D.1 Attachment 4: Monthly Status Report Template

View the file

Other files

File Type Posted
A0003_ID09180038_SF30.pdf PDF
ID09180038_REQUEST_FOR_PROPOSAL_A0001.pdf PDF
Amendment_A0002_ID09180038_MPTA_Q&A.pdf PDF
A0002_ID09180038_SF30.pdf PDF
A0001_ID09180038_D.8_PAST_PERFORMANCE_REFERENCE_SHEET.docx DOCX document
Amendment_A0001_ID09180038_D.3_-_PRICE_SUMMARY_WORKBOOK.xlsx XLSX spreadsheet
Amendment_A0001_ID09180038_D.1_ATTACHMENT_1_HISTORICAL_AND_PROJECTED_WORKLOAD.pdf PDF
A0001_ID09180038_SF30.pdf PDF
ID09180038_SECTION_D.1_PERFORMANCE_WORK_STATEMENT.pdf PDF
ID09180038_D.1_ATTACHMENT_2_GOVERNMENT_FURNISHED_PROPERTY.pdf PDF
ID09180038_D.1_ATTACHMENT_6_SAMPLE_TASK_ORDER_2.pdf PDF
ID09180038_REQUEST_FOR_PROPOSAL.pdf PDF
ID09180038_D.8_PAST_PERFORMANCE_REFERENCE_SHEET.pdf PDF
ID09180038_D.1_ATTACHMENT_1_HISTORICAL_AND_PROJECTED_WORKLOAD.pdf PDF
ID09180038_D.4_KEY_PERSONNEL_REQUIREMENTS_SUMMARY.pdf PDF
ID09180038_D.1_ATTACHMENT_7_-_SAMPLE_TASK_ORDER_3_-_TASK_ORDER_0001.pdf PDF
ID09180038_D.3_-_PRICE_SUMMARY_WORKBOOK.xlsx XLSX spreadsheet
ID09180038_D.1_ATTACHMENT_3_PROBLEM_NOTIFICATION_REPORT.pdf PDF
ID09180038_D.1_ATTACHMENT_5_SAMPLE_TASK_ORDER__1.pdf PDF
ID09180038_D.6_NON-DISCLOSURE_AGREEMENT.pdf PDF
ID09180038_D.7_SMALL_BUSINESS_PARTICIPATION_INFORMATION_SHEET.pdf PDF
ID09180038_D.2_TRAVEL_AUTHORIZATION_REQUEST.pdf PDF
ID09180038_D.5_QUALITY_ASSURANCE_SURVEILLANCE_PLAN.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID09180038 – D.1_Attachment 4 – Monthly Status Report (MSR)

D.1 PERFORMANCE WORK STATEMENT (PWS) ATTACHMENT 4 – MONTHLY STATUS

REPORT

Reporting Month:

Date Submitted:

Contractor Name:

Manpower Personnel Testing Analysis (MPTA) Contract Number #

Financial Review / Expenses (for each CLIN) Contract $ Awarded (this Contract Year (CY)) Amount $, by CLIN

CLIN # 0001

Time elapsed this CY: Percentage % (# months /

12) Current $ expended against CY: Percentage % (expended / awarded) Amount funded this CY: Dollar $ Less expense incurred and billed Dollar $ (through what date) Less expenses, incurred, but not billed Dollar $ (covers what period of time) Remaining CLIN funded amount available Dollar $

CLIN # 0002 Same format as above CLIN # 0003 And so forth CLIN(s) not funded Amount $

SAMPLE: Activities During this Month

The following new individuals were engaged to provide services on the contract:

Govt. Lab Cat (Samples) Contractor Lab Cat Name CLIN

Senior Management, Supervisor Project Manager Assistant Project Manager Project Assistant Web Designer / Manager Database Analyst / Programmer Graphics Designer, Senior Graphic Designer

Risks/Issues & Concerns:

Project Status Dashboard:

Financial Status: (red, yellow or green) Personnel: (red, yellow or green) Project Performance:(red, yellow or green)

ID09180038 – D.1_Attachment 4 – Monthly Status Report (MSR)

Utilization of Personnel:

Name CLIN Start

Date End Date

Date of Latest Inventory

# of Hours Requested

# of Hours worked

# of Hours Remaining

Burn Rate

Task Order Number

Hours Worked to Date by Labor Category:

Hours Month 1 Month 2 Month 3 >>>>> Month 11 Month 12 Total

CLIN 0001

Name

LABOR CATGORIES (SAMPLE)

Senior Management, Supervisor

Employee name Project Manager

Employee name Assistance Project Manager Project Assistant Wed Designer / Manager

CLIN 0002 - Expenditures

CLIN 0003 - Expenditures Based on discussion at the monthly SMR meetings, provide highlights of accomplishments and problems that occurred during previous six-month reporting period.

Provide highlights of activities and problems anticipated during the next reporting period