HPS NW Structured Cabling - Front Ends Complete (1).pdf
PDF 3 MB Posted
- Attached to
- Southwest Elementary School Structured Cabling
- Solicitation number
- RFP HOWE 260000000985 2
- Issued by
- Livingston County, Michigan
About this file
Summary
This is an Advertisement for Bids and associated contract documents issued by Howell Public Schools in Michigan for structured cabling work at Northwest Elementary School located at 1233 Bower Street, Howell, Michigan 48843. The scope of work includes providing all labor, materials, equipment, and services necessary to complete communications structured cabling systems, including copper cabling, optical fiber cabling, cabinets, racks, frames, patch panels, faceplates, connectors, fire/smoke seals, cored sleeves, labeling, testing, and closeout documentation for both interior and exterior applications. The pre-bid meeting is scheduled for Wednesday, February 4th, 2026 at 10:00 AM via Microsoft Teams. Bids are due by 12:00 noon EST on Wednesday, February 25th, 2026, submitted electronically through Precon Suite or as hard copy sealed bids to the Howell Public Schools Administration Building, 411 N. Highlander Way, Suite D, Howell, Michigan 48843. The bid opening and public reading will occur on February 25th, 2026 at 1:00 PM via Microsoft Teams. Contract award is anticipated on or about March 10th, 2026, with submittals complete by April 30th, 2026, and substantial completion by May 31st, 2027. The project is part of the Howell Public Schools 2023 Bond Program.
Bids exceeding the state threshold of $31,321 must be accompanied by either a certified cashier's check or U.S. treasury listed security bond equal to 5% of the bid amount. Successful bidders with proposals of $50,000 or more are required to furnish a satisfactory Performance and Payment Bond in the amount of 100% of the bid, with the cost included in the proposal. All bids must include sworn and notarized statements disclosing familial relationships with Board of Education members, compliance with the Iran Economic Sanctions Act, and an Equal Opportunity Statement. The Contract Sum is based on a stipulated sum arrangement, and bidders must provide unit prices for specified structured cabling items as detailed in Section 004322. Contractor qualification requirements include three years of financial statements prepared by an independent CPA, evidence of successful completion of similar projects within the past five years, OSHA 300A forms and EMR for the prior three years, sample certificates of insurance, and a letter stating bonding capacity. All applicable sales, use, employment, and other taxes must be included in the bid. The project is not tax exempt. The Board of Education reserves the right to reject any or all bids in whole or in part and to waive any informality, selecting the bid it determines to be in the best interest of the Owner rather than necessarily accepting the lowest bidder.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HPS SW Structured Cabling - Front Ends Complete (1).pdf | ||
| 25 HPS SWES 01 Clarifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADVERTISEMENT FOR BIDS
HOWELL PUBLIC SCHOOLS
2023 BOND PROGRAM
NORTHWEST ELEMENTARY SCHOOL
STRUCTURED CABLING
Howell Public Schools will receive firm prime contractor bids for the labor, materials, equipment, and all other services to complete the structured cabling scope of work at the following two projects: Northwest Elementary School located at 1233 Bower St., Howell, MI 48843.
The bid documents consist of Plans and Specifications prepared by Kingscott Associates, and Front-End documents consisting of Instructions to Bidders, Scopes of Work, and Bid Forms prepared by AUCH Construction. Documents may be downloaded from Precon Suite (formerly Pipeline Suite) on or after Wednesday, January 28th, 2026. If you need assistance viewing bid documents or project documents through Precon Suite, please contact Amal Morrison with AUCH Construction at 248-334- 2000.
A Pre-Bid meeting will be held virtually on Microsoft Teams on Wednesday, February 4th, 2026 at 10:00 AM. To access the Microsoft Teams meeting, please use the following URL: https://www.microsoft.com/en-us/microsoft-teams/join-a-meeting/ then enter… Meeting ID: 213 709 239 896 04 Passcode: TU3Sj3bR This pre-bid meeting will be for both Northwest Elementary and Southwest Elementary structured cabling bids. While attendance is not mandatory, participation in this meeting is strongly encouraged for all bidders.
Bids will be accepted via Precon Suite for electronic bid submission. Hard copy sealed bids will also be accepted; however, we strongly encourage using the Precon Suite electronic submission process. Please upload the appropriate proposal forms provided by the construction manager in the submission. If hard copy bids are delivered, they must be a sealed bid on the forms furnished by the Construction Manager and must be completed in full. An opaque envelope bearing your proposal must identify your company, the project name, the proposal being bid and be addressed and delivered to:
Howell Public Schools Administration Building 411 N. Highlander Way; Suite D Howell, MI 48843 Attn: Mr. Paul Pominville, Assistant Superintendent of Operations and Technology Project: HPS Northwest Elementary Structured Cabling
Bids must be delivered no later than 12:00 noon (EST), Wednesday, February 25th, 2026 to the locations indicated above.
The Board of Education will not accept bids submitted after the date and time specified for bid submission. All late bid proposals will be returned to the bidder unopened. Precon Suite will not allow electronic bid submissions after the due date and time.
Completing the electronic bid submission questions and uploading bid forms does take time, which must be accounted for and be fully completed and submitted prior to the bid due date and time.
Bids over the State threshold of $31,321 must be accompanied with either a certified cashier’s check or a U.S. treasury listed security bond in the amount of 5% of the bid amount. Bids received without this guaranty will not be read or considered. Electronic scans of the cashier’s checks are not accepted. All cashiers’ checks must be delivered prior to the due date and time, and be made payable to Howell Public Schools. Cashier’s Checks will be returned to the bidder upon execution of the contract. All proposals shall be firm for a period of ninety (90) days.
Bids must be accompanied by a sworn and notarized statement disclosing any familial relationship that exists between the owner or any employee of the bidder and any member of the Board of Education, or the Superintendent. Additionally, bids shall be accompanied by a sworn and notarized statement for the Iran Economic Sanctions Act Affidavit of Compliance and Equal Opportunity Statement. Bids not accompanied by these documents will not be accepted.
Bids will be publicly opened and read via a public and virtual meeting on Microsoft Teams held at the Howell Public Schools
Admin. Building starting at 1:00 PM on Wednesday, February 25th, 2026 in the Edinburgh Room. To access the MS Teams meeting, please use the following URL: https://www.microsoft.com/en-us/microsoft-teams/join-a-meeting/ then enter… Meeting ID: 210 197 186 715 09 Passcode: yw9Vb6KS
Successful bidders whose proposals are $50,000 or more will be required to furnish a Satisfactory Performance and Payment Bond in the amount of 100% of their bid. The cost of the Bond shall be included in each proposal.
The Board of Education reserves the right to reject any and/or all bids in whole or in part, and to waive any informality therein.
The Board of Education reserves the right to accept that bid which in its opinion is in the best interest of the Owner, or to award the contract to an alternate bidder other than the bidder(s) submitting the best financial Bid (low bidder) in its sole and absolute discretion.
Board of Education Howell Public Schools
HOWELL PUBLIC SCHOOLS INSTRUCTIONS TO BIDDERS
2023 Bond Program Northwest Elementary Structured Cabling
CM – INSTRUCTIONS TO BIDDERS
DATE: January 28, 2026
PROJECT: HOWELL PUBLIC SCHOOLS
2023 BOND PROGRAM
NORTHWEST ELEMENTARY STRUCTURED CABLING
DESCRIPTION: Structured Cabling for the new Northwest Elementary
TRADES: Proposal 27 : Structured Cabling
See Scopes of Work as listed in Proposal Forms.
