustment, $.

BPIP = Bituminous Price Index, as published by the Department for the month the work is performed, $/ton ($/metric ton).

BPIL = Bituminous Price Index, as published by the Department for the month prior to the letting for work paid for at the contract price; or for the month the agreed unit price letter is submitted by the Contractor for extra work paid for by agreed unit price, $/ton ($/metric ton).

%ACV = Percent of virgin Asphalt Cement in the Quantity being adjusted. For HMA mixtures, the % ACV will be determined from the adjusted job mix formula. For bituminous materials applied, a performance graded or cutback asphalt will be considered to be 100% ACV and undiluted emulsified asphalt will be considered to be 65% ACV.

Q = Authorized construction Quantity, tons (metric tons) (see below).

For HMA mixtures measured in square yards: Q, tons = A x D x (Gmb x 46.8) / 2000. For HMA mixtures measured in square meters: Q, metric tons = A x D x (Gmb x 1) / 1000. When computing adjustments for full-depth HMA pavement, separate calculations will be made for the binder and surface courses to account for their different Gmb and % ACV.

For bituminous materials measured in gallons: Q, tons = V x 8.33 lb/gal x SG / 2000 For bituminous materials measured in liters: Q, metric tons = V x 1.0 kg/L x SG / 1000

Where: A = Area of the HMA mixture, sq yd (sq m).

D = Depth of the HMA mixture, in. (mm).

Gmb = Average bulk specific gravity of the mixture, from the approved mix design.

V = Volume of the bituminous material, gal (L).

SG = Specific Gravity of bituminous material as shown on the bill of lading.

SECTION (1-2)SR, (75-1)SR-1

Basis of Payment. Bituminous materials cost adjustments may be positive or negative but will only be made when there is a difference between the BPIL and BPIP in excess of five percent, as calculated by:

Percent Difference = {(BPIL – BPIP) ÷ BPIL} × 100

Bituminous materials cost adjustments will be calculated for each calendar month in which applicable bituminous material is placed; and will be paid or deducted when all other contract requirements for the work placed during the month are satisfied. The adjustments shall not apply during contract time subject to liquidated damages for completion of the entire contract.

CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)

Effective: January 1, 2025 Revised: January 1, 2026

Revise the first paragraph of Article 285.05 of the Standard Specifications to read:

“ 285.05 Fabric Formed Concrete Revetment Mat. The grout shall consist of a mixture of cement, fine aggregate, and water so proportioned and mixed as to provide a pumpable slurry.

Fly ash or ground granulated blast furnace (GGBF) slag, and concrete admixtures may be used at the option of the Contractor. The grout shall have an air content of not less than 6.0 percent nor more than 9.0 percent of the volume of the grout. The mix shall obtain a compressive strength of 2500 psi (17,000 kPa) at 28 days according to Article 1020.09.”

Revise Article 302.02 of the Standard Specifications to read:

“ 302.02 Materials. Materials shall be according to the following.

(a) Cement

(b) Water

(c) Hydrated Lime .................................................................................................... 1012.01

(d) By-Product, Hydrated Lime ................................................................................ 1012.02

(e) By-Product, Non-Hydrated Lime ........................................................................ 1012.03

(f) Lime Slurry ......................................................................................................... 1012.04

(g) Fly Ash

(h) Soil for Soil Modification (Note 1) ....................................................................... 1009.01

(i) Bituminous Materials (Note 2)

Note 1. This soil requirement only applies when modifying with lime (slurry or dry).

Note 2. The bituminous materials used for curing shall be emulsified asphalt RS-2, CRS- 2, HFE 90, or HFE 150; rapid curing liquid asphalt RC-70; or medium curing liquid asphalt MC-70 or MC-250.”

Revise Article 312.07(c) of the Standard Specifications to read:

“ (c) Cement .................................................................................................................... 1001”

SECTION (1-2)SR, (75-1)SR-1

Add Article 312.07(i) of the Standard Specifications to read:

“ (i) Ground Granulated Blast Furnace (GGBF) Slag ...................................................... 1010”

Revise the first paragraph of Article 312.09 of the Standard Specifications to read:

“ 312.09 Proportioning and Mix Design. At least 60 days prior to start of placing CAM II, the Contractor shall submit samples of materials to be used in the work for proportioning and testing.

The mixture shall contain a minimum of 200 lb (120 kg) of cement per cubic yard (cubic meter).

