HSIN PMO Questions and DHS Responses_L14OCT11.pdf

PDF 114 KB Posted

Attached to
Homeland Security Information Network (HSIN) Program Management Support Services
Solicitation number
HSHQDC-11-R-00144
Issued by

About this file

Industry Questions and DHS Responses

View the file

Other files

File Type Posted
HSHQDC-11-R-00144_Amendment 00007.pdf PDF
Attachment D_AM6_17Oct11.pdf PDF
HSHQDC-11-R-00144_AM5.pdf PDF
HSHQDC-11-R-00144_AM 00006.pdf PDF
Attachment D_AM5L_14Oct11.pdf PDF
HSIN AMENDMENT 00005_14OCT11.pdf PDF
HSIN PMO_PR Qs and As _14OCT11.pdf PDF
Attachment F-Revised.pdf PDF
Attachment B-Revised.pdf PDF
Attachment E-Revised.pdf PDF
Attachment 1_Questions and Answers III.pdf PDF
Attachment D-Revised.pdf PDF
Attachment A1-Revised.xlsx XLSX spreadsheet
Amendment 000004.pdf PDF
HSIN 3x SOO Excerpt.pdf PDF
Amendment 000003.pdf PDF
Questions and Answers II.pdf PDF
Target Architecture.pdf PDF
Questions and Answers I.pdf PDF
Amendment 000002.pdf PDF
Attachment D-Revised.pdf PDF
Attachment G-Revised.pdf PDF
Amendment 000001.pdf PDF
Attachment A1.xlsx XLSX spreadsheet
Attachment E.pdf PDF
1449-HSHQDC-11-R-00144.pdf PDF
Attachment F.pdf PDF
Attachment D.pdf PDF
Attachment C.pdf PDF
Attachment G.pdf PDF
Attachment A2.xlsx XLSX spreadsheet
Attachment B.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of Homeland Security Washington, DC 20528

14 October 2014

Subject: Request For Proposal (RFP) No. HSHQDC-11-R-00144 Homeland Security Information Network (HSIN) Program Management

Support Industry Questions and DHS Responses

Dear Offeror:

Attached please find DHS responses to additional Industry Questions regarding the HSIN Program Management Support RFP.

Respectfully, /s/

Susan Eicher Contracting Officer Intelligence and Operations Acquisitions Division Office of Procurement Operations

14 October 2011

The following Industry Questions and DHS Responses are provided regarding Task Order 01 Section 4.5, which states "the Contractor shall provide implementation and development project team resources to support the consolidation, integration, or interoperability of existing DHS Sensitive but Unclassified (SBU) Information Sharing and Collaboration Portals or Applications on the HSIN Platform.

1. Question: How large is the current HSIN 1.x SharePoint site?

DHS Response: ~37K users and ~15TB work of data.

2. Question: How many site collections are included?

DHS Response: ~1000K and not relevant to PMO contract.

3. Question: How many documents are stored on the site?

DHS Response: This information is not relevant to the HSIN PMO requirement.

4. Question: How large is the HSIN 1.x SharePoint database?

5. Question: Are there custom components in HSIN 1.x (SharePoint 2003) that need to be upgraded to SharePoint 2010?

DHS Response: No.

6. Question: Will HSIN 2.x data be migrated to HSIN 3.x?

DHS Response: Users and relevant content only will be migrated to HSIN 3.x.

7. Question: How many other portals will be consolidated into HSIN 3.x under this Task Order?

DHS Response: The target for FY 2012 is 7.

8. Question: What are the different data streams of current HSIN?

9. Question: Is there implementation requirement that would require development for the contractor that is awarded the task?

DHS Response: Yes, in partnership with the HSIN 3.x development contractor.

10. Question: With regards to task 4.5, is there any implementation or development deliverable other than PM, Scrum support and requirements analysis?

DHS Response: Yes; systems engineering lifecycle (SELC) documentation will be produced by the HSIN development contractor.

11. Question: We would like to propose exceptionally qualified personnel for the key positions. They are currently working on similar but non-sensitive DHS projects. These individuals would require either renewed or new SECRET clearances. Is this a detrimental factor?

DHS Response: Please refer to Solicitation Provision FAR 52.212-1 and Solicitation Attachment D for Proposal Content and Proposal Evaluation Information.

12. The following Industry Questions and DHS Responses address the HSIN 3.X Statement of Objectives (SOO) which was provided solely for informational purposes under Amendment 000004 to provide Offerors’ insight into the HSIN Program and assist Offerors’ in their proposal preparation efforts.

SOO Section Question & DHS Response

3. Deliverable Details

Plan (PMP) that describes the contractor’s overall approach to management of the task order

- Within the proposal the contractor shall submit a draft version of the Project Management as well as information on the following subjects:

• Project Management Approach

• Requirements Management

• Release Management

• Quality Management

• Schedule Management

• Risk Management with Risk Register based off of proposal assumptions

• Agile Development Methodology

• Testing Approach This Project Management Plan should be refined during the transition phase and finalized before starting the initial agile development sprints.

Question: Is the Government requiring this information as part of the Task Order 1 response in addition to the original requirement – (Staffing and Management Plan for Task Order 1)? If so, is this to be included within the 4 pages allocated for this section? If not, can the Government please provide revised instructions regarding how we are to address these areas within our proposal response, including page limitations, outline, etc.?

DHS Response: The SOO was provided for informational purposes only. The Solicitation does not request the Offeror to address SOO deliverables in its Proposal responses. Please refer to Solicitation Provision FAR 52.212-1 and Solicitation Attachment D for Proposal Content and Proposal Evaluation Information.

Section 3.0 Question: In Section 3.0, the SOO states "The contractor will comply with HSIN Project Management Office (PMO) methods, tools, standards and data requests." Are the methods, tools, and standards referred going to be the proposed approach we develop in SOW - Subtask 1.1: Program Management Processes and Methodologies (HSHQDC-11-R-00144)?

DHS Response: No. The HSIN Program is a mixed lifecycle program. Some methods, tools, and standards exist. The contractor is invited to improve upon them.

Section 4.0 Question: In Section 4.0, the SOO states "Both the contractor and the government will have scrum masters to manage the daily schedule and user story backlog". Is the government scrum master the same as the proposed resource in SOW - Subtask 3.1.1: Scrum Manager (HSHQDC-11-R-00144)?

DHS Response: Yes.

General Question: What is the role and level of involvement of the PMO contractor during the transition period? Will the contract be awarded prior to that period?

DHS Response: The HSIN Development Contract has already been awarded. The effort will be in assisting the government in overseeing HSIN 3.x implementation.