HSR15-107 Request for Qualifications for Environmental Services for for the Merced to Fresno Project Section.
Solicitation number
0000000020
Issued by
Fresno County, California

About this file

This is a pre-bid conference presentation from the California High-Speed Rail Authority (CHSRA) regarding two RFQs: #15-107 for As-Needed Environmental Services for the Merced to Fresno Project Section and #15-108 for the Fresno to Bakersfield Project Section. The presentation outlines key details for both five-year contracts, with RFQ #15-107 not to exceed $4.8 million and RFQ #15-108 not to exceed $4.9 million. The scope includes environmental impact analysis, specialized environmental services, and CEQA/NEPA compliance. Key dates include: RFQ issued January 6, 2016; pre-bid conference January 21, 2016; questions due January 28, 2016; SOQs due February 12, 2016 by 3 PM PST; notice of selection March 14, 2016; and notice to proceed May 2016.

The project requires 30% small business participation, including 10% disadvantaged business enterprises (DBE) and 3% disabled veteran business enterprises (DVBE). The Merced to Fresno section covers approximately 65 miles and was environmentally cleared in 2012, while the Fresno to Bakersfield section spans 116 miles and was cleared in 2014. The Authority recognizes certifications from California Department of General Services, California Unified Certification Program, and Small Business Administration 8(a) Program. The project is part of California's larger high-speed rail initiative connecting San Francisco to Los Angeles/Anaheim in Phase 1 (520 miles) with Phase 2 extending to Sacramento and San Diego (additional 300 miles).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCHEDULE

10:30-11:00 a.m. Sign In & Networking 11:00-12:00 p.m. Formal Presentation

- Diana Gomez, Central Valley Regional Director

- Scott Rothenberg, Supervising Environmental Planner

- Jose Camarena, Contract Compliance Manager

12:00-12:30 a.m. Networking

CONNECTING AND TRANSFORMING

CALIFORNIA

Pre Bid Conference for Request for Qualifications for As-Needed Environmental Services for Merced to Fresno Project Section RFQ No. 15-107 and Fresno to Bakersfield Project Section RFQ No. 15-108 January 21, 2016 Fresno, CA

DIANA GOMEZ

CENTRAL VALLEY REGIONAL DIRECTOR

• California is 7th Largest Economy in the World

• Comparable to Northeast Corridor in Terms of Distance, Population and Complexity

• Transformative Investment

• Connecting all California Population Centers

HIGH-SPEED RAIL: More Than A Transportation Program

• 12 Countries with High-Speed Rail

• Over 18,500 Miles of High-Speed Rail

• 1.6 Billion Annual Passengers

• High-Speed Rail first introduced in Japan in 1960s

HIGH-SPEED RAIL: Around the World

• Curbs Congestion » LAX to SFO is the Busiest Short-Haul Market in US » 1 in 5 Flights out of Bay Area Heads to LA » Six of Top 30 Congested Urban Areas in US Located in

California

• Population Growth » Estimated to Reach 50 Million by 2050

• Air Quality/Sustainability » Meets Goals of AB 32/SB 375 » Worst Air Communities in the Country

• Alternatives are Costly » 2-3 Times More Expensive

WHY HIGH-SPEED RAIL IN CALIFORNIA?

• Phase 1 » 520 miles » San Francisco to Los

Angeles/ Anaheim

• Phase 2 » Extends 300 miles » Connections to

Sacramento & San Diego

CONNECTING CALIFORNIA

• Ties Economies Together » San Francisco to Fresno = 60 Minutes » Bakersfield to Los Angeles = 60 Minutes » San Francisco to Los Angeles = 2 Hours 40 Minutes

• Connects With and Reinforces Local Mobility

• Foundation for Sustainable Growth

• Opportunities for Revitalization in Downtown Cores

HIGH-SPEED RAIL: Helping Shape Cities

• Central Valley will Serve as the “Backbone” of a System that will Tie Major Regions of California Together

• Fastest Growing Region in the State

• Revitalize Central Valley Downtown Centers

• Creates Jobs in a Region with High Unemployment

• Best, Most Cost-Efficient Location for Testing

CENTRAL VALLEY: Backbone Of High-Speed Rail

• Construction Package 1: 29 Miles » DB: Tutor Perini/Zachry/Parsons » PCM: Wong+Harris

• Construction Package 2-3: 65 Miles » DB: Dragados/Flatiron » PCM: Arcadis

• Construction Package 4: 22 Miles » DB: Apparent Best Value Proposer

California Rail Builders

» PCM: HNTB

CONNECTING CALIFORNIA: Central Valley Backbone

SCOTT ROTHENBERG

SUPERVISING ENVIROMENTAL PLANNER

HIGH-SPEED RAIL: Environmental Benefits

• Reducing and Zeroing Out Construction Emissions » Tree Planting » VERA Agreements

• Minimizing Construction Emissions » Recycling Steel and Concrete » Tier 4 Equipment » Using Recycled Materials

• Zero-Net Energy Operations

• Smart Station Planning

• Work with State and Federal Agencies on Regional Approaches to Mitigation and Resource Protection

• Continue partnership with the California Department of Conservation to protect Important Farmland in Central Valley into Perpetuity.

• Design and Implement Regional Mitigation Strategies for North, Central Valley and South

• Finalize Lazy K Mitigation Agreement in the Merced to Fresno Project Section to Also Serve as Model for Future Agreements

• Initiate Contract for Mitigation services in the Fresno to Bakersfield segment

• Addressing Native American Meanings of Nature and Habitats in a Joint Consideration of Cultural Resource Significance While Selecting Habitat Mitigation.

