Hurricane_Shutters_and_Installation_-_Windows_and_Doors_(Addendum_#1_Revision).pdf

PDF 547 KB Posted

Attached to
Hurricane Shutters and Installation - Windows and Doors
Solicitation number
25-0065-ITB-C
Issued by
Pinellas County, Clewiston City, Florida

About this file

This is an Invitation to Bid (ITB-C) from Pinellas County Utilities department for hurricane shutter installation at two administrative buildings. The solicitation seeks a qualified contractor to install hurricane-resistant accordion-style aluminum shutters at the Dunn WRF Administrative Building (4100 Dunn Dr, Palm Harbor) and South Cross WRF Administrative Building (7401 54th Ave N, St. Petersburg). The project involves installing shutters on a total of seventeen (17) openings at the Dunn site and sixteen (16) openings at the South Cross site, including various window and door sizes. The bid was issued on November 6, 2024, with a non-mandatory site visit scheduled for November 13, 2024, and a question submission deadline of November 14, 2024. Proposals are due by December 3, 2024, at 3:00 pm, and must be submitted electronically via OpenGov.

The contract requires hurricane shutters to be impact-rated to CAT 5 building requirements, made of aluminum, manually operated, lockable, and colored to match existing shutters or building envelope. Vendors must be licensed, have a minimum of three years in business, and use products listed in the Florida Product Approval System. The awarded contractor will provide a 24-month warranty on workmanship and materials. Bidders must submit a bid bond guarantee of 5% of the base bid and comply with various county requirements, including insurance provisions, E-Verify compliance, and local, state, and federal regulations. The contract will be awarded to the lowest responsive and responsible bidder, with Pinellas County reserving the right to add or delete locations/services as needed.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION TO BID - CONSTRUCTION (ITB-C)

25-0065-ITB-C

HURRICANE SHUTTERS AND INSTALLATION - WINDOWS AND

DOORS

Pinellas County

Pinellas County Courthouse Annex Bldg., Sixth Floor

Clearwater, FL 33765

THE MISSION OF PINELLAS COUNTY

"Pinellas County Government is committed to progressive public policy, superior public service, courteous public contact, judicious exercise of authority and sound management of public resources to meet the needs and concerns of our citizens today and tomorrow."

ISSUE/RELEASE DATE: November 6, 2024

QUESTION SUBMISSION DEADLINE: November 14, 2024

PROPOSAL SUBMISSION DEADLINE: December 3, 2024, 3:00 pm

RESPONSES MUST BE SUBMITTED ELECTRONICALLY VIA OPENGOV TO:

https://procurement.opengov.com/portal/pinellasfl https://procurement.opengov.com/portal/%7bproject.government.code%7d

Pinellas County

INVITATION TO BID - CONSTRUCTION (ITB-C)

Hurricane Shutters and Installation - Windows and Doors

Table of Contents No table of contents entries found.

Attachments:

A - OpenGov Fillable- Final

B - E-Verify_Affidavit

C - 25-0065-ITB-C Sample Simplified Construction Agreement

D - Sample Change Order

E - Sample Application for Payment

Invitation to Bid - Construction (ITB-C) #25-0065-ITB-C Title: Hurricane Shutters and Installation - Windows and Doors

1. Notice

INVITATION TO BID

SUBMITTALS ARE OPENED PUBLICLY AND ARE ACCEPTED VIA OPENGOV

ITB - Simplified Construction

25-0065-ITB-C

Hurricane Shutters and Installation - Windows and Doors

ALL QUESTIONS MUST BE SUBMITTED IN OPENGOV WITHIN THE QUESTION & ANSWER SECTION.

SOLICITATION MEETINGS: Site Visit: Non-Mandatory; Pre-Conference: None

SUBMITTALS MAY NOT BE WITHDRAWN FOR120 DAYS AFTER OPENING DATE.

PUBLIC MICROSOFT TEAMS MEETING - https://teams.microsoft.com/l/meetup-join/19%3ameeting_YTk2ZDM5NzgtZmFiOS00ZWM1LTk1NjgtYWIxOWZiYzliMGQ4%40thread.v2/0?co ntext=%7b%22Tid%22%3a%22c32ee18f-a4c7-46ff-af40-

8ed605642745%22%2c%22Oid%22%3a%227427c034-238b-4d40-aa5d-19b05166cbf8%22%7d @ 3:30 on the Bid 2 Submittal Date.

Meeting ID: 292 583 511 912

Passcode: avjUPp

Or call in (audio only)

+1 813-644-3116

Phone Conference ID: 487 254 075#

The Purchasing and Risk Management Division for the Pinellas County Board of County Commissioners has transitioned to OpenGov Procurement for contractor/vendor registration, and for posting, submitting and receiving bids, quotes and proposals for active solicitations. Contractors/Vendors must register with OpenGov Procurement (https://procurement.opengov.com/signup) to participate in active County solicitations.

