J.3 IDIQ Pricing Schedule

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet2

J.3 IDIQ Pricing Schedule HSHDC-13-R-00072
Offerors shall provide Contractor-Site labor rates. Offerors shall complete all cells highlighted in green.
Year 1
Labor Category (Contractor Site)Labor RateLabor HoursLabor Subtotal
Subject Matter Expert1540$ - 0
Program Manager1163$ - 0
Mid-level Systems Analyst883$ - 0
Total Labor$ - 0
Year 1 Indirect RateYear 1 Evaluation ValueMaterial Subtotal
Materials$43,000.00$ 43,000.00

Total Year 1 Value $ 43,000.00

Year 2
Labor Category (Contractor Site)Labor RateLabor HoursLabor Subtotal
Subject Matter Expert7448$ - 0
Program Manager6090$ - 0
Mid-Level Systems Analyst5913$ - 0
Total Labor$ - 0
Year 2 Indirect RateYear 2 Evaluation ValueMaterial Subtotal
Materials$48,000.00$ 48,000.00

Total Year 2 Value $ 48,000.00

Year 3
Labor Category (Contractor Site)Labor RateLabor HoursLabor Subtotal
Subject Matter Expert7820$ - 0
Program Manager6410$ - 0
Mid-Level Systems Analyst8561$ - 0
Labor Total$ - 0
Year 3 Indirect RateYear 3 Evaluation ValueMaterial Subtotal
Materials$52,000.00$ 52,000.00

Total Year 3 Value $ 52,000.00

Year 4
Labor Category (Contractor Site)Labor RateLabor HoursSubtotal
Subject Matter Expert7140$ - 0
Program Manager6420$ - 0
Mid-level Systems Analyst6696$ - 0
Labor Total$ - 0
Year 4 Indirect RateYear 4 Evaluation ValueMaterial Subtotal
Materials$49,000.00$ 49,000.00

Total Year 4 Value $ 49,000.00

Year 5
Labor Category (Contractor Site)Labor RateLabor HoursSubtotal
Subject Matter Expert8340$ - 0
Program Manager6340$ - 0
Mid-level Systems Analyst5340$ - 0
Labor Total$ - 0
Year 5 Indirect RateYear 5 Evaluation ValueMaterial Subtotal
Materials$42,000.00$ 42,000.00

Total Year 5 Value $ 42,000.00

Total Evaluated Price$ 234,000.00
Per Far 16.601(a), "Materials" means-
1)Direct materials, including supplies transferred between divisions, subsidiaries, or affiliates
of the contractor under a common control;
2)Subcontracts for supplies and incidental services for which there is not a labor category
specified in the contract;
3)Other direct costs (e.g., incidental services for which there is not a labor category specified
in the contract, travel, computer usage charges, etc); and
4)Applicable indirect costs.