PAGE_2_-_A003.doc
DOC document 48 KB Posted
- Attached to
- DRY-DOCK AND REPAIRS OF CGC ALEX HALEY (WMEC 39)
- Solicitation number
- HSCG85-17-R-P45157
About this file
Page 2 - Amendment 003
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30-A003.pdf | ||
| SF30-A002.pdf | ||
| PAGE_2_-_A002.doc | DOC document | |
| ATTACHMENT_2_-_SUPPLIES_&_SERVICES_-_PRICES(REVISED).doc | DOC document | |
| ATTACHMENT_4_-_SOLICITATION_PROVISIONS_(AHDD)(REVISED).doc | DOC document | |
| ATTACHMENT_3_-_CONTRACT_CLAUSES_AND_SUPPLEMENTAL_TERMS_AND_CONDITIONS(REVISED).doc | DOC document | |
| SF30-A001.pdf | ||
| ATTACHMENT_2_-_SUPPLIES_&_SERVICES_-_PRICES.doc | DOC document | |
| ALEX_HALEY_(WMEC_282)_DD_FQ2_R1_APW_final_21NOV16_(2).pdf | ||
| ATTACHMENT_4_-_SOLICITATION_PROVISIONS_(AHDD).doc | DOC document | |
| ATTACHMENT_5_-_Request_for_Clarification_Form.doc | DOC document | |
| ATTACHMENT_6-Notice_of_Filing_Protests.pdf | ||
| ATTACHMENT_3_-_CONTRACT_CLAUSES_AND_SUPPLEMENTAL_TERMS_AND_CONDITIONS.doc | DOC document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Proposal
Solicitation No. HSCG85-17-R-P45157
Dry-dock & Repairs of CGC ALEX HALEY (WMEC 39)
Amendment 003
The purpose of this amendment is as follows:
a.
The answers to the following Request for Clarifications are as follows:
QUESTION NO. 1: Work Item No. D-42, Thruster Unit (General), paragraph
3.1.1; Contractor cannot identify the make and manufacture of the bow thruster to identify and contact the required tech rep specified in Para. 3.1.1. Please provide a contact for the bow thruster tech rep services so that the contractor can adequately satisfy the requirements of 3.1.1.
ANSWER: Propulsion Systems, Inc and JHB Propellers/Tappan New York. 206-789-
0944.
QUESTION NO. 2: Work Item D-58, Vent Jalousies, Install Catch Basin & Drain, paragraph 3.3.2; 3.3.2 states 4 jalousies are to be inspected, however S1-29-2 is listed twice. Assumption is this should include S1-24-2 instead. Please verify.
ANSWER: Correct, should read S1-24-2.
QUESTION NO. 3: Work Item D-53, Masts (Forward Topmasts, Foremasts, and
Singlemasts) Preserve, 100%, paragraph 4; 4.2 seems to be cut off from a complete note. Please provide any missing information from Paragraph 4.
ANSWER: Paragraph 4.2 for this work item should read: “Note: Expect a large amount of damage to electrical mountings, ladders, and hardware and include in Condition Found
Reports. “ QUESTION NO. 4: Work Item D-34, Rudders, Inspect and Repair, paragraph 3.3; 3.3 seems to indicate that one of rudders is leaking. For bid purposes, are we to estimate one leaking rudder repair as part of the item cost?
ANSWER: For bidding purposes, estimates will reflect only the ONE rudder.
QUESTION NO. 5: Work Item O-26, Propeller Shaft, Remove, Inspect and Reinstall, paragraph 3.12.3; 3.12.2 seems to have information missing from the table. Please provide any known information regarding referenced parts.
ANSWER: Disregard Table-1 CPP parts. Coast Guard will request contractors to recommend parts through a CFR after inspection.
QUESTION NO. 6: Work Item O-35, Rudder Removal, One Rudder only, paragraph 3.3.1; 3.3.1 requires a pre-docking rudder angle indicator test be done. D-33
(Rudder Stock Bearings Check Clearances and Carrier Bearing Recess Preservation) paragraph 3.2.1 already has the test being performed. For pricing, cost of test should be omitted from O-35, correct? Spec should be revised to say costs included elsewhere.