Should you need technical assistance with OpenGov, the following options are available:

Phone: (855) 680-4747, 8 a.m. to 8 p.m., Monday - Friday

Email:procurement-support@opengov.com

Chat is available in the OpenGov application

Web:https://help.procurement.opengov.com https://teams.microsoft.com/l/meetup-join/19%3ameeting_YTk2ZDM5NzgtZmFiOS00ZWM1LTk1NjgtYWIxOWZiYzliMGQ4%40thread.v2/0?context=%7b%22Tid%22%3a%22c32ee18f-a4c7-46ff-af40-8ed605642745%22%2c%22Oid%22%3a%227427c034-238b-4d40-aa5d-19b05166cbf8%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_YTk2ZDM5NzgtZmFiOS00ZWM1LTk1NjgtYWIxOWZiYzliMGQ4%40thread.v2/0?context=%7b%22Tid%22%3a%22c32ee18f-a4c7-46ff-af40-8ed605642745%22%2c%22Oid%22%3a%227427c034-238b-4d40-aa5d-19b05166cbf8%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_YTk2ZDM5NzgtZmFiOS00ZWM1LTk1NjgtYWIxOWZiYzliMGQ4%40thread.v2/0?context=%7b%22Tid%22%3a%22c32ee18f-a4c7-46ff-af40-8ed605642745%22%2c%22Oid%22%3a%227427c034-238b-4d40-aa5d-19b05166cbf8%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_YTk2ZDM5NzgtZmFiOS00ZWM1LTk1NjgtYWIxOWZiYzliMGQ4%40thread.v2/0?context=%7b%22Tid%22%3a%22c32ee18f-a4c7-46ff-af40-8ed605642745%22%2c%22Oid%22%3a%227427c034-238b-4d40-aa5d-19b05166cbf8%22%7d https://procurement.opengov.com/signup mailto:procurement-support@opengov.com https://help.procurement.opengov.com/

Please Note:

From time to time, addenda may be issued to this solicitation. Any such addenda will be posted to https://procurement.opengov.com/portal/pinellasfl. Receipt of addenda confirmation is required in

OpenGov.

AUTHORIZED BY:

Merry Celeste, CPPB

Division Director of Purchasing and Risk Management

2. Introduction

2.1. Summary

Pinellas County Utilities department is looking for a reliable company to install hurricane-resistant accordion type aluminum shutters at two of its sites: Dunn WRF Administrative Building and South Cross

WRF Administrative Building

2.2. Contact Information

Gayle May, CPPB, NIGP-CPP

Procurement Analyst Coordinator

400 S Ft Harrison

Clearwater, FL 33777

Email: gmay@pinellas.gov

Phone: (727) 464-3795

Department:

UTILITIES

2.3. Timeline

Issue Date November 6, 2024

Site Visit Information November 13, 2024, 9:00am

Dunn WRF Administrative Building (Dunn) @ 9:00

AM

4100 Dunn Dr, Palm Harbor, FL 34683

South Cross WRF Administrative Building (South

Cross) @ 10:00 AM

7401 54th Ave N, St. Petersburg, FL 33709

Question Submission Deadline November 14, 2024, 3:00pm

Bid Submission Deadline December 3, 2024, 3:00pm mailto:gmay@pinellas.gov tel:(727)464-3795

3. Special Conditions

3.1. PRICING/PERIOD OF CONTRACT

Unit prices bid of listed items shall be held firm from the date the contract is signed by the Contractor until the project is completed and accepted by the Board of County Commissioners. Unless otherwise approved by the County, the Contractor shall commence Work under this Agreement with an adequate force and equipment within 15 consecutive calendar days after receipt of written notice from the

County to proceed and to fully complete all necessary Work under the same within not more than 90 consecutive calendar days.

3.2. PRE-BID CONFERENCE:

Not applicable.

3.3. NON-MANDATORY SITE VISIT:

The sole purpose of the site visit is to provide a tour of the site(s) that will be supported by the contract.

The scope of work and/or bid specifications shall not be discussed during this visit. All questions relating to this bid and the scope of work or technical specifications must be submitted in writing.

There will be a Site Visit at the following date, time, and location:

11/13/2024

Dunn WRF Administrative Building (Dunn) @ 9:00 AM

4100 Dunn Dr, Palm Harbor, FL 34683

South Cross WRF Administrative Building (South Cross) @ 10:00 AM

7401 54th Ave N, St. Petersburg, FL 33709

Please note: If an interested vendor cannot attend the scheduled non-mandatory site visit, please contact Gayle May at gmay@pinellas.gov by 11/8/2024 for potential rescheduling during the advertisement period of the solicitation.

3.4. PRE-COMMENCEMENT MEETING

Upon award of bid, the County will coordinate a pre-commencement meeting with the successful

Contractor. The meeting will require Contractor and the County Representative(s) to review specific contract details and deliverable documents at this meeting to ensure the project documents and work areas are understood.

3.5. BID BOND GUARANTEE

A. All bids must be accompanied by a Bid Bond guarantee in the sum of 5% of the base bid and made payable to Pinellas County. Said bid bond shall be a guarantee that should the bid be mailto:gmay@pinellas.gov accepted, the bidder will, within (10) days after the acceptance of its bid, enter into an agreement with Pinellas County for the services proposed to be performed and will at that time furnish an acceptable agreement surety. Cash, certified check, cashier’s check, trust company treasurer check, company or personal checks and bank draft of any national or state bank are not acceptable.

B. Said bid bond and the monies payable thereon, will, at the option of the County, be forfeited if the bidder fails to execute the written agreement and furnish the required surety bond within

10 consecutive calendar days following written notice of the award of the contract.

C. Attorneys-in-fact who sign bonds must file with such bond one (1) certified copy of their power of attorney to sign said bond.