HIGH-SPEED RAIL: Conservation and the Environment

MERCED TO FRESNO PROJECT SECTION

• Approximately 65 Miles

• Environmentally Cleared in

• Includes:

» Construction Package 1

• RFQ #HSR 15-107

» As-Needed Environmental Services for Merced to Fresno Project

Section » Five Year Duration » The Estimated Dollar Amount is not to Exceed $4,800,000

MERCED TO FRESNO RFQ OVERVIEW

FRESNO TO BAKERSFIELD PROJECT SECTION

• Approximately 116 Miles

• Environmentally Cleared in

• Includes » Construction Package 1 » Construction Package 2-3 » Construction Package 4

• RFQ #HSR 15-108

» As-Needed Environmental Services for Merced to Fresno Project

Section » Five Year Duration » The Estimated Dollar Amount is not to Exceed $4,900,000

FRESNO TO BAKERSFIELD RFQ OVERVIEW

• Environmental Impact Analysis, Documentation and CEQA/NEPA Compliance » Preparation and/or Peer Review of CEQA and NEPA Documents » Preparation of Environmental Re-Examinations and Re-Evaluations to

Augment Existing Environmental Documents

RFQs SCOPE OF WORK

• Specialized Environmental Services » Environmental Justice » Socio-Economic Studies » Land Use Studies » Economic Impact Assessments » Acoustical and Vibration Analysis » Transportation Planning and Traffic Engineering » Air Quality Analysis and Climate Change Studies » Biological Resources and Wetland Studies » Public Utility and Energy Studies » Hydrology and Water Resource Investigations » Geology, Soils and Seismicity Studies » Hazardous Materials and Waste Research » Safety and Security Analyses

RFQs SCOPE OF WORK

» Agricultural and Forest Land Studies » Aesthetics and Visual Resources Analyses » Community Impact and Other Demographic Assessment » Cultural Resource Investigations » Electromagnetic Fields (EMF) and Electromagnetic Interference (EMI) » Cumulative Impact Assessments » Compensatory Mitigation » Environmental Compliance and Mitigation Monitoring » Regulatory Permitting and Approvals » Geographic Information Systems (GIS) and Information Management

Service Systems » Sections 4(f) of USDOT Act of 1966 and Section 6(f) of Land and Water

Conservation Fund Act of 1965

RFQs SCOPE OF WORK CONTINUED

• January 6: RFQ Issued

• January 21: Pre-Bid Conference

• January 28: Last Day to Submit Questions

• February 12: SOQs due to Authority by 3 p.m. (PST)

• March 14: Notice of Selection

• May 2016: Notice to Proceed Issued

RFQs TIMELINE (SUBJECT TO CHANGE)

• The Authority Evaluation/Selection Committee Shall Review and Evaluate Each Statement of Qualification to Determine if it Meets the Requirements of the RFQ.

• Following the Evaluation of SOQs, the Authority Will Hold Discussions/Interviews with Selected Offerors.

• The Evaluation/Selection Committee Will Then Recommend the Top Ranking Offeror for Award of the Contract and Enter into Negotiations.

RFQs EVALUATION PROCESS

• All State Contracts are Advertised Through http://caleprocure.com

• The RFQ Solicitations Shall Follow the Process in California Code of Regulations

• Offerors are Required to Comply with the Participation by Small, Disadvantaged and Disabled Veteran Business Enterprises

HOW TO PROPOSE

• The RFQs Will be Available in Electronic Format Only on the State’s Contract Register at www.caleprocure.com. A Link Can be Found on the Authority’s Website www.hsr.ca.gov

• All Questions Regarding Both RFQs Must be Submitted in Writing Through www.caleprocure.com

HOW TO PROPOSE (CONTINUED)

The SOQs for Both RFQs Must be Delivered as follows:

» One Original Copy, Six Hard Copies, and a CD /DVD Copy to

Attention: Kimberly Hodge California High-Speed Rail Authority 770 L Street, Suite 620 MS3 Sacramento, CA 95814

» No Later Than 3:00 PM (PST), February 12, 2016

SUBMITTAL FOR RFQ 15-107 AND RFQ 15-108

CONTRACT COMPLIANCE MANAGER

JOSE CAMARENA

• 30% Goal for Small Business Participation » 10% Disadvantaged Business

Enterprises (DBE) » 3% Disabled Veteran Business

Enterprises (DVBE)

SMALL BUSINESS PROGRAM

• Businesses That Count Toward Overall Goal are Certified:

»Small/Micro Businesses Enterprises »Disabled Veteran Business Enterprises »Disadvantaged Business Enterprises »8(a) – Certified Firms

• Authority Recognizes Certifications from:

»California Department of General Services (SBE, DVBE, MBE) »California Unified Certification Program (DBE) »Small Business Administration - 8(a) Program

COMMITMENT TO DIVERSE SMALL BUSINESSES

DOING BUSINESS WITH HIGH-SPEED RAIL

• Targeting: California

• Construction: Direct, Indirect Jobs in Hard-Hit Sectors

• Permanent

• U.S. Conference of Mayors: High-Speed Rail Will Add $4.3 Billion to Los Angeles Regional Economy and 55,000 Jobs by 2035

• Bay Area Council: Caltrain Electrification Would Create almost 9,600 Jobs and Generate $2.5 Billion in Economic Activity

HIGH-SPEED RAIL: Creating Jobs & Workforce Development

Primes

Subs

NETWORKING TIME