REVISED SPECIFICATIONS

View the file

Other files

File Type Posted
AMEND0002KENNEBEC.doc DOC document
AMEND0001.doc DOC document
KENNEBECSOLICITATION.docx DOCX document
KENNEBEC_(WLIC_160B)_DD_FQ1_RLM_17Rev_0_.doc DOC document
KENNEBEC_SECTION_B.xls XLS spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC KENNEBEC (WLIC 802)

SPECIFICATION FOR DRYDOCK REPAIRS

FY2017

Developed By: Raymond L Murray (Rev-1, 10 June 2016)

TABLE OF CONTENTS

iiiRevisions Record ivConsolidated List of References viiiConsolidated List of Government-furnished Property ixConsolidated List of Critical Inspection Items xPrincipal Characteristics

1General Requirements

10WORK ITEM 1: Hull Plating (Side Scan), Ultrasonic Testing

14WORK ITEM 2: Hull Plating (U/W Body), Inspect

18WORK ITEM 3: Hull Plating (Freeboard), Ultrasonic Testing

20WORK ITEM 4: Appendages (U/W), Leak Test

23WORK ITEM 5: Propulsion Shaft Fairwaters and Rope Guards, Inspect

26WORK ITEM 6: Propulsion Shafting, Remove, Inspect, and Reinstall

30WORK ITEM 7: Propulsion Shafting, Straighten

32WORK ITEM 8: Mechanical Shaft Seal Assemblies, Renew

35WORK ITEM 9: Propulsion Shafting, Optical Or Laser Alignment Check

38WORK ITEM 10: Propulsion Shaft Bearings (External), Renew

41WORK ITEM 11: Propulsion Stern Tube Bearings, Renew

44WORK ITEM 12: Propellers, Remove, Inspect, and Reinstall

48WORK ITEM 13: Propeller, Minor Repairs and Reconditioning, Perform

52WORK ITEM 14: Keel Coolers, Clean, Inspect and Hydro

56WORK ITEM 15: Fathometer Transducer, Renew

59WORK ITEM 16: Sea Valves and Waster Pieces, Overhaul or Renew

65WORK ITEM 17: Sea Strainers - Duplex (All Sizes), Overhaul

69WORK ITEM 18: Rudder Assembly; Remove, Inspect and Reinstall

74WORK ITEM 19: Spud Wells, Preserve

76WORK ITEM 20: Decks - Exterior, Preserve (“Non-Skid Broadcast Grit” System)

79WORK ITEM 21: Stern Tube Interior Surfaces, Preserve 100%

82WORK ITEM 22: Hull Plating Freeboard, Preserve “100%”

85WORK ITEM 23: Cathodic Protection / Zinc Anodes, Renew

88WORK ITEM 24: Drydock

92WORK ITEM 25: Lead-Based Paint, 100% Abatement, Perform

96WORK ITEM 26: Temporary Services, Provide - Tender

99WORK ITEM 27: Sea Trial Performance, Support, Provide

103WORK ITEM 28: Boat Davit Winch, Shrink Wrap

105WORK ITEM 29: Buoy and Cargo Handling Crane, Shrink Wrap

107WORK ITEM 30: U/W Body, Preserve (100%)

111WORK ITEM 31: Pilothouse Overhead Steel Plating, Renew

114WORK ITEM 32: Lead-Based Paint, 100% Abatement, Perform

Revisions Record This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE
REV#
WORK ITEM#
CHANGES MADE
10 June 2016
1

Para. 3.1.2 Changed the need for a technical representative from N/A to Applicable

10 June 2016
1
12 Para. 1.1
Removed the word center from this sentence
10 June 2016
1
18 Para. 3.1.7
Deleted Para. 3.1.7
10 June 2016
1
26 Para. 3.2 Service Selection Table

3.3.9 Heavy Lift Equip hrs.

Changed table to read 5 days @ 4 hrs per day or 20 hrs

10 June 2016
1
26 Para. 3.3.14
Changed the need for refrigerated stores to N vice Y

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

Consolidated List of References

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.