D. Bid bond shall have been issued within 30 days of the date for receiving bids.

3.6. LICENSES, PERMITS, FEES AND TAXES

A. Pursuant to section 218.80, Florida Statutes, Pinellas County discloses to the contractor the following permits and fees generally which will have to be obtained by and will be payable by the contractor who is the successful bidder or proposer. Specific permits required will be shown in Appendix 1 – Permits. Contractor will be reimbursed for the actual amount paid for the permits as evidenced by official receipts from the office(s) collecting the fees. No reimbursement will be provided for license fees. Permits/fees may include the following:

1. Impact Fees.

2. Inspection Fees.

3. Other permits or fees required by Pinellas County for the completion of the work, if applicable.

4. License fees: The Pinellas County Construction Licensing Board (PCCLB), an independent government agency, may require licensure or registration of a State of Florida construction license. These are not Pinellas County Government fees, but the contractor is hereby put on notice that fees may be required by the PCCLB. License fees are not reimbursable.The foregoing list of fees apply only to those fees imposed by Pinellas County or imposed by another governmental agency which has assigned or delegated the responsibility for issuance of permits, licenses and conduction of inspections and attendant collection of fees to Pinellas County. The contractor is responsible for determining if other fees and permits are required by any other Federal, State, or local governmental entity, agency, or board.

B. All sales, consumer, use, and other similar taxes associated with the Work or portions thereof, which are applicable during the performance of the work, shall be paid by the contractor.

C. Compliance with permit and licenses requirements: The contractor shall comply with all applicable Local, State and Federal permit conditions and license requirements, applicable building and construction code requirements and such other rules and regulations as may apply to the prosecution of Work. Failure of the contractor to comply with the above-specified requirements shall result in contractor being prohibited from performing work pursuant to this agreement. Any additional costs incurred by the contractor as a result of non-compliance shall be the responsibility of the contractor and shall not be paid by the County. Additionally, contractor shall be required to pay any fines due as a result of non-compliance with the applicable requirements.

3.7. COMPLIANCE WITH LAWS

The contractor agrees to comply, at its own expense, with all Federal, State and Local laws, codes, statutes, ordinances, rules, regulations and requirements applicable to the Project or Job Order

Contract, including but not limited to, those dealing with taxation, workers' compensation, equal employment, safety (including, but not limited to, the Trench Safety Act, Chapter 553.60-553.64, Florida

Statutes), labor, work hours, labor conditions, environment, and related matters. If the contractor observes that the contract documents are at variance therewith, it shall promptly notify the Design

Professional/Engineer/Project Manager in writing.

3.8. QUANTITIES

A. Quantities shown on the Bid Submittal Form are estimated for bidding purposes only and shall be verified by the contractor before placing orders for material. No payment shall be allowed for excess materials.

B. Payment for work performed under this agreement shall be based on the pay items and bid quantities shown on the Bid Submittal Form, subject to such extension of pay quantities as may be required.

C. Regardless of uncertainties of material supply and production at the time of bidding, bidders shall base their bids in strict accordance with items, materials and methods as set forth in the contract documents.

D. Pay items that are required to complete the scope of the Work, as defined by the project plans and specifications may be added to the list of pay items by the design professional/engineer/project manager at a later date through a change order process.

3.9. QUANTITIES REFLECTED IN PERMITTING DOCUMENTS

Any construction items or quantities reflected in the permitting documents, if any, required for this project are provided only for the purpose of enabling permitting authorities to assess the probable impact of the project on environmental concerns, and are in no way intended to reflect or represent actual construction items or quantities for pay purposes.

3.10. AWARD OF CONTRACT

The contract will be awarded for the entire Work (with or without optional/alternates items) to the lowest responsible and responsive bidder, provided that the bid is reasonable, and that it is in the best interest of the County to accept.

3.11. AFTER NOTICE OF AWARD TO CONTRACTOR

Subsequent communications between the County and the contractor shall be delivered to the County's representative. A Preconstruction Conference will be held following execution of the contract documents and prior to the Notice to Proceed.

3.12. INTENT OF THE CONTRACT DOCUMENTS

A. It is the intent of the Contract Documents to describe a functionally complete Project (or portion thereof) to be constructed in accordance with the Contract Documents which combine to define the Scope of Work. Any Work, materials or equipment that may reasonably be inferred from the

Contract Documents as being required to produce the intended result shall be supplied whether or not specifically called for. When words which have a well-known technical or trade meaning are used to describe Work, materials or equipment, such words shall be interpreted in accordance with that meaning. Reference to standard Specifications, manuals or codes of any technical society, organization or association or to the laws or regulations of any governmental authority having jurisdiction over the Project, whether such reference be specific or by implication, shall mean the latest standard Specification, manual, code, law or regulation in effect at the time the Work is performed, except as may be otherwise specifically stated herein.

B. The Contract Documents and all referenced standards cited therein are essential parts of the

Agreement requirements. A requirement occurring in one is as binding as though occurring in all. They are intended to be complementary and to describe and provide for a complete Project.

C. Plans are intended to show general arrangements, design and extent of Work. Specifications are separated into divisions for convenience of reference only and shall not be interpreted as establishing divisions for the Work, trades, subcontracts, or extent of any part of the Work. In the event of a discrepancy between or among the Plans, Specifications or other Contract

Document provisions, the Contractor shall be required to comply with the provision which is the more restrictive or stringent requirement upon the Contractor, as determined by the Design

Professional/Engineer/Project Manager. Unless otherwise specifically mentioned, all anchors, bolts, screws, fittings, fillers, hardware, accessories, trim and other parts required in connection with any portion of the Work to make a complete, serviceable, finished and first quality installation shall be furnished and installed as part of the Work, whether or not called for by the

Contract Documents.

