ATTACHMENT_1-HAMILTON_(WMSL_753)_DS_FQ3_FY17_REV-0.pdf
PDF 2 MB Posted
- Solicitation number
- HSCG85-17-R-P45360
About this file
ATTACHMENT 1 - Specifications
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC HAMILTON (WMSL 753)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2017
Developed By: Sarah E Schmid
(Rev-0, 25 October 2016)
USCGC HAMILTON (WMSL-753) DOCKSIDE AVAILABILITY FY2017
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ............................................................................... vii Consolidated List of Critical Inspection Items .......................................................................................... viii Principal Characteristics ............................................................................................................................... ix General Requirements WORK ITEM 1: Tanks (Fuel Oil Service), Clean and Inspect WORK ITEM 2: Tanks (Ballast), Clean and Inspect WORK ITEM 3: Galley Grease Fire Extinguishing System, Inspect and Test WORK ITEM 4: Gas Turbine Module Fixed CO2 Fire Extinguishing System, Inspect and Test WORK ITEM 5: Heptafluoropropane (HFP) Fire Extinguishing System, Inspect and Test WORK ITEM 6: Water Mist Fire Extinguishing System, Annual Inspection and Biennial Discharge Test, Perform WORK ITEM 7: Carriage and Centerline Winch, Inspection and Test WORK ITEM 8: Tanks (Grey Water and Lift Stations), Clean and Inspect WORK ITEM 9: Oily Water Separator System, Groom WORK ITEM 10: Flight Deck Net, Weight Testing WORK ITEM 11: Flight Deck Safety Nets, Renew-Optional Item WORK ITEM 12: Tanks (Ballast), Preserve “100%”-Optional WORK ITEM 13: Tanks (Ballast), Preserve “Partial”-Optional WORK ITEM 14: Tanks (Grey Water and Lift Stations), Preserve “100 %” -Optional WORK ITEM 15: Tanks (Grey Water and Lift Stations), Preserve “Partial” -Optional WORK ITEM 16: Tanks (Water Mist), Preserve “100%”-Optional WORK ITEM 17: Tanks (Water Mist), Preserve “Partial”-Optional WORK ITEM 18: Temporary Services, Dockside, Home Pier WORK ITEM 19: Stores Elevator Door Frame, Correct WORK ITEM 20: Flex Hose Assemblies, Renew-Optional WORK ITEM 21: Surfaces, Preserve (Partial) WORK ITEM 22: Deck Covering (Polymeric), Repair and Seal iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:
MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm
Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp
Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::
www.gpoaccess.gov
The Government is aware of the following internet web links where contractors may procure commercial specifications:
American Welding Society (AWS): http://www.awspubs.com/index.php
ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/
NFPA: http://www.nfpa.org
SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace
COAST GUARD DRAWINGS
(ASC100001C)
Coast Guard Drawing 750-WMSL 085-025, Rev -, Compartment Areas & Volumes NSC 3 & Follow
(AS3085012)
Coast Guard Drawing 750-WMSL 100-073, Rev -, Topside Configuration for NSC 4 Only
Coast Guard Drawing 750-WMSL 801-009, Rev -, Booklet of General Plans (NSC 4 Only)
Coast Guard Drawing 750-WMSL-085-021, Rev C, Tank Capacity Curves
Coast Guard Drawing 750-WMSL-100-082, Rev A, General Arrangements (NSC 4 ONLY)
Coast Guard Drawing 750-WMSL-167-001, Rev J, Manhole List Installation and Fabrication Details Ship
Wide (ASC167001)
Coast Guard Drawing 750-WMSL-505-006, Rev D, List of Hoses (ASC505006)