All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:

· MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm

· Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp

· Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws:: www.gpoaccess.gov The Government is aware of the following internet web links where contractors may procure commercial specifications:

· American Welding Society (AWS): http://www.awspubs.com/index.php

· ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/

· NFPA: http://www.nfpa.org

· SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace

COAST GUARD DRAWINGS

Coast Guard Drawing 160 WLIC 0103-3, Rev A, Booklet of General Plans

Coast Guard Drawing 160 WLIC 1101-001, Rev C, Shell Pltg Expansion & Framing

Coast Guard Drawing 160 WLIC 244-003, GA OF 6" TYPE FSE MANEGUARD SEAL (SUPERSEDS 160-WLIC-244-001, 160-WLIC-244-002) Rev -, Type FSE Seal (6” Fully Split)

Coast Guard Drawing 160 WLIC 4105-006, Rev -, Engine Cooling System (KENNEBEC)

Coast Guard Drawing 160 WLIC 4105-007, Rev -, Arrangement Of Engine Cooling Piping (KENNEBEC)

Coast Guard Drawing 160 WLIC 4301-001, Rev G, Shafting and Propeller Arrangement and Details

Coast Guard Drawing 160 WLIC 4301-003, Rev C, Shafting Arrangement and Details

Coast Guard Drawing 160 WLIC 4400-3, Rev-, Propeller

Coast Guard Drawing 160 WLIC 4800-1, Rev-, Sea Chest Structures

Coast Guard Drawing 160 WLIC 4803-1, Rev-, Fire Main Piping

Coast Guard Drawing 160 WLIC 4804-1, Rev-, Diagram Fresh Water System

Coast Guard Drawing 160B WLIC 0500-001, Rev -, Lines Corrected

Coast Guard Drawing 160B WLIC 0700-001, Rev B, Docking Plan (KENNEBEC)

Coast Guard Drawing 160B WLIC 1101-001, Rev C, Shell Plating Expansion and Longitudinal Framing

Coast Guard Drawing 160B WLIC 1103-002, Rev A, Vertical Keel, Skeg, and Bottom Girders

Coast Guard Drawing 160B WLIC 1105-001, Rev B, Transverse Watertight and Oil Tight Bulkheads

Coast Guard Drawing 160B WLIC 1108-002, Rev B, Shaft Struts and Stern Tubes

Coast Guard Drawing 160B WLIC 1205-1, Rev F, Spudwells and Spuds

Coast Guard Drawing 160B WLIC 1205-3, Rev B, Hull Zinc

Coast Guard Drawing 160B WLIC 2200-001, Rev A, Steering Machinery Arrangement, Rudder Stock and Fittings

Coast Guard Drawing 160B WLIC 2901-004, Rev -, Curves of Form

Coast Guard Drawing 160B WLIC 4301-1, Rev-, Shafting & Prop Arrangement & Details, and Bill of Material

Coast Guard Drawing 160B WLIC 4400-3, Rev-, Propeller

Coast Guard Drawing 160B WLIC 6700-2, Rev-, Transducers Install

Coast Guard Drawing 160B-WLIC 1107-2, Rev D, Pilot House

Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem

Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters

Details, and Bill of Material (BM)

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Coast Guard Technical Publication (TP) 3494, Aug 2008, Technical Manual for Type F.S.E. Seal

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2014, Auxiliary Machine Systems

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2014, Drydocking

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2014, Temporary Services

OTHER REFERENCES

American Bureau of Shipping (ABS) 2, Rule Requirements for Survey After Construction, 2014, Part 7, Appendix Section 10, Guide for Bronze and Stainless Steel Propeller Castings

American Society for Nondestructive Testing (ASNT) SNT-TC-1A, 2013, Recommended Practice for Personal Qualification and Certification in Nondestructive Testing

American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D1709, 2008, Standard Test Methods for Impact Resistance of Plastic Film by the Free-Falling Dart Method

ASTM International (ASTM) D1922, 2008, Standard Test Method for Propagation Tear Resistance of Plastic Film and Thin Sheeting by the Pendulum Method

ASTM International (ASTM) D3951, Reapproved 2010, Standard Practice for Commercial Packaging

ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means

ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component Adhesives (An)

ASTM International (ASTM) D882, 2009, Standard Test Method for Tensile Properties of Thin Plastic Sheeting

ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates

Commercial Item Description (CID) A-A-52624, Nov 2008, Antifreeze, Multi Engine Type, Ethylene Glycol (For Caterpillar applications, use CAT Extended Life Pre-Mix coolant.)

Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Anti-seize, Zinc Dust-Petrolatum

Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth-Insert

Fernstrum Gridcooler Installation and Maintenance Manual, 2013, Form 175

International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing Tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50 m, Inclusive

International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50m, Inclusive

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2008 Edition, Bronze Gate, Globe, Angle and Check Valves

MIL-A-18001, May 2005, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)

MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning

MIL-PRF-16173, 2006, Corrosive Preventive Compound, Solvent Cutback, Cold Application

MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut-Back, Cold-Application

MIL-PRF-24647, Apr 2013, Paint System, Anticorrosive and Antifouling, Ship Hull

MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant

MIL-STD-167-1, Nov 2005, Mechanical Vibrations of Shipboard Equipment (Type I - Environmental and Type II - Internally Excited)

MIL-STD-2191, Nov 1992, Repair Welding, Weld Cladding, Straightening, and Cold Rolling of Main Propulsion Shafting

Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA-PRO-160, Jan 2006, Chapter 16, Cofferdams

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2014 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2015, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2007, Near-White Metal Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of Metals by Waterjetting Prior to Recoating

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning

Consolidated List of Government-furnished Property

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK ITEM
MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST

($/Unit)

6
Y
**Propeller shaft
NSN: 2010-01-076-3907
1 ea.
8
N
Wartsila Type FSE Seal (6” Fully Split). Shaft Seal Assembly
PN: H78011-01

NSN: 2995-01-604-5903

2 ea.
13,350
10
N
Aft Strut Bearing
NSN: 3120-01-051-2510
2 ea.
$683
11
N
Stern Tube Bearing
NSN: 3120-01-046-8511
2 ea.
$1865
12
Y
Propeller (right hand)
NSN: 2010-01-037-7295
1 ea.
$
12
Y
Propeller (left hand)
NSN: 2010-01-037-7597
1 ea.
$
15
N
***Fathometer Transducer, Shallow Water, 50-200 kHz (Airmar Technology SS505)
NSN: 5845-01-470-2500
2 ea.
343.63
18
Y
**Rudder Blade
NSN: 2040-01-560-3314
1 ea.
25,000.00
18
Y
**Rudder stock
NSN: 2040-01-563-7697
1 ea.
9,000.00
18
N
Bearing Sleeve
NSN: 3120-01-560-3316
1 ea.
2.500.00
24
Y
*Transducer Cover Plate
N/A
2 ea.
50.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter

Consolidated List of Critical Inspection Items The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item
Title
1
Hull Plating (Side Scan), Ultrasonic Testing
4
Appendages (U/W), Leak Test
6
Propulsion Shafting, Remove, Inspect, and Reinstall
9
Propulsion Shafting, Optical Or Laser Alignment Check
10
Propulsion Shaft Bearings (External), Renew
11
Propulsion Stern Tube Bearings, Renew
17
Sea Strainers - Duplex (All Sizes), Overhaul
18
Rudder Assembly; Remove, Inspect and Reinstall
25
Lead-Based Paint, 100% Abatement, Perform
30
U/W Body, Preserve (100%)
31
Pilothouse Overhead Steel Plating, Renew

Principal Characteristics

160' WLIC (B-CLASS), Inland Construction Tender

Physical

Length overall
160' 10"
Depth (main deck at side to baseline)
10' 0"
Maximum beam
30' 0"
Height of highest fixed projection
46’ 0” (above keel)
Height of highest projection with antenna mast extended
65’ 0” (above keel)
Frame spacing
1' 0"
Full load draft
5' 0” LCF Draft
Full load displacement
474.73 Long Tons (Fresh water)
Shore tie voltage requirements
N/A

HULL

Hull material
Steel

Machinery

Number of propellers
2
Number of blades per propeller
4
Diameter of propeller
48"
Pitch
44" fixed
RPM
475
Shaft diameter
N/A

Tank Capacities

Fuel tanks
16047 Gal. - Total for all Fuel Tanks
Fresh water tanks
3306 Gal.
Lube oil
170 Gal.