3.13. SANITATION

The Contractor shall provide and maintain adequate sanitary conveniences for the use of persons employed on the Work. These conveniences shall be maintained at all times without nuisance, and their use shall be strictly enforced. The location of these conveniences shall be subject to the Design

Professional/Engineer/Project Manager’s approval.

3.14. ERRORS AND OMISSIONS

The Contractor shall not take advantage of any apparent error or omission in the Contract Documents. If any errors and/or omissions appear in the Contract Documents, or construction stakeout, the

Contractor shall immediately notify the Purchasing Department, in writing, of such errors and/or omissions. In the event the Contractor knows or should have known of any errors and/or omissions and fails to provide such notification, it shall be deemed to have waived any claim for increased time or compensation it may have had and he shall be held responsible for the results and the costs of rectifying any such errors and/or omissions.

3.15. CONTRACTORS AND SUBCONTRACTORS

A. Qualification

1. The Contractor shall assure that all personnel are competent, careful and reliable. All personnel must have sufficient skill and experience to properly perform the Work assigned them. All personnel shall have had sufficient experience to perform their assigned task properly and satisfactorily and to operate any equipment involved, and shall make due and proper effort to execute the Work in the manner prescribed in the Contract Documents, or the Design Professional/Engineer/Project Manager may take action as prescribed below.

2. Whenever the Design Professional/Engineer/Project Manager shall determine that any person is incompetent, unfaithful, intemperate, disorderly or insubordinate, such person shall upon notice, be discharged from the Work and shall not again be employed on it except with the written consent of the Design Professional/Engineer/Project Manager.

Should the Contractor fail to remove such person or persons the Design

Professional/Engineer/Project Manager may withhold all estimates which are or may become due, or may suspend the Work until such orders are complied with.

B. Identification

1. Within 10 days after the award of any subcontract, either by himself or a subcontractor, the

Contractor shall deliver to the Design Professional/Engineer/Project Manager a statement setting forth the name and address of the subcontractor and a summary description of the

Work subcontracted.

2. The Contractor shall be as fully responsible to the County for acts and omissions the subcontractor and of persons either directly or indirectly employed by the subcontractor, as the Contractor is for the acts and omissions of persons directly employed by the Contractor.

3.16. AUTHORITY OF THE PROJECT MANAGER

A. All Work shall be done in accordance with the Contract Documents.

B. It is agreed by the parties hereto that the Design Professional/Engineer/Project Manager shall decide all questions, difficulties and disputes, of whatever nature, which may arise relative to the interpretation of the Plans, construction, prosecution and fulfillment of the Agreement, and as to the character, quality, amount and value of any Work done, and materials furnished, under or by reason of the Agreement.

C. The County retains the right to inspect all Work to verify compliance with the Contract

Documents. The Design Professional/Engineer/Project Manager may appoint such designees and/or representatives as desired. They shall be authorized to inspect all Work done and all materials furnished. This right of inspection in no way means or implies County control or other supervision over the Work done or the work site. This right is solely for the County's benefit and imposes no duties or responsibilities on the County and confers no rights on any other parties.

Such inspection may extend to all or any part of the Work and to the manufacture, preparation or fabrication of the materials to be used. Such designees and/or representatives shall not be authorized to revoke, alter or waive any requirement of the Contract Documents.

D. The designees and/or representatives shall be authorized to call to the attention of the

Contractor any failure of the Work or materials to conform to the Contract Documents, and shall have the authority to reject materials or suspend the Work until any questions at issue can be referred to and decided by the Design Professional/Engineer/Project Manager. The Contractor shall be immediately notified in writing of any such suspension of the Work and such notice shall state in detail the reasons for the suspension. The presence of the inspector or other designee shall in no way lessen the responsibility of the Contractor.

E. Contractor's Supervision

F. Prosecution of Work:

1. The Contractor shall give the Work the constant attention necessary to assure the scheduled progress and it shall cooperate fully with the Design Professional/Engineer/Project Manager and with other Contractors at Work in the vicinity.

G. Contractor's Superintendent:

1. The Contractor shall at all times have on the Work as his agent, a competent superintendent capable of thoroughly interpreting the Plans and Specifications and thoroughly experienced in the type of Work being performed, who shall receive the instructions from the Design

Professional/Engineer/Project Manager or his/her authorized representatives. The superintendent shall have full authority to execute the orders or directions of the Design

Professional/Engineer/Project Manager and to supply promptly any materials, tools, equipment, labor and incidentals which may be required. Such superintendence shall be furnished regardless of the amount of Work sublet.

2. The Contractor's superintendent shall speak and understand English, and at least one responsible person who speaks and understands English shall be on the Project during all working hours.

H. Supervision for Emergencies:

1. The Contractor shall have a responsible person available at or reasonably near the work site on a 24-hour basis, 7 days a week, in order that he/she may be contacted in emergencies and in cases where immediate action must be taken to maintain traffic or to handle any other problem that might arise. The Contractor's responsible person for supervision for emergencies shall speak and understand English. The Contractor shall submit, by certified mail, phone numbers and names of personnel designated to be contacted in cases of emergencies along with a description of the Project location to the Florida Highway Patrol and all other local law enforcement agencies.

