ATTACHMENT4 – REQUEST FOR CLARIFICATION
OFFERORS’ QUESTIONS
Offeror’s Name:
Date:
Question No.
REQUEST FOR CLARIFICATION
Hamilton Dockside Repairs FY17 FQ3
RFP No.: HSCG85-17-R-P45360 PARA NO.
SOLICITATION SECTION: PARA NO.
DEFINITE ITEM NO. PARA NO.
TITLE:
PARA NO.
1. Qeustion: Table 1 and table 2 state that areas for surface preparation will be designated by Coast
Guard Inspector. For bidding purposes, what is the estimated square feet?
Response: Contractors shall review the specifications and drawings and/or perform a ship check to estimate the square feet.
2. Question: Will power tool cleaning be accepted vise SP-6 as stated in PARA: 3.5-3.5.2?
Response: IAW specification, power tool cleaning (SP-11) is acceptable in compartments with uninsulated exhaust piping, and SP-6 is required for the stern deck and recesses
3. Question: Work Item 7, Para 3.9.1 states to renew all wire ropes for Carriage winch IAW Coast
Guard Tech Manual 7348A. The 7348A section 3 refers you to drawing B2-502-0009 sheets
12/13 for lengths of wire rope. The drawing does not give lengths of wire. Is it the intent of the
Government to have contractor price wire rope on CFR in PARA 3.9 or have contractor price wire rope in bid? If it is to be in contractor’s bid, can the Government provide lengths of the wire rope to be replaced and type of wire?
Response: Contractor will price the wire rope via CFR.