PAGE_2_-_AMEND._002.doc
DOC document 49 KB Posted
- Attached to
- DOCKSIDE REPAIRS OF CGC MIDGETT FY 18
- Solicitation number
- HSCG85-18-R-P45G41
About this file
Page 2 - SF 30 Amendment 002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30-A002.pdf | ||
| SF30-A001.pdf | ||
| PAGE_2_-_AMEND._001.doc | DOC document | |
| MIDGETT_(WHEC_378W)_DS_FQ1_LDG_18R0(REV).pdf | ||
| ATTACHMENT_4_-_Request_for_Clarification_Form.doc | DOC document | |
| ATTACHMENT_3_-_SCHEDULE_OF_ITEMS_-_PRICES.doc | DOC document | |
| ATTACH._2-Continuation.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL
SOLICITATION NO. HSCG85-18-R-P45G41
Dockside Repairs of CGC MIDGETT (WHEC 726)
Amendment 002
The purpose of this amendment is as follows:
a.
The responses to the following Request for Clarifications are as follows:
QUESTION NO. 7: Work Item No. O-09, 5, Tank Preserve Partial, paragraph 3.3.1; Since the locations have yet to be identified, contractor does not know if and or how much scaffold may be needed to support the 100 Sq Ft Partial Preservation in each of the 3 Tanks listed in Items 1 and 2.
Q: Contractor recommends scaffolding be subject to CFR and a CR as needed?
ANSWER: Under this work item, contractor will submit a CFR if it is deem necessary for scaffolding and a change request will be issued accordingly.
b.
All other terms and conditions cited under this requirement will remain unchanged.