00000_1215_FLT

REC_00000_FLT_Commercial Project @ Contractor’ Facility (1212)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

Coast Guard Drawings

None

Coast Guard Publications

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Other References

None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.

3.6 Local Policy. None.

3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:

3.7.1 SFLC Standard Specification 6310, Requirements for Preservation of Ship Structures.

3.7.1.1 SFLC Std Spec 6310, page C-2, Section C1.5.1. Change from "lead-containing paint as 0.06%" to "lead-containing paint as 0.009%".

3.7.1.2 SFLC Std Spec 6310, page 4, Section 2 References, Group- Other References. Add “The Society for Protective Coatings (SSPC) Paint Application Guide No. 11, 2008, Protecting Edges, Crevices, and Irregular Steel Surfaces by Stripe Coating”

3.7.1.3 SFLC Std Spec 6310, page Appendix C-6, add "Hempel Hempadur Multi-Strength GF 35870" with FED-STD-595 color "Black/Red" under ANTI-ABRASION COATING, ICE BREAKING CAPABLE VESSELS, <235’.

3.7.1.4 Standard Spec 6310, page Appendix A-7, Under "UNDERWATER (U/W) BODY/BOOT-TOP", Add line Column 1: Option for U/W Body and Boot-Top, Steel Hulls, <154', in Salt Water. Column 2: Blank. Column 3: SSPC-SP 10/NACE NO. 2 using grit conforming to MIL-A-22262 / (1.5-3.5) - or - SSPC-SP WJ-2(M)/NACE WJ-2(M). Columns 4 and 5: Same as "U/W Body and Boot-Top, Aluminum Hull, High Speed (>30 knots)".

3.7.2 SFLC Standard Specification 0000 General Requirements.

3.7.2.1 SFLC Std Spec 0000, paragraph 1.3 ‘Acronyms and term definitions’, page 5, “PCL (Paint Containing Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

Vessel Name
Hull #
Work Item #
Work Item Title

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE & TIME
ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION (Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL. HUMID-ITY
DEW PT.
SURFACE
AMBIENT
ΔT

| DP - Surface |

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

Abrasive Manufacturer:

Abrasive Sieve Size:

Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings:

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

Abrasive Manufacturer:

Abrasive Sieve Size:

Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading (mils)

Mean Reading (mils) IAW ASTM DD4417).

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

SOLUBLE SALT CONDUCTIVITY Measurements IAW SSPC-GUIDE 15.

Date
Test Locations
Conductivity (Microsiemens/CM)
Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

Vessel Name
Hull #
Work Item #
Work Item Title
Coating Mfg
Product Name
Batch #
Induction Time
Coating System Sequence (Primer/Touchup/3rd Coat, etc.)

Dry Film Thickness (DFT) Measurements IAW SSPC-PA 2.

SPOT
1
2
3
4
5
AVERAGE VALUE

*BASE METAL READING (BMR) Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Application Method (Airless, Conventional Spray, Rolled)
Average DFT
Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

11000_SideScan_1215_FLT REC_11000_Side_Scan_FLT_160 WLIC ‘B’ Class (ALL) (1211)

WORK ITEM 1: Hull Plating (Side Scan), Ultrasonic Testing

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to perform thickness measurements of underwater (u/w) hull plating by ultrasonic side scan method.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 160B WLIC 0700-001, Rev B, Docking Plan (KENNEBEC) Coast Guard Drawing 160 WLIC 1101-1, Rev C, Shell Pltg Expansion & Framing

COAST GUARD Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Other References

American Society for Nondestructive Testing (ASNT) SNT-TC-1A, 2013, Recommended Practice for Personal Qualification and Certification in Nondestructive Testing

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):

· 3.3 Side scan requirements and procedures.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

· Hull zinc anode system

· Docking blocks.