I. Worksite Traffic Supervisor: (When the work involves road construction/reconstruction or changes affect normal traffic patterns)

1. The Contractor shall have a Worksite Traffic Supervisor who will be responsible for initiating, installing and maintaining all traffic control devices as described in Section 102 of the Florida

Department of Transportation Standard Specifications for Road and Bridge Construction, and in the Plans. The Worksite Traffic Supervisor shall have at least one year of experience directly related to worksite traffic control in a supervisory or responsible capacity and shall be certified by the American Traffic Safety Services Association Worksite Traffic Supervisor

Certification Program or an equal approved by the Florida Department of Transportation.

Approved alternate Worksite Traffic Supervisors may be used when necessary.

2. The Worksite Traffic Supervisor shall be available on a 24 hour per day basis and shall review the Project on a day to day basis as well as being involved in all changes to traffic control.

The Worksite Traffic Supervisor shall have access to all equipment and materials needed to maintain traffic control and handle traffic related situations. The Worksite Traffic Supervisor shall ensure that routine deficiencies are corrected within a 24-hour period.

3. The Worksite Traffic Supervisor shall be available on the site within 45 minutes after notification of an emergency situation, prepared to positively respond to repair the Work zone traffic control or to provide alternate traffic arrangements.

4. Failure of the Worksite Traffic Supervisor to comply with the provisions of the Sub-article may be grounds for decertification or removal from the Project or both. Failure to maintain a designated Worksite Traffic Supervisor or failure to comply with these provisions will result in temporary suspension of all activities except traffic and erosion control and such other activities deemed to be necessary for Project maintenance.

J. General Inspection Requirements

1. Cooperation by the Contractor: No Work shall be done nor materials used, without suitable supervision or inspection by the Design Professional/Engineer/Project Manager or his/her representative, and the Contractor shall furnish the Design Professional/Engineer/Project

Manager with every reasonable facility for ascertaining whether the Work performed and materials used are in accordance with the requirements and intent of the Plans and

Specifications. If the Design Professional/Engineer/Project Manager so requests, the

Contractor shall, at any time before final acceptance of the Work, remove or uncover such portions of the finished Work as may be directed. After examination, the Contractor shall restore the uncovered portions of the Work to the standard required by the Specifications.

Should the Work so exposed or examined prove unacceptable, the uncover or removal, and the replacing of the covering or making good of the parts removed, shall be at the

Contractor's expense. However, should the Work thus exposed or examined prove acceptable, the uncovering or removing, and the replacing of the covering or making good of the parts removed, shall be paid for as Unforeseeable Work.

K. Failure of the Design Professional/Engineer/Project Manager to Reject Work During

Construction:

1. If, during or prior to construction operations, the Design Professional/Engineer/Project

Manager should fail to reject defective Work or materials, whether from lack of discovery of such defect or for any other reason, such initial failure to reject shall in no way prevent his/her later rejection when such defect is discovered, or obligate the County to final acceptance, and the Contractor shall make no claim for losses suffered due to any necessary removals or repairs of such defects.

L. Failure to Remove and Renew Defective Materials and Work:

1. Should the Contractor fail or refuse to remove and renew any defective materials used or

Work performed, or to make any necessary corrections in an acceptable manner and in accordance with the requirements of the Specifications, within the time indicated in writing, the Design Professional/Engineer/Project Manager shall have the authority to cause the unacceptable or defective materials or Work to be repaired, removed and renewed, as may be necessary; all at the Contractor's expense.

2. Any expense incurred by the County in making these repairs, removals, or renewals, which the Contractor has failed or refused to make, shall be paid for out of any moneys due or which may become due the Contractor. Continued failure or refusal on the part of the

Contractor to make any or all necessary repairs promptly, fully and in an acceptable manner shall be sufficient cause for the County, at its option, to perform the Work with its own organization, or to contract with any other individual, firm or corporation to perform the

Work. All costs and expenses incurred thereby shall be charged against the defaulting

Contractor and the amount thereof deducted from any moneys due or which may become due him, or shall be charged against the applicable bond. Any Work performed subsequent to forfeiture of the Agreement, as described in this Paragraph, shall not relieve the

Contractor in any way of its responsibility for the Work performed by it.

M. Inspection by the Federal Government:

1. When the Work involves the Federal Government it is to pay a portion of the cost of construction the construction Work will be subject to inspection by its representatives as they may deem necessary, but such inspection will in no case make the Federal Government a party to Agreement.

3.17. PROSECUTION OF WORK ON SATURDAYS, SUNDAYS AND RECOGNIZED

HOLIDAYS

A. All Work must be done during Regular Workday hours (7:00 AM to 7:00 PM) Monday through

Friday. The County may require alternative Work hours due to specific individual Project conditions when necessary. Work will not be done beyond hours specified herein or on

Saturdays, Sundays or holidays unless authorized in advance by the Design

Professional/Engineer/Project Manager to meet special requirements. Contractor must comply with the County noise ordinance.

B. Work will not be permitted on Saturdays, Sundays and recognized Holidays unless permission to

Work has been requested in writing by the Contractor and approval, in writing, has been granted by the Design Professional/Engineer/Project Manager. Request for permission to Work must be received by the Design Professional/Engineer/Project Manager no less than 24 hours prior to the regular Workday.

C. No Work will be permitted on:

1. New Year’s Day

2. Independence Day

3. Thanksgiving Day

4. Christmas Day

D. When approval is granted in accordance with the provisions stated above, Work will be allowed on:

1. Martin Luther King, Jr. Day

2. Memorial Day

3. Juneteenth

4. Labor Day

5. Veterans Day

6. Friday after Thanksgiving Day

7. If Christmas or New Year's Day shall fall on Tuesday or Thursday, the preceding Monday or the following Friday shall be recognized as a holiday also. If any recognized holiday shall fall on a Saturday, the preceding Friday shall be observed as a holiday. If any recognized holiday shall fall on a Sunday, the following Monday shall be observed as a holiday.

3.18. PINELLAS COUNTY’S COMMITMENT TO SAFETY

A. All work shall be completed in a safe manner and consideration for cost of any equipment needed to perform contract in a safe manner, including personal protection equipment, shall be included in the contract bid.

B. If County discovers an unsafe act or condition in contractor’s performance under this contract, County shall inform Design Professional/Engineer/Project Manager of unsafe act or condition. If unsafe act or condition poses the threat of imminent danger, Design

Professional/Engineer/Project Manager shall be authorized to stop work until unsafe act or condition is remedied. No time extension shall be allowed. If remedy causes contractor to fail to meet the time specified, County shall be entitled to liquidated damages. If unsafe act or condition does not pose the threat of imminent danger, Design Professional/Engineer/Project

Manager shall be authorized to require contractor to remedy the unsafe act or unsafe condition as soon as possible, but in no event later than 3 days from date of notice. No time extension shall be allowed. If remedy causes contractor to fail to meet the time specified, County shall be entitled to liquidated damages as outlined in Liquidated Damages.

3.19. CHANGES IN THE WORK

A. If changes to the Scope of the Work are required or if the Contract time or the total Contract

Amount is increased by the additional Work, a Change Order approved by the Board will be required.

B. Should a Change Order be required, and the County and the Contractor are unable to agree on the requested change, the Contractor shall, nevertheless, promptly perform the change as directed in writing by the Design Professional/Engineer/Project Manager. If the Contractor disagrees with the Design Professional/Engineer/Project Manager's adjustment determination, the Contractor must make a claim pursuant to the Claims and Dispute Section herein, or else be deemed to have waived any claim on this matter it might otherwise have had.

C. In an emergency endangering life or property, or as expressly set forth herein, the Design

Professional/Engineer/Project Manager has the authority to order the necessary Work in writing. The County shall not be liable to the Contractor for any increased compensation without such written order. The payment authorized by a written order shall represent full and complete compensation to the Contractor for labor, materials, incidental expenses, overhead, profit, impact costs, and time associated with the Work authorized by such written order.

D. Execution by the Contractor of a properly authorized Change Order (see Appendix Sample

Change Order) shall be considered a waiver of all claims or requests for additional time or compensation for any activities prior to the time of execution related to items included in the

Change Order.

3.20. CLAIMS AND DISPUTES

A. A Claim is a demand or assertion by one of the parties seeking an adjustment or interpretation of the terms of the Contract Documents, payment of money, extension of time or other relief with respect to the terms of the Contract Documents. The term "Claim" also includes other disputes and matters in question between the County and the Contractor arising out of or relating to the Contract Documents. The responsibility to substantiate a claim shall rest with the party making the Claim.

B. Claims by the Contractor shall be made in writing to the Design Professional/Engineer/Project

Manager within two (2) regular Workdays after the commencement of the event giving rise to such Claim or else the Contractor shall be deemed to have waived the claim. Written supporting data shall be submitted to the Design Professional/Engineer/Project Manager within 15 calendar days after the occurrence of the event, unless the County grants additional time in writing, or else the Contractor shall be deemed to have waived the Claim. All Claims shall be priced in accordance with provisions of the section in this document entitled Changes in the Work.

C. The Contractor shall proceed diligently with its performance as directed by the County, regardless of any pending Claim, action, suit, or administrative proceeding, unless otherwise agreed to by the County in writing. The County shall continue to make payments in accordance with the Contract Documents during the pendency of any Claim.

3.21. MEASUREMENT AND PAYMENT

A. All Work completed under the terms of this Agreement shall be measured according to United

States Standard Measures.

B. All measurements shall be taken horizontally or vertically, unless specifically provided otherwise.

C. In the measurement of items to be paid for on the basis of area of finished Work, when the pay quantity is designated to be determined by calculation, the lengths and/or widths to be used in the calculations shall be the station-to-station dimensions shown on the Plans, the station-to-station dimensions actually constructed within the limits designated by the Manager, or the final dimensions measured of the completed Work within the lines shown on the Plans or designated by the Project Manager. The method, or combination of methods, shall be those which reflect with reasonable accuracy the actual area of finished Work as determined and authorized by the

Project Manager.

D. The Contractor shall accept compensation provided under the terms of this Agreement as full payment for furnishing all materials and for performing all Work contemplated and embraced under this Agreement. Such compensation shall also be for any and all loss or damage arising out of the nature of the Work or from the action of the elements, or from any unforeseen difficulties or obstructions encountered during the Agreement Time until final acceptance by the

County.

E. Whenever any change, or combination of changes in the Specifications, results in an increase or decrease in the original Contract quantities, and the Work added or decreased/eliminated is of the same general character as that called for in the Specifications, the Contractor shall accept payment in full at the original schedule of values for the actual quantity of Work performed, with no allowance for any loss of anticipated profits.

F. Where the pay quantity for an item is designated to be Lump Sum, and the Plans or

Specifications indicate an estimated quantity, compensation for that item will be adjusted proportionately if a plan change results in a significant change in the quantity from such estimated plan quantity.

G. Failure to construct any item to plan or authorized dimensions within the Specification tolerances shall result in reconstruction by the Contractor to acceptable tolerances at no additional cost to the County, acceptance at no pay, or acceptance at reduced final pay as determined by the Project Manager.