Coast Guard Drawing 750-WMSL-522-001, Rev F, Diagram Machinery Space Water Mist (ASC522001)
Coast Guard Drawing 750-WMSL-522-002, Rev -, Machinery Space Water Mist System Description
(ASC522001-02)
Coast Guard Drawing 750-WMSL-555-011, Rev C, Machinery Space Watermist System Schematic
(ASC555049)
Coast Guard Drawing 750-WMSL-583-004, Rev H, Stern Launch & Recovery Arrangement & Details
(ASC583004)
Coast Guard Drawing 750-WMSL-593-001, Rev H, Bilge and Pollution Control System Diagram
Coast Guard Drawing 750-WMSL-612-003, Rev C, Helo Landing Area Safety Nets & Wheel Stops Arr and Details (ASC612003) http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace v (Rev-0)
Coast Guard Drawing 750-WMSL-612-3, Rev C, Helo Landing Area Safety Nets & Wheel Stops Arr and
Details (ASC612003)
Coast Guard Drawing 750-WMSL-631-002, Rev M, Paint Schedule (ASC631002)
Coast Guard Drawing 750-WMSL-801-009, Rev A, Booklet of General Plans (NSC 4 Only)
Coast Guard Drawing 750-WMSL-801-009, Rev A, Booklet of General Plans (NSC 4 ONLY)
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors
Manual
Coast Guard Technical Manual (TechMan 7141), 25-JUN-07, Ultra Fog High Pressure Sprinkler Systems
Coast Guard Technical Publication (TP) 7019, 31-MAY-07, Main Gas Turbine - Model LM2500 -
Service Manual
Coast Guard Technical Publication (TP) 7096, 10-OCT-07, Carbon Doixide Safety Manual
Coast Guard Technical Publication (TP) 7097, 21-JUN-07, Fire Protection System - Model FM-200
Coast Guard Technical Publication (TP) 7108A, SWBS 573, Mar 2016, Stores Elevator - Model 20833
Coast Guard Technical Publication (TP) 7118, Carbon Dioxide Fire Protection System – Series 70
Coast Guard Technical Publication (TP) 7346, SWBS 593, 18 April 2008, Bilge Water Separator Ultra
Sep Model US5000-J316
Coast Guard Technical Publication (TP) 7348A, 29-MAR-11, Small Boat Retrieval System Equipment
Manual
Coast Guard Technical Publication (TP) 7525
Coast Guard Technical Publication (TP) 7525, 26-MAR-08, Cutter Information Book (CIB) - Auxiliary
Machinery (Vol. IV)
Coast Guard Technical Publication (TP) 7525, Cutter Information Book Auxiliary Machinery (Vol. IV) –
Rev. 1
Coast Guard Technical Publication 7427 (TP 7427), 2014, R-102 Restaurant Fire Suppression System –
Design, Installation, Recharge and Maintenance Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General
Requirements
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2014, General
Requirements
Surface Forces Logistics Center Standard Specification 0450 (SFLC Std Spec 0450), 2014, Electrical
Power for Contractor Tools and Equipment
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2014, Shipboard
Electrical Cable Test
Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2014, Shipboard
Electrical Cable Test
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2014, Shipboard
Electrical Cable Removal, Relocation, Splice, Repair, and Installation
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), Jan 2014, Auxiliary
Machinery Systems
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures vi (Rev-0)
Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2014, Install Interior
Deck Covering Systems
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2014, Temporary
Services
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2014, Temporary
Hull Accesses
OTHER REFERENCES
American Society of Mechanical Engineers (ASME) A17.2, Guide for the Inspection of Elevators, Escalators and Moving Walks.
