Amend 1 Q and As for Posting.docx
DOCX document 13 KB Posted
- Attached to
- S&RTS Morocco (Tangier & Agadir)
- Solicitation number
- HTC711-21-Q-R014
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend 3.pdf | ||
| Amend 2.docx | DOCX document | |
| Amend 2 Q and As for Posting.docx | DOCX document | |
| Amend 2 Atch 4 - Technical Evaluation Criteria (Morocco) 3-15-21 Final.docx | DOCX document | |
| SRTS General Compliance Tool Rev 1.xlsx | XLSX spreadsheet | |
| Amend 1.docx | DOCX document | |
| Atch 1 - PWS-v1 Morocco (BM) Final 2-20-21.docx | DOCX document | |
| Atch 5_Contractor Plan for Continuation of Essential Contractor Services.docx | DOCX document | |
| Atch 3 - RFQ Information Sheet.docx | DOCX document | |
| Atch 2 SORv1 - Morocco (Final) 2-20-21 (BM).xlsx | XLSX spreadsheet | |
| Combined Synopsis-Solicitation-HTC711-21-Q-R014 Final.docx | DOCX document | |
| Atch 4 - Technical Evaluation Criteria (Morocco) 2-20-21 Final.docx | DOCX document | |
| HTC711-21-Q-R014 RFQ Final.docx | DOCX document | |
| SRTS General Compliance Tool.xlsx | XLSX spreadsheet |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
S&RTS Ports of Morocco – HTC711-21-Q-R014 Questions & Answers – 9 March 2021
1. Can you please advise if the S&RTS contract holder is responsible for Ad Valorem Port charges applied at Tangier and Agadir Ports?
ANSWER: No: See PWS 4.1.2.1 The Government shall take responsibility for all tariff charges or port fees generated throughout the course of this contract.
2. Can you provide last year incumbent and contract number?
ANSWER: There is not an incumbent, but this requirement was previous on contract. Information for the previous contract, HTC711-20-D-R034, can be found on Beta.SAM.gov.
3. Is a US Small Business Sub-contracting Plan a requirement?
ANSWER: No: FAR Part 19-Small Business, does not apply to overseas contracts. Therefore, a small business subcontracting plan is not required. The SRTS Compliance Tool Rev 1 is attached to Amendment 1.
4. I just wanted to ask if there is an incumbent contract or contractor associated to the requirement. If any, please provide the contractor's name and contract number.
ANSWER: See Question # 2.