SPEC_REV0_MANTA_FY14.pdf
PDF 863 KB Posted
- Attached to
- USCGC MANTA DRYDOCK & REPAIRS Federal contract opportunity
- Solicitation number
- HSCG80-14-Q-P45482
About this file
SPECIFICATION FOR USCGC MANTA
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30_Amendment_01_CGC_Manta.pdf | ||
| SCHEDULE_OF_SUPPLIES_SERVICES_FOR_CGC_MANTA_111413.xls | XLS spreadsheet | |
| Past_Performance_Questionnaire.doc | DOC document | |
| GOVERNMENT_PROPERTY_REPORT_SF_1149.doc | DOC document | |
| SOLCITATION_FOR_CGC_MANTA_DRYDOCK_121813_.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC MANTA (WPB 87320)
SPECIFICATION FOR DRYDOCK REPAIRS
FY2014
Developed By: Roderick A Stroud
(Rev-0, 27 November 2013)
USCGC MANTA (WPB-87) DRYDOCK AVAILABILITY FY2014
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ...................................................................................................................................................... iii Consolidated List of References ............................................................................................................................... iv Consolidated List of Government-furnished Property ............................................................................................ vii Consolidated List of Critical Inspection Items ......................................................................................................... ix Principal Characteristics ............................................................................................................................................ x General Requirements WORK ITEM 1: Perform Ultrasonic Thickness Measurements (D) WORK ITEM 2: Perform Ultrasonic Thickness Measurements (O) WORK ITEM 3: Bilge Surfaces (Lazarette), Preserve (“Partial”) (D) WORK ITEM 4: Dirty Oil Tank, Clean and Inspect (D) WORK ITEM 5: Tanks (MP Fuel Service), Clean and Inspect (D) WORK ITEM 6: Oily Water Tank, Preserve (D) WORK ITEM 7: Superstructure, Preserve (“100%”) (O) WORK ITEM 8: Depth Sounder, Capastic Fairing, Renew (O) WORK ITEM 9: Main Engine/Reduction Gear, Realign (O) WORK ITEM 10: Propulsion Shafts, Remove, Inspect, and Reinstall (D) WORK ITEM 11: Propulsion Shaft, Repair (O) WORK ITEM 12: Propulsion Shaft, Straighten (O) WORK ITEM 13: Intermediate Water-Lubricated Propulsion Shaft Bearing, Renew (O) WORK ITEM 14: Aft Water-Lubricated Propulsion Shaft Bearing, Renew (O) WORK ITEM 15: Intermediate Bearing Carrier, Renew (O) WORK ITEM 16: Aft Bearing Carrier, Renew (O) WORK ITEM 17: Stern Tubes, Interior Surfaces, Preserve 100% (O) WORK ITEM 18: Stern Tubes, Interior Surfaces, Repair (O) WORK ITEM 19: Propellers, Remove, Inspect, and Reinstall (D) WORK ITEM 20: Fathometer Transducer, Renew (O) WORK ITEM 21: Speed Log, Skin Valve Assembly, Clean and Inspect (D) WORK ITEM 22: Sea Water System (Sea Valves, Strainers, Piping), Clean, Inspect and Repair (D) WORK ITEM 23: Rudder Assemblies, Remove, Inspect and Reinstall (D) WORK ITEM 24: RHIB Notch Skid Pads, Inspect (D) WORK ITEM 25: RHIB Notch Skid Pad Studs, Renew (O) WORK ITEM 26: Stern Launch Door, Remove, Inspect and Reinstall (D) WORK ITEM 27: Grey Water Holding Tank, Clean and Inspect (D) WORK ITEM 28: Sewage Holding Tank , Clean and Inspect (D) WORK ITEM 29: Grey Water Piping, Clean and Flush (D) WORK ITEM 30: Sewage Piping, Clean and Flush (D) WORK ITEM 31: U/W Body, Preserve (“100%”) (O) WORK ITEM 32: Hull Plating Freeboard, Preserve (“100%”) (D) WORK ITEM 33: Superstructure, Preserve “Partial” (D) WORK ITEM 34: Cathodic Protection / Zincs, Renew (D) WORK ITEM 35: Drydocking (D) WORK ITEM 36: Temporary Services, Provide (D) WORK ITEM 37: Telephone Service, Provide (D) WORK ITEM 38: Pilothouse Deck (Aluminum), Inspect, Preserve, and Renew Electrical Matting (D) WORK ITEM 39: Install Stainless Steel Hull Inserts and Renew BMDE Concentric Rings (D) iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:
• MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm
• Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp
• Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::
www.gpoaccess.gov
The Government is aware of the following internet web links where contractors may procure commercial specifications:
• American Welding Society (AWS): http://www.awspubs.com/index.php
• ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/
• NFPA: http://www.nfpa.org
• SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 085-001, Rev -, Tank Capacity - 95% Curves Coast Guard Drawing 87 WPB 085-010, Rev D, Docking Plan Coast Guard Drawing 87 WPB 085-011, Rev C, Lifting Slings Coast Guard Drawing 87 WPB 085-012, Rev A, Lifting Cradle Coast Guard Drawing 87 WPB 111-001, Rev G, Shell Expansion Coast Guard Drawing 87 WPB 116-001, Rev -, Longitudinal Girders & Bulkheads Coast Guard Drawing 87 WPB 122-001, Rev C, Watertight Bulkheads Coast Guard Drawing 87 WPB 161-001, Rev C, Skeg Construction Coast Guard Drawing 87 WPB 163-001, Rev H, Sea Chest Details Coast Guard Drawing 87 WPB 165-001, Rev D, Transducer Details Coast Guard Drawing 87 WPB 182-001, Rev A, Main Engine & Generator Foundations Coast Guard Drawing 87 WPB 243-001, Rev M, Propulsion Shaft Details Coast Guard Drawing 87 WPB 243-050, Rev -, Propulsion Shaft: Single Sheet Detail Coast Guard Drawing 87 WPB 245-003, Rev A, Propeller Details Coast Guard Drawing 87 WPB 256-001, Rev W, Sea Water Cooling Piping Coast Guard Drawing 87 WPB 259-001, Rev D, Engine Exhaust Piping Coast Guard Drawing 87 WPB 423-001, Rev U, Speed Log & Depth Sounder System Coast Guard Drawing 87 WPB 526-001, Rev H, Scuppers & Deck Drains Piping Coast Guard Drawing 87 WPB 561-001, Rev J, Steering System Details v (Rev-0)
Coast Guard Drawing 87 WPB 562-001, Rev A, Rudder Details Coast Guard Drawing 87 WPB 583-001, Rev U, RIB Deployment Structure Coast Guard Drawing 87 WPB 593-001, Rev K, Sewage Piping Coast Guard Drawing 87 WPB 593-002, Rev C, Oily Water Separator Piping Coast Guard Drawing 87 WPB 601-001, Rev L, Outboard Profile & General Arrangements Coast Guard Drawing 87 WPB 634-001, Rev C, Deck Coverings and Details Coast Guard Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters Coast Guard Fleet Drawing FL 2804-12, Rev-, U.S.C.G. Emblem NAVSEA Drawing 803-921865, Rev R, Cathodic Protection Hull Zinc Anodes
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 4506, Wartsila TM-EL-68839, Issue A, Mar 2005, Rudderstock
Seal Type EL Coast Guard Technical Publication (TP) 4593B, Mar 2003, SWBS 562, Rudderstock Seal-Type EJ Coast Guard Technical Publication (TP) 4593C, Feb 2002, SWBS 243, Manufacturer's Instruction Book, 87' WPB Propulsion Shaft Seals, John Crane Type F.S.E.