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets
Code of Federal Regulations (CFR) Title 46, Part 90-139, 2011, Shipping
Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections
MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-D-16791, Jan 1993, Detergents, General Purpose (Liquid, Nonionic)
MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of
Reliability Is Required
MIL-PRF-24176C, Oct 2004, Cement, Epoxy, Metal Repair and Hull Smoothing
MIL-PRF-24613, Dec 1990, Deck Covering Materials, Interior, Cosmetic Polymeric
MIL-PRF-24667C, May 2008, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application
National Fire Protection Association (NFPA) 25, 2014, Standard for the Inspection, Testing, and
Maintenance of Water-Based Fire Protection Systems
Naval Air Warfare Center (NAVAIR) NAEC ENG 7576, Shipboard Aviation Facilities Resume, Jan
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and
Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets
The Society for Protective Coatings (SSPC) Paint Application Specification No. 1 (SSPC-PA Guide 1), 2004, Shop, Field, And Maintenance Painting of Steel
The Society for Protective Coatings (SSPC) Paint Application Specification No. 3 (SSPC-PA Guide 3), 1995, A Guide to Safety in Paint Application
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2013, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power Tool Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 10 (WAB)/NACE WAB-2, 2015, Near-White Metal Wet Abrasive Blast
Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 6 (WAB)/NACE WAB-3, Commercial Wet Abrasive Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE Joint Surface Preparation Standard SSPC-SP
10/NACE No.2, 2004, Near-White Blast Cleaning vii (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM
DESCRIPTION
NSN/PN QTY ESTIMATED
COST
($/UNIT)
6 N Recirculation tank sock filters
P/N: 10011036 4 ea. 25.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter viii (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5
(Inspection report particulars)):
Work
Item Title
1 Tanks (Fuel Oil Service), Clean and Inspect
2 Tanks (Ballast), Clean and Inspect
Water Mist Fire Extinguishing System, Annual Inspection and Biennial Discharge Test, Perform
9 Oily Water Separator System, Groom ix (Rev-0)
PRINCIPAL CHARACTERISTICS
418' WMSL
PHYSICAL
Length overall 418' 0"
Length between perpendiculars 390' 0"
Maximum beam 54' 0"
Beam @ 01 level 47' 9-1/8"
Depth (01 level @ side to baseline) 39' 2-3/4"
01 deck camber foredeck 1/4" in 1'-0"
Minimum berth depth 20' 0"
Height of highest projection Approximately 119'
Draft, design 14.40'
Design displacement 3925 long tons
MACHINERY
Two diesel engines MTU 20V, 20-cylinder 9,730 SHP each
One gas turbine General Electric LM2500; 29,500 SHP
Type of propulsion CODAG
Electrical system 24 Volt DC
Two controllable pitch propellers Rolls-Royce 5 blade, 14' 0" diameter; 229 RPM max
Two reduction gears RENK
One cross connect gear RENK
HULL
Hull material 5086 Aluminum
HSLA-80 Steel
ABS EH 36 Steel
ABS AH 36
Frame spacing
FWD of FR 9 2' 3"
FR 9 to FR 10 6' 9"
FR 10 to FR 98 4' 1"
FR 98 to FR 99 3'-8"
ELECTRICAL
Power Three 1360 kW, 450 V, 60 Hz, 3 Phase, 1800 RPM Caterpillar 3512B diesel engines with Baylor ship service generators
Shore tie cable Seven MIL-C-24368/2 (NATO) shore power receptacles, 400 A each
TANK CAPACITIES
Diesel oil 220,359 gal
Fresh water 12,454 gal
JP-5 Fuel 35,182 gal
1 (Rev-0)
00000_0316_FLT
REC_00000_FLT_Commercial Project @ CG Facility (1212)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-0)
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.2 Contractor-provided fire extinguishers. The Contractor shall provide portable fire extinguishers.
3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec
0000, in accomplishing the following task:
Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.
Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes
(provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at
Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1 USCG facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC
Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable
Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3 (Rev-0)
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is David Isenbarger
843-720-7703.
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an
NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
Air Emission Permit: Unit has a Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.
3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The
Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System
(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste
Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the
Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;
ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the
Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix B, Requirements For
Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.6 Additional Requirements. The Contractor shall be aware of the following:
3.5.6.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the
Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast
4 (Rev-0)
Guard facility without COR or KO-approval.
3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor shall prepare for and comply with local and state regulations.
3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor shall furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.
3.6 Local Policy. None.
3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:
3.7.1 SFLC Standard Specification 6310, Requirements for Preservation of Ship Structures.
3.7.1.1 SFLC Std Spec 6310, page C-2, Section C1.5.1. Change from "lead-containing paint as 0.06%" to "lead-containing paint as 0.009%".
3.7.1.2 SFLC Std Spec 6310, page 4, Section 2 References, Group- Other References. Add “The Society for
Protective Coatings (SSPC) Paint Application Guide No. 11, 2008, Protecting Edges, Crevices, and Irregular Steel
Surfaces by Stripe Coating”
3.7.1.3 SFLC Std Spec 6310, page Appendix C-6, add "Hempel Hempadur Multi-Strength GF 35870" with FED-
STD-595 color "Black/Red" under ANTI-ABRASION COATING, ICE BREAKING CAPABLE VESSELS, <235’.
