ATTACHMENT_3_-_Continuation_of_Combined_Synopsis-Solicitation.doc
DOC document 347 KB Posted
- Attached to
- USCGC BERTHOLF (WMSL 750) DRY DOCK REPAIRS FY14
- Solicitation number
- HSCG85-13-R-P45N36
About this file
Revised ATTACHMENT 3 - Continuation of Combined Synopsis/Solicitation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30-0003(BERTHOLF).pdf | ||
| Page_2_-Amendment_No._0003.doc | DOC document | |
| Amendment_0002.doc | DOC document | |
| Amendment_0001.pdf | ||
| ATTACHMENT_1_-_Specifications.pdf | ||
| ATTACHMENT_6_-_Notice_of_Filing_Protests.pdf | ||
| ATTACHMENT_3_-_Continuation_of_Combined_Synopsis-Solicitation.doc | DOC document | |
| ATTACHMENT_4_-_Request_for_Clarification.doc | DOC document | |
| ATTACHMENT_2_-_Schedule_of_Supplies-Services.doc | DOC document | |
| ATTACHMENT_5_-_Past_Performance_Questionnaire.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 3
Amendment 0002
CONTINUATION OF COMBINED SYNOPSIS/SOLICITATION
CONTRACT CLAUSES
FAR 52.212-4 CONTRACT TERMS AND CONDITIONS – COMMERCIAL ITEMS (JUL 2013)
ADDENDUM
(1) FAR 52.204-1 APPROVAL OF CONTRACT (DEC 1989)
This contract is subject to the written approval of the Branch Chief, CPD, C&P2 and shall not be binding until so approved.
(2) FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address: http://www.arnet.gov/far/index.html
| FAR 52.211-15 |
| Defense Priority and Allocation Requirements (APR 2008) DO N5 Rating |
| FAR 52.215-21 |
| Requirements for Certified Cost or Pricing Data and Other Than Certified Cost or Pricing Data – Modifications (OCT 2010) |
| FAR 52.223-3 |
| Hazardous Material Identification and Material Safety Data (JAN 1997) Alternate I (JUL 1995) |
| FAR 52.225-25 |
| Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran – Representation and Certification (Dec 2012) |
| FAR 52.223-12 |
| Refrigeration Equipment and Air Conditioners (MAY 1995) |
| FAR 52.246-2 |
| Inspection of Supplies – Fixed Price (AUG 1996) |
| FAR 52.246-4 |
| Inspection of Services – Fixed Price (AUG 1996) |
| FAR 52.232-18 |
| Availability of Funds (APR 1984) |
| FAR 52.242-2 |
| Production Progress Reports (APR 1991) |
| FAR 52.242-15 |
| Stop-Work Order (AUG 1989) |
| FAR 52.242-17 |
| Government Delay of Work (APR 1984) |
| FAR 52.245-1 |
| Government Property (APR 2012) , Alternate I (April 2012) |
| FAR 52.245-9 |
| Use and Charges (APR 2012) |
| FAR 52.246-16 |
| Responsibility for Supplies (APR 1984) |
| FAR 52.247-55 |
| F.O.B. Point for Delivery of Government Furnished Property (JUN 2003) |
| HSAR 3052.205-70 |
| Advertisements, Publicizing Awards, and Releases (SEP 2012) |
| HSAR 3052.211-70 |
| Index for Specifications (DEC 2003) |
| HSAR 3052.212-70 |
| Contract Terms and Conditions Applicable to DHS Acquisition of Commercial Items (SEP 2012) |
| HSAR 3052.217-90 |
| Delivery and Shifting of Vessel (DEC 2003) |
| HSAR 3052.217-91 |
| Performance (DEC 2003) |
| HSAR 3052.217-92 |
| Inspection and Manner of Doing Work (DEC 2003) |
| HSAR 3052.217-93 |
| Subcontracts (DEC 2003) |
| HSAR 3052.217-94 |
| Lay Days (DEC 2003) |
| HSAR 3052.217-95 |
| Liability and Insurance (DEC 2003) |
| HSAR 3052.217-96 |
| Title (DEC 2003) |
| HSAR 3052.217-97 |
| Discharge of liens (DEC 2003) |
| HSAR 3052.217-98 |
| Delays (DEC 2003) |
| HSAR 3052.217-99 |
| Department of Labor Safety and Health Regulations for Ship Repair (DEC 2003) |
| HSAR 3052.217-100 |
| Guarantee (JUN 2006) |
| HSAR 3052.222-70 |
| Strikes or Picketing Affecting Timely Completion of the Contract Work (DEC 2003) |
| HSAR 3052.222-71 |
| Strikes or Picketing Affecting Access to a DHS Facility (DEC 2003) |
| HSAR 3052.223-70 |
| Removal or Disposal of Hazardous Substances—Applicable Licenses and Permits (JUN 2006) (“…30 days…”) |
| HSAR 3052.223-90 |
| Accident and Fire Reporting (DEC 2003) |
| HSAR 3052.242-72 |
| Contracting Officer’s Technical Representative (DEC 2003) |
(3) HSAR 3052.223-70 REMOVAL OR DISPOSAL OF HAZARDOUS SUBSTANCES – APPLICABLE LICENSES AND PERMITS (JUN 2006)
The Contractor shall have all licenses and permits required by Federal, state, and local laws to perform hazardous substance(s) removal or disposal services. If the Contractor does not currently possess these documents, it shall obtain all requisite licenses and permits within [“30”] days after date of award. The Contractor shall provide evidence of said documents to the Contracting Officer or designated Government representative prior to commencement of work under the contract.
(End of clause)
(4) HAZARDOUS WASTE
Contractors performing dockside ship repair work at Government facilities are required to comply with FAR 52.223-3, Hazardous Material Identification and Material Safety Data (JAN 1997) Alt I, the U.S. Coast Guard shipboard hazardous waste policy, as prescribed in COMDINST M16478.1B, and MLCA standard specifications. Disposal of all hazardous wastes shall be performed by the Contractor and the Contractor shall meet all federal and state requirements. The Contractor is also required to submit an acceptable hazardous waste management plan to the Port Engineer at the Arrival Conference. The plan will be reviewed by the facility hazardous waste manager. An acceptable plan must address, at a minimum, the following requirements:
(a) EPA and local authority hazardous waste generator ID numbers or registration of the Contractors, his transporters, and disposal facilities (TSDFs);
(b) An inventory of all hazardous chemicals, compounds and other agents brought aboard the facility accompanied by their respective Material Safety Data Sheets;
(c) A list of all anticipated hazardous wastes to be generated and a federal/state/local regulation cross reference list for those wastes;
(d) Waste collection and containment procedures;
(e) A hazardous material spill and cleanup plan including tools and materials that will be on hand and readily available to facility containment and cleanup;
(f) Training certification for the Contractor's hazardous waste manager.
The Contractor shall note the local environmental regulations in Boston, and for Boston Harbor, are more stringent than in many jurisdictions. As with all environmental regulations, it is the Contractor's responsibility to research, prepare for, and comply with, the local and state regulations.
All waste generated under the performance of this contract shall be disposed under ISC Boston's EPA hazardous waste generator ID number. The Contractor shall notify the Contracting Officer's Technical Representative (COTR) 24 hours prior to any waste removals, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays). All hazardous waste manifests shall be reviewed and signed by ISC Boston hazardous waste personnel. The point of contact for environmental issues is the Environmental Protection Specialist at ISC Boston (617)223-3387.
(5) VOLATILE ORGANIC COMPOUNDS (VOC) REGULATIONS
(a) Contractors are required to comply with federal, state and local VOC compliance laws and regulations. Among other requirements, certain Contractors may also be required to operate pursuant to a Title V permit. The need for such a permit will depend on the provisions of the applicable state’s “State Implementation Plan” (SIP) and the type/quantity of the Contractor’s regulated emissions, including VOCs. Certain SIPs may also mandate certain Contractors to operate under the terms of a compliance plan intended to reduce VOC emissions.
(b) Contractors, therefore, must submit the following to the designated Port Engineer not later than two weeks after contract award:
1) Copies of any federal, state or local permits required and applicable to the use or application of VOCs at Contractor’s facility or offsite work places;
2) Copies of any compliance plans required and applicable to the use or application of VOCs at Contractor’s facility or offsite work places.
(c) If no federal, state or local permits or compliance plans are required and applicable to the use or application of VOCs at Contractor’s facility or offsite workplaces, then Contractor shall submit to the designated Port Engineer a letter, notarized under oath, that such documents are not required.
(d) Contractors will submit the following to the designated Port
Engineer not later than two weeks after contract award: Data Sheets (MSDS) documents, certificates, specifications or any other manufacturing data verifying the VOC ratings of paints to be applied to the Cutter in accordance with MLCA Standard Spec 63000N, Section 5.3.1.
(6) TELEPHONE CHARGE
The Commanding Officer of the Cutter will pay all toll charges and applicable taxes and surcharges for long-distance telephone calls placed by ship’s personnel. All other charges shall be borne by the Contractor.
(7) ACCESSIBILITY OF CONTRACTOR'S FACILITY
The Contractor shall provide a facility accessible from a navigable waterway at which a ship of the characteristics described in the attached specification can, using its own propulsion, safely arrive, lie afloat and depart at all states of the tide and at any time day or night. The facility and its approaches shall have a minimum water depth of _22__ feet and a minimum vertical clearance of _139_ feet.
(8)
SECURITY REQUIREMENTS:
A. For each affected Coast Guard Facility, the Contractor shall provide a list of all on-site personnel, including sub-contractors (including second and third tier subcontractors) and suppliers, to the contracting officer. The contractor shall update this list when changes occur. Contractor personnel not listed may be denied access to the Coast Guard Facility. Contractor personnel will be restricted to designated working areas. Any personnel violating this policy may lose access to the Coast Guard Facility. Contractor personnel shall have photo identification at all times while working on Coast Guard facilities.
B. Contractor and delivery personnel may be required to present personal photo identification to gain access to a Coast Guard installation. If identification does not indicate United States citizenship, Coast Guard Security may require proof of the legal right to work in the United States. Contractor and delivery personnel also may be subjected to an immigration status and outstanding criminal warrants check.
C. Contractors shall provide the Contracting Officer’s Representative with 24 hours of advance notice of every delivery to the site (e.g. concrete, lumber, parts, etc) and provide the company name, delivery person. And phone number of the firm(s) making deliveries. All vehicle access to Government property requires vehicle registration and proof of liability insurance. Otherwise access to the Coast Guard facility may be denied.
(9) INSURANCE REQUIREMENTS
A. The contractor shall, at its own expense, procure and maintain the following insurance with respect to performance under the contract. In accordance with HSAR 3052.228-70, Insurance (DEC 2003), the Contractor shall furnish the Contracting Officer with proof of insurance for the duration of the contract, including:
1. Ship Repairer's legal Liability insurance to insure the risks described in HSAR 3052.217-95, Liability and Insurance (DEC 2003), in the amount of $500,000 per occurrence.
2. Comprehensive General Liability insurance to insure the risks described in HSAR 3052.217-95 Liability and Insurance (DEC 2003) in the amount of $500,000 on account of any one accident or occurrence with respect to each vessel, boat and barge upon which work is to be performed under this solicitation and the contract resulting there from.
3. Full insurance coverage in accordance with the State Workman’s Compensation law (or its equivalent) for all places of performance under this contract.
4. Full insurance coverage in accordance with the United States Longshore and Harbor Workers’ Compensation Act.
B. As evidence that he has obtained the insurance specified in this schedule, the contractor shall furnish the contracting officer with a certificate or certificates executed by an agent of the insurer authorized to execute such certificated. Such certificated shall be furnished before commencement of work. Each certificate shall state that (NAME OF INSURER) has insured (NAME OF CONTRACTOR), in accordance with the Liability and Insurance clause and the Insurance Requirements clause contained herein. Each certificate shall set forth that each policy of insurance represented thereby will expire on (DATE) and that each such policy contains the following clause:
“It is agreed that in the event of cancellation, or any material change in the policy adversely affecting the interest of the Government in the insurance, thirty (30) days prior written notice will be given to the Contracting Officer.”
C. An Offeror who proposes to self-insure for and of the risks set forth in the Liability and Insurance clause and in the Insurance Requirements clause contained herein shall submit satisfactory evidence to permit the Contracting Officer to determine that the offer’s assets are sufficient for the risks set forth in such clauses. The offeror shall submit with his proposal two (2) certified copies of documents listing his assets and liabilities and such other information as deemed necessary by the offeror or as required by the Contracting Officer. For approval of self-insurance under the State Workmen’s Compensation Law and the United States Longshore and harbor Worker’s Compensation Act, evidence of qualifications as a self-insurer under the applicable compensation statue must be furnished to the Contracting Officer.
The insurance certificate must provide the name of the US Coast Guard vessel and the contract and/or solicitation number as specifically insured.
(10) ACCESS TO VESSEL
(a) A reasonable number of officers, employees, and associates of the Government, or other Prime Contractors with the Government, and their subcontractors, shall, as authorized by the Contracting Officer, have, at all reasonable times, admission to the plant, and access to vessel(s) to perform and fulfill their respective obligations to the Government on a noninterference basis.
The Contractor shall make reasonable arrangements with the Government or Contractors of the Government, as shall have been identified and authorized by the Contracting Officer, to be given admission to the Contractor's facilities and access to the vessel(s) and to office space, work areas, storage or shop areas, or other facilities and services, necessary for the performance of their respective responsibilities and reasonable to their performance. All such above personnel shall be required to comply with all Contractor rules and regulations governing personnel at its shipyard, including those relative to safety and security.
(b) The Contractor further agrees, as authorized by the Contracting Officer, to afford to a reasonable number of officers, employees, and associates of bidders on other contemplated work, the same privileges of admission to the Contractor's plant and access to the vessel(s) on a noninterference basis subject to all Contractor rules and regulations governing personnel in its shipyard, including those relative to safety and security.
(11) INDEMNIFICATION FOR ACCESS TO VESSELS
Notwithstanding any provision in the "Access to Vessels" clause, or any other clause of the contract, the Contractor agrees to allow officers, employees, and associates of the Government, or other Prime Contractors with the Government and their subcontractors, and officers, employees, and associates of quoters on other contemplated work, admission to the Contractor's facilities and access to the vessel without any further request for indemnification from any party, which has not been previously included in the contract price.
(12) INSPECTIONS
Except as specified elsewhere, the U.S. Coast Guard shall rely on the Contractor to accomplish all inspection and testing needed to ensure that the work conforms to contract quality requirements.
Records of all inspection work by the Contractor shall be kept complete and available to the Government during the term of this contract and for such longer period as may be specified elsewhere in this contract.
The name and telephone number of the U.S. Coast Guard Inspector will be provided after the award of a contract resulting from this solicitation.
(13) GROWTH WORK
(a) The Contractor shall not perform growth work without the Contracting Officer's authorization. Growth work is work within the scope of the contract, which has not been previously priced as a pre-priced CLIN. The Contracting Officer reserves the right to contract for growth work on the basis of a negotiated, firm, fixed price, when it is in the best interest of the Government. If a firm-fixed price contract is awarded, and during the performance period a repair within scope is identified but the Contracting Officer and Contractor are unable to agree on the cost of the work, a bilateral modification may be incorporated into the contract using a Time and Materials modification for this specific repair. In this situation, FAR 52.212-4, Alternate I, will be incorporated.
(b) The Contractor shall furnish a price breakdown directly to the Contracting Officer, itemized as required by the Contracting Officer, of any proposal submitted for a contract modification. Unless otherwise directed, the breakdown shall be submitted on an SFLC 002 proposal form provided at the arrival conference permitting an analysis of all materials, labor, equipment, subcontract, overhead costs, and profit covering all work involved in the change/modification whether such work was deleted, added or changed. Any amount claimed for subcontracts shall be supported by a separate, similar price breakdown. If the proposal includes a request for a time extension, justification shall be furnished with the proposal.
(14) COMPOSITE LABOR RATE: The composite labor rate offered shall be the sole labor hour rate used to price the Prime Contractor's direct labor hours for contract changes, i.e. growth work. The Contractor shall not receive any compensation in addition to this rate for the Prime Contractor's direct labor associated with such changes under this contract.
(a) The composite labor hour rate shall represent total compensation for the following:
(1) direct labor wages and salaries;
(2) all employee benefits including, but not limited to, paid leave, supplemental pay, insurance, retirement, savings, and legally required benefits;
(3) other direct costs associated with transit time, delay, disruption, expendable supplies, and equipment;
(4) all indirect costs such as overhead and general and administrative expense;
(5) any port or association fees, rents, or other levies;
(6) profit (fee); and
(7) all direct and indirect costs and profit associated with the following support functions:
Supervision and Management Planning and Estimating
Material Handling Housekeeping
Engineering Transportation/Drivers
Quality Assurance Contract Administration
Security Testing
(b) The composite labor hour rate will be applied to production labor hours only. Production labor hours include only those hours necessary and reasonable to perform direct production functions and do not include the hours expended on the support functions listed above. This exclusion of support function hours applies whether such support functions are normally charged directly or indirectly by the Contractor's accounting system. These support functions are to be priced into the composite labor rate quoted and shall not be separately compensated.
(c) The Quantity of Composite Labor hours indicated in the Schedule of Supplies/Services, is only an estimate and is an Optional Item pursuant to this solicitation. The Estimated Quantity represents the Government’s best estimate of the total number of additional hours that may be required throughout the contract. The Government may elect to exceed this value at the prices stated in the schedule and its discretion during performance of the contract. The inclusion of this item does not obligate the Government to exercise the item nor entitle the Contractor to compensation if not exercised.
(15) DISCOVERIES AND CHANGES TO CONTRACT
Condition Found Report, Change Orders and Quick Chits will be transmitted electronically by using email. The bullets below display the process of how these documents are to be followed for the duration of the contract performance period:
(a) Condition Found Report (CFR)- All readings and inspections are to be taken within 24 hours after the machinery or system is opened. All reports of reading and inspections required by the specifications shall be submitted to the COR in writing using a “Condition Found Report (CFR)” form, within 24 hours after the readings and/or inspections are made.
Promptness in taking and reporting readings is particularly importance for underbody work items such as shaft bearing or rudder bearing clearances. Often during the progress of a work item, conditions are discovered by the contractor which are considered abnormal for reasons of safety, expected reliability, health, or habitability. These conditions must be brought to the attention of the Coast Guard using a CFR. Details provided by the Contractor in a CFR are important because the CFR may result in a contract change. To spend the contract progress, the Contractor should include in his/her CFR the following details as a minimum:
(i) A sequential number
(ii) The contract item which the “CFR” relates to.
(iii) A clear statement, definition, and description of the condition found, including but not limited to frame numbers, part numbers, materials and dimensions as appropriate.
(iv) A proposed or recommended repair to correct the defective condition.
(v) Indicate whether the report requires Coast Guard action, or if it is provided “for Info” only. If action is required, indicate the response time require by the Coast Guard and whether or not a contract extension would be needed if the additional work is authorized.
(vi) A space on the form for the Coast Guard to make comments.
(vii) All CFR’s will be dated, submitted, and signed by a representative of the Contractor.
Contracting Officer’s Representative (COR) will respond to the Contractor’s within 24 hours of receiving a Condition Found Report. A copy of ALL condition Found Reports shall be retained in the Cutter’s file.
(b) Change Request (CR) Process will occur when the contemplated change is above $3,000.00 in the following order:
1. Condition Found Report – Generated by the Contractor and provided to COR.
2. Condition Report Reply – Generated by the COR and provide to Contractor.
3. Change Request – CR and IGE are generated by the COR and entered in the Contract Workbook. COR will assign the Change Request number.
4. COR provides copy of Change Request to the Contractor.
5. Contractor’s Proposal – provided to the KO for the identified tasking on CR.
6. Negotiations – if needed, take place to establish pricing.
7. Approved Change Request – forwarded to Contractor and COR by the KO.
8. Modification to Contract – The KS/KO will issue a modification covering all CRs.
Change Request must be submitted by the COR to the Contractor within 24 hours after responding to the CFR. Contractor must submit proposal to the Contracting Officer within 72 hours of receipt of the Change Request.
(c) Quick Chit (QC) Process will occur when the contemplated change is below $3,000.00 in the following order:
1. Condition Found Report – Generated by the Contractor and provided to COR.
2. Condition Report Reply – Generated by the COR and provide to Contractor.
3. Quick Chit – COR will go over the scope of work with the contractor and request to submit a proposal for the change.
4. Contractor’s Proposal – provided to the COR within 24 hours..
5. Negotiations – COR and Contractor’s representative will negotiate to establish pricing for the change. Once COR and Contractor agree on scope of work and associated costs, COR will assign a Quick Chit number and fill in agreed price.
6. Approved Change Request – COR to forward (via e-mail or fax) copies of agreed settlement to Contractor, and enter all information into Contract Workbook.
7. Modification to Contract – The KS/KO will issue a modification covering all QCs.
A modification will be issued to incorporate and implement all changes made by change orders and quick chits.
(16) CONTRACT DEFICIENCY REPORT
The Contracting Officer or Contracting Officer’s Representative (COR) may issue a Contract Deficiency Report (CDR), SFLC Form 005. The Contractor shall respond in writing within 24 hours of receipt, unless otherwise approved by the Contracting Officer, to the COR. The COR will comment on the Contractor's response and will forward the Deficiency Report and comments to the Contracting Officer, with a copy to the Contractor and Availability Program Manager. The Contracting Officer will render a final determination and provide it to the Contractor and COR in writing.
(17) OPTIONAL ITEMS:
Optional Items may be awarded if inspection reports reveal the necessity for activation or when funds are made available, at the price quoted in the Contractor’s proposal and without any other consideration whatsoever. However, after midnight on January 6, 2014, the contractor shall have the right to refuse to accept the award of such Optional Items.
Such award refusals shall bar neither the Government not the Contractor from subsequently negotiating with each other for performance of the work embodied in the refused Optional Item/s.
Optional items shall be awarded by written notice to the Contractor through issuance of a contract modification (SF-30). Transmission of the SF-30 notice of exercise to the contractor via FAX is authorized; for purposes of determining the exact tome of FAX transmission, the time, date, and year of transmission automatically applied to the FAX and/or FAX transmission record of transmission at the contracting office shall govern. Evaluation of the Optional items will not obligate the Government.
(18) FAR 52.217-7 Option for Increased Quantity—Separately Priced Line Item (Mar 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within fourteen (14) days after Period of Performance commences. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
(End of Clause)
(19) MAINTAINING, REPORTING, AND DISPOSING OF GOVERNMENT PROPERTY IN THE PERFORMANCE OF A SHIP REPAIR CONTRACT
1. The Government Property Clause incorporated by reference delineates the Contractor's overall responsibility when taking possession of government property in performance of a contract. In performance of this contract the Contractor will be required to properly identify, track and control property within its possession. This includes, a) property furnished by the government (GFP) to the Contractor in conjunction with specific CLIN Items. These items and their values are listed in the specification, b) property that is pre-existing in a location that during the course of performance will be replaced or renewed.
2. The items listed in the specification, as government furnished property will be provided in the quantities designated. Government furnished property may be provided in person by an official Coast Guard employee, shipment via commercial carrier, etc. The Contractor shall sign for all government furnished property using either a DD Form 1149, entitled, “Requisition and Invoice/Shipping Document” or a DD Form 1348, entitled, “Issue Release/Receipt Document”. A copy of the DD 1149 or DD 1348 must be sent within 48 hours of receipt of property, to the designated Government Property Administrator. The name of the individual assigned as Property Administrator will be furnished to the Contractor at time of award. The Contractor shall not take receipt of property that is not listed in the specification, has not been previously identified as becoming part of the contract (via contract modification) or which otherwise cannot be identified. Such irregularities shall be immediately reported to the Property Administrator.
3. The Contractor shall complete the report provided herein, entitled, “Government Property Report”. This report is intended as a living document whereby relevant fields shall be filled in, maintained and kept current at all times. All property described in paragraph 1 (a and b) above shall be reported on the report. At contract completion the Contractor and the Property Administrator shall ensure that all fields are appropriately completed. A signature block is provided at the end of the report for both parties to attest to the report's accuracy and completeness. The Government Property Report shall clearly delineate the complete track that all Government property took over the course of the contract. This completed report must accompany the Contractor's final invoice. Final payment may be delayed, without penalty of interest, until such time as the report is received. A separate copy of the completed report and any final DD 1149s or DD 1348s executed, as a result of carrying out disposition instructions shall be provided to the Property Administrator.
4. Pursuant to the Government Property Clause the authority to render disposition instructions of Government property associated with this contract is delegated to the Property Administrator. The Contractor shall comply with all instructions in the contract for the return of government property to the Coast Guard. This includes government property taken off the vessel (shafts, propellers, etc.), government property returned to the vessel (special tools, etc.) or surplus government property not used during performance of the contract.
(20) CONTRACTING OFFICER’S AUTHORITY
No oral or written statement of any person other than the Contracting Officer will in any manner or degree modify or otherwise affect the terms of this contract. The Contracting Officer is the only person authorized to approve changes in any of the requirements under this contract, and, notwithstanding any provisions contained elsewhere in this contract, said authority remains solely with the Contracting Officer. In the event the Contractor effects any such change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in cost incurred as a result thereof.
(21) CONTRACTOR PERFORMANCE EVALUATION
The U.S. Coast Guard Surface Forces Logistic Center (SFLC) will monitor and evaluate the successful offeror’s past performance of this contract and prepare a Contractor Performance Assessment Report (CPAR) in accordance with FAR Part 42.15. All information contained in this assessment may be used, within the limitations of FAR 42.15, by the government for future source selections and in accordance with FAR 15.304, when past performance is an evaluation factor for award.
(b) NOTIFICATION: Upon completion of the contract, the contractor will be notified of the assessment. The contractor will be allowed 30 days to respond to the SLFC’s assessment of its performance entered into CPARS. The contractor’s response, if any, will be made part of the CPAR system at https://www.cpars.csd.disa.mil.
(c) INFORMATION: Information included in the CPAR may include, but is not limited to, the contractor’s record of conforming to contract requirements and to standards of good workmanship; the contractor’s record of forecasting and controlling costs; the contractor’s adherence to contract schedules, including the administrative aspects of performance; the contractor’s history of reasonable and cooperative behavior and commitment to customer satisfaction; the contractor’s record of integrity and business ethics, and generally, the contractor’s business-like concern for the interest of the customer.
(d) RELEASE OF DATA: CPARS information is considered business sensitive and will not be released except: (1) to other Federal procurement activities which request it; (2) when SFLC must release pursuant to a Freedom of Information Act (FOIA) request; or (3) when prior written consent is requested and obtained from the contractor.
(22) METHOD OF PAYMENT AND INVOICING INSTRUCTIONS
INVOICE SUBMISSION PROCESS:
1. The Contractor shall prepare a proper invoice IAW FAR clause 52.212-4, and in addition to the information required by FAR 52.212-4(g) as cited in the contract. All invoices shall be itemized to correlate to the Schedule of Supplies/Services as follows:
(A) The Government will make payment under this contract based on a percentage or stage of completion. The Contractor may invoice each contract line item (CLIN) as work progresses.
(B) The amount invoiced shall be calculated based on those prices stipulated in the contract Schedule of Supplies/Services.
(C) A CLIN may not be invoiced until the percentage complete reaches 25 percent. Future invoices for that CLIN have no limitation as to the percentage of completion required before invoicing. (The minimum percentage of completion (25%) to be reached prior to billing each CLIN may be waived by the Contracting Officer on a case by case basis for large dollar CLINS.)
(D) In addition to the information required by FAR 52.212-4 (g) Invoices shall include:
1) Contract Number, Delivery Order/Task Order Number, DOC Number
2) Name and Address of the Contractor
3) Invoice Number and Invoice Date
4) DUNS Number - The Data Universal Numbering System (DUNS) number is the primary identifier in Central Contractor Registration (CCR), (see FAR 52.232-33, Payment by Electronic Funds Transfer – Central Contractor Registration (OCT 2003)). Contractors are
5) located and identified in CCR by their DUNS number. Therefore, to facilitate payment, the DUNS number shall be recorded on every invoice submitted to the U.S. Coast Guard.
6) Name of the Contract Specialist and/or Contracting Officer
7) Invoice Routing Code (IRC): SFLC -2
8) Indicate Small Business Status
9) Indicate if Final Invoice: The Contractor’s final invoice submitted under the contract must be marked as follows: (THIS INVOICE CONSTITUTES THE FINAL INVOICE – UPON PAYMENT OF THIS INVOICE NO OTHER MONIES ARE DUE UNDER CONTRACT NUMBER (to be assigned upon contract award).
10) The percentage of completion for each CLIN identified;
11) Vessel name
12) The overall percentage and dollar amount previously billed, currently billed and unbilled,
13) Shipping and Payment Terms
14) Name, title, phone number, and mailing address of person to be notified in the event of a defective invoice.
All information must be included in an invoice for it to constitute a proper invoice. All improper invoices will be rejected which could delay payment.
2. The Contractor shall forward invoices via email to LT Kevin Thomas, the Contracting Officer’s Representative (COR) at Kevin.M.Thomas@uscg.mil or in person to the COR.
3. The COR shall review and verify invoice(s), sign and return the invoice to the Contractor.
4. The Contractor shall complete the Contractor Invoice Submission Form (sample attached).
5. The Contractor shall submit the Contractor Invoice Submission Form, a PDF file of the invoice, and any necessary documents for supplies or services via the U.S. Coast Guard Finance Center website at:
http://www.fincen.uscg.mil/centralinv/central_inv_contr.cfm Contractor Invoice Submission Form Directions: Please complete as much information as possible. All blocks in red text are required entries.
Note: Web-Invoices are accepted only for Coast Guard Contracts over the Simplified Acquisition Threshold (Document Type 24).
THIS WEB FORM IS NOT AN OFFICIAL INVOICE. THE OFFICIAL INVOICE MUST BE ATTACHED
Invoice Information Invoice Routing Code: (help) Invoice Number: (help) Contract Number: (help) Invoice Date: (help) BPA Number: (help) Invoice Amount: (help) Delivery/Task Order Number: (help) Discount Terms: %
Discount Days: Net Days: (help)
Company Information Attachment of Official Invoice Company Name: (help) DUNS: Plus 4: (help) Point of Contact Name: (help) Point of Contact Email: (help) Phone: (help) Fax: (help)
Please verify your entry on the next page. Attach invoice and any supporting documentation after verification.
· Attachment must be a single PDF file no larger than 3 MB. Grey-scale PDFs are not compatible. This will be our official invoice. Supporting documentation must be combined in the single PDF file or submitted to your contracting office separately via email.
· Need help creating a PDF file? Click here for instructions.
Bottom of Form
6. The Contractor must select the correct Invoice Routing Code for timely invoice processing. The Invoice Routing Code for this contract is SFLC-2.
7. Visit the U.S. Coast Guard Finance Center Website for instructions regarding invoice attachments. http://www.fincen.uscg.mil/centralinv/central_inv_contr.cfm
8. A copy of the invoice and any supporting documentation shall also be e-mailed to the following individual(s):
Wilma.L.Estrada@uscg.mil Additional work verbally agreed to by the parties that has not yet been incorporated into the contract by modification shall not be included in an invoice. Payments will not be made for any work to which a modification has not been properly executed. Invoices submitted for payment that includes such a request will be reduced by the unmodified amount.
NOTE: 10% OF THE TOTAL CONTRACT PRICE WILL BE WITHHELD UNTIL ALL DELIVERABLES, REQUIRED BY THE CONTRACT, ARE RECEIVED AND ACCEPTED.
FURTHER CONSIDERATIONS WITH INVOICING:
In accordance with the Prompt Payment Act, for the purposes of determining a payment due date and the date on which interest will begin to accrue if a payment is late, a proper invoice shall be deemed to have been received:
(1) On the later of:
(i) For invoices that are mailed the date a proper invoice is actually received by the designated billing office and annotates the invoice with date of receipt at the time of receipt.
