industry_day_presentation_5-14-14.pdf
PDF 1 MB Posted
- Attached to
- Industry Day DeCA Whole Facility Maintenance
- Solicitation number
- ID08140013
- Issued by
-
GSA Federal Acquisition Service
About this file
GSA Presentation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Industry_Day_Sign_In_Sheet.pdf | ||
| Questions_and_responses.docx | DOCX document | |
| DeCA_Facilities_Support_Questionnaire_v1.doc | DOC document | |
| Draft_TI_Manual_2015_v1.docx | DOCX document | |
| DeCA_Facilities_Support_Questionnaire.doc | DOC document | |
| Draft_TI_Manual_2015.docx | DOCX document | |
| PWS_final_draft_5-5_(1).docx | DOCX document | |
| DFC_Map.jpg | JPG image |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Acquisition Service
U.S. General Services Administration
Industry Day for
DeCA Facility Maintenance Requirement
5/14/14
Agenda
Introductions and Purpose
Ground Rules
Description of Requirement
Acquisition Strategy
Technical Instruction (TI) Process
Small Business Subcontracting Plan
Lunch Break (approximately 11:30a-12:30p)
PWS and Pricing Methodology Discussion/Q&A
Introductions
GSA Team
DeCA Team
Purpose
Acquisition Planning and Market Research
Provide interested vendors an overview of the DeCA facility maintenance program and requirements
Describe the basic strategy for this acquisition
Opportunity for industry to provide input and feedback on the project and upcoming solicitation
Ground Rules for the Day
This is an open forum seeking industry input on requirements and processes. Ideas and information presented may be recorded and publicized (FedBizOpps) or otherwise recorded for this event
No agreements, promises or other commitments are made or implied by the Government or Contractors participating in Industry day
The Government facilitator will acknowledge each speaker and attempt to provide equal opportunity and time to speak. Please allow others to express themselves without interruptions
Side conversations are discouraged and discussion related to this solicitation will be shared with the group
Ground Rules for the Day
Questions will be answered to the best of the knowledge of plans, desires, and general situation as it exists at this time. Please recognize that this project is in acquisition planning stage. Contractor recommendations may or may not be incorporated into Government documents.
PWS Specific Q&A in the afternoon discussion
There is no classified information involved with this requirement
To ensure everyone has access to the same information, non-proprietary questions and answers will be recorded and placed on the web (FedBizOpps)
The public forum portion of Industry day is not appropriate for proprietary disclosures
Description of Requirement
• Scope
– Provide facility maintenance services to the
Defense Commissary Agency (DeCA) commissaries throughout the United States, to include Alaska and Hawaii, and the U.S. territories of Guam and Puerto Rico
– Two Types of Maintenance
• Scheduled /Preventative Maintenance
• Unscheduled Maintenance
• Unscheduled Maintenance- Four subcategories
– Emergency Maintenance and Repairs (2 hour response)
– Priority Maintenance (respond by noon following business day)
– Routine Maintenance (respond and schedule within 7 days)
– Repair and Maintenance (Major system replacement, HVAC, refrigeration, incidental construction)
Description of Requirement
Description of Requirement
2.3.1 Commissary Equipment In Place (CEIP)
2.3.2 After hours services
2.3.3 Maintenance Types
2.3.4 Minor Construction
2.3.5 Financial Reporting
2.3.6 Computerized Maintenance Management System (CMMS)
2.3.7 Government Technical instruction (TI) Tracking
2.3.8 Maintenance Response and Call Center Operation
2.3.9 Use and Servicing of Refrigerant
2.3.10 Environmental controls
2.3.11 Transition Period
2.3.12 Phase Out – Continuity of Services
2.3.13 Contractor Personnel
Description of Requirement
2.3.14 Quality Control Plan
2.3.15 Quality Assurance/Quality Assurance Surveillance Plan
2.3.16 Performance Requirements and Responsibilities
2.3.17 Suspension of Preventative Maintenance Services
2.3.18 Contractor Liability
2.3.19 Contract Closeout
2.3.20 Past Performance Information Retrieval System (PPIRS)
2.3.21 Sample Forms
2.3.22 Equipment Identification and Operation and Maintenance
Manuals
2.3.23 Records
Other Appendices
Acquisition Strategy
One solicitation for multiple award of contract by geographic maintenance groups
• 8 Maintenance Groups–up to 8 contracts/contractors
• Base period plus 4 option years
• 30-day transition period prior to Fully Operation
Base Period
Performance Work Statement and Quality Assurance
Surveillance Plan (QASP)
Small Business Plan requirement- as applicable
Acquisition Strategy
NAICS: 561210 Facility Support Services Size Standard: $35.5M
Proposed Procurement Methodology Best Value under FAR Parts 12 and 15
Broad Evaluation Factors Areas
Technical
Past Performance
Price
Acquisition Strategy- Pricing
Price Schedule
• Firm Fixed Price for Preventative Maintenance – monthly
• Firm Fixed Price for TIs- based on fixed labor rates
• Unscheduled Maintenance
• SCA or DBA wage determination will apply
Construction Tasks Fixed price post-award through separate RFQ to contract
Concerns Pricing and inclusion for Routine Maintenance as a fixed
Milestone Approximate Date
Sources Sought Posted to FBO Apr 21, 2014
Industry Day May 14, 2014
Facilities Support Questionnaire Responses Due May 30, 2014
Issue Solicitation (GSA) Aug 25, 2014
Pre-proposal Conference/Site Visit Sep 2, 2014
Proposals Due Oct 9, 2014
Oral Presentations Nov 20, 2014
Complete Discussions/Negotiations Dec 19, 2014
Contract Award Feb 27, 2015
Approximate High-level Milestones
Technical Instruction (TI) Process
TI Process map
Historical TI Data
Request questions/input from industry in the afternoon discussion
Construction
DeCA Facility Maintenance – Current TI Process
C o n tr a c to r G
S A
P B
D e lie n t
Performs work
G
F
Accepts work
Submits invoice
Requests
Work in
Vendor
System
Under
$2500
Over
$2500
Reviews TI quote makes Construction
Determination
PBS
YES
Provides
Notice to
Proceed NO
END
Store approves
TI quote
Field Engineer reviews TI quote
Provides
TI quote
Current Contract 6 Zone Boundaries
New Contract 8 Zone Boundaries
2614 2593
3785 3769
MG1 MG2 MG3 MG4 MG5 MG6
FY11
FY12
FY13
Annual Non-Construction TI Volume
Number reflect the quantity of TIs for each respective year/maintenance group.
