Questions and Answers

Solicitation #HSCG85-16-Q-P45G56

USCGC SPAR (WLB 206) UNPLANNED DOCKSIDE REPAIRS FY2016

Q1.

We are looking at page 8 of 25 in the Combined Synopsis/Solicitation, Transportation To and From Vessel, we assume the departing airport is ISC CG Kodiak, if we are going to Seattle, where would the C-130 land? Sea-Tac, Boeing Field, McChord AFB?

Answer: The transportation will be from Kodiak AK to Anchorage AK.

Q2.

All the qualified companies for this solicitation will require 7-8 weeks, basically around 50-55 days, the solicitation allows for less than half the time at 23 Days.

Answer: The period of Performance has been changed.

The Original POP is 02 May 2016 Thru 25 May 2016. New POP is 03 May 2016 thru 25 May 2016.