(ii) For invoices electronically transmitted by the contractor via web based submission, the date a transmission is received by the designated billing office, and receipt confirmation is provided to the designated recipient; or
(ii) The seventh day after the date on which the property is actually delivered or performance of the services is actually completed; unless—
a) The agency has actually accepted the property or services before the seventh day in which case the acceptance date shall substitute for the seventh day after the delivery date; or
b) A longer acceptance period is specified in the contract, in which case the date of actual acceptance or the date on which such longer acceptance period ends shall substitute for the seventh day after the delivery date;
(2) On the date placed on the invoice by the contractor, when the agency fails to annotate the invoice with date of receipt of the invoice at the time of receipt (such invoice must be a proper invoice); or
(3) On the date of delivery, when the contract specifies that the delivery ticket may serve as an invoice.
(4) Web based submission by the contractor and receipt confirmation does not reflect Government review or acceptance of the invoice.
(5) For inquiries and payment status please visit https://fincen.uscg.mil/secure/payment.htm All payments for partial performance rendered by the Government under this contract are based on the assumption that the Contractor will, in good faith, execute and honor all payment terms entered into between it, the Prime Contractor, and any subcontractor thereof in the performance of this contract. The Contractor hereby acknowledges the Government’s right to reduce or suspend progress payments based on non-payment in accordance with any payment terms of the subcontract agreement.
Any amount deemed not payable will be deducted from the Contractor’s invoice. Deducted amounts may be resubmitted on the next invoice for reconsideration.
PROGRESS PAYMENTS:
A. The Contractor may invoice requesting progress payments without discount, other than any prompt payment discount offered, not more frequently than every two weeks.
B. The invoice amount should reflect the percentage and dollar amount of completion established by the cutter’s appropriate weekly progress report. Payments shall be derived from the accomplished percentage of completion as determined by the Contracting Officer.
C. All material and work paid for by progress payments shall thereby become the sole property of the Government, but this provision shall not relieve the contractor from the obligation to complete the requirements of the contract.
D. The Contractor shall be paid the remaining amount due upon completion and acceptance of all work under this contract.
(23) 52.232-99, Providing Accelerated Payment to Small Business Subcontractors (DEVIATION) (AUG 2012)
This clause implements the temporary policy provided by OMB Policy Memorandum M-12-16, Providing Prompt Payment to Small Business Subcontractors, dated July 11, 2012.
(a) Upon receipt of accelerated payments from the Government, the contractor is required to make accelerated payments to small business subcontractors to the maximum extent practicable after receipt of a proper invoice and all proper documentation from the small business subcontractor.
(b) Include the substance of this clause, including this paragraph (b), in all subcontracts with small business concerns.
(c) The acceleration of payments under this clause does not provide any new rights under the Prompt Payment Act.
(End of clause)
(End of FAR 52.212-4 Addendum)
52.212-5--Contract Terms and Conditions Required to Implement Statutes or Executive Orders -- Commercial Items. (AUG 2013)
a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
(1) 52.222-50, Combating Trafficking in Persons (FEB 2009) (22 U.S.C. 7104(g)).
____ Alternate I (AUG 2007) of 52.222-50 (22 U.S.C. 7104(g)).
(2) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(3) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Pub. L. 108-77, 108-78).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the contracting officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
[Contracting Officer check as appropriate.] _X_ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Sept 2006), with Alternate I (Oct 1995) (41 U.S.C. 253g and 10 U.S.C. 2402).
_X_ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Apr 2010) (Pub. L. 110-252, Title VI, Chapter 1 (41 U.S.C. 251 note)).
___ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Jun 2010) (Section 1553 of Pub L. 111-5) (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009).
_X_ (4) 52.204-10, Reporting Executive compensation and First-Tier Subcontract Awards (Jul 2013) (Pub. L. 109-282) (31 U.S.C. 6101 note).
___ (5) 52.204-11, American Recovery and Reinvestment Act—Reporting Requirements (Jul 2010) (Pub. L. 111-5).
_X_ (6) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Aug 2013) (31 U.S.C. 6101 note).
_X_ (7) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (Jul 2013) (41 U.S.C. 2313).
___ (8) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (May 2012) (section 738 of Division C of Public Law 112-74, section 740 of Division C of Pub. L. 111-117, section 743 of Division D of Pub. L. 111-8, and section 745 of Division D of Pub. L. 110-161).
___ (9) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Nov 2011) (15 U.S.C. 657a).
_X_ (10) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Jan 2011) (if the offeror elects to waive the preference, it shall so indicate in its offer)(15 U.S.C. 657a).
___ (11) [Reserved]
___ (12) (i) 52.219-6, Notice of Total Small Business Aside (Nov 2011) (15 U.S.C. 644).
___ (ii) Alternate I (Nov 2011).
___ (iii) Alternate II (Nov 2011).
___ (13) (i) 52.219-7, Notice of Partial Small Business Set-Aside (June 2003) (15 U.S.C. 644).
___ (ii) Alternate I (Oct 1995) of 52.219-7.
___ (iii) Alternate II (Mar 2004) of 52.219-7.
_X_ (14) 52.219-8, Utilization of Small Business Concerns (Jul 2013) (15 U.S.C. 637(d)(2) and (3)).
_X__ (15) (i) 52.219-9, Small Business Subcontracting Plan (Jul 2013) (15 U.S.C. 637 (d)(4)).
___ (ii) Alternate I (Oct 2001) of 52.219-9.
___ (iii) Alternate II (Oct 2001) of 52.219-9.
___ (iv) Alternate III (July 2010) of 52.219-9.
___ (16) 52.219-13, Notice of Set-Aside of Orders (Nov 2011) (15 U.S.C. 644(r)).
___ (17) 52.219-14, Limitations on Subcontracting (Nov 2011) (15 U.S.C. 637(a)(14)).
_X_ (18) 52.219-16, Liquidated Damages—Subcontracting Plan (Jan 1999) (15 U.S.C. 637(d)(4)(F)(i)).
___ (19) (i) 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns (Oct 2008) (10 U.S.C. 2323) (if the offeror elects to waive the adjustment, it shall so indicate in its offer).
___ (ii) Alternate I (June 2003) of 52.219-23.
___ (20) 52.219-25, Small Disadvantaged Business Participation Program—Disadvantaged Status and Reporting (Jul 2013) (Pub. L. 103-355, section 7102, and 10 U.S.C. 2323).
___ (21) 52.219-26, Small Disadvantaged Business Participation Program—Incentive Subcontracting (Oct 2000) (Pub. L. 103-355, section 7102, and 10 U.S.C. 2323).
___ (22) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (Nov 2011) (15 U.S.C. 657f).
_X_ (23) 52.219-28, Post Award Small Business Program Rerepresentation (Jul 2013) (15 U.S.C. 632(a)(2)).
___ (24) 52.219-29, Notice of Set-Aside for Economically Disadvantaged Women-Owned Small Business (EDWOSB) Concerns (Jul 2013) (15 U.S.C. 637(m)).
___ (25) 52.219-30, Notice of Set-Aside for Women-Owned Small Business (WOSB) Concerns Eligible Under the WOSB Program (Jul 2013) (15 U.S.C. 637(m)).
_X_ (26) 52.222-3, Convict Labor (June 2003) (E.O. 11755).
_X_ (27) 52.222-19, Child Labor—Cooperation with Authorities and Remedies (Mar 2012) (E.O. 13126).
_X_ (28) 52.222-21, Prohibition of Segregated Facilities (Feb 1999).
_X_ (29) 52.222-26, Equal Opportunity (Mar 2007) (E.O. 11246).
_X_ (30) 52.222-35, Equal Opportunity for Veterans (Sep 2010) (38 U.S.C. 4212).
_X_ (31) 52.222-36, Affirmative Action for Workers with Disabilities (Oct 2010) (29 U.S.C. 793).
_X_ (32) 52.222-37, Employment Reports on Veterans (Sep 2010) (38 U.S.C. 4212).
_X_ (33) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496).
_X_ (34) 52.222-54, Employment Eligibility Verification (Jul 2012). (Executive Order 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial items as prescribed in 22.1803.)
___ (35) (i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008) (42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
___ (ii) Alternate I (May 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
___ (36) 52.223-15, Energy Efficiency in Energy-Consuming Products (Dec 2007) (42 U.S.C. 8259b).
___ (37) (i) 52.223-16, IEEE 1680 Standard for the Environmental Assessment of Personal Computer Products (Dec 2007) (E.O. 13423).
___ (ii) Alternate I (Dec 2007) of 52.223-16.
_X_ (38) 52.223-18, Encouraging Contractor Policies to Ban Text Messaging while Driving (Aug 2011).
_X_ (39) 52.225-1, Buy American Act--Supplies (Feb 2009) (41 U.S.C. 10a-10d).
___ (40) (i) 52.225-3, Buy American Act--Free Trade Agreements--Israeli Trade Act (Nov 2012) (41 U.S.C. chapter 83, 19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, Pub. L. 103-182, Pub. L. 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43).
___ (ii) Alternate I (Mar 2012) of 52.225-3.
___ (iii) Alternate II (Mar 2012) of 52.225-3.
___ (iv) Alternate III (Nov 2012) of 52.225-3.
___ (41) 52.225-5, Trade Agreements (Nov 2012) (19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).
_X_ (42) 52.225-13, Restrictions on Certain Foreign Purchases (Jun 2008) (E.O.’s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
___ (43) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Jul 2013) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. 2303 Note).
___ (44) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov 2007) (42 U.S.C. 5150).
___ (45) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (Nov 2007) (42 U.S.C. 5150).
___ (46) 52.232-29, Terms for Financing of Purchases of Commercial Items (Feb 2002) (41 U.S.C. 255(f), 10 U.S.C. 2307(f)).
___ (47) 52.232-30, Installment Payments for Commercial Items (Oct 1995) (41 U.S.C. 255(f), 10 U.S.C. 2307(f)).
_X_ (48) 52.232-33, Payment by Electronic Funds Transfer— System for Award Management (Jul 2013) (31 U.S.C. 3332).
___ (49) 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management (Jul 2013) (31 U.S.C. 3332).
___ (50) 52.232-36, Payment by Third Party (Jul 2013) (31 U.S.C. 3332).
___ (51) 52.239-1, Privacy or Security Safeguards (Aug 1996) (5 U.S.C. 552a).
_X_ (52) (i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006) (46 U.S.C. Appx 1241(b) and 10 U.S.C. 2631).
___ (ii) Alternate I (Apr 2003) of 52.247-64.
(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or executive orders applicable to acquisitions of commercial items:
[Contracting Officer check as appropriate.]
___ (1) 52.222-41, Service Contract Act of 1965 (Nov 2007) (41 U.S.C. 351, et seq.).
___ (2) 52.222-42, Statement of Equivalent Rates for Federal Hires (May 1989) (29 U.S.C. 206 and 41 U.S.C. 351, et seq.).
___ (3) 52.222-43, Fair Labor Standards Act and Service Contract Act -- Price Adjustment (Multiple Year and Option Contracts) (Sep 2009) (29 U.S.C.206 and 41 U.S.C. 351, et seq.).
___ (4) 52.222-44, Fair Labor Standards Act and Service Contract Act -- Price…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .