additional questions acq.doc
DOC document 24 KB Posted
- Attached to
- RECOVERY - Urban Levee Remediation Rio Grande and Cibolo Creek from Station 10+00 to 453+00, Presidio, TX
- Solicitation number
- IBM10B0009
About this file
Additional questions responses from Acquisition
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Abstract Spreadsheet.xls | XLS spreadsheet | |
| Presidio 100 Tech Memo-Geotech Appendix 20100602.pdf | ||
| Presidio question and response.doc | DOC document | |
| Presidio Levee Specs 02.35.27 20100803.pdf | ||
| IBM10B0009 A004.pdf | ||
| IBM10B0009 A003.pdf | ||
| IBM10B0009 A002.pdf | ||
| Abstract Spreadsheet.xls | XLS spreadsheet | |
| pre-bid attendees.pdf | ||
| IBM10B0009 A001.pdf | ||
| IBWC 117.pdf | ||
| IBM10B0009.pdf | ||
| IBWC 110.pdf | ||
| davisbacon.txt | TXT text file | |
| sf28.pdf | ||
| IBWC 116.pdf | ||
| sf24_f.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Question - Work schedule is defined as 7:00 AM-4:00 PM M-F. Is it possible to work a 12 hour day six days a week? We will be responsible for the overtime pay for the government supervision.
Response: Reference H.12, Work Schedule. As stated in this provision, any time outside the stated times will be requested and coordinated with government representative.
2. Question - The CM will be hired by IBWC and will be paid by the GC. What rate has IBWC allocated?
Response: Rates to be charged to the contractor if required for government inspector outside normal duty hours is estimated at $37, plus time and a half for overtime. A separate CM contract will be awarded. Rates are unknown at this time.
3. Question - Will the Field Environmental monitor be hired by IBWC? If so what rate has IBWC allocated?
Response: The IBWC will award a separate Contract Management contract for this project. It is not known if the scope of work will include a Field Environmental monitor.
4. Question - QC advisor will he/she be hired by IBWC? If so at what rate?
Response: Same as question 3 above.
5. Question - Is this a not to exceed or plan quality job?
Response: Not clear of the question. This is a firm fixed price contract.
6. Question - Is there any Minority Owned business requirement?
Response: This is a small business set-aside, therefore subcontract requirement to include “Minority Owned” business is not a requirement.
7. Question - Why is builders risk being required on this job?
Response: It is a requirement for all our construction projects.
8. Question - We noticed in the general notes on drawing page 2 of 91 it states “All work shall be done by a contractor having a valid contractor’s license issued by the state of Texas Registrar of contractors”.
Response: Reference 52.229-3, Federal, State and Local Taxes of the contract, page 27, by reference. Ultimately Contractor is responsible in ensuring compliance of any taxes applicable to this project.
9. Question - Currently Bids are due July 29th, 2010. Will there be an extension issued?
Response – Amendment A001 extended bid opening date to August 5, 2010, 3:00 PM, MST. No further extension at this time.