3.2 Work coordination and preparation. The Contractor shall plan all specified vessel work detailed in this specification package to ensure the side scan survey does not necessitate a work stoppage. The Contractor shall abide by the following guidance, to facilitate the ultrasonic survey:

· Ensure that all u/w body surface preparation and primer coat application tasks are completed within ten days of lifting the vessel.

· Provide a continuous supply of fresh water at .50 gpm within 50 feet of the vessel with standard hose bib fitting.

· Provide 110 VAC electrical power, and scaffolding or other suitable means of access to bring inspection personnel within one foot of all the body surface inspection areas that are five feet above ground level.

· After completion of the hull survey, and authorized hull repairs, resume/complete u/w body preservation process by applying the second coat of the anti-corrosive coating system, and all anti-fouling paint coats.

· Pay close attention to manufacturer’s recommended practices in regards to paint system overcoat time limitations and required degree of surface cleanliness prior to resuming u/w body coating application.

3.3 Side scan requirements and procedures. The Contractor shall ensure the following referring to the Coast Guard drawings listed in Section 2 (References) herein as guidance during the performance of the tasks specified below and submit a CIR.

3.3.1 Testing company and personnel. Provide the services of a qualified ultrasonic testing company, with suitable side scan equipment, to conduct a “Scanning Crawler Automated Test” of the vessel’s u/w hull plating for the presence of metal corrosion and deterioration. Ensure the following:

· All scanning operations are completed by personnel meeting the personnel qualification and certification, as required by contractor process. This contractor developed personnel qualification and certification process must meet, at a minimum, ASNT Recommended Practice No. SNT-TC-1A.

· An SNT Level III Analyst is on site, to oversee the project and evaluate the collected data.

· An SNT Level III or II Analyst is on site, to verify with a hand held gauge all areas on the hull identified as thinner than the specified criteria, in order to expedite all repair procedures.

· Qualified personnel are provided to complete all on-site corrosion inspections.

3.3.2 Coast Guard notification. Accomplish all required tasks within 10 calendar days of the start of the availability.

3.3.2.1 Provide a daily update to the COR on all areas inspected and potential issues or schedule changes.

3.3.2.2 Notify the COR at least 3 days prior to completion for an onsite review of readings and repair areas.

3.3.3 Scanning parameters. Use the following parameters during the course of this inspection:

· Automated scanning resolution shall be set to 0.5” x 0.5”

· Plates where scan data indicating wastage greater than or equal to 25% nominal plate thickness shall be highlighted in “RED” and designated “repair areas”.

· Plates where scan data indicating wastage greater than or equal to 15% to 24% of nominal plate thickness shall be highlighted in “YELLOW”.

· Plates where scan data indicating wastage greater than or equal to 10% to 14% of nominal plate thickness shall be highlighted in DARK GREEN.

· Hand held UT readings shall be taken to verify bad metal areas found with the side scan equipment. All readings shall be provided to the COR and the lowest reading marked on the hull at the bad metal location.

· Areas that are accessible but cannot be reached by the automated scanner shall be scanned with a hand-held meter at a resolution of 2” x 2”. Any repair areas found during the hand scan shall be marked on the ships hull and their approximate positions recorded on the plate drawings and report summary..

3.3.3.1 Any scanning parameter or scope of work changes must be approved by the KO.

3.3.3.2 The echo to echo transducer is not authorized due to inconsistent readings and technical difficulties.

3.3.3.3 There shall be no deviation from the color scheme specified above.

3.3.4 Ensure that the side scan inspection area includes the Port, Starboard, and Transom exterior shell plate below the water line, but shall exclude the following list.

· Areas under and within 6-inches of blocks and side blocks (areas that are accessible 6 inches from blocks and side blocks must be hand scanned.)

· Areas up to 6-inches around any obstacle on the hull including sea suctions, discharges, rudderposts, knuckle, bow stem, stabilizer tubes, and stern tubes, as applicable.

· Any areas blocked by immovable scaffolding or shipyard activity.

3.4 Side scan reports. The Contractor shall submit to the COR a final report within 3 working days after the side scan inspection is completed. A copy of all repair areas shall be clearly marked, in yellow or white, on the provided shell plate drawing(s), and provide a summary document of same areas. Submit two hard copies of the report with two CD’s containing the electronic (raw) data, as part of the CIR submission prior to departing the job site. Ensure the reports include:

· Inspection overview.

· Data sheets for each plate with designated repair areas outlined in blue.

· Mosaic of scanned data overlaid on Coast Guard Drawing 160 WLIC 1101-1.

3.4.1 Photos. Provide digital photos of all designated repair areas.

3.4.2 Electronic files. Ensure CD’s contain a complete copy of the report, interactive data files, and digital pictures. All electronic files shall be compatible with standard USCG workstation operating software. Electronic files format shall be such that the CG has the capability to change the percent of wastage (format conditioning) per plate. Electronic files shall be capable of being opened using MS Word, MS Excel, or PDF software. Digital pictures shall be recorded in JPEG format.

4. NOTES

This section is not applicable to this work item.

11000_0815_FLT

REC_11000_UWHIB_FLT_160B WLIC (802 CGC KENNEBEC) (1211)

WORK ITEM 2: Hull Plating (U/W Body), Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to inspect/survey the vessel’s Under Water (U/W) hull plating, including U/W appendages and coating system.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 160B WLIC 0700-001, Rev B, Docking Plan (KENNEBEC) Coast Guard Drawing 160B WLIC 1101-001, Rev C, Shell Plating Expansion and Longitudinal Framing Coast Guard Drawing 160B WLIC 1103-002, Rev A, Vertical Keel, Skeg, and Bottom Girders Coast Guard Drawing 160B WLIC 1108-002, Rev B, Shaft Struts and Stern Tubes Coast Guard Drawing 160B WLIC 2200-001, Rev A, Steering Machinery Arrangement, Rudder Stock and Fittings

Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Other References

ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means

The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Inspection. The Contractor shall accompany the Underwater Hull Inspection Board (UWHIB) in the performance of the below inspection tasks, as applicable, using the drawings listed in Section 2 (References) as guidance. The Contractor shall provide the following, to facilitate the UWHIB in assessing the condition of the designated U/W hull components and systems:

· A hull repair supervisor and a marker.

· Temporary staging and other necessary equipment, as applicable, for ensuring safe access to all areas of the U/W hull.

NOTES

1. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.

2. Some of the components and/or systems addressed in this work item may not be applicable to all vessel classes.

3.2.1 Hull plating.

3.2.1.1 The Contractor shall inspect the condition of the hull plating (including thruster tunnel plating, as applicable), for the presence of marine growth, deformation, and any evidence of major corrosion or electrolytic action.

3.2.1.2 The Contractor shall inspect the hull and keel areas, report on the condition of butt-welded seams, doubler plates, lap seams, and for any signs of damaged plating or unusual waviness in the plating.

3.2.2 Sea chests and all other cooling system intake components. The Contractor shall inspect all sea chests, tunnels, hull openings, and grates for general appearance, loose, damaged, or missing grates, loose or missing fasteners, condition of sea strainers and lockwire on bolts, marine growth on grating slots, and any obstructions in the openings that might prevent proper suction and discharge of water.

3.2.3 Rudders. The Contractor shall check general condition, condition around the drain plugs, and check for pitting, if any, on the leading and trailing edges.

3.2.4 Propeller and shaft associated components. The Contractor shall inspect the condition of propellers for signs of corrosion, pitting, erosion, fouling, cracks, dings, and nicks by side and blade; inspect fairwaters, rope guards, shafts, and mechanical seals - look for missing screws, physical damage to the blades, pitting, condition of dunce caps, and condition of securing devices.

3.2.5 Transducers. The Contractor shall check general condition for cuts, cracks, corrosion, and surface defects around the openings. Check transducer securing nuts for tightness, and inspect cables for chafing and other damage.