H. Waiver of Claims

1. The Contractor's acceptance of final payment shall constitute a full waiver of any and all

Claims by the Contractor against the County arising out of this Agreement or otherwise related to the Project, except those previously made in writing and identified by the

Contractor as unsettled at the time the final estimate is prepared.

2. Neither the acceptance of the Work nor payment by the County shall be deemed to be a waiver of the County's rights to enforce any continuing obligations of the Contractor hereunder or to the recovery of damages for defective Work not discovered by the County at the time of final inspection.

I. Termination of Contractor’s Responsibility: The Agreement will be considered complete when all

Work has been completed and has been accepted by the Board. The Contractor will then be released from further obligation except as set forth in his bonds and in this Division.

3.22. PAYMENTS WITHHELD

To the maximum extent permitted by §218.735, Florida Statutes (2007), the Design

Professional/Engineer/Project Manager may decline to certify for payment or County may decline to approve any Certificate for Payment, or portions thereof issued by Design Professional/Engineer/Project

Manager, because of subsequently discovered evidence or subsequent inspections. County may nullify the whole or any part of any Certificate for Payment previously issued and County may withhold any payments otherwise due Contractor under this Agreement or any other agreement between County and

Contractor, to such extent as may be necessary in County's opinion to protect it from loss because of: (a) defective Work not remedied; (b) third party claims filed or reasonable evidence indicating probable filing of such claims; (c) failure of Contractor to make payment properly to subcontractors or for labor, materials or equipment; (d) reasonable doubt that the work can be completed for the unpaid balance of the Contract Amount; (e) reasonable indication that the Work will not be completed within the Contract

Completion Time; (f) unsatisfactory prosecution of the Work by Contractor; or (g) any other material breach of the Contract Documents. If these conditions are not remedied or removed, County may, after

3 days written notice, rectify the same at Contractor's expense. County also may offset against any sums due Contractor the amount of any liquidated or un-liquidated obligations of Contractor to County, whether relating to or arising out of this Agreement or any other agreement between Contractor and

County.

3.23. COVENANT AGAINST CONTINGENT FEES

The Contractor warrants that no person or selling agency has been employed or retained to solicit or secure this Agreement upon an agreement or understanding for a commission, percentage, brokerage or contingent fee, except bona fide employees of bona fide established commercial or selling agencies maintained by the Contractor for the purpose of securing business. For breach or violation of this warranty the County shall have the right to annul this Agreement without liability or, in its discretion, to deduct from the Agreement Amount/Job Order Amount or consideration, or otherwise recover, the full amount of such commission, percentage, brokerage or contingent fee.

3.24. LANDS FOR WORK AND ACCESS THERETO

A. The County will furnish and define the limits of land for access to the construction site and for the site proper. All information shown in the Contract Documents constitutes the extent of land provided by the County. Any and all other lands required by the Contractor shall be procured by the Contractor at the Contractor's expense.

B. As the work progresses, the Contractor shall keep the site reasonably clear of rubbish, trash, waste and other disposable materials on a daily basis. If the Contractor allows the site to become littered and unsightly, any payments otherwise due may be withheld until the

Contractor cleans up the site to the satisfaction of the Design Professional/Engineer/Project

Manager. If the Contractor fails to clean-up the site, the County may choose to clean-up the site at the Contractor's expense.

C. Temporary buildings (storage sheds, shops, offices, etc.) may be erected by the Contractor only with the approval of the Design Professional/Engineer/Project Manager after obtaining necessary permits, and shall be built with labor and materials furnished by the Contractor without expense to the County. Such temporary buildings and/or utilities shall remain the property of the Contractor and will be removed by the Contractor at its expense upon the completion of the Work. With the written consent of the Design Professional/Engineer/Project

Manager, such buildings and/or utilities may be abandoned and need not be removed.

D. The Contractor shall confine all construction equipment, the storage of materials and equipment and the operations of workers to the Project site and land and areas identified in and permitted by the Contract Documents, and shall not unreasonably encumber the Project site with construction equipment or other material or equipment. The Contractor shall assume full responsibility for any damage to any such land or area, or to the County or occupant thereof, or any land or areas contiguous thereto, resulting from the performance of the Work.

3.25. SITE INVESTIGATION

A. The Contractor shall visit the site of the proposed Work and fully acquaint themself with conditions relating to construction and labor so that they may fully understand the facilities, difficulties and restrictions attending the execution of Work under the Agreement. The

Contractor shall thoroughly examine and be familiar with the Contract Documents/Detailed

Scope of Work. Failure or omission of the Contractor to receive or examine any form, instrument, addendum, or other documents, or to visit the site and acquaint themself with conditions existing thereon, shall in no way relieve the Contractor from any obligation with respect to the Agreement.

B. The County does not warrant the accuracy or completeness of these reports, soil samples, or any other site condition information or data made available including, but not limited to, underground utility location. The submission of a bid shall be taken as prima-facie evidence of compliance with this paragraph.

C. The Contractor acknowledges that they have satisfied themself as to the nature and location of the Work; the general and local conditions, including but not restricted to, those bearing upon transportation, disposal, handling and storage of materials; availability of labor, water, electric power, roads; and uncertainties of weather, river stages, tides or similar physical conditions at the site; the conformation and conditions of the ground; the character of equipment and facilities needed preliminary to and during prosecution of the Work.

D. The Contractor further acknowledges that they have satisfied themself as to the character, quality and quantity of surface and subsurface materials, obstacles, or conditions to be encountered.

