HSCG85-17-Q-P45024

USCGC FIR DRYDOCK REPAIRS

Amendment 0003

Page 1of 1

QUESTION 1:

How many square feet of clad welding should be expected to perform repairs?

ANSWER: square feet of repairs will need to be determined upon inspection of cutter with PE.

QUESTION 2:

Will these two ballast tanks 4-21-0-0-W and 4-0-0-W be pumped down to low suction by the Coast Guard before it comes to the shipyard, so the tanks can be opened, pumped out the rest of the way, so the zinc anodes can be renewed? If not, what will the amount of ballast water to be in the tanks when it arrives at the shipyard?

ANSWER:

All ballast tanks pumped down to low suction, utilizing our fuel load to adjust trim as necessary for dry dock entry.