3.2.6 Zinc anodes.

3.2.6.1 The Contractor shall remove all marine growth and oxide coating from all hull, rudder, shaft strut, and sea chest using a light-wire brush.

3.2.6.2 The Contractor shall visually inspect all zinc anodes; check the soundness of mounting strap and stud welds, missing fasteners, and percentage of remaining material.

3.2.7 Coating system inspections. The Contractor shall accomplish the below inspections, in conjunction with the underwater hull inspection conducted by the Underwater Hull Inspection Board (UWHIB). Document the condition found as “Partial - Condition A”, “Partial - Condition B”, “Partial Condition C”, or “100%”, as applicable (see 4.1 (Definitions). Submit a CFR.

NOTE

The following inspections are for determining the existing condition of the coating system for the underwater body surfaces, which are deemed “Critical-coated” surfaces; they must be carried out by a SSPC-QP-1 certified contractor/sub-Contractor or a NACE Inspector – see SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.2.7.1 Visual. Perform a visual inspection of the existing U/W body coating system.

3.2.7.2 Dry film thickness (DFT) measurements. Take total DFT measurements of the U/W body coating system, in accordance with SSPC-PA 2.

4. NOTES

4.1 Definitions.

4.1.1 "Partial – Condition A”: The condition that exists where the substrate is exposed in up to 33% of the entire U/W body.

4.1.2 "Partial - Condition B": The condition that exists where the anticorrosive (AC) undercoating system has incurred damage, but, the u/w body hull substrate is not exposed in any location.

4.1.3 "Partial - Condition C”: The condition that exists where damage is confined to the antifoulant (AF) topcoating; the epoxy undercoating system is not exposed in any location.

4.1.4 "100%”: The condition that exists where more than 33% of the U/W body hull substrate is exposed.

4.2 UWHIB convention. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.

11010_1013_FLT

REC_11010_UT_FLT_160’ WLIC ‘B’ Class (ALL) (0911) WORK ITEM 3: Hull Plating (Freeboard), Ultrasonic Testing

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to conduct ultrasonic testing (UT) of freeboard hull plating.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 160 WLIC 1101-001, Rev C, Shell Pltg Expansion & Framing Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Other References

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 UT measurements. The Contractor shall perform a total of 250 UT measurements of freeboard hull surfaces, in locations designated by the Coast Guard Inspector, using Coast Guard Drawing 160 WLIC 1101-001 for guidance, in accordance with SFLC Std Spec 0740, Appendix C. Mark up a copy of Coast Guard Drawing 160 WLIC 1101-001 to show all locations selected for measurement and record all measurements in Table 1 (UT Measurements Summary Sheet - Port/Stbd Shell) provided at the end of this item. Submit CFR, to also include the marked up drawing and completed Table 1.

Table 1 - UT MEASUREMENTS SUMMARY SHEET PORT/STBD SHELL

SHOT #
STRAKE #
FWD/MID/AFT
ORIG PL
MEASURED PL
PERCENT
PLATE #
TOP/MID/BOT
THICKNESS
THICKNESS
WASTAGE

4. NOTES

This section is not applicable to this work item.

11400_0415_FLT

REC_11400_UWAppndgs_FLT_160B WLIC (802 CGC KENNEBEC) (1014) WORK ITEM 4: Appendages (U/W), Leak Test

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to perform leak test of the U/W appendages.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 160B WLIC 0700-001, Rev B, Docking Plan Coast Guard Drawing 160B WLIC 1101-001, Rev C, Shell Plating Expansion and Longitudinal Framing Coast Guard Drawing 160B WLIC 1103-002, Rev A, Vertical Keel, Skeg, and Bottom Girders Coast Guard Drawing 160B WLIC 1108-002, Rev B, Shaft Struts and Stern Tubes Coast Guard Drawing 160B WLIC 2200-001, Rev A, Steering Machinery Arrangement, Rudder Stock and Fittings

Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Other References

ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component Adhesives (An)

MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph:

· 3.2 Leak test particulars.

· 3.4 Appendage air test.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work.