E. Any failure by the Contractor to acquaint themself with any aspect of the Work or with any of the applicable conditions shall not relieve the Contractor from responsibility for adequately evaluating the difficulty or cost of successfully performing the Work under the Contract

Documents, nor shall it be considered the basis for any claim for additional time or compensation.

F. The County assumes no responsibility for any conclusions or interpretations made by the

Contractor on the basis of the information made available by the County. The County also assumes no responsibility for any understanding or representations made by its officers or agents during or prior to the execution of this Agreement, unless such understanding or interpretations are made in writing.

3.26. PROTECTION OF EXISTING STRUCTURES, UTILITIES, WORK AND

VEGETATION

A. Location of existing structures and utilities provided in the Contract Documents are approximate only. Any damage to existing structures or Work of any kind, or the interruption of a utility service resulting from failure to comply with the requirements of the Contract Documents, shall be repaired or restored promptly by, and at the expense of the Contractor.

B. The Contractor will preserve and protect all existing vegetation such as trees, shrubs and grass on or adjacent to the site which do not unreasonably interfere with the construction as may be determined by the Design Professional/Engineer/Project Manager. The Contractor will be responsible for all unauthorized cutting or damaging of trees and shrubs, including damage due to careless operation of equipment, stockpiling of materials or tracking of grass areas by equipment.

C. The Contractor's attention is directed to the fact that Type "A" or Type "B" TREE PROTECTION

BARRIERS, as per Pinellas County Design Professional/Engineer/Project Manager Department

Index No. 1111, shall be constructed when called for on the Plans, or as directed by the Design

Professional/Engineer/Project Manager. Barriers shall be maintained in place until their removal is directed by the Design Professional/Engineer/Project Manager.

D. Care will be taken by the Contractor in felling trees authorized for removal to avoid unnecessary damage to vegetation that is to remain in place. Any limbs or branches of trees broken during such operations shall be trimmed without cutting into the trunk and left with a clean cut and a small stub. The Contractor will be liable for, or may be required to replace or restore at its own expense, all vegetation that may be destroyed or damaged due to the Contractor's failure to protect and preserve same as required herein.

E. Where the Contractor hauls material or equipment to the Project over roads and bridges on the

State road system, County road system or City street system, and such use causes damage, the

Contractor shall immediately, at its expense, repair such road or bridge to as good a condition as before the hauling began. Such hauling shall be conducted in accordance with all applicable environmental and safety regulations.

F. The Contractor shall fully protect the Work from loss or damage and shall bear the cost of any such loss or damage until final payment has been made. If the Contractor or any one for whom the Contractor is legally liable for is responsible for any loss or damage to the Work, or other

Work or materials of the County or County's separate contractors, the Contractor shall be charged with the same, and any monies necessary to replace such loss or damage shall be deducted from any amounts due the Contractor.

G. The Contractor shall not disturb any benchmark established by the County with respect to the

Project. If the Contractor, or its subcontractors, agents or any one for whom the Contractor is legally liable, disturbs County benchmarks, the Contractor shall immediately notify the Design

Professional/Engineer/Project Manager. The County shall have the benchmarks reestablished and the Contractor shall be liable for all costs incurred by the County associated therewith.

3.27. OTHER WORK

A. The Contractor will cooperate with County forces or others who may be engaged in authorized

Work prior to final completion of the Project.

B. The Contractor shall cooperate with the owners of any underground or overhead utility lines in their removal and rearrangement operations in order that these operations may progress in a reasonable manner and that service rendered by these parties will not be interrupted.

C. The County may perform other Work related to the Project at the site by the County's own forces, have other Work performed by utility owners or let other direct contracts. If the fact that such other Work is to be performed is not noted in the Contract Documents, notice thereof will be given to the Contractor. If the Contractor believes that such performance will involve additional expense to the Contractor or require additional time, the Contractor shall send written notice of that fact to the County and the Design Professional/Engineer/Project Manager within 48 hours of being notified of the other Work. If the Contractor fails to send the above required 48 hour notice, the Contractor will be deemed to have waived any rights it otherwise may have had to seek an extension to the Agreement Time or adjustment to the Agreement

Amount. The Contractor shall afford each utility owner and other contractors (or the County, if the County is performing the additional Work with the County's employees) proper and safe access to the site and a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such Work and shall properly connect and coordinate its

Work with theirs. The Contractor shall not endanger any Work of others by cutting, excavating or otherwise altering their Work and will only cut or alter their Work with the written consent of the Design Professional/Engineer/Project Manager and the others whose Work will be affected.

D. If any part of the Contractor's Work depends, for proper execution or results, upon the Work of any other contractor other than a subcontractor or utility owner, the Contractor shall inspect and promptly report to the Design Professional/Engineer/Project Manager, in writing, any delays, defects or other problems in such other Work that render it impossible for the

Contractor to obtain proper execution or results. The Contractor's failure to report will constitute an acceptance of the other Work as fit and proper for integration with the

Contractor’s Work.

3.28. TERMINATION

A. Termination for Default:

1. The Contractor shall be considered in material default of the Agreement and such default shall be considered cause for the County to terminate the Agreement, in whole or in part, as further set forth in this paragraph, for any of the following reasons:

a. Failing to begin Work under the Contract Documents within the time specified herein;

b. Failing to properly and timely perform the Work as directed by the Design

Professional/Engineer/Project Manager or as provided for in the approved Construction

Progress Schedule;

c. Performing the Work unsuitably or…