3.7.1.4 Standard Spec 6310, page Appendix A-7, Under "UNDERWATER (U/W) BODY/BOOT-TOP", Add line
Column 1: Option for U/W Body and Boot-Top, Steel Hulls, <154', in Salt Water. Column 2: Blank. Column 3:
SSPC-SP 10/NACE NO. 2 using grit conforming to MIL-A-22262 / (1.5-3.5) - or - SSPC-SP WJ-2(M)/NACE
WJ-2(M). Columns 4 and 5: Same as "U/W Body and Boot-Top, Aluminum Hull, High Speed (>30 knots)".
3.7.2 SFLC Standard Specification 0000 General Requirements.
3.7.2.1 SFLC Std Spec 0000, paragraph 1.3 ‘Acronyms and term definitions’, page 5, “PCL (Paint Containing
Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”
3.7.2.2 Change Std Spec 0000 paragraph 3.2.4.2.3(QP 1 inspector or tech rep duties) bullet, “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph
3.1.19 of SFLC Std Spec 6310 (Critical drying time requirements)).” to “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.17 of SFLC
Std Spec 6310 (Critical drying time requirements)).”
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
5 (Rev-0)
6 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM # WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
7 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
8 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
9 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Reading
(mils)
Mean Reading (mils) IAW ASTM DD4417).
10 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
SOLUBLE SALT CONDUCTIVITY Measurements IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
11 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
COATING MFG PRODUCT NAME
BATCH
INDUCTION
TIME
COATING SYSTEM SEQUENCE
(PRIMER/TOUCHUP/3RD COAT, ETC.)
Dry Film Thickness (DFT) Measurements IAW SSPC-PA 2.
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL READING
(BMR) Required, If Magnetic
Pull-Off (Type I/Banana) Gauge Is
Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
1 AVG. BMR DEVIATION
1 AVG. BMR DEVIATION
APPLICATION METHOD (AIRLESS, CONVENTIONAL SPRAY,
ROLLED)
AVERAGE DFT
12 (Rev-0)
12305_0316_FLT
REC_12311_FLT_«REC»
WORK ITEM 1: Tanks (Fuel Oil Service), Clean and Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
TABLE 1 - FUEL SERVICE TANK
TYPE OF TANK LOCATION
CAPACITY - 95%
(GALLONS)
EST. LOW SUCTION
(GAL)
Fuel-Oil Service 5-36-2-F 21724 Up to 5% of Tank Content
May Remain
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 750-WMSL-085-031, Rev -, Tank Capacity Curves
Coast Guard Drawing 750-WMSL-085-032, Rev -, Tank Sounding and Moment of Intertia
Tables (WMSL 753 Only)
Coast Guard Drawing 750-WMSL-100-082, Rev A, General Arrangements (NSC 4 ONLY)
Coast Guard Drawing 750-WMSL-101-002, Rev G, C & A, Innerbottom (ASC101002)
Coast Guard Drawing 750-WMSL-101-004, Rev G, C & A, First Platform (ASC101004)
Coast Guard Drawing 750-WMSL-167-001, Rev J, Manhole List Installation and Fabrication
Details
Coast Guard Drawing 750-WMSL-540-005, Rev B, Fuel Oil System Schematic (ASC540016)
Coast Guard Drawing 750-WMSL-801-009, Rev A, Booklet of General Plans (NSC 4 ONLY)
GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes
13 (Rev-0)
OTHER REFERENCES
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets
MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of Reliability Is Required
Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):
3.6. Inspection
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec
0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
Fuel
Piping
Tank access cover
3.1.4.1 The Contractor shall remove (approximately 2% of original CAPACITY - 95%). Document a complete chain of custody record of the removed tank contents from the vessel to the point of final destination or delivery. Submit a CFR to the COR upon completion of work.
3.1.4.2 Dispose of removed fluids in accordance with all applicable Federal, state, and local regulations
(See 4.2 : Tank content restoration).
NOTE
Vessel may come in with less tank fluid contents than specified above.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
14 (Rev-0)
3.2 Operational test, initial. Prior to commencement of work, the Contractor shall witness Coast Guard
Personnel perform an initial operational test of the TLI’s for tanks listed in paragraph 1.1 (Intent), to demonstrate existing operational condition. Submit a CFR.
3.3 Plug log. The Contractor shall keep a written record of all plugs put in any tanks vents. A separate list shall be kept for each tank being entered.