ANSWER: Contractor shall bid on rudder angle indicator test, D-33 para. 3.2.1, and disregard the similar requirement listed under Optional item O-35 (para. 3.3.1). Future specs will be revised to say costs included in the definite CLIN.
QUESTION NO. 7: Work Item O-26, Propeller Shaft, Remove, Inspect and Reinstall, paragraph 3.4.2.2; What FO tanks are these? What are their capacity?
ANSWER: FO 5-36-0-F 18,000 gal, FO 5-36-1-F and 5-36-2-F are 10,500 gal
QUESTION NO. 8: Contractor requested various pictures to determine interferences and components on various work items.
ANSWER: Due to the size of these pictures and for security purposes, offerors must submit a request, via e-mail, to Valerie.s.riverachase@uscg.mil. These pictures will not be post in www.fbo.gov.
QUESTION NO. 9: Work Item D-54, Electrical Matting Renew; How many man holes are there in the deck of the pilot house? How many UT shots are required per 3.1.5?
ANSWER: No escape scuttles or man holes on the deck of the pilot house. Per paragraph 3.1.5, 75 UT shots are required.
QUESTION NO. 10: Work Item D-58, Vent Jalousies, Install Catch Basin & Drain; Can the USCG provide diagrams that depict the intended installations?
ANSWER: As mentioned in 3.3.1, the design of the drain system should be similar to the design of the enclosure around the jalousie for the Emergency Generator Compartment. DWG 282-WMEC-501-74 of this system will be provided in the contract amendment.
QUESTION NO. 11: Work Item D-40, Sea Valve (<=2.5 Inch) Renewal, 4 notes; : The first six valve listed are unknown. Can the Coast Guard supply a drawing showing all sea water valve by the valve numbers? Or can the six valve be a change order after the type of valves are found?
ANSWER: Contractor will submit a Condition Found Report upon verification of the six valves. Change Request will be issued and this change will be incorporated to the contract by issuance of a modification.
QUESTION NO. 12: Work Item No. D-42, Thruster Unit (General); Is a technical manual available for the thruster unit? How much hydraulic fluid is contained in the thruster system?
ANSWER: Contractor will submit a request, via e-mail, to valerie.s.riverachase@uscg,mil for a copy of the tech manual. System holds approx 75 gallons.
QUESTION NO. 13: Work Item O-47, Tanks (MP Fuel Storage and Overflow) Preserve 100%; What is the manufacturer and model number of the TLI’s in each tank?
ANSWER: Two types of TLI’s installed on the cutter are GEMS 36000 Series Tank Level Indicating Transmitters and 45600 Series Transmitters.
QUESTION NO. 14: Work Item D-53, Masts (Forward Topmasts, Foremasts, and
Singlemasts) Preserve, 100%; Can the contractor use the referenced drawing of the mast as a basis for determination of the antennas and other attachments to the mast?
ANSWER: The DWG should be used as a guide. Pictures were provided in response to another RFC which can also be used to determine antennas and other attachments to the mast.
QUESTION NO. 15: Work Item D-67, No. 2 Main Diesel Engine, Block Renewal;
Will the lower engine frame remain in place and be utilized with the new block?
After the replacement engine block has been secured in place, does the USCG crew have responsibility for re-assembly of the engine. Do contracted provided tech services end when the block has been secured to the lower engine frame?
ANSWER: No, lower engine frame will not remain in place to be utilized with new block. Contractor shall reassemble. Coast Guard will secure block for sea transit. Contractor shall reassemble and overhaul in accordance with contract spec work item.
QUESTION NO. 16: Work Item D-23, Propulsion Shaft Alignment (Dry-Dock) Check; From Diehl Engineering #1 They are calling for external strain gage measurements in the dock, but it is unclear if the intent is to have external strain measurements performed when the ship is back in the water. On the 210’s the Coast Guard said yes they want external strain in the water, but on the 378 and 400 foot boats where they had us do external strain measurements in the dock only, and then patched the spot’s up on the shaft before the ship went back in the water. So you will need to ask the Coast Guard what their intent is.
#2 If the Coast Guard said yes, they want underwater strain measurements, we are going to have to quote to do it the traditional way with wires that come out from under the fiberglass and lead up to the deck, then are snipped off after by a diver after the measurements are complete. This is how the Coast Guard has always performed the underwater measurements in the past when it is invoked in the specification. I have always maintained that this is not a good thing to do since the wires create a pathway for corrosion to the shaft. That is why I developed the underwater nodes that are embedded in the fiberglass. However, the manufacturer of the nodes did not sell enough of them to keep making them and so they are no longer available.
#3 If the Coast Guard insists that they want underwater strain measurements, then I think it would be best for LUDD to have the Coast Guard sign a waiver that LUDD will not be held responsible for the resulting shaft corrosion.
ANSWER: The Coast Guard intent is to have a Consulting Engineer come just prior to the ship docking and sets strain gages on the shaft internal to the cutter to measure the pre-docking conditions (para 3.3.1). After drydockng the cutter, Consulting Engineer comes back and puts one or two additional gages on the shafts and takes a second set of readings (para 3.3.2). These additional strain gages are placed on the shafts at locations external to the hull. They cannot be read after the ship is back in the water. So, just prior to undocking, Consulting Engineer takes a 2nd set of measurements using both the external to the hull and the internal to the hull strain gages, (para 3.3.3 pre-undocking) then removes or patches over the external strain gages. The final strain measurement (Post Drydocking, Para 3.3.4 in the spec) is taken using the internal strain gages only. Note that there is also a load cell measurement requirement in paragraph 3.5 and 3.6.
QUESTION NO. 17: Work Item D-60, Vacuum Sewage System, Hydroject Cleaning; How many linear feet of piping will required cleaning?
ANSWER: All horizontal runs will require cleaning and areas with highest buildup. As per para 3.3.3 length that needs cleaning will be determined by pipe camera prior to commencing work.
QUESTION NO. 18: Work Item No. O-06, Hull and Structural Plating (General) – 15.3 Pound Steel Plate, Renew; Will lead paint abatement, if necessary, be the subject of a change request.
ANSWER: No. Lead paint abatement, if necessary will be a subject of a CFR.
As per Ref 1.1, Contractor to renew 15.3 pound steel shell plating. Activation up to 5 times with each activation for 5 sq ft.
QUESTION NO. 19: Work Item No. D-16, Propulsion Shaft Fairwaters and Rope Guards, Inspect and Repair; paragraph 1.2 indicates that there is no GFE, para 3.3.2 indicates fairwaters are GFE. Are the replacement fairwaters GFE?
ANSWER: Coast Guard acknowledges, if replacements are required, Contractor will submit a CFR and CG will provide GFE as per paragraph 3.3.5 of spec.
QUESTION NO. 20: Work Item D-21, Controllable Pitch Propeller System Maintenance; What are manufacturer names and part numbers for the pumps listed in para 3.8.1.1 Pump Data? Are technical manuals available for the pumps listed in paragraph 3.8.1.1 Pump Data?
ANSWER: Part numbers are listed in Pump Data paragraph 3.8.1.1 as pump “type”. Pump manufacturer is Allweiler. Tech manuals will be provided in a CD. L
QUESTION NO. 21: Work Item No. D-22, CPP Hubs, General Maintenance; Lead time for purchase and reciept of propeller blade seals is likely problematic. Can the USCG make these blade seals GFE and purchase them in advance of the contract award?
ANSWER: Coast Guard acknowledges, but Contractors will be required to provide material. All eight items were renewed during FY13 Drydock, same is expected for FY17 Drydock.
QUESTION NO. 22: Work Item No. O-27, Propeller Shaft, Renew; what is the weight of the propeller shaft?
ANSWER: Propeller shaft weighs approx 12,700LBS.
QUESTION NO. 23: Work Item No. O-30, Stern Tube Shaft, Renew; what is the weight of the stern tube shaft?
ANSWER: Stern tube weighs approx 10,000 lbs.
b.
All other terms and conditions cited on the solicitation will remain unchanged.