RFP – HSCG23-09-R-MNQ234, AMENDMENT 8
FINAL
ATTACHMENT 1
MASTER QUESTION SET 3 FOR
BOATSWAIN’S MATE “A” SCHOOL TRAINING BOAT
| QUESTIONS |
| USCG ANSWERS |
QUESTION #1: Please define "all sea conditions".
REF: RFP, Attachment (A) – Specification 051-2.1 ANSWER #1: Sea conditions up to the Operating Environment limits of 6 foot seas and 30 knot winds as indicated in Specification 070-6.2.
QUESTION #2: Does the government have a preference for Interior Finish materials other than the guidance of no wood shall be used (078-5.1)?
REF: RFP, Attachment (A) – Specification 078-5.1 ANSWER #2: No.
QUESTION #3: The E-4 Lightning Protection Standard has been changed to the TE-4 Lightning Protection Technical Information Report. Should TE-4 be used in place of E-4?
REF: RFP, Attachment (A) – Specification 300-1.1 ANSWER #3: Yes.
QUESTION #4: The part number corresponds with a Marinco part number. Should the Marinco plug #4100C12R or equal be used?
REF: RFP, Attachment (A) – Specification 320-2.5 ANSWER #4: The Hubbel part number is correct.
See: http://www.hubbellcatalog.com/wiring/section-v-datasheet.asp?FAM=Marine&PN=M4100C12R
QUESTION #5: The specified search light only has 200,000 candela intensity. Is 200,000 candela acceptable or should another light or bulb be used that has 500,000 candle power?
REF: RFP, Attachment (A) – Specification 332-1.1 ANSWER #5: The ACR RLC100-12D is acceptable at 200,000 candlepower.
QUESTION #6: CLIN 2006 and CLIN 4006 Familiarization Training in the provided Price Scenario Worksheet states a quantity of zero. Should the quantity be for the respective number of boats ordered in that year?
REF: RFP, Attachment (D) – Price Scenario Worksheet ANSWER #6: The Price Scenario Worksheet is correct. It is expected the boats in years 2-4 will go to Yorktown, which will already have Training Boats and will not need the training. The last two boats on the contract may go to other units that would need training. If this happens, a contract change will be negotiated to modify the shipping location.
QUESTION #7: In the RFP synopsis, section 10 it appears that copies of the OEM manuals are requested. Is this meant to be submitted with the proposal?
REF: RFP Synopsis, – Section 10 ANSWER #7: The manuals are not required.
FINAL