Coast Guard Technical Publication (TP) E-424-0230, SWBS 424, June 2006, Electromagnetic Log User’s
Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2012, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2012, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2012, Install Interior
Deck Covering Systems Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2012, Drydocking Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2012, Temporary
Services Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2012, Temporary
Hull Accesses
OTHER REFERENCES
ASTM International (ASTM) 6966, 2008, Standard Practice for Collection of Settled Dust Samples Using
Wipe Sampling Methods for Subsequent Determination of Metals ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component
Adhesives (An) ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates Bollinger Shipyard, USCG CPB Project MTU-FA 771903, 07 Feb 2000, Engine/Gearbox Plant
Alignment Instructions 8V396 TE94/Flange mounted BW 255 Bollinger Shipyards Drawing D97-0829, Rev J, Installation Drawing, 87’ USCG CPB/MTU 8V396TE94 Code of Federal Regulations (CFR) Title 29, Part 1910, Jul 2008, Occupational Safety and Health
Standards Code of Federal Regulations (CFR) Title 33 CFR, Jul 2010, Navigation and Navigable Waters vi (Rev-0)
Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety
Administration, Department Of Transportation Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Antiseize, Zinc Dust-
Petrolatum Commercial Item Descriptions (CID) A-A-59316, Nov 2003 Abrasive Materials for Blasting DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections Federal Standard (FED-STD) 595, 2008, Colors Used In Government Procurement International Standard for Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller -
Manufacturing Tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50 m, Inclusive MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning MIL-DTL-15562, May 1996, Matting or Sheet, Floor Covering Insulating for High Voltage requirements MIL-PRF-16173, 2006, Corrosive Preventive Compound, Solvent Cutback, Cold Application MIL-PRF-23236, Aug 2003, Coating Systems for Ship Structures MIL-PRF-24139, Mar 1987, Grease, Multipurpose, Water Resistant.
MIL-PRF-24635, 2009, Coating Systems, Weather-Resistant, Exterior Use MIL-PRF-24647, Jun 2006, Paint System, Anticorrosive and Antifouling, Ship Hull MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant MIL-STD-1687, Sep 1994, Thermal Spray Processes For Naval Ship Machinery Application MIL-STD-2191, Nov 1992, Repair Welding, Weld Cladding, Straightening, and Cold Rolling of Main
Propulsion Shafting Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and
Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of Metals by Waterjetting Prior to Recoating
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2004, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No. SSPC-SP 12/NACE No.5, Surface Preparation and Cleaning of Steel & Other Hard Materials by High and Ultrahigh Pressure Water Jetting Prior to Recoating vii (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM
DESCRIPTION
NSN/PN QTY ESTIMATED
COST
($/UNIT)
9 Y Alignment Kit N/A 1 ea 5000.00 10 Y **Propeller shaft NSN: 2010-01-458-9175 2 ea. 9,566.14 10 N **Type FSE Face
(split)
PN: H75440-01-2-2 NSN:
5330-01-521-3559 2 ea. 1,995.07
10 N **Type FSE Seal (split)
PN: H75440-01-1-1 NSN:
2040-01-521-2654
2 ea. 4,070.35
10 N Type FSE Seal Cup (split)
PN: H75440-01-1-3 NSN:
3120-01-521-2390
2 ea. 188.24
10 N Type FSE O-Cord PN: H75440-01-1-4 NSN:
3120-01-521-2268
2 ea. 252.84
10 N Type FSE Emergency Seal
PN: H75440-01-3-6 NSN:
5330-01-521-4855
2 ea. 260.92
10 N **Shaft Seal Bellow PN: H75440-01-2-1
NSN: 5340-01-521-3573
2 ea. 270.45
10 N *Compression Tool Assembly
N/A 1 ea. 200.00
10 N *Alignment Kit N/A 1 set 3,000.00 13 N **Thordon bearing, Grade Orange (5.5" OD x 4" ID x 7.87" (200mm) LG)
PN: F54615-02-8-1 NSN:
3120-21-914-2012
2 ea. 325.47
14 N **Thordon bearing, Grade Orange
(5.5" OD x 4" ID x 11.41" (290mm) LG)
PN: F54615-02-8-0 NSN:
3120-21-914-2011
2 ea. 399.50
15 N **Intermediate bearing carrier
NSN: 3130-01-F11-2388
P/N: 87 WPB 243-001 Item
2 ea. 899.53
16 N **Aft bearing carrier NSN: 3130-01-F11-2200 P/N: 87 WPB 243-001 Item
2 ea. 5360.00
19 Y **Starboard Propeller (RH)
PN: RH706-3350.00 NSN:
2010-01-457-0573
1 ea. 12,498.00
19 Y **Port Propeller
(LH)
PN: LH706-3350.00 NSN:
2010-01-459-0421
1 ea. 12,498.00
19 N *Propeller Nut Wrench
N/A 1 ea 200.00
19 N **Propeller Nut NSN: 2010-01-458-9217 2 ea. 281.00 19 N **Propeller Nut, NSN: 5310-01-458-9125 2 ea. 252.94 viii (Rev-0)
Locking 19 N Anode, Propeller Nut NSN: 5342-01-481-8403 2 ea. 272.00 19 Y *Pilot Nut NSN: 2010-01-276-3952 1 ea. 795.33 20 N *** Fathometer transducer, shallow water, 50-200 kHz
NSN: 5845-01-531-2648 1 ea. 441.70
21 Y **Doppler Speed Log Measurement
Rod
NSN: 6605-01-470-1266 1 ea. 4645.09
23 Y **Rudder Assembly, port
NSN: 2040-01-461-1944 1 ea. 2,000.00
23 Y **Rudder Assembly, starboard
NSN: 2040-01-461-1943 1 ea. 2,000.00
23 N Upper Roller Bearing NSN: 3110-01-512-5534 2 ea. 244.62 23 N Wartsila EL Seals Kit NSN: 2040-01-565-9776 2 ea. 6300.00 23 N **Lower Bearing NSN: 3120-20-000-7677
PN: TBF113090
2 ea. 360.50
35 Y *Transducer Cover Plate
N/A 2 ea. 50.00
38 N Anti-fatigue matting (556 cushion ease solid 3’ x 3’)
NSN: 7220-01-598-6144 15 ea. 45.15
39 N MDE Exhaust Concentric Rings
NSN: 2990-01-537-5198 2 ea. 2,850.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter ix (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item Title
1 Perform Ultrasonic Thickness Measurements (D)
3 Bilge Surfaces (Lazarette), Preserve (“Partial”) (D)
10 Propulsion Shafts, Remove, Inspect, and Reinstall (D)
19 Propellers, Remove, Inspect, and Reinstall (D)
22 Sea Water System (Sea Valves, Strainers, Piping), Clean, Inspect and Repair (D)
23 Rudder Assemblies, Remove, Inspect and Reinstall (D)
24 RHIB Notch Skid Pads, Inspect (D)
35 Drydocking (D)
38 Pilothouse Deck (Aluminum), Inspect, Preserve, and Renew Electrical Matting (D) x (Rev-0)
PRINCIPAL CHARACTERISTICS
PC_87_WPB_0511
87' WPB
PHYSICAL CHARACTERISTICS
Length Overall 87'
Length between Perpendiculars 81' 7"
Depth 10' 11"
Maximum Beam 19.4'
Draft, Mean to Design Waterline 5' 9"
Height of Highest Projection 50.2'
Full Load Displacement 93.5 long tons
Minimum Operating Displacement 83.9 long tons
Displacement, Light Ship 77.9 long tons
Framing Longitudinal
Bulkheads Four watertight bulkheads located below the Main Deck
Anchor 40 lb Fortress with 480 ft. 3 strand 5/8" dia. Line stayset
HULL CHARACTERISTICS
Hull/Main Weatherdeck Material ABS Grade AH 36
Superstructure 5086 Aluminum
MACHINERY CHARACTERISTICS
Main Propulsion Two MTU 8V396TE94, sequential turbo-charged diesels
Reduction Gears Two ZF Type BW 255
Propulsion Shaft Two AQUAMET 22, 101.6mm
Shaft Diameter 4" xi (Rev-0)
Shaft Seal Two John Crane mechanical seals
Shaft Bearing, Intermediate Thordon Elastomeric Bearing
Shaft Bearing, Aft Thordon Elastomeric Bearing
Number of Propellers 2
Number of Blades 5
Diameter of Propeller 1040mm
Pitch 1230 mm fixed
Shaft RPM 828
Rudders Two 316L Stainless Steel
Ship's Service Generators Two Man Model D08241F01 diesel with Stanford 60KW Generator
TANK CAPACITIES
3-9-1-F (Fuel Oil) 1450 gal
3-9-2-F (Fuel Oil) 1450 gal
3-12-2-F (Waste Oil) 85 gal
3-12-1-F (Oily Water) 85 gal
3-7-0-Q (Sewage Collection) 352 gal
3-7-1-Q (Grey Water) 52 gal
3-12-1-W (Fresh Water) 200 gal
3-12-2-W (Fresh Water) 200 gal
1 (Rev-0)
00000_0813_FLT
REC_00000_FLT_ Commercial Project @ Contractor’ Facility (1212)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None.
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2012, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2012, Requirements for Preservation of Ship Structures
OTHER REFERENCES
ASTM International (ASTM) 6966, 2008, Standard Practice for Collection of Settled Dust Samples Using
Wipe Sampling Methods for Subsequent Determination of Metals Code of Federal Regulations (CFR) Title 29, Part 1910, Jul 2008, Occupational Safety and Health
Standards The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal Code of Federal Regulations (CFR) Title 33 CFR, Jul 2010, Navigation and Navigable Waters Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety
Administration, Department Of Transportation
3. REQUIREMENTS
2 (Rev-0)
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Cutter and Boat Authorized Coatings).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with SFLC Std Spec 6310, Appendix C (Cutter and Boat Authorized Coatings).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.
3.5 HW disposal. The Contractor is considered as the generator of all contract-generated hazardous wastes and shall use its facility’s EPA generator ID number for management, transportation, and disposal of said hazardous wastes. Ensure the following:
3.5.1 Contractor’s hazardous waste handlers shall comply with applicable requirements of 40 CFR 262.
3.5.2 All contract generated hazardous wastes shall be packaged in 49 CFR-compliant containers.
3.5.3 The designated wastes shall be disposed of at a state or Federally-approved and permitted HW TSDF.
3.5.4 Name of destination TSDF shall be submitted to the KO at the Arrival Conference.
3.6 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2012 Edition Standard Specifications and supersede published content:
3.6.1 SFLC Std Spec 8634, Drydocking, Appendix A, page A5, paragraph A2.7.1.3 Side Blocks: Remove formula value shown as g – Acceleration of gravity – 32.3 Ft/sec2, and replace with formula value g - Acceleration of gravity - 32.174 ft/sec2.
3.6.2 SFLC Std Spec 0740, Welding and Allied Processes. SFLC Std Spec 0740 added Appendix E, Stray Current Protection: New Appendix is posted with SFLC Standard Specifications as a separate document on internet and intranet webpage.
3.6.2.1 SFLC Std Spec 0740, Welding and Allied Processes, page 1, paragraph 1.2 Appendices: Add ‘Stray Current Protection’ to ‘Process Standard column of appendices table. Add ‘E’ to ‘Appendix’ column of
3 (Rev-0) appendices table.
3.6.2.2 SFLC Std Spec 0740, Welding and Allied Processes, page 4, paragraph 3.1.3 Stray current protection:
Add “The Contractor shall meet all requirements for stray current protection as specified in Appendix E - Stray Current Protection.” directly after paragraph 3.1.3 title.
3.6.2.3 SFLC Std Spec 0740, Welding and Allied Processes, page 4, paragraph 3.1.3 Stray current protection:
Delete paragraphs 3.1.3.1 and 3.1.3.2.
3.6.3 SFLC Std Spec 0450, Electrical Power for Contractor’s Tools and Equipment, page 1, paragraph 1.1 Intent:
Add sentence, “Note that stray current protection for welding equipment is covered in SFLC Standard Specification 0740, Welding and Allied Processes, Appendix E.” to end of paragraph.
3.6.3.1 SFLC Std Spec 0450, Electrical Power for Contractor’s Tools and Equipment, page 5, paragraph 3.4 Equipment Grounding: Add sentence, “Stray current protection for welding equipment is covered in SFLC Standard Specification 0740, Welding and Allied Processes, Appendix E.” to end of paragraph.
3.6.3.2 SFLC Std Spec 0450, Electrical Power for Contractor’s Tools and Equipment, page 6, paragraph 3.4 Equipment Grounding: Delete paragraphs 3.4.1.4 and 3.4.1.5.
3.6.3.3 SFLC Std Spec 0450, Electrical Power for Contractor’s Tools and Equipment, page 6, paragraph 3.4 Equipment Grounding: Delete Figure 5.
3.6.4.1 SFLC Std Spec 0000, General Requirements, page 22, paragraph 3.3.3.1 NOTE. Add "Flame-retardant polyethylene deck plate with a non-slip diamond pattern from 10 to 40mil thickness" to body of Note.
3.6.5 SFLC Std Spec 6310, Requirements, page 10, Add “3.1.6.5 Preconstruction Primers. Also known as shop primers, preconstruction primers are used as a temporary coating to protect steel from corrosion during welding, storage, and fabrication. Preconstruction primers shall be removed prior to applying the permanent coating system on all critical coated surfaces. Preconstruction primers may be left in place in other interior areas (such as machinery spaces, habitability spaces, etc.) if they are intact, uncontaminated, and compatible with the overcoating system.”
3.6.5.1 SFLC Standard Specification 6310 Appendix B, page B12 , the formatting for Notes 17-19 is in error, change to the following
• SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Note 17, delete sentence, “Persistent corrosion in a particular area of an aluminum bilge may dictate the need for a protective High Build Epoxy coating to be applied to that local area.”
• SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Note 18, replace entire note with “Persistent corrosion in a particular area of an aluminum bilge may dictate the need for a protective High Build Epoxy coating to be applied to that local area. “
• SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Note 19, replace entire note with “Painting plastic surfaces is highly discouraged, but after it is done once, it must be maintained.”
• SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Add Note “20. For aluminum surfaces, remove all oil, grease, dirt, metal oxides (corrosion products) and other foreign material by cleaning per SSPC-S
4 (Rev-0)
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 0000 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
5 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
Vessel Name Hull # Work Item # Work Item Title
Location of Work (incl. frame #’s) Area (sqft)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-12, SP-11, SP-10…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max.
threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
Name of QP-1/NACE Inspector Signature Cert. # Date / Time
6 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE &
TIME
ACTIVITY
(Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION
(Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL.
HUMID-
ITY DEW
PT. SURFACE AMBIENT
ΔT
| DP -
Surface |
7 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
Location of Work (Frame References) Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils) Min Max Mean
SSPC-SP-10/NACE No. 2 SSPC-SP-12/NACE No. 5
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings: ______________
8 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils) Min Max Mean
SSPC-SP-10/NACE No. 2 SSPC-SP-12/NACE No. 5
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils Mean Mil Reading (IAW ASTM D4417-Method B) for above 10 readings (by column):
_____ mils _____ mils _____ mils _____ mils _____ mils
9 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15
DATE TEST LOCATIONS CONDUCTIVITY
(microsiemens/cm)
10 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
Coating Mfg Product Name Batch # Induction Time
Coating System Sequence (Primer/Touchup/3rd Coat, etc.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2
SPOT 1 2 3 4 5 AVERAGE
VALUE
*BASE METAL
READING (BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation 3 Before
Adjustments After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation 3 Before
Adjustments After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation 3 Before
Adjustments After Adjustments
Avg.
Application Method (Airless, Conventional Spray, Rolled) Average DFT
11 (Rev-0)
11000 _JLW_1210_87WPB
WORK ITEM 1: Perform Ultrasonic Thickness Measurements (D)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform up to 250 thickness measurements (UT shots) of hull plating and frames, by ultrasonic methods.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 085-010, Rev D, Docking Plan Coast Guard Drawing 87 WPB 111-001, Rev G, Shell Expansion
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2012, Welding and Allied Processes
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):
• 3.2 (UT measurements).
3.1.2 Tech Rep.
Not applicable.
12 (Rev-0)
3.1.3 Protective measures - general. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 UT measurements. The Contractor shall perform up to 250 UT measurements in locations designated by the Coast Guard Inspector, in accordance with SFLC Std Spec 0740, Appendix C.
Create a sketch to show all locations selected for measurement and record all measurements in Table 1 (UT Measurements Summary Sheet - Port/Stbd Shell) provided at the end of this item.
Submit a CIR that contains the sketch and completed Table I.
This section is not applicable to this work item.