All bidders are advised to make note of project schedule and completion date.
OWNER: HOWELL PUBLIC SCHOOLS
411 N. Highlander Way
Howell, MI 48834
CM: AUCH CONSTRUCTION
65 University Drive Pontiac, MI 48342 248-334-2000 Fax: 248-334-3404 Russ Ragone, Project Manager
ARCHITECT: KINGSCOTT ASSOCIATES
259 E. Michigan Ave., Suite 308 Kalamazoo, MI 49007 Steve Lucas, Construction Administrator
BIDDING
PROCEDURE: It is mandatory that the specific procedures be followed. These are summarized here:
1. Sealed bids on forms provided. Envelope must show your company name, project name, and category of work being bid. Address to:
Howell, MI 48843
Attention: Paul Pominville, Assistant Superintendent of Operations and Technology Project: HPS Northwest Elementary
2. Bids over the State threshold of $31,321 must be accompanied with either a certified cashier’s check or a U.S. treasury listed security bond in the amount of 5% of the bid amount. Bids received without this guaranty will not be read or considered. Electronic scans of the cashier’s checks are not accepted. All cashiers’ checks must be delivered prior to the due date and time, and be made payable to Howell Public Schools. Cashier’s Checks will be returned to the bidder upon execution of the contract.
3. Successful bidders for work in excess of $50,000 will be required to provide Payment and
Performance Bonds issued by sureties approved by the U.S. Treasury Department and licensed to do business in Michigan. Sureties must be acceptable to the CM and Howell Public Schools. Refer to the General Conditions of the Contract for Construction for the detailed requirements of the Payment & Performance Bonds.
4. Bids due by or before 12:00 PM, February 25th, 2026 electronically via Precon Suite (formerly
Pipeline Suite) or hard copies at the Howell Public Schools Administration Offices, 411 N.
Highlander Way, Suite D, Howell, MI 48843. All late bid proposals will be returned to the bidder unopened. Precon Suite will not allow electronic bid submissions after the due date and time.
Completing the electronic bid submission questions and uploading bid forms does take time, which must be accounted for and be fully completed and submitted prior to the bid due date and time.
Northwest Elementary Structured Cabling
5. Bids will be publicly opened and read via a public and virtual meeting on Microsoft Teams held at the Howell Public Schools Admin. Building starting at 1:00 PM (EST) on Wednesday, February 25th, 2026 in the Edinburgh Room. To access the Microsoft Teams meeting for the bid opening, please use the following URL: https://www.microsoft.com/en-us/microsoft-teams/join-a-meeting/ then enter… Meeting ID: 210 197 186 715 09 Passcode: yw9Vb6KS
6. A Pre-Bid meeting will be held virtually on Microsoft Teams on Wednesday, February 4th, 2026 at 10:00 AM. To access the Microsoft Teams meeting, please use the following URL:
https://www.microsoft.com/en-us/microsoft-teams/join-a-meeting/ then enter… Meeting ID: 213 709 239 896 04 Passcode: TU3Sj3bR This pre-bid meeting will be for both Northwest Elementary and Southwest Elementary structured cabling bids. While attendance is not mandatory, participation in this meeting is strongly encouraged for all bidders.
7. No proposal shall be withdrawn for a period of 90 days from date of bid.
8. Bids must include a signed and notarized Familial Disclosure Statement and Iran Economic
Sanctions Act Affidavit of Compliance as well as a signed Equal Opportunity Statement. Bids not accompanied by these documents will not be accepted.
CONTRACTOR’S
QUALIFICATION
STATEMENT:
Contractor may be required to provide the following documents as part of post bid evaluation; failure to provide said documents may disqualify contractor for consideration for award of contract:
1. Online Auch qualification statement located by clicking the link at the bottom of the homepage at www.auchconstruction.com or AIA 305 qualification statement and supplemental information as requested.
2. Three (3) years financial statements prepared by an independent Certified Public
Accountant.
3. Evidence of the successful completion of the projects over the past five (5) years of similar size, scope and value to this project. Work under those projects must have been performed by its own workforce and under the company name.
4. Evidence of the contractor’s safety record including OSHA 300A forms for the prior 3 years and the contractor’s EMR for the last 3 years on their insurance carrier’s letterhead.
5. Contractor’s sample certificate of insurance.
6. Letter stating the contractor’s bonding capacity on their insurance carrier’s letterhead.
TAXES: This project is not tax exempt. All applicable rates, use, employment and other applicable taxes are to be included in your proposal.
BIDDING
DOCUMENTS: The bid documents consist of Plans and Specifications prepared by Kingscott Associates, and Front
End documents consisting of Instructions to Bidders, Scopes of Work, and Bid Forms prepared by AUCH Construction. Documents may be downloaded from Precon Suite (formerly Pipeline Suite) on or after Wednesday, January 28th, 2026. If you need assistance viewing bid documents or project documents through Precon Suite, please contact Amal Morrison with AUCH Construction at 248-334- 2000.
Drawings and Specifications remain the property of the Architect.
Northwest Elementary Structured Cabling
QUESTIONS, OR
DISCREPANCIES: Should a bidder find discrepancies or ambiguities in, or omissions from the Contract
Documents, or should it be in doubt as to their true meaning, it shall notify the Architect or C.M. at once, or in any case not less than seven (7) days before the proposal due date. The Architect shall review same where information sought is not clearly indicated or specified, and shall distribute an addendum to all bidders of record. Neither the Owner, Architect, nor the C.M. shall be responsible for any oral instructions. No addendum will be issued later than two (2) days prior to bid due date.
The Board of Education reserves the right to reject any and/or all bids in whole or in part, and to waive any informality therein.
The Board of Education reserves the right to accept that bid which in its opinion is in the best interest of the Owner, or to award the contract to an alternate bidder other than the bidder(s) submitting the best financial Bid (low bidder) in its sole and absolute discretion.
SITE LOGISTICS
PLAN: The site logistics plan shall be referenced for coordination and inclusion as part of the bid documents.
CONTRACTOR
MILESTONE
SCHEDULE: Contractors will abide by the following milestone schedule requirements:
• Bids Due: February 25th, 2026
• Post-bid review conference: February 26th, 2026
• Contracts to be awarded on or about: March 10th, 2026
• Submittals Complete: April 30th, 2026
• Substantial Completion (all trades): May 31st, 2027
• Training & Closeouts by: May 1st, 2027
PROJECT
SCHEDULE: The project schedule shall be referenced for coordination and inclusion as part of the bid documents.
The project schedule is a general guideline; thus every single specific item associated with this project may not be specifically listed; however, general construction sequencing will serve as the guiding framework. Updates to the project schedule should be anticipated and abided by.
END OF SECTION
Northwest Elementary – Structured Cabling
Bid Proposal Form 004113 1
BID PROPOSAL FORM FOR TRADE CONTRACTS
Note: This sheet, proposal sheet and last two sheets of this proposal form must be filled in to be complete.
Incomplete proposals may be disqualified.
NAME OF BIDDER:
ADDRESS:
CITY/STATE/ZIP:
CONTACT PERSON: E-MAIL:
PHONE: FAX:
CONSTRUCTION
MANAGER: AUCH CONSTRUCTION
65 University Drive Pontiac, MI 48342 Attn: Russ Ragone, Project Manager
ARCHITECT: KINGSCOTT ASSOCIATES
259 E. Michigan Ave., SUITE 308 Kalamazoo, MI 49007 Attn: Steve Lucas, Construction Administrator
PROPOSAL: Pursuant to and in compliance with the instructions to bidders and contract documents for the above-named project, the undersigned agrees to enter into a contract with the Howell Public Schools.
The undersigned hereby acknowledges that his proposal, as stated below, includes all the labor and services required and only those materials in compliance with the specifications and shown on the drawings.
The undersigned acknowledges that he has carefully examined the drawings and specifications and visited the site to fully inform himself of all existing conditions and limitations, and that his proposal includes a sum to cover the cost of all items included in the contract.
The undersigned further agrees to commence work on the project following the signing of the contract or within five working days thereof.
The undersigned agrees to coordinate, properly schedule and complete his portion of the work in compliance with the project schedule.
Bid Proposal Form 004113 2
GENERAL NOTES
(Applicable to all Bid Items)
A. The Contractor shall be deemed to be aware of, and include the cost for, all state and local laws, codes, ordinances, building rules and regulations, and other statutory provisions, all as are or may become applicable to the Work.
B. Contractor shall coordinate with other trades that affect the installation of the Work, and with the
Construction Manager.
C. The Construction Manager shall provide key benchmark and control points. All other layout to be provided by the Contractor.
D. Bidders shall exclude costs of testing from bid unless required by the proposal form or the trade specification, and shall cooperate with testing agency hired by the Construction Manager.
E. Each Trade Contractor shall cooperate and coordinate with other contractors for expedient completion of the
Work of this project.
F. The Scope of Work for each Bid Item includes any hoisting, delivery, receiving, handling and/or storage requirements. The term Provide is defined by AIA as Furnished and Installed for its final intended use.
G. Schedule and sequence manpower loading, and prefabrication and erection of work shall be in accordance with the construction completion dates and as indicated on the construction schedule.
H. The Scope of Work for each Bid Item includes cleaning and maintaining streets free of dirt, mud, gravel and other debris caused by the Work of that Bid Item. Dust control onsite is the responsibility of the contractor who’s dust is caused by the Work of that Bid Item. Contractors are cautioned that local authorities intend to enforce local ordinances in this regard, and violators will be ticketed and prosecuted.
I. The Scope of Work for each Bid Item includes strict adherence to the safety requirements and considerations as defined in the General Conditions and Supplementary General Conditions.
J. Each Contractor shall review existing building and site conditions prior to commencing the Work and advise
Construction Manager of any claim to changes in the Work within three (3) calendar days therefore, or waive its right for claim for changes in the existing site condition. Each Contractor shall be responsible for restoring site to its original conditions upon completion of its work.
K. All excess materials and delivery/packaging materials shall be legally disposed of off-site, unless otherwise indicated in the contract documents.
L. All bidders are required to review and provide pricing for (where applicable) the alternate work itemized on the Bid Proposal Form with their bids. Material and equipment suppliers are requested to list the total State of Michigan sales and use tax included in their proposal.
M. The apparent low bidders shall furnish a list of subcontractors and suppliers within 3 days of request for same.
N. The Contractor is committed to nondiscrimination in employment. All qualified applicants are welcome to apply for jobs with the Contractor. The Contractor shall not discriminate against any employee or applicant for employment because of race, color, religion, sex, age, physical impairment, national origin, height, weight, or marital status.
O. Summary.
All bidders are expected to familiarize themselves with the Instruction to Bidders, this Bid Proposal Form as applicable, General and Supplementary Conditions, and the drawings and technical specifications covering their work. The following proposal sheets summarize the general scope of work in an attempt to help define the work of the separate trade contractors. The individual trade proposal forms are a guide to the scope of work, but are not intended to be all inclusive of the work to be covered.
Northwest Elementary – Structured Cabling
Bid Proposal Form 004113 3
PROPOSAL 27: Structured Cabling
GENERAL SCOPE: General Conditions CM Supplementary Conditions and Procedures
The scope of work shall include the following specification sections in their entirety, unless specifically stated as being excluded by this scope of work.
Technical Specifications and Construction Documents for
Kingscott Project Number 2600-41C
Division 00 – Procurement & Contracting Requirements Division 01 – General Requirements Specification Section 271116 – Communications Cabinets, Racks, Frames, and Enclosures Specification Section 271323 – Communications Optical Fiber Backbone Cabling Specification Section 271513 – Communications Copper Horizontal Cabling
The scope of work shall specifically include, yet not be limited to the following items for the entire set of documents:
1. Provide all labor, material & equipment necessary to complete the communications structured cabling systems scopes of work.
2. Provide all documentation and coordination to comply with E-Rate requirements, as detailed in the project documents and Specification Section 011100 – Summary of Work.
3. Provide all permits, fees, bonds, inspections etc. required for this proposal’s of work.
4. Provide all required layout, surveying & engineering necessary to perform this work.
5. Contact Miss Dig and a private utility locator to locate existing utilities prior to excavations.
6. Provide the communications structured cabling systems including, but not limited to, copper cabling, optical fiber cabling, cabinets, racks, frames, etc. COMPLETE for both interior and exterior.
7. Include multiple mobilizations as necessary to meet the project schedules and logistics plans.
8. Coordinate and obtain all required specialty testing and reports specific to this work.
9. Provide cored sleeves for all penetrations of the masonry, floor, or foundation system.
10. Provide fire/smoke seals for all penetrations created by this contractor’s work including all penetrations created for above ceiling cabling. Provide sleeves, conduits, and seals as required.
Each seal shall provide 1 hour rating unless otherwise indicated. Provide stickers and label penetrations as indicated.
11. Provide all patch panels as indicated. Connect cabling at the patch panels.
12. Provide all required labeling of patch panels and cabling.
13. Provide fiber and fiber panels as indicated.
14. Provide faceplates and connectors as required.
15. Provide specified supports for this scope of work for above ceiling cabling at as indicated.
16. Provide boring under hardscapes to remain for site fiber. Provide restoration of landscape outside of clearing limits due to sitework performed by this contractor.
17. Provide racks, cable organizers, and all items as indicated to complete the communications room and communications grounding scope of work.
18. Protect existing structures, sidewalks, asphalt, and all other items to remain during execution of this work.
19. Provide daily clean up, removal, and legal disposal offsite of all debris and excess material.
20. Provide all closeout documents, training, attic stock, warranties, as-built drawings, etc. as required.
The scope of work shall specifically exclude the following items:
1. None
TOTAL FOR PROPOSAL 27: $
(Structured Cabling)
UNIT PRICES: (provide unit prices below are same for adds/deducts)
Structured Cabling System: Complete in full the unit price sheet in Specification Section 004322 (also included for download from the Front Ends folder in Precon Suite).
Northwest Elementary – Structured Cabling
Bid Proposal Form 004113 4
CHANGES IN THE WORK: The prices listed above are to include overhead and profit. For authorized changes in the work involving additions to or deductions from the contract price, the bidder agrees to perform or delete such authorized work at net cost to him plus the following percentage of net cost. Percentages shall be considered to be all direct costs. Taxes, social security payments, and insurance premiums shall not be considered direct costs.
For work by Subcontractor's own forces - Maximum 10%
Involving Additions percent
Involving Deductions percent
For work under subcontract – Maximum 7%
Involving Additions percent
Involving Deductions percent
SUBSTITUTIONS: See Schedule 'A' at sheet following end of this Proposal Form for voluntary alternates and/or substitutions.
ADDENDA: If addenda have been received during the bidding period, the bidder shall fill in their numbers and dates, which will be an acknowledgment of his having received same and included in this proposal the work involved.
Addendum No. Dated
Addendum No. Dated
Addendum No. Dated
LABOR, MATL AND
PERFORMANCE BONDS: Successful bidders whose proposals are $50,000 or more are required to furnish a satisfactory Performance and Payment Bond in the amount of 100% of their bid. The cost of the bond shall be included in each proposal and stated below in total.
Bond Premium $
Successful bidders will provide Payment and Performance Bonds issued by sureties listed by the Treasury Department and licensed to do business in Michigan. Sureties must be acceptable to the CM and Howell Public Schools.
Northwest Elementary – Structured Cabling
Bid Proposal Form 004113 5
CONTRACTOR
MILESTONE
SCHEDULE: Contractors will abide by the following milestone schedule requirements:
• Bids Due: February 25th, 2026
• Post-bid review conference: February 26th, 2026
• Contracts to be awarded on or about: March 10th, 2026
• Submittals Complete: April 30th, 2026
• Substantial Completion (all trades): May 31st, 2027
• Training & Closeouts by: May 1st, 2027
TAXES: The bidder shall include all applicable federal, state and municipal sales and excise taxes.
PROPOSAL GUARANTEE: A certified or cashier's check payable to "Howell Public Schools" or a satisfactory bid bond executed by the bidder by a Treasury listed surety company in the amount of five percent (5%) of the bid shall be included with any proposal in excess of $31,321.00
No proposal shall be withdrawn for a period of 60 days from the date of bid.
Accompanying this proposal is a proposal guarantee, as required, consisting of:
ACCEPTANCE OF
PROPOSAL: The Owner reserves the right to reject any and/or all bids and to waive any informalities should it be deemed in its best interest to do so.
Upon receipt of written notice of the acceptance of this bid, the bidder will execute the formal contract within 10 days.
Respectfully submitted, Company:
Name:
Title:
Date:
Phone: Fax:
E-Mail:
INSTRUCTIONS: Submit one copy and retain one for your file.
Submit the Familial Disclosure Statement, Equal Opportunity Statement, and Iron
Economic Sanctions Act Affidavit included herein.
Failure to comply will result in the disqualification of the bidder’s proposal.
**END OF PROPOSAL**
Bid Proposal Form 004113 6
SCHEDULE 'A'
VOLUNTARY ALTERNATES / SUBSTITUTIONS
NOTE: Value Engineering is encouraged.
The Bidder proposes the following Voluntary Alternates for the sums to be deleted from the Base Bid as stated below:
VOLUNTARY ALTERNATE NO. 1:
which would save the Owner
( ________ ) Dollars
VOLUNTARY ALTERNATE NO. 2:
VOLUNTARY ALTERNATE NO. 3:
The Bidder proposes the above Alternates for the following reason:
The Bidder requests acceptance of the following substitutions: (Attach)
Wright & Hunter, LLC Northwest Elementary School Technology Advisors Howell Public Schools Detroit, Michigan Howell, Michigan
2600.41C UNIT PRICES FORM 004322 - 1
SECTION 004322 - UNIT PRICES FORM
PARTICULARS
1.1 THE FOLLOWING IS THE LIST OF UNIT PRICES REFERENCED IN THE BID
SUBMITTED BY:
1.2 (BIDDER) ________________________________
1.3 TO (OWNER ): HOWELL PUBLIC SCHOOLS
1.4 DATED _________________ AND WHICH IS AN INTEGRAL PART OF THE BID FORM.
1.5 THE FOLLOWING ARE UNIT PRICES FOR SPECIFIC PORTIONS OF THE WORK AS
LISTED, AND ARE APPLICABLE TO AUTHORIZED VARIATIONS FROM THE
CONTRACT DOCUMENTS. ALL UNIT PRICES SHALL INCLUDE MATERIALS,
INSTALLATION, OVERHEAD, AND PROFIT
STRUCTURED CABLING UNIT PRICES
2.1 PROVIDE AND INSTALL (1) ONE CAT 6A CABLE IN WALL, INCLUDING JACKS ON
BOTH ENDS, TERMINATIONS, FACEPLATE, LABELING, AND TESTING.
2.2 PROVIDE AND INSTALL (2) TWO CAT 6A CABLE IN WALL, INCLUDING JACKS ON
BOTH ENDS, TERMINATIONS, FACEPLATE, LABELING, AND TESTING.
2.3 PROVIDE AND INSTALL (1) ONE CAT 6A CABLE IN CEILING, INCLUDING JACKS
ON BOTH ENDS, TERMINATIONS, SURFACE BACK BOX, LABELING, AND TESTING.
2.4 PROVIDE AND INSTALL (2) TWO CAT 6A CABLE IN CEILING, INCLUDING JACKS
ON BOTH ENDS, TERMINATIONS, SURFACE BACK BOX, LABELING, AND TESTING.
2.5 PROVIDE AND INSTALL (1) ONE CAT 6 CABLE TO PARKING LOT LIGHTING POLES,
INCLUDING JACKS ON BOTH ENDS, TERMINATIONS, FACEPLATE, LABELING,
AND TESTING. $_________________________________________________________
2.6 PROVIDE AND INSTALL (1) ONE 48-PORT MODULAR PATCH PANEL NOT
POPULATED WITH JACKS.
2.7 PROVIDE AND INSTALL (1) ONE EQUIPMENT RACK, AS SPECIFIED.
Northwest Elementary – Structured Cabling
Bid Proposal Form 004113 1
EQUAL OPPORTUNITY STATEMENT
Howell Public Schools authority:
It is the publicly stated policy of not to discriminate against any employee, applicant for employment, contractor, or material supplier, because of race, religion, color, national origin, ancestry or sex. With regard to employment, such non-discrimination includes, but is not limited to, our (my) policies of recruitment, recruitment, advertising, selection for apprenticeship or other training, rates of pay, promotion, transfer, lay-off or termination.
In all advertising for employment, subcontractors, or suppliers we (1) shall state that all applicants or respondents will receive consideration without regard to race, religion, color, national origin, ancestry or sex.
We (I) understand that any contract for the Howell Public Schools – Northwest Elementary shall be in consideration of our maintaining the above mentioned non-discrimination policy.
We (I) understand that we (I) may be required to submit further information covering the race, color and work classification for our employees and those of our sub-contractors to be employed on this project.
NAME OF BIDDER (COMPANY):
SIGNATURE:
NAME:
(Typed or Printed)
TITLE:
Bid Proposal Form 004113 2
FAMILIAL DISCLOSURE FORM
All bidders must complete the following disclosure form in compliance with MCL 380.1267 and attach this information to the bid.
By the attached sworn and notarized statement, we are disclosing the following familial relationship(s) that exists between the owner or any employee of the bidder and any member of the Howell Public School Board of Education, or Board of Directors or the superintendent of the school district, immediate superintendent of the intermediate school district, or chief executive officer of the public school academy.
Disclose any familial relationship and complete the form below in its entirety:
The following are familial relationships as described above (provide employee name, family contact name, family contact position, and familial relationship or NONE).
NONE
-OR-
Owner/ Employee Name Related To: Relationship
1.
2.
3.
4.
5.
Signature(s)
Title:
Name of Firm:
STATE OF )
) SS
COUNTY OF )
On this day of , 20 , before me a Notary Public in and for said county, personally appeared , agent of the said firm and who acknowledged the same to be his free act and deed as such agent.
Notary Public
My Commission Expires
Bid Proposal Form 004113 3
AFFIDAVIT OF COMPLIANCE – IRAN ECONOMIC SANCTIONS ACT
Michigan Public Act No. 517 of 2012
The undersigned, the owner or authorized officer of the below named contractor (the “Contractor”), pursuant to the compliance certification requirement provided in the Howell Public Schools (the “School District”) Request For Proposals For Northwest Elementary (the “RFP”), hereby certifies, represents and warrants that the Contractor (including its officers, directors and employees) is not an “Iran linked business” within the meaning of the Iran Economic Sanctions Act, Michigan Public Act No. 517 of 2012 (the “Act”), and that in the event Contractor is awarded a contract as a result of the aforementioned RFP, the Contractor will not become an “Iran linked business” at any time during the course of performing the Work or any services under the contract.
The Contractor further acknowledges that any person who is found to have submitted a false certification is responsible for a civil penalty of not more than $250,000.00 or 2 times the amount of the contract or proposed contract for which the false certification was made, whichever is greater, the cost of the School District’s investigation, and reasonable attorney fees, in addition to the fine. Moreover, any person who submitted a false certification shall be ineligible to bid on a request for proposal for three (3) years from the date the it is determined that the person has submitted the false certification.
CONTRACTOR:
BIDDER’S FIRM NAME
BY (SIGNATURE)
PRINTED NAME AND TITLE
STATE OF MICHIGAN )
)SS
COUNTY OF )
Subscribe and sworn before me on this Seal:
day of , 20 , a Notary Public in and for County, Notary Public
My Commission Expires
JOB NO. 2600.41C
SHEET TITLE
SHEET NO.
REVISIONS/REVIEW
KEY PLAN
DATE
NORTH
SCHEMATIC DESIGN 05.16.2024
H ow el l P ub lic
S ch oo ls
KALAMAZOO | CHELSEA | GRAND RAPIDS | ROYAL OAK
N or th w es t E le m en ta ry Sc ho ol
DESIGN DEVELOPMENT 09.12.2024
CONSTRUCTION DOCUMENTS 12.19.2024
A U
C H
Staging & Parking
AUCH Trailer
Construction Gate A
Temporary Road
Gate & Construction Fence June 2027
Construction Fence June 2025
Construction Fence June 2025
Construction Fence June 2025
No Heavy Equipment After Install of Underground Storm Water Chambers
Construction Gate B
Construction Gate C
Construction Fence June 2027
Sitework, Utilities, Curb, & Asphalt Leveling Course : June 1, 2026 to Aug 12, 2026
Sitework Phase 2
Sitework Phase 1 Everything within Red Fence area June 1, 2025 through July 2027
Sitework Phase 3 Building Demo, Sitework, Utilities, Curb, & Asphalt complete : June 1, 2027 to Aug 12, 2027
Site Logistics Plan AUCH Construction
Construction Fence and Gates (2) June 2025
Excerpt from C2.2
Front Entrance Area of Existing School Building
Existing Building Sign
Mechanical Room (early start/completion for foundations & masonry)
Topsoil Stockpile
Area
September 5, 2025
Temporary Road
Activity ID Activity Name Original Duration
Start Finish
HPS : Northwest Elementary SchoolHPS : Northwest Elementary School 760 9-12-24 A 9-8-27
PreconstructionPreconstruction 470 9-12-24 A 7-20-26
DesignDesign 155 9-12-24 A 2-14-25 A
PermittingPermitting 96 11-1-24 A 7-18-25 A
BiddingBidding 57 1-20-25 A 4-4-25 A
Submittals (TBD at Post-Bid Meetings)Submittals (TBD at Post-Bid Meetings) 232 3-17-25 A 2-13-26
Procurement (TBD at Post-Bid Meetings)Procurement (TBD at Post-Bid Meetings) 120 2-2-26 7-20-26
ConstructionConstruction 632 3-24-25 A 9-8-27
Phase 1Phase 1 598 3-24-25 A 7-21-27
SiteSite 598 3-24-25 A 7-21-27
CS1380 Miss Dig & Private Utility Locating 5 3-24-25 A 3-28-25 A
CS1000 Mobilization 1 3-31-25 A 3-31-25 A
CS1010 Construction Fence 5 3-31-25 A 4-7-25 A
CS1020 Soil Erosion 3 4-3-25 A 4-8-25 A
CS1030 Site Clearing & Demolition 15 4-4-25 A 4-23-25 A
CS1490 AUCH Construction Trailer Placement 1 4-11-25 A 4-11-25 A
CS1040 Mass Grading 20 4-16-25 A 5-23-25 A
CS1360 Temp Haul Road (away from building pad) & staging/parking area 15 4-21-25 A 5-23-25 A
CS1060 Rough Grading 15 5-12-25 A 7-31-25 A
CS1520 Underground Utilities - Sanitary 10 5-26-25 A 6-13-25 A
CS1180 Building Pad Rough Grade Complete 1 5-30-25 A 5-30-25 A
CS1080 Sanitary Tie-in under Bower St. (contingent on Plumbing Permit) 2 6-2-25 A 6-3-25 A
CS1510 Underground Utilities - Water 7 6-9-25 A 6-13-25 A
CS1370 Temp Haul Road around bldg perimeter (as masonry progresses) 20 6-23-25 A 9-26-25 A
CS1090 Storm Structure Tie-in under existing SE corner 2 6-25-25 A 6-27-25 A
CS1070 Underground Storm Water Detention System 15 6-30-25 A 7-18-25 A
CS1050 Underground Utilities - Storm Pipe & Structures 30 7-7-25 A 8-8-25 A
CS1120 Temp Playground Structure Relocation 10 7-18-25 A 7-25-25 A
CS1170 Bus Lot Rough Grade Complete 1 7-31-25 A 7-31-25 A
CS1220 Main Parking Lot & Loop Rough Grade Complete 1 7-31-25 A 7-31-25 A
CS1110 Underground Site Electrical 15 8-25-25 A 9-19-25 A
CS1160 Bus Lot Light Pole Bases & Electrical 5 9-22-25 A 9-26-25 A
CS1260 Main Parking Lot & Loop Light Pole Bases & Electrical 5 9-22-25 A 9-26-25 A
CS1100 Water Main Tap (contingent on Plumbing Permit) 10 11-7-25 A 11-10-25 A
CS1500 Frost Laws Lift 1 3-31-26* 3-31-26
CS1550 Topsoil & Seed at UG Storm Detention (Landscaping Phase 1 Area) 5 4-1-26* 4-7-26
CS1200 Remove Temp Haul Road Around Bldg & Rough Grade All Areas 10 7-28-26* 8-11-26
CS1190 Playground Area Rough Grade Complete 1 8-11-26 8-12-26
CS1210 Site Paving & Landscaping Rough Grade Complete 1 8-11-26 8-12-26
CS1530 Touch-up, Recompact & Recertify Bus Lot Rough Grade 3 8-11-26 8-14-26
CS1540 Touch-up, Recompact & Recertify Main Parking Lot & Loop Rough Grade 3 8-11-26 8-14-26
CS1270 Main Parking Lot & Loop Signage Bases & Electrical 5 8-12-26 8-19-26
CS1280 Seat Wall Foundations 2 8-12-26* 8-14-26
CS1330 Playground Fence Posts at 12" Wide Concrete Curb only 2 8-12-26* 8-14-26
CS1130 Bus Lot Aggregate Base 10 8-14-26 8-28-26
CS1140 Bus Lot Curb & Gutter 10 8-14-26 8-28-26
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2026 2027 2028
Frost Laws Lift
Topsoil & Seed at UG Storm Detention (Landscaping Phase 1 Area)
Remove Temp Haul Road Around Bldg & Rough Grade All Areas
Playground Area Rough Grade Complete
Site Paving & Landscaping Rough Grade Complete
Touch-up, Recompact & Recertify Bus Lot Rough Grade
Touch-up, Recompact & Recertify Main Parking Lot & Loop Rough Grade
Main Parking Lot & Loop Signage Bases & Electrical
Seat Wall Foundations
Playground Fence Posts at 12" Wide Concrete Curb only
Bus Lot Aggregate Base
Bus Lot Curb & Gutter
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
HPS : Northwest Elementary Data Date:1-5-26
Print Date: 1-11-26
Print Date: :1-5-26
Start Finish
CS1230 Main Parking Lot & Loop Curb & Gutter 5 8-14-26 8-21-26
CS1240 Main Parking Lot & Loop Aggregate Base 5 8-14-26 8-21-26
CS1290 Seat Wall Masonry 3 8-14-26 8-19-26
CS1250 Main Parking Lot & Loop Leveling Course 5 8-21-26 8-28-26
CS1300 Site Concrete (All Areas) 20 8-21-26 9-21-26
CS1150 Bus Lot Leveling Course 10 8-28-26 9-14-26
CS1310 Site Concrete at Playground Areas Complete 1 8-28-26 8-31-26
CS1390 Playground Equipment 30 8-31-26 10-13-26
CS1320 Site Concrete at Landscape Courtyard Area Complete 1 9-14-26 9-15-26
CS1340 Playground Fence Posts only 3 9-21-26 9-24-26
CS1350 Playground Fence Chain Link Fabric 2 9-21-26 9-23-26
CS1400 Playground Surfacing 15 10-13-26 11-3-26
CS1410 Landscaping & Plantings (Landscaping Phase 2 Area) 20 11-3-26* 12-3-26
CS1460 Bus Lot Wearing Course 5 5-3-27* 5-7-27
CS1430 Main Parking Lot & Loop Wearing Course 5 5-10-27 5-14-27
CS1470 Bus Lot Striping 2 5-10-27 5-11-27
CS1480 Bus Lot Signage 2 5-10-27 5-11-27
CS1440 Main Parking Lot & Loop Striping 2 5-17-27 5-18-27
CS1450 Main Parking Lot & Loop Signage 2 5-17-27 5-18-27
CS1420 Landscape Restoration & Touchup (Landscaping Phase 2 Area) 15 7-1-27* 7-21-27
BuildingBuilding 494 6-2-25 A 5-4-27
Area 1100 / 2100Area 1100 / 2100 451 6-2-25 A 3-4-27
CB1000 Exterior Foundations Excavation (starting at Mech. Room) 5 6-2-25 A 6-12-25 A
CB1030 Interior Wall & Column Foundations 8 6-3-25 A 6-13-25 A
CB1010 Exterior Foundations Form & Pour (starting at Mech. Room) 7 6-5-25 A 6-13-25 A
CB1160 Exterior Perimeter Below-Grade Masonry 7 6-24-25 A 7-2-25 A
CB1020 Elevator Pit Foundations 5 7-7-25 A 7-11-25 A
CB1410 Waterproofing on Below-Grade Masonry 3 7-17-25 A 7-24-25 A
CB1040 Bearing Exterior Masonry Block Walls - 1st Floor 15 7-23-25 A 8-15-25 A
CB1050 Bearing Interior Masonry Walls - 1st Floor 12 7-23-25 A 8-29-25 A
CB1450 Bearing Interior Masonry Walls - 2nd Floor 12 7-23-25 A 8-29-25 A
CB1400 Foundation Inspection 1 7-25-25 A 7-25-25 A
CB1440 Bearing Exterior Masonry Block Walls - 2nd Floor 15 7-30-25 A 8-29-25 A
CB1420 Backfill Exterior Perimeter Below-Grade Masonry 3 8-4-25 A 8-8-25 A
CB1150 Under-Slab Plumbing 15 9-15-25 A 1-23-26
CB1100 Spray Foam Insulation at Brick Veneer 10 10-17-25 A 12-4-25 A
CB1460 Masonry Brick Veneer 25 11-12-25 A 1-23-26
CB1430 Structural Steel & Joists - 1st Floor 7 11-18-25 A 1-13-26
CB1060 Structural Steel & Joists - 2nd Floor 7 12-8-25 A 1-22-26
CB1110 Metal Framing for Exterior Wall Panels 15 1-5-26 A 2-9-26
CB1490 Weather Protection (windows & openings) 10 1-14-26* 1-27-26
CB1330 Steel Deck - Roof 5 1-22-26* 1-29-26
CB1070 Steel Deck - 1st Floor 7 1-29-26 2-9-26
CB1080 EPDM Roofing 20 1-29-26 2-26-26
CB1170 Second Floor Slab on Deck 7 1-29-26 2-9-26
CB1480 Re-establish Rough Grade 3 2-9-26 2-12-26
CB1500 Start Temp Heat & Thaw Rough Grade Soils 10 2-9-26 2-23-26
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2026 2027 2028
Main Parking Lot & Loop Curb & Gutter
Main Parking Lot & Loop Aggregate Base
Seat Wall Masonry
Main Parking Lot & Loop Leveling Course
Site Concrete (All Areas)
Bus Lot Leveling Course
Site Concrete at Playground Areas Complete
Playground Equipment
Site Concrete at Landscape Courtyard Area Complete
Playground Fence Posts only
Playground Fence Chain Link Fabric
Playground Surfacing
Landscaping & Plantings (Landscaping Phase 2 Area)
Bus Lot Wearing Course
Main Parking Lot & Loop Wearing Course
Bus Lot Striping
Bus Lot Signage
Main Parking Lot & Loop Striping
Main Parking Lot & Loop Signage
Landscape Restoration & Touchup (Landscaping Phase 2 Area)
Under-Slab Plumbing
Masonry Brick Veneer
Structural Steel & Joists - 1st Floor
Structural Steel & Joists - 2nd Floor
Metal Framing for Exterior Wall Panels
Weather Protection (windows & openings)
Steel Deck - Roof
Steel Deck - 1st Floor
EPDM Roofing
Second Floor Slab on Deck
Re-establish Rough Grade
Start Temp Heat & Thaw Rough Grade Soils
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
HPS : Northwest Elementary Data Date:1-5-26
Print Date: 1-11-26
Start Finish
CB1120 Spray Foam Insulation at Exterior Wall Panels 5 2-9-26 2-16-26
CB1130 Sheathing & Weather Barrier at Exterior Wall Panels 15 2-16-26 3-9-26
CB1510 Verify No Frost in Rough Grade Soils 2 2-23-26 2-25-26
CB1180 SOG Sand Base & Insulation 10 2-25-26 3-11-26
CB1470 Under-Slab Electrical 8 3-4-26 3-16-26
CB1140 Exterior Wall Panels 20 3-9-26 4-6-26
CB1190 Slab on Grade 15 3-16-26 4-6-26
CB1560 Metal Roofing 20 3-23-26 4-17-26
CB1520 Concrete Slab Cure 20 4-6-26 5-4-26
CB1360 Aluminum Framing & Glazing 20 4-13-26 5-11-26
CB1090 Non-Bearing Interior Masonry Walls on Thickened Slab areas 15 4-20-26 5-11-26
CB1200 Interior Framing 60 4-20-26 7-14-26
CB1210 Overhead MEP 60 4-20-26 7-14-26
CB1570 MEP Equipment 20 4-20-26 5-18-26
CB1600 Fire Riser & Fire Protection 20 4-20-26 5-18-26
CB1220 In-Wall MEP 25 4-27-26 6-2-26
CB1370 Elevator 60 4-27-26 7-21-26
CB1230 Drywall 60 6-2-26 8-25-26
CB1260 Low Voltage Wiring 15 7-14-26 8-4-26
CB1240 Primer & Paint First Coat 25 8-25-26 9-30-26
CB1290 Millwork & Casework 30 8-25-26 10-7-26
CB1310 Hollow Metal Door, Frames, & Hardware 20 8-25-26 9-23-26
CB1340 Ceiling Grid 30 8-25-26 10-7-26
CB1350 Ceramic Tile 15 8-25-26 9-16-26
CB1580 Mechanical RTU's 10 9-8-26* 9-21-26
CB1590 Emergency Generator 10 9-8-26* 9-21-26
CB1320 Security Hardware 5 9-23-26 9-30-26
CB1380 Lockers 30 9-30-26 11-11-26
CB1530 Polished Concrete 15 9-30-26 10-21-26
CB1540 Concrete Sealer 2 9-30-26 10-2-26
CB1250 Light Fixtures 35 10-7-26 11-25-26
CB1270 Ceiling Tiles 15 11-25-26 12-18-26
CB1300 Flooring 30 12-18-26 2-2-27
CB1390 Food Service Equipment 30 1-12-27 2-23-27
CB1280 Painting Finish Coat 20 2-2-27 3-2-27
CB1550 Resinous Epoxy 2 3-2-27 3-4-27
Area 1200Area 1200 459 6-16-25 A 3-23-27
CB3000 Exterior Foundations Excavation 5 6-16-25 A 6-24-25 A
CB3010 Exterior Foundations Form & Pour 10 6-16-25 A 6-24-25 A
CB3020 Interior Wall & Column Foundations 10 6-16-25 A 6-24-25 A
CB3340 Exterior Perimeter Below-Grade Masonry 7 7-3-25 A 7-8-25 A
CB3360 Waterproofing on Below-Grade Masonry 3 7-18-25 A 2-16-26
CB3350 Backfill Exterior Perimeter Below-Grade Masonry 3 8-4-25 A 8-8-25 A
CB3030 Bearing Exterior Masonry Walls 20 9-3-25 A 1-5-26
CB3040 Bearing Interior Masonry Walls 15 9-3-25 A 1-23-26
CB3130 Under-Slab Utilities 15 9-8-25 A 3-13-26
CB3080 Spray Foam Insulation at Brick Veneer 10 1-5-26 1-16-26
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2026 2027 2028
Spray Foam Insulation at Exterior Wall Panels
Sheathing & Weather Barrier at Exterior Wall Panels
Verify No Frost in Rough Grade Soils
SOG Sand Base & Insulation
Under-Slab Electrical
Exterior Wall Panels
Slab on Grade
Metal Roofing
Concrete Slab Cure
Aluminum Framing & Glazing
Non-Bearing Interior Masonry Walls on Thickened Slab areas
Interior Framing
Overhead MEP
MEP Equipment
Fire Riser & Fire Protection
In-Wall MEP
Elevator
Drywall
Low Voltage Wiring
Primer & Paint First Coat
Millwork & Casework
Hollow Metal Door, Frames, & Hardware
Ceiling Grid
Ceramic Tile
Mechanical RTU's
Emergency Generator
Security Hardware
Lockers
Polished Concrete
Concrete Sealer
Light Fixtures
Ceiling Tiles
Flooring
Food Service Equipment
Painting Finish Coat
Resinous Epoxy
Waterproofing on Below-Grade Masonry
Bearing Exterior Masonry Walls
Bearing Interior Masonry Walls
Under-Slab Utilities
Spray Foam Insulation at Brick Veneer
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
HPS : Northwest Elementary Data Date:1-5-26
Print Date: 1-11-26
Start Finish
CB3370 Masonry Brick Veneer 15 1-19-26 2-6-26
CB3050 Structural Steel & Joists 15 1-26-26 2-13-26
CB3090 Metal Framing for Exterior Wall Panels 15 2-9-26 3-2-26
CB3060 Steel Deck 5 2-16-26 2-20-26
CB3100 Spray Foam Insulation at Exterior Wall Panels 5 2-16-26 2-23-26
CB3070 EPDM Roofing 20 2-26-26 3-26-26
CB3110 Sheathing & Weather Barrier at Exterior Wall Panels 15 3-9-26 3-30-26
CB3140 SOG Sand Base & Insulation 15 3-16-26 4-3-26
CB3380 Metal Roofing 20 3-23-26 4-17-26
CB3150 Slab on Grade 15 4-6-26 4-27-26
CB3120 Exterior Wall Panels 20 4-6-26 5-4-26
CB3160 Non-Bearing Interior Masonry Walls 15 5-11-26 6-2-26
CB3330 Aluminum Framing & Glazing 20 5-11-26 6-9-26
CB3290 Folding Panel Partition 15 6-2-26 6-23-26
CB3170 Interior Framing 35 7-14-26 9-1-26
CB3180 Overhead MEP 35 7-14-26 9-1-26
CB3190 In-Wall MEP 15 7-21-26 8-11-26
CB3200 Drywall 30 8-25-26 10-7-26
CB3210 Low Voltage Wiring 10 9-1-26 9-16-26
CB3220 Primer & Paint First Coat 20 10-7-26 11-4-26
CB3230 Millwork 15 10-7-26 10-28-26
CB3240 Hollow Metal Door, Frames, & Hardware 15 10-7-26 10-28-26
CB3250 Ceiling Grid 15 10-7-26 10-28-26
CB3260 Ceramic Tile 10 10-7-26 10-21-26
CB3280 Security Hardware 5 10-28-26 11-4-26
CB3270 Light Fixtures 20 11-25-26 12-28-26
CB3300 Ceiling Tiles 15 12-28-26 1-19-27
CB3320 Flooring 20 2-2-27 3-2-27
CB3310 Painting Finish Coat 15 3-2-27 3-23-27
Area 1300Area 1300 474 6-25-25 A 4-13-27
CB5000 Exterior Foundations Excavation 5 6-25-25 A 7-1-25 A
CB5010 Exterior Foundations Form & Pour 10 6-25-25 A 7-1-25 A
CB5020 Interior Wall & Column Foundations 10 6-25-25 A 7-1-25 A
CB5340 Exterior Perimeter Below-Grade Masonry 7 7-8-25 A 7-18-25 A
CB5350 Waterproofing on Below-Grade Masonry 3 7-18-25 A 7-24-25 A
CB5360 Backfill Exterior Perimeter Below-Grade Masonry 3 8-4-25 A 8-8-25 A
CB5030 Bearing Exterior Masonry Walls 25 8-7-25 A 10-16-25 A
CB5040 Bearing Interior Masonry Walls 20 8-7-25 A 10-16-25 A
CB5110 Under-Slab Utilities 20 9-24-25 A 4-10-26
CB5320 Spray Foam Insulation at Brick Veneer 10 12-4-25 A 1-30-26
CB5370 Masonry Brick Veneer 20 12-11-25 A 2-27-26
CB5050 Structural Steel & Joists 15 2-16-26 3-6-26
CB5330 Metal Framing for Exterior Wall Panels 20 3-2-26 3-30-26
CB5060 Steel Deck 5 3-9-26 3-13-26
CB5380 Concrete Foundation Column Caps 3 3-16-26 3-18-26
CB5390 Metal Roofing 20 3-23-26 4-17-26
CB5070 EPDM Roofing 20 3-26-26 4-23-26
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2026 2027 2028
Masonry Brick Veneer
Structural Steel & Joists
Metal Framing for Exterior Wall Panels
Steel Deck
Spray Foam Insulation at Exterior Wall Panels
EPDM Roofing
Sheathing & Weather Barrier at Exterior Wall Panels
SOG Sand Base & Insulation
Metal Roofing
Slab on Grade
Exterior Wall Panels
Non-Bearing Interior Masonry Walls
Aluminum Framing & Glazing
Folding Panel Partition
Interior Framing
Overhead MEP
In-Wall MEP
Drywall
Low Voltage Wiring
Primer & Paint First Coat
Millwork
Hollow Metal Door, Frames, & Hardware
Ceiling Grid
Ceramic Tile
Security Hardware
Light Fixtures
Ceiling Tiles
Flooring
Painting Finish Coat
Under-Slab Utilities
Spray Foam Insulation at Brick Veneer
Masonry Brick Veneer
Structural Steel & Joists
Metal Framing for Exterior Wall Panels
Steel Deck
Concrete Foundation Column Caps
Metal Roofing
EPDM Roofing
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
HPS : Northwest Elementary Data Date:1-5-26
Print Date: 1-11-26
Start Finish
CB5080 Spray Foam Insulation at Exterior Wall Panels 5 3-30-26 4-6-26
CB5090 Sheathing & Weather Barrier at Exterior Wall Panels 15 4-6-26 4-27-26
CB5120 SOG Sand Base & Insulation 15 4-13-26 5-1-26
CB5130 Slab on Grade 15 5-4-26 5-22-26
CB5100 Exterior Wall Panels 20 5-4-26 6-2-26
CB5140 Non-Bearing Interior Masonry Walls 15 6-2-26 6-23-26
CB5310 Aluminum Framing & Glazing 15 6-9-26 6-30-26
CB5150 Interior Framing 30 9-1-26 10-14-26
CB5160 Overhead MEP 30 9-1-26 10-14-26
CB5170 In-Wall MEP 15 10-14-26 11-4-26
CB5190 Low Voltage Wiring 10 10-14-26 10-28-26
CB5180 Drywall 30 11-4-26 12-18-26
CB5200 Primer & Paint First Coat 15 12-18-26 1-12-27
CB5210 Millwork 20 12-18-26 1-19-27
CB5230 Hollow Metal Door, Frames, & Hardware 15 12-18-26 1-12-27
CB5240 Ceiling Grid 15 12-18-26 1-12-27
CB5250 Ceramic Tile 10 12-18-26 1-5-27
CB5260 Light Fixtures 20 1-12-27 2-9-27
CB5270 Security Hardware 5 1-12-27 1-19-27
CB5280 Lockers 20 1-12-27 2-9-27
CB5290 Ceiling Tiles 15 2-9-27 3-2-27
CB5300 Flooring 20 3-2-27 3-30-27
CB5220 Painting Finish Coat 15 3-23-27 4-13-27
Area 1400Area 1400 489 7-2-25 A 5-4-27
CB7000 Exterior Foundations Excavation 5 7-2-25 A 7-8-25 A
CB7010 Exterior Foundations Form & Pour 10 7-2-25 A 7-8-25 A
CB7020 Interior Wall & Column Foundations 3 7-2-25 A 7-8-25 A
CB7330 Exterior Perimeter Below-Grade Masonry 7 7-17-25 A 7-23-25 A
CB7340 Waterproofing on Below-Grade Masonry 3 7-18-25 A 7-24-25 A
CB7350 Backfill Exterior Perimeter Below-Grade Masonry 3 8-4-25 A 8-8-25 A
CB7030 Bearing Exterior Masonry Walls 20 11-3-25 A 1-30-26
CB7040 Bearing Interior Masonry Walls 10 11-3-25 A 2-6-26
CB7050 Spray Foam Insulation at Brick Veneer 10 2-2-26 2-13-26
CB7320 Masonry Brick Veneer 15 2-16-26 3-6-26
CB7070 Structural Steel & Joists 15 3-9-26 3-27-26
CB7110 Steel Deck 5 3-30-26 4-3-26
CB7060 Metal Framing for Exterior Wall Panels 15 3-30-26 4-20-26
CB7120 Under-Slab Utilities 15 4-13-26 5-1-26
CB7080 Spray Foam Insulation at Exterior Wall Panels 5 4-20-26 4-27-26
CB7130 EPDM Roofing 20 4-23-26 5-21-26
CB7090 Sheathing & Weather Barrier at Exterior Wall Panels 10 4-27-26 5-11-26
CB7140 SOG Sand Base & Insulation 15 5-4-26 5-22-26
CB7150 Slab on Grade 15 5-26-26 6-15-26
CB7100 Exterior Wall Panels 15 6-2-26 6-23-26
CB7180 Aluminum Framing & Glazing 20 6-30-26 7-28-26
CB7160 Interior Framing 20 10-14-26 11-11-26
CB7170 Overhead MEP 20 10-14-26 11-11-26
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2026 2027 2028
Spray Foam Insulation at Exterior Wall Panels
Sheathing & Weather Barrier at Exterior Wall Panels
SOG Sand Base & Insulation
Slab on Grade
Exterior Wall Panels
Non-Bearing Interior Masonry Walls
Aluminum Framing & Glazing
Interior Framing
Overhead MEP
In-Wall MEP
Low Voltage Wiring
Drywall
Primer & Paint First Coat
Millwork
Hollow Metal Door, Frames, & Hardware
Ceiling Grid
Ceramic Tile
Light Fixtures
Security Hardware
Lockers
Ceiling Tiles
Flooring
Painting Finish Coat
Bearing Exterior Masonry Walls
Bearing Interior Masonry Walls
Spray Foam Insulation at Brick Veneer
Masonry Brick Veneer
Structural Steel & Joists
Steel Deck
Metal Framing for Exterior Wall Panels
Under-Slab Utilities
Spray Foam Insulation at Exterior Wall Panels
EPDM Roofing
Sheathing & Weather Barrier at Exterior Wall Panels
SOG Sand Base & Insulation
Slab on Grade
Exterior Wall Panels
Aluminum Framing & Glazing
Interior Framing
Overhead MEP
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
HPS : Northwest Elementary Data Date:1-5-26
Print Date: 1-11-26
Start Finish
CB7190 In-Wall MEP 10 11-4-26 11-18-26
CB7210 Low Voltage Wiring 10 11-11-26 11-25-26
CB7200 Drywall 20 12-18-26 1-19-27
CB7220 Primer & Paint First Coat 20 1-19-27 2-16-27
CB7230 Millwork 15 1-19-27 2-9-27
CB7240 Hollow Metal Door, Frames, & Hardware 10 1-19-27 2-2-27
CB7250 Ceiling Grid 10 1-19-27 2-2-27
CB7260 Ceramic Tile 5…