FY13 Construction = 137 TIs across all maintenance groups
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
MG1 MG2 MG3
FY11
FY12
FY13
$3.7M $3.5M
$5M
$3.8M
$6.2M $6.1M
$3.6M
Annual Non-Construction TI Value
Number reflect the quantity of TIs for each respective year/maintenance group.
$4.1M $4M
FY13 Construction = $6.6M across all
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
MG4 MG5 MG6
FY11
FY12
FY13
Annual Non-Construction TI Value
$3M $3.3M $3.1M $3.3M
$2.2M
$2.6M
$2.1M
Number reflect the quantity of TIs for each respective year/maintenance group.
$4M
$5.9M FY13 Construction = $6.6M across all
Small Business Subcontracting Plan
Plan will be required to be submitted for evaluation and approved prior to award
Potential areas for subcontracting include: Commissary Equipment in Place (CEIP), Call Center services, individual site maintenance personnel throughout the MG, etc.
Current Region 8 Small Business Goals:
Small Business Socio Economic
Goal (%) SDB Goal % WOSB Goal % HUBZone Goal % SDVOSB Goal %
Region 8 54.00% 7.00% 5.00% 4.44% 4.44%
Break for lunch
Please be back in an hour
Performance Work Statement (PWS)
The Contractor shall be responsible for non-personal facility maintenance services to include minor exterior preventative maintenance, unscheduled maintenance, and real property repair/replacement within a five foot perimeter to the exterior walls of a covered facility.
Discussion/ Q&A
Performance Work Statement (PWS)
2.3.1 Commissary Equipment in Place (CEIP)
2.3.2 After hours services
2.3.3 Maintenance Types
2.3.4 Minor Construction
2.3.5 Financial Reporting
2.3.6 Computerized Maintenance Management System (CMMS)
2.3.7 Government Technical instruction (TI) Tracking
2.3.8 Maintenance Response and Call Center Operation
2.3.9 Use and Servicing of Refrigerant
2.3.10 Environmental controls
2.3.11 Transition Period
2.3.12 Phase Out – Continuity of Services
2.3.13 Contractor Personnel
Performance Work Statement (PWS)
2.3.14 Quality Control Plan
2.3.15 Quality Assurance/Quality Assurance Surveillance Plan
2.3.16 Performance Requirements and Responsibilities
2.3.17 Suspension of Preventative Maintenance Services
2.3.18 Contractor Liability
2.3.19 Contract Closeout
2.3.20 Past Performance Information Retrieval System (PPIRS)
2.3.21 Sample Forms
2.3.22 Equipment Identification and Operation and Maintenance
Manuals
2.3.23 Records
Other Appendices
Appendix 1- Commissary Locations
Appendix 2- Equipment List
Appendix 3- Preventative Maintenance (PM) Tasks
Appendix 4- Quality Assurance Surveillance Plan (QASP)
Appendix 5- Performance Standards
Appendix 6- Temp Standards
Appendix 7- Refrigerant Log
Appendix 8- Lamping
Appendix 9- Safety and Environmental Management
Appendix 10- Sample Forms
Appendix 11- OCC Breakdown
Appendix 12- TI Manual
Appendix 13- Roof Plan
Appendix 14- Year Built
Appendix 15- Financial Reporting
Appendix 16- Refrigeration Alarm
Appendix 17- Emergencies
Wrap-up Reminders
Minutes to this meeting as well as the solicitation and amendments, if/when issued will be posted to the FedBizOpps
Any further questions/feedback send email to GSA
Stephen.kane@gsa.gov and derek.wilbur@gsa.gov
Documents can be electronically downloaded from FBO
It is the interested parties' responsibility to check the website periodically for any amendments that may include additional draft document
The Government will not issue paper copies mailto:Stephen.kane@gsa.gov mailto:Stephen.kane@gsa.gov mailto:Stephen.kane@gsa.gov mailto:Stephen.kane@gsa.gov mailto:Stephen.kane@gsa.gov mailto:derek.wilbur@gsa.gov mailto:derek.wilbur@gsa.gov mailto:derek.wilbur@gsa.gov mailto:derek.wilbur@gsa.gov mailto:derek.wilbur@gsa.gov
Helpful Hints to Potential Offerers
The time to affect this solicitation is now – not after its release
Do not build your proposal on draft documents
Ensure your proposal addressed everything required in the solicitation (i.e. Instruction to Offerers)
The awardee(s) are expected to perform all elements of the PWS
Thank you