3.3.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.
3.3.2 Ensure the plug log is available to the Coast Guard inspector when the inspector is performing his close-out inspection on each tank.
NOTE
Initial and post repair operational tests apply only to tanks that possess TLIs.
3.4 Cleaning requirements. The Contractor shall remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as residual fuel or water, sediment, sludge, rust, or biological growth, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths. The Contractor shall refer to Coast Guard Drawing Coast Guard
Drawing 750-WMSL-540-005 for guidance.
3.5 Tank content and waste disposal. The Contractor shall dispose of residual tank contents and any cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit CFR to the COR upon completion of work.
3.6 Inspection. The Contractor shall accomplish the following tasks:
3.6.1 Visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces.
Submit a CFR including the following, as applicable:
Tank structural condition.
Inaccessible areas.
Condition of tank coating, including measurements taken, percentage, location, and type of coating failure (if tank interior surfaces are coated).
Tank level indicator (TLI) and/or float switch condition, as applicable.
Sounding/vent tube and striker plate condition.
Suction and discharge piping condition.
Fastener material and condition (correct fastener material is stainless steel).
3.6.2 Measure up to 10 “pits” within each tank as designated by the Coast Guard Inspector using a
Contractor supplied ‘Pit Gauge’. Include pit measurement results in CFR specified above, showing where pit measurements were taken and the depth of the pit.
15 (Rev-0)
3.7 Ultrasonic thickness (UT) measurement. The Contractor shall take a total of 50 UT measurements of tank plating, in locations designated by the Coast Guard Inspector, in accordance with SFLC Std Spec
0740. Submit a CFR.
3.7 Tank closing. The Contractor shall ensure that the tank(s) remain open for at least 24 hours after completion of any KO-authorized repair and preservation procedures. Notify the COR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183.
Chase threads on studs to ensure even installation of the access covers. Use MIL-DTL-1222 as guidance.
Renew all hardware and cotton grommets IAW CG Drawing 167-001.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.8 Operational test, post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all designated tank TLI’s to be in satisfactory operating condition. Submit a CFR.
4. NOTES
4.1 Tank content removal. The Ship’s force will pump down the tanks to the maximum extent possible with the installed pumping system.
4.2 Tank content restoration. The Ship’s force will refill all tanks upon completion.
16 (Rev-0)
12316_0316_FLT
REC_12316_FLT_«REC»
WORK ITEM 2: Tanks (Ballast), Clean and Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
TABLE 1 – LIST OF TANKS
TYPE OF
STRUCTURE
LOCATION CAPACITY - 95%
(gallons)
ESTIMATED LOW
SUCTION (gallons) Ballast Tank 5-16-1-W 14438
Up to 5% of Tank Content
May Remain Ballast Tank 5-16-2-W 14459 Ballast Tank 5-22-0-W 12762
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 750-WMSL-085-031, Rev -, Tank Capacity Curves
Coast Guard Drawing 750-WMSL-085-032, Rev -, Tank Sounding and Moment of Inertia Tables
(WMSL 753 Only)
Coast Guard Drawing 750-WMSL-100-082, Rev A, General Arrangements (NSC 4 ONLY)
Coast Guard Drawing 750-WMSL-101-002, Rev G, C & A, Innerbottom (ASC101002)
Coast Guard Drawing 750-WMSL-101-004, Rev G, C & A, First Platform (ASC101004)
Coast Guard Drawing 750-WMSL-167-001, Rev J, Manhole List Installation and Fabrication
Details
Coast Guard Drawing 750-WMSL-540-005, Rev B, Fuel Oil System Schematic (ASC540016)
Coast Guard Drawing 750-WMSL-801-009, Rev A, Booklet of General Plans (NSC 4 ONLY)
GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes
17 (Rev-0)
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):
3.6. Inspection
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec
0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
Piping
Tank Covers
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test - initial. Prior to commencement of work, the Contractor shall witness Coast Guard
Personnel perform an initial operational test of the TLI’s for tanks listed in paragraph 1.1 (Intent), to demonstrate existing operational condition. Submit a CFR.
3.3 Plug log. The Contractor shall keep a written record of all plugs put in any tanks vents. A separate list shall be kept for each tank being entered.
3.3.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.
3.3.2 The plug log shall be available to the Coast Guard inspector when the inspector is performing his close-out inspection on each tank.
3.4 Content removal. The Contractor shall remove access cover(s); remove and dispose of all fluids and/or residues in accordance with all applicable Federal, state, and local regulations. Plug all inlet and outlet piping in the tank to prevent contaminants from entering the tank. Use plugs with an attached lanyard, ring or other system that will ensure plugs are not lost in the pipe openings. Maintain a plug accountability log outside the tank(s) to prevent any of the installed temporary plugs from being lost inside the tank or forgotten inside at tank closure.
18 (Rev-0)
3.5 Cleaning. The Contractor shall clean the designated structure’s (see paragraph 1.1 : Intent) interior surfaces free of all foreign materials, such as sediment, sludge and fungal growth. Remove all persistent residues, taking care not to damage the tank coating system. Remove cleaning media and residues continuously from the compartment during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations.
3.6 Inspection. The Contractor shall visually inspect all interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
Structural condition
Inaccessible areas, if any
Condition of coating, including measurements taken, percentage, location, and type of coating failure.
Tank level indicator (TLI) and/or float switch condition.
Sounding tube and striker plate condition.
Suction and discharge piping condition.
Fastener material (stainless steel) and condition.
3.6.1 Measure up to 10 “pits” within each tank as designated by the Coast Guard Inspector using a
Contractor supplied ‘Pit Gauge’. Include pit measurement results in CFR specified above, showing where pit measurements were taken and the depth of the pit.
3.6.2 Ultrasonic thickness (UT) measurement. The Contractor shall take a total of 50 UT measurements of tank plating, in locations designated by the Coast Guard Inspector, in accordance with SFLC Std Spec
0740, Appendix C. Use Coast Guard Drawing 750-WMSL-801-009 as guidance. Submit a CFR.
3.7 Closing. The Contractor shall ensure that the compartment(s) remain open for at least 24 hours after completion of any KO-authorized tank repairs and preservation. Notify the COR at least 24 hours prior to closing the compartment(s). After satisfactory inspection by the Coast Guard Inspector, and completion of all authorized repairs, close the manhole cover(s) with new gasket material conforming to ASTM
D1330 and new cotton grommets on each stud (as applicable). Renew all hardware and cotton grommets in accordance with Coast Guard Drawing 750-WMSL-167-001.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.8 Operational test – post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate the designated tank TLI’s to be in satisfactory operating condition. Submit a CFR.
4. NOTES
This section is not applicable to this work item.
19 (Rev-0)
55500_LCM_0216_418
WORK ITEM 3: Galley Grease Fire Extinguishing System, Inspect and Test
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to inspect the galley grease fire extinguishing system.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 750-WMSL-100-082, Rev A, General Arrangements (NSC 4 ONLY)
Coast Guard Drawing 750-WMSL-801-009, Rev A, Booklet of General Plans (NSC 4 ONLY)
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication 7427 (TP 7427), 2014, R-102 Restaurant Fire Suppression
System – Design, Installation, Recharge and Maintenance Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep. The Contractor shall provide the services of a Qualified Technical Representative for the Ansul R-102 grease fire suppression system to accomplish the following on site:
Advise on manufacturer's proprietary system information.
20 (Rev-0)
Assist with the inspections and tests of the Ansul R-102 grease fire suppression system.
Ensure compliance with manufacturer's procedures and standards during system disassembly, inspection, and reassembly as applicable.
3.1.2.1 Ensure the Tech Rep has experience with the system/equipment stated above and demonstrated on their résumé. Submit the name and résumé of the Tech Rep to the COR at the Arrival Conference.
NOTE
Inspections and tests of four fire suppression systems (Water Mist, Gas
Turbine Module Fixed CO2, Galley Grease Fire, and Heptafluoropropane
(HPF)) will be conducted during this maintenance period.
One Tech Rep may provide the required services for any or all of the four fire suppression systems provided that the Tech Rep meets the requirements in paragraph 3.1.2.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec
0000, paragraph 3.3.5 (Interferences).
3.2 Maintenance requirements. Due to disruption of galley operation while testing and inspecting the fire…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .