This is a contract progress report form (Form IA-C713) used by the Department of the Interior, Indian Affairs to track contractor performance and completion percentages on federal contracts. The form serves as a standardized template for contractors to report their progress on specific work elements during defined reporting periods.

The form includes fields for basic contract information such as contractor details, report number, coverage period, project number, contract number, and completion date. The main section contains a table where contractors list individual work elements along with their percentage of total contract value, percentage completed during the current reporting period, and cumulative percentage completed. The form includes a progress or completion certificate section where both the contractor and contracting officer must sign to verify satisfactory completion of the indicated work percentages per contract specifications. Additionally, the form requires confirmation of whether payrolls have been submitted for the reporting period and notes that the information may be used for computing progress payments at the contracting officer's discretion according to the contract's payment clause.

View the file

Other files

File Type Posted
RFI_Form.pdf PDF
Sol_140A2325Q0238.pdf PDF
Wage_Rates.pdf PDF
IA_Form_3000v2_Material_Approval_Submittal.pdf PDF
Question_Log.xlsx XLSX spreadsheet
Release_of_Claims.pdf PDF
IA_C113_Progress_Schedule.pdf PDF
STATEMENT_OF_WORK.pdf PDF
Fed_Health_and_Safety_Codes_and_Stnds.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of the Interior, Indian Affairs

CONTRACT PROGRESS REPORT

CONTRACTOR ADDRESS

REPORT NO. PERIOD COVERED

FROM: TO:

PROJECT NO. CONTRACT NO. COMPLETION DATE

LINE

NO.

WORK ELEMENT % OF

TOTAL

% COMPLETED

THIS PERIOD

% COMPLETED

CUMULATIVE

TOTAL

REMARKS

At the Contracting Officer's discretion and according to the payments clause of the contract, the information provided on this form may be used for computing progress payments.

PROGRESS OR COMPLETION CERTIFICATE

I hereby certify that the contractor has satisfactorily completed the indicated percentage of the contract per contract specifications.

SUBMITTED BY: _________________________

TYPE OR PRINT NAME AND TITLE SIGNATURE DATE

REVIEWED BY OR FOR CONTRACTING OFFICER

TYPE OR PRINT NAME AND TITLE SIGNATURE DATE

FORM IA-C713

Have payrolls been submitted for this time period? YES / NO