Amendment_3_-_HSCG85-17-Q-P45024_FIR_DD_FY17.pdf
PDF 5 KB Posted
- Attached to
- USCGC FIR FY2017 DRYDOCK REPAIRS
- Solicitation number
- HSCG85-17-Q-P45024
About this file
Amendment 3 Questions Answered
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HSCG85-17-Q-P45024
USCGC FIR DRYDOCK REPAIRS
Amendment 0003
Page 1of 1
QUESTION 1:
How many square feet of clad welding should be expected to perform repairs?
ANSWER: square feet of repairs will need to be determined upon inspection of cutter with PE.
QUESTION 2:
Will these two ballast tanks 4-21-0-0-W and 4-0-0-W be pumped down to low suction by the Coast Guard before it comes to the shipyard, so the tanks can be opened, pumped out the rest of the way, so the zinc anodes can be renewed? If not, what will the amount of ballast water to be in the tanks when it arrives at the shipyard?
ANSWER:
All ballast tanks pumped down to low suction, utilizing our fuel load to adjust trim as necessary for dry dock entry.
File details come from the government source that posted it. Updated .