Cement may be replaced with fly ash or ground granulated blast furnace (GGBF) slag according to Article 1020.05(c)(1) or 1020.05(c)(2), respectively, however the minimum cement content in the mixture shall be 170 lbs/cu yd (101 kg/cu m). Blends of coarse and fine aggregates will be permitted, provided the volume of fine aggregate does not exceed the volume of coarse aggregate. The Engineer will determine the proportions of materials for the mixture according to the “Portland Cement Concrete Level III Technician Course” manual. However, the Contractor may substitute their own mix design. Article 1020.05(a) shall apply, and a Level III PCC Technician shall develop the mix design.”

Revise Article 352.02 of the Standard Specifications to read:

“ 352.02 Materials. Materials shall be according to the following.

(a) Cement (Note 1)

(b) Soil for Soil-Cement Base Course ....................................................................... 1009.03

(c) Water

(d) Bituminous Materials (Note 2)

Note 1. Bulk cement may be used for the traveling mixing plant method if the equipment for handling, weighing, and spreading the cement is approved by the Engineer.

Note 2. The bituminous materials used for curing shall be emulsified asphalt RS-2, CRS-2, HFE 90, or HFE 150; rapid curing liquid asphalt RC-70; or medium curing liquid asphalt MC-70 or MC-250.”

Revise Article 404.02 of the Standard Specifications to read:

“ 404.02 Materials. Materials shall be according to the following.

(a) Cement

(b) Water

(c) Fine Aggregate .................................................................................................... 1003.08

(d) Bituminous Material (Tack Coat) .......................................................................... 1032.06

(e) Emulsified Asphalts (Note 1) (Note 2) .................................................................. 1032.06

(f) Fiber Modified Joint Sealer .................................................................................. 1050.05

(g) Additives (Note 3)

Note 1. When used for slurry seal, the emulsified asphalt shall be CQS-1h according to Article 1032.06(b).

SECTION (1-2)SR, (75-1)SR-1

Note 2. When used for micro-surfacing, the emulsified asphalt shall be CQS-1hP according to Article 1032.06(e).

Note 3. Additives may be added to the emulsion mix or any of the component materials to provide the control of the quick-traffic properties. They shall be included as part of the mix design and be compatible with the other components of the mix.

Revise the last sentence of the fourth paragraph of Article 404.08 of the Standard Specifications to read:

“When approved by the Engineer, the sealant may be dusted with fine sand, cement, or mineral filler to prevent tracking.”

Revise Note 2 of Article 516.02 of the Standard Specifications to read:

“ Note 2. The sand-cement grout mix shall be according to Section 1020 and shall be a 1:1 blend of sand and cement comprised of a Type I, IL, or II cement at 185 lb/cu yd (110 kg/cu m). The maximum water cement ratio shall be sufficient to provide a flowable mixture with a typical slump of 10 in. (250 mm).”

Revise Note 2 of Article 543.02 of the Standard Specifications to read:

“ Note 2. The grout mixture shall be 6.50 hundredweight/cu yd (385 kg/cu m) of cement plus fine aggregate and water. Fly ash or ground granulated blast furnace (GGBF) slag may replace a maximum of 5.25 hundredweight/cu yd (310 kg/cu m) of the cement. The water/cement ratio, according to Article 1020.06, shall not exceed 0.60. An air-entraining admixture shall be used to produce an air content, according to Article 1020.08, of not less than 6.0 percent nor more than 9.0 percent of the volume of the grout. The Contractor shall have the option to use a water-reducing or high range water-reducing admixture.”

Revise Article 583.01 of the Standard Specifications to read:

“ 583.01 Description. This work shall consist of placing cement mortar along precast, prestressed concrete bridge deck beams as required for fairing out any unevenness between adjacent deck beams prior to placing of waterproofing membrane and surfacing.”

Revise Article 583.02(a) of the Standard Specifications to read:

“ (a) Cement .................................................................................................................... 1001”

Revise the first paragraph of Article 583.03 of the Standard Specifications to read:

“ 583.03 General. This work shall only be performed when the air temperature is

45 °F (7 °C) and rising. The mixture for cement mortar shall consist of three parts sand to one part cement by volume. The amount of water shall be no more than that necessary to produce a workable, plastic mortar.”

Revise Article 606.02(h) of the Standard Specifications to read:

SECTION (1-2)SR, (75-1)SR-1

“ (h) Fibers (Note 1) ........................................................................................................ 1014”

Revise Note 1 in Article 606.02(h) of the Standard Specifications to read:

“ Note 1. Fibers, when required, shall only be used in the concrete mixture for slipform applications.”

Revise the third paragraph in Article 606.10 of the Standard Specifications to read:

“ Welded wire fabric shall be 6 x 6 in. (150 x 150 mm) mesh, #4 gauge (5.74 mm), 58 lb (26 kg) per 100 sq ft (9 sq m).”

Revise Article 1001.01(d) of the Standard Specifications to read:

“ (d) Rapid Hardening Cement. Rapid hardening cement shall be according to the Bureau of Materials Policy Memorandum “Portland or Blended Cement Acceptance Procedure for Qualified and Non-Qualified Plants”, and ASTM C 1600, Type URH, Type VRH, or Type RH-CAC. It shall be used according to Article 1020.04 or when approved by the Engineer.

The Contractor shall submit a report from the manufacturer or an independent lab that contains results for testing according to ASTM C 1600 which shows the cement meets the requirements of either Type URH, Type VRH, or Type RH-CAC. Test data shall be less than 1 year old from the date of submittal.

Revise Article 1001.01(e) of the Standard Specifications to read:

“ (e) Other Cements. Other cements shall be according to the Bureau of Materials Policy Memorandum “Portland or Blended Cement Acceptance Procedure for Qualified and Non- Qualified Plants”, and ASTM C 1157 or ASTM C 1600, as applicable. Other cements shall be used according to Article 1020.04 or when approved by the Engineer. For cements according to ASTM C 1157, the Contractor shall submit a report from the manufacturer or an independent lab that contains results of tests which shows the cement meets the requirements Type GU, HE, MS, MH, or LH. For cements according to ASTM C 1600, the Contractor shall submit a report from the manufacturer or an independent lab that contains results of tests which shows the cement meets the requirements Type MRH or GRH. Test data shall be less than 1 year old from the date of submittal.”

Revise Article 1002.02 of the Standard Specifications to read:

“ 1002.02 Quality. Water used with cement in concrete or mortar and water used for curing concrete shall be clean, clear, and free from sugar. In addition, water shall be tested and evaluated for acceptance according to one of the following options.

OPTION 1.

(a) Acceptable limits for acidity and alkalinity when tested according to ITP T 26.

(1) Acidity -- 0.1 Normal NaOH ........................................................................ 2 ml max.*

(2) Alkalinity -- 0.1 Normal HCI ....................................................................... 10 ml max.*

*To neutralize 200 ml sample.

SECTION (1-2)SR, (75-1)SR-1

(b) Acceptable limits for solids when tested according to the following.

(1) Organic (ITP T 26) .................................................................................... 0.02% max.

(2) Inorganic (ITP T 26) .................................................................................. 0.30% max.

(3) Sulfate (SO4) (ASTM D 516-82) ............................................................... 0.05% max.

(4) Chloride (ASTM D 512) ............................................................................ 0.06% max.

(c) The following tests shall be performed on the water sample and on deionized water. The same cement and sand shall be used for both tests.

(1) Unsoundness (ASTM C 151).

(2) Initial and Final Set Time (ASTM C 266).

(3) Strength (ASTM C 109).

The test results for the water sample shall not deviate from the test results for the deionized water, except as allowed by the precision in the test method.

OPTION 2. Water shall meet the requirements ASTM C 1602 Tables 1 and 2 as outlined in Sections 5.1, 5.2, and 5.4.”

Revise Note 2/ in Article 1003.01(b) of the Standard Specifications to read:

“ 2/ Applies only to sand. Sand exceeding the colorimetric test standard of 11 (Illinois

Modified AASHTO T 21) will be checked for mortar making properties according to Illinois Modified ASTM C 87 and shall develop a compressive strength at the age of 14 days when using Type I, IL, or II cement of not less than 95 percent of the comparable standard.

Revise the second sentence of Article 1003.02(e)(1) of the Standard Specifications to read:

“ The test will be performed with Type I, IL, or II portland cement having a total equivalent alkali content (Na2O + 0.658K2O) of 0.90 percent or greater.”

Revise the first sentence of the second paragraph of Article 1003.02(e)(3) of the Standard Specifications to read:

“ The ASTM C 1293 test shall be performed with Type I, IL, or II portland cement having a total equivalent alkali content (Na2O + 0.658K2O) of 0.80 percent or greater.”

Revise the second sentence of Article 1004.02(g)(1) of the Standard Specifications to read:

“ The test will be performed with Type I, IL, or II portland cement having a total equivalent alkali content (Na2O + 0.658K2O) of 0.90 percent or greater.”

Add the following Section to the Standard Specifications.

“SECTION 1014. FIBERS FOR CONCRETE

SECTION (1-2)SR, (75-1)SR-1

1014.01 General. Fibers used in concrete shall be Type II or Type III (polyolefin or carbon) according to ASTM C 1116. The testing required for Type II fibers or Type III polyolefin fibers shall be performed by an independent lab a minimum of once every five years, and the test results provided to the Department. Manufacturers of Type III carbon fibers shall provide materials certification documentation not more than 6 years old a minimum of once every 5 years to the Department. The Department will maintain a qualified product list. The method of inclusion of fibers into concrete mixtures shall be according to the manufacturer’s specifications.

At the discretion of the Engineer, the concrete mixture shall be evaluated in a field demonstration for fiber clumping, ease of placement, and ease of finishing. The field demonstration shall consist of a minimum 2 cu yd (1.5 cu m) trial batch placed in a 12 ft x 12 ft (3.6 m x 3.6 m) slab.

1014.02 Concrete Gutter, Curb, Median and Paved Ditch. Fibers shall be Type III. Fibers shall have a minimum length of 1/2 in. (13 mm) and a maximum length of 0.75 in. (19 mm). The maximum dosage rate in the concrete mixture shall not exceed 1.5 lb/cu yd (0.9 kg/cu m). The minimum dosage rate shall be per the manufacturer’s recommendation.

1014.03 Concrete Inlay or Overlay. Fibers shall be Type III. Fibers shall have a minimum length of 1.0 in. (25 mm), a maximum length of 2 1/2 in. (63 mm), and a maximum aspect ratio (length divided by the equivalent diameter of the fiber) of 150. The maximum dosage rate shall not exceed 5.0 lb/cu yd (3.0 kg/cu m). The minimum dosage rate shall be per the manufacturer’s recommendation.

1014.04 Bridge Deck Fly Ash, Ground Granulated Blast Furnace (GGBF) Slag, High

Reactivity Metakaolin, or Microsilica (Silica Fume) Concrete Overlay. Fibers shall be Type III. The dosage rate shall be a minimum of 3.0 lb/cu yd (1.8 kg/cu m), unless a field demonstration according to Article 1014.01 indicates that a lower dosage rate is necessary.

Based on the results of the field demonstration, the Department has the option to reduce the dosage rate of fibers, but the dosage will not be reduced to less than 2.0 lb / cu yd (1.2 kg/cu m).

1014.05 Bridge Deck Latex Concrete Overlay. Fibers shall be Type II or III. Fibers shall have a minimum length of 0.75 in. (19 mm), a maximum length of 1.75 in. (45 mm), and an aspect ratio (length divided by the equivalent diameter of the fiber) of between 70 and 100. The dosage rate shall be a minimum of 3.0 lb/cu yd (1.8 kg/cu m), unless a field demonstration according to Article 1014.01 indicates that a lower dosage rate is necessary. Based on the results of the field demonstration, the Department has the option to reduce the dosage rate of fibers, but the dosage will not be reduced to less than 2.0 lb/cu yd (1.2 kg/cu m).”

Add the following Section to the Standard Specifications:

“SECTION 1015. HIGH PERFORMANCE SHOTCRETE

1015.01 Packaged Shotcrete With Aggregate. The packaged shotcrete with aggregate shall be a pre-blended dry combination of materials for the wet-mix shotcrete method according to ASTM C 1480, Type FA or CA, Grade FR, Class I. The fibers shall be Type III according to Article 1014.01. The cement and finely divided minerals in the mixture shall be a minimum

6.65 cwt/cu yd (395 kg/cu m), and the portland cement shall not be below 4.70 cwt/cu yd (279 kg/cu m). Microsilica is required in the mixture and shall be a minimum of 5 percent by weight (mass) of cementitious material, and a maximum of 10 percent. Strength requirements shall be

SECTION (1-2)SR, (75-1)SR-1

according to ASTM C 1480 except that the strength at 28 days shall be at least 4000 psi (27,500 kPa). Strength testing shall be according to ASTM C 1140. The air content as shot shall be 4.0 – 8.0 percent when tested according to AASHTO T 152, and the coarse aggregate shall be a maximum size of 1/2 in. (12.5 mm).

The packaged shotcrete shall have a water soluble chloride ion content of less than 0.15% by weight of cementitious material when tested according to ASTM C 1218 or AASHTO T 260.

The testing according to ASTM C 1480, ASTM C 1140, AASHTO 152, and ASTM C 1218 or

AASHTO T 260 shall be performed by an independent lab a minimum of once every 5 years, and the test results shall be provided to the Department. The Department will maintain a qualified product list. Batching and mixing shall be per the manufacturer’s recommendations.

1015.02 Packaged Shotcrete Without Aggregate. The packaged shotcrete that does not include pre-blended aggregate shall be according to Article 1015.01, except the added aggregate shall be according to Articles 1003.02 and 1004.02. The aggregate gradation shall be according to the manufacturer. The Department will maintain a qualified product list. Batching and mixing shall be per the manufacturer’s recommendations.”

Revise Section 1017 of the Standard…