13 (Rev-0)
TABLE I - UT MEASUREMENTS SUMMARY SHEET PORT/STBD SHELL
SHOT # STRAKE # FWD/MID/AFT ORIG PL MEASURED PL PERCENT
PLATE # TOP/MID/BOT THICKNESS THICKNESS WASTAGE
14 (Rev-0)
11001 _JLW_1210_87WPB
WORK ITEM 2: Perform Ultrasonic Thickness Measurements (O)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform up to 250 thickness measurements (UT shots) of hull plating and frames, by ultrasonic methods, in 10 lots of 25 measurements.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 085-010, Rev D, Docking Plan Coast Guard Drawing 87 WPB 111-001, Rev G, Shell Expansion
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2012, Welding and Allied Processes
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
Not applicable.
3.1.2 Tech Rep.
15 (Rev-0)
3.1.3 Protective measures - general. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 UT measurements. The Contractor shall perform up to 250 UT measurements in locations designated by the Coast Guard Inspector, in accordance with SFLC Std Spec 0740, Appendix C.
Create a sketch to show all locations selected for measurement and record all measurements in Table 1 (UT Measurements Summary Sheet - Port/Stbd Shell) provided at the end of this item.
Submit a CFR that contains the sketch and completed Table I.
16 (Rev-0)
TABLE I - UT MEASUREMENTS SUMMARY SHEET PORT/STBD SHELL
SHOT # STRAKE # FWD/MID/AFT ORIG PL MEASURED PL PERCENT
PLATE # TOP/MID/BOT THICKNESS THICKNESS WASTAGE
17 (Rev-0)
11302_JLW_1210_87WPB
WORK ITEM 3: Bilge Surfaces (Lazarette), Preserve (“Partial”) (D)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to partially preserve the bilge surfaces in the Lazarette (2-22-0-E) designated in the table below.
AREA TO BE PREPARED AND COATED APPROX.
SQFT
Lazarette Bilge 190
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 601-001, Rev L, Outboard Profile & General
Arrangements Coast Guard Drawing 87 WPB 116-001, Rev -, Longitudinal Girders & Bulkheads Coast Guard Drawing 87 WPB 122-001, Rev C, Watertight Bulkheads
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2012, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2012, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 General. The Contractor shall refer to Coast Guard Drawings 87 WPB 601-001, 87 WPB 116-001, and 87 WPB 122-001.
18 (Rev-0)
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):
• 3.4 (Substrate inspection).
3.1.2 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences):
• Deck grating and associated framing.
• Bilge piping.
• Electrical wiring.
• RHIB notch.
• Emergency helm pump.
• Hydraulic hoses.
• HPU.
• Accumulator.
• Valves.
• Control and junction boxes.
• Lube oil storage tank (26 gallon capacity)
• Emergency steering column.
• Bilge alarm.
• Zinc.
• Float switch.
3.2 Protective measures. The Contractor shall furnish and install suitable covering to seal off and protect all non-affected surfaces/equipment and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, remove protective material and inspect for the presence of contamination. Clean all equipment and spaces, contaminated due to improper protection, to original condition of cleanliness.
3.3 Surface preservation. The Contractor shall partially prepare and touch-up coat bilge surface areas designated in paragraph 1.1 (Intent)), including all adjacent structural members, using the system specified for “Bilges, Cofferdams, and Forepeaks, Option I”, in SFLC Std Spec 6310, Appendix B (Cutters and Boat Interior Painting Systems). Select color Red (20152) as the finish/top coat color.
NOTE
Application of the topcoat specified herein may require the use of plural-component spray equipment, or other suitable methods, to compensate for the coating system’s relatively short pot life.
3.4 Substrate inspection. After completion of surface preparation and before primer coat application, the Contractor shall perform a visual inspection of all prepared surfaces. Submit a
CIR.
3.5 In-process quality control measures. The Contractor shall abide by all the safety, 19 (Rev-0) preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph
3.2.4.2 (In-process QC measures for “critical-coated surfaces).
NOTE
Surfaces being preserved are considered “critical-coated surfaces”.
20 (Rev-0)
12300_JLW_1210_87WPB
WORK ITEM 4: Dirty Oil Tank, Clean and Inspect (D)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean the following tank:
TYPE OF
TANK LOCATION CAPACITY - 95%
(gallons)
LOW SUCTION
(GALLONS)
Dirty Oil 2-13-2-F 85
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 085-001, Rev -, Tank Capacity - 95% Curves Coast Guard Drawing 87 WPB 601-001, Rev L, Outboard Profile & General
Arrangements
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General Requirements
OTHER REFERENCES
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS)
C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Operational test – initial. Prior to commencement of work, the Contractor shall witness an operational pre-test by Coast Guard personnel of all designated tank TLIs to demonstrate existing operational condition. Submit a CFR.
3.2 Cleaning requirements. The Contractor shall remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage the
21 (Rev-0) coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.
3.3 Tank content and waste disposal. The Contractor shall dispose of tank contents and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.
3.4 Inspection. The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
• Tank structural condition.
• Inaccessible areas.
• Dirty oil tank - Tank Level Indicator (TLI) and/or float switch condition.
• Sounding tube and striker plate condition.
• Suction and discharge piping condition.
• Fastener material and condition (correct fastener material is stainless steel).
• Strainers – verify that strainers are not touching the hull or tank bhds.
3.5 Tank closing. The Contractor shall ensure that the tank(s) remain open for at least 24 hours after completion of all authorized repair and preservation procedures. Notify the COR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183.
3.6 Operational test – final. After all authorized work is complete, in the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLI(s) to be in satisfactory operating condition (see 4.1 (Equipment operation)). Submit a CFR.
4. NOTES
4.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.
22 (Rev-0)
12302_JLW_1210_87WPB
WORK ITEM 5: Tanks (MP Fuel Service), Clean and Inspect (D)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tanks:
TYPE OF
TANK LOCATION CAPACITY - 95%
(gallons)
LOW SUCTION
(GALLONS)
Diesel Fuel 3-9-1-F 1450 40 Diesel Fuel 3-9-2-F 1450 40
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 601-001, Rev L, Outboard Profile & General
Arrangements
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General Requirements
OTHER REFERENCES
Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS)
C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General. The Contractor shall refer to Coast Guard Drawing 87 WPB 601-001 for guidance.
3.1.1 Operational test – initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs to demonstrate
23 (Rev-0) existing operational condition. Submit a CFR.
3.2 Cleaning requirements. The Contractor shall remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.
3.3 Tank content and waste disposal. The Contractor shall dispose of tank contents and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.
3.4 Inspection. The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
• Tank structural condition.
• Inaccessible areas.
• Sounding tube and striker plate condition.
• Suction and discharge piping condition.
• Fastener material and condition (correct fastener material is stainless steel).
• Strainers – verify that strainers are not touching the hull or tank bhds.
• TLI and/or float switch condition.
3.5 Tank closing. The Contractor shall ensure that the tank(s) remain open for at least 24 hours after completion of any KO-authorized repair and preservation procedures. Notify the COR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183.
3.6 Operational test – final. After all authorized work is complete, in the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLI(s) to be in satisfactory operating condition (see 4.1 (Equipment operation)). Submit a CFR.
4. NOTES
24 (Rev-0)
12310_JLW_0111_87WPB
WORK ITEM 6: Oily Water Tank, Preserve (D)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to preserve the following tank:
TYPE OF
TANK LOCATION CAPACITY - 95%
(gallons)
% OF TANK
COATING REPAIR
Oily Water STBD Centerline, between FR 13 & 14 85 100%
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 085-001, Rev -, Tank Capacity - 95% Curves Coast Guard Drawing 87 WPB 593-002, Rev C, Oily Water Separator Piping Coast Guard Drawing 87 WPB 601-001, Rev L, Outboard Profile & General
Arrangements
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General Requirements Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2012, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2012, Temporary Hull Accesses
OTHER REFERENCES
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS)
C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General. The Contractor shall accomplish the following for the tank listed in paragraph 1.1
25 (Rev-0)
(Intent). Refer to Coast Guard Drawing 87 WPB 601-001 and 87 WPB 085-001.
3.1.1 Operational test – initial. Prior to commencement of work, the Contractor shall witness an operational pre-test by Coast Guard personnel of all designated tank TLIs to demonstrate existing operational condition. Submit a CFR.
3.1.2 Temporary access openings. Due to limited access to work areas, the Contractor may, with express permission of the KO (via submission of a CFR), cut access holes to facilitate accomplishment of the work specified herein.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .