ICE_updated_5-28-25.pdf
PDF 217 KB Posted
- Attached to
- Various Parks locations - Hurricane Ian repairs
- Solicitation number
- QQ-2025-043
- Issued by
- Collier County, Florida
About this file
This is an Independent Cost Estimate (ICE) document prepared by Collier County for hurricane repair projects funded by federal or state grant programs. The document covers repairs at three specific park locations: Golden Gate Community Center's Wheels Park observation tower, East Naples Community Park's gate, and Vineyards Community Park's pavilion soffit, all related to damages from Hurricane Ian. The total estimated project cost is $38,250.00, with a specific breakdown of $16,750.00 for the three repair tasks, each priced between $1,750.00 and $7,500.00. The estimate was prepared on 02/20/25 by Felicia Kirby-Jacobs and is scheduled to be finalized on 05/28/25.
The cost estimate was developed using in-house engineering or technical estimates, as indicated by the checked methodology box. The procurement action follows federal compliance requirements, ensuring a clear basis for determining procurement benefits, providing essential financial planning information, and establishing a foundation for cost/price analysis. The document uses a standard template for tracking cost details, including sections for standard and non-standard items, with space to document materials, labor, overhead, and profit calculations. The specific repairs are categorized as lump sum (LS) tasks, with each location receiving a distinct unit price for the required hurricane damage restoration work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Various_Parks_locations_-_Hurricane_Ian_repairs.pdf | ||
| FPP_FEMA_FY25_5.1.25.pdf | ||
| Updated_Scope_5-28-25_-_Various_parks_locations_-_Hurricane_Ian_repairs.docx | DOCX document | |
| Insurance_Requirements_Non-Contracted_Services.docx | DOCX document | |
| MOP.pdf | ||
| PO_Terms_and_Conditions.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COLLIER COUNTY
For the Acquisition of Goods and Services Funded By Federal/State Grant Programs
Independent Cost Estimate PRUPOSE: In connection with every procurement action, except a micro-purchase, an Independent Cost Estimate (ICE) must be prepared in advance of receiving a quote, bid, or proposal. This is necessary because the ICE documentation:
• Ensures a clear basis for determining the benefits of the procurement;
• Provides essential procurement and financial planning information;
• Documents Federal compliance in a consistent manner; and,
• Provides a basis for the cost/price analysis.
Description of Procurement Date of Estimate
Total Estimated Price/Cost
Method: The above estimate is developed from: CHECK ALL THAT APPLY
Published catalogs or price lists (attach pertinent catalog of price list pages)
Recent prices for the same or similar item (identify contracts, purchase orders, sources, and additional helpful information (e.g. dates of award), and attach any pertinent documents
In-house Engineering or technical estimates (see details below or attach estimate).
Independent Third Party estimate developed by (attach estimate).
Other (specify):
Cost Estimate Details:
Cost of Standard Items
Product Cost ($/ea.)
Notes/Data Source Unit Freight Total
Cost of Services, Repairs, or Non-Standard Items Item / Task:
Materials Other Direct
Costs Labor
(rate, hours) Labor Class
Allocated Overhead SG&A Profit Total
PREPARED BY:
Name Date est. FY14 v. 3
Various Parks locations - Hurricane Ian repairs - OPC
Scope Description Unit Qty Unit Price Total Base Bid
LS 1 $7,500.00 $7,500.00
LS 1 $1,750.00 $1,750.00
LS 1 $7,500.00 $7,500.00
Golden Gate Community Center - Wheels Park observation tower Golden East Naples Community Park - Repair gate Vineyards Community Park - Pavilion soffit repair
Total $16.750.00
| ADPA184.tmp |
| 21-8101 Bid Schedule |
| ADPC69B.tmp |
| 21-8101 Bid Schedule |
| ADPD6F6.tmp |
| 21-8101 Bid Schedule |
| 2024-2400FM Hurricane Ian Restoration Project signs ICE backup.pdf |
| 21-81XX Bid Schedule |
| OPC.pdf |
| Sheet1 |
| OPC.pdf |
| Sheet1 |
| OPC.pdf |
| Sheet1 |
| Date of Estimate: 2/20/25 |
| Description of Procurement: Various Parks locations - Hurricane Ian Repairs |
| Total Estimated PriceCost: 38250 |
| Published catalogs or price lists attach pertinent catalog of price list pages: Off |
| Recent prices for the same or similar item identify contracts purchase orders sources and additional: Off |
| Inhouse Engineering or technical estimates see details below or attach estimate: On |
| Independent Third Party estimate developed by: Off |
| Third Party Name: |
| Other specify: Off |
| Othertext: |
| ProductRow1: see attached |
| UnitRow1: |
| FreightRow1: |
| TotalRow1: |
| NotesData SourceRow1: |
| ProductRow2: |
| UnitRow2: |
| FreightRow2: |
| TotalRow2: |
| NotesData SourceRow2: |
| ProductRow3: |
| UnitRow3: |
| FreightRow3: |
| TotalRow3: |
| NotesData SourceRow3: |
| ProductRow4: |
| UnitRow4: |
| FreightRow4: |
| TotalRow4: |
| NotesData SourceRow4: |
| Item Task: |
| MaterialsRow1: |
| Text1: |
| Text5: |
| Text9: |
| Text13: |
| SGARow1: |
| ProfitRow1: |
| TotalRow1_2: |
| MaterialsRow2: |
| Text2: |
| Text6: |
| Text10: |
| Text14: |
| SGARow2: |
| ProfitRow2: |
| TotalRow2_2: |
| MaterialsRow3: |
| Text3: |
| Text7: |
| Text11: |
| Text15: |
| SGARow3: |
| ProfitRow3: |
| TotalRow3_2: |
| MaterialsRow4: |
| Text4: |
| Text8: |
| Text12: |
| Text16: |
| SGARow4: |
| ProfitRow4: |
| TotalRow4_2: |
| Name_6: Felicia Kirby - Jacobs |
| Date_5: 5/28/25 |
File details come from the government source that posted it. Updated .