Hideaway Bid Tabs 5-9-23 sm.xlsx
XLSX spreadsheet 36 KB Posted
- Attached to
- BID#2023-31
- Solicitation number
- S-C01010-00006542
- Issued by
- Clackamas County, Oregon
About this file
This document appears to be a bid tabulation sheet for the Johnson Creek Tributary (Hideaway Court) Culvert Replacement Project, a contract opportunity issued by Clackamas County, Oregon. The project involves various construction activities such as mobilization, temporary traffic control, drainage facilities, clearing and grubbing, and the installation of a culvert crossing structure. The bid closing date is May 9, 2023, at 2:00 PM Pacific Time. The bid tabulation sheet provides the engineer's estimate and bid prices from three contractors for the different line items of the project.
The bid tabulation sheet shows the engineer's estimate and bid prices for 23 different bid items, including unit prices and total amounts. The bid items cover a range of work, including temporary features, roadwork, a bridge/culvert crossing structure, aggregates, and right-of-way development. The lowest bid price is $544,211.00, while the highest bid price is $624,533.00. The engineer's estimate for the overall project is $547,680.00.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Johnson Creek / Hideaway Ct | Engineers Estimate | Colton Homes | JQ Construction | |||||||||
| Bid Item # | Item # | Item Description | Unit | Quantity | UNIT PRICE | Eng Estimate | Unit Price | By unit Price | Unit Price | By Unit Price | low | high |
| General Conditions | ||||||||||||
| 1 | 180 | Work Place Harassment Prevention Plan | LS | 1 | $2,000.00 | 2,000.00 | 1,000.00 | $1,000.00 | $620.00 | $620.00 | $620.00 | $1,000.00 |
| 2 | 196 | Extra Work as Authorized | FA | 1 | $40,000.00 | 40,000.00 | 40,000.00 | $40,000.00 | $40,000.00 | $40,000.00 | $40,000.00 | $40,000.00 |
| Part 00200 - Temporary Features and Appurtenances | ||||||||||||
| 3 | 210 | Mobilization | LS | 1 | 20,000.00 | 20,000.00 | 35,000.00 | $35,000.00 | $55,896.00 | $55,896.00 | $35,000.00 | $55,896.00 |
| 4 | 221 | Temporary Work Zone Traffic Control, Complete | LS | 1 | 15,000.00 | 15,000.00 | 2,000.00 | $2,000.00 | $4,430.00 | $4,430.00 | $2,000.00 | $4,430.00 |
| 5 | 226 | Temporary Barrier | LF | 38 | 100.00 | 3,800.00 | 600.00 | $22,800.00 | $40.00 | $1,520.00 | $1,520.00 | $22,800.00 |
| 6 | 240 | Temporary Drainage Facilities | LS | 1 | 30,000.00 | 30,000.00 | 30,000.00 | $30,000.00 | $38,535.00 | $38,535.00 | $30,000.00 | $38,535.00 |
| 7 | 280 | Temporary Fence, 6 Ft Chain Link Fence with Concrete Blocks | LF | 100 | 20.00 | 2,000.00 | 40.00 | $4,000.00 | $16.00 | $1,600.00 | $1,600.00 | $4,000.00 |
| 8 | 280 | Erosion Control | LS | 1 | 15,000.00 | 15,000.00 | 3,000.00 | $3,000.00 | $5,080.00 | $5,080.00 | $3,000.00 | $5,080.00 |
| 9 | 290 | Turbidity Monitoring | LS | 1 | 4,000.00 | 4,000.00 | 3,000.00 | $3,000.00 | $3,860.00 | $3,860.00 | $3,000.00 | $3,860.00 |
| 10 | 290 | Pollution Control Plan | LS | 1 | 2,000.00 | 2,000.00 | 1,000.00 | $1,000.00 | $830.00 | $830.00 | $830.00 | $1,000.00 |
| Part 00300 - Roadwork | ||||||||||||
| 11 | 305 | Construction Survey Work | LS | 1 | 15,000.00 | 15,000.00 | 2,000.00 | $2,000.00 | $15,831.00 | $15,831.00 | $2,000.00 | $15,831.00 |
| 12 | 310 | Removal of Structures and Obstructions | LS | 1 | 50,000.00 | 50,000.00 | 30,000.00 | $30,000.00 | $35,132.00 | $35,132.00 | $30,000.00 | $35,132.00 |
| 13 | 320 | Clearing and Grubbing | LS | 1 | 5,000.00 | 5,000.00 | 18,000.00 | $18,000.00 | $4,690.00 | $4,690.00 | $4,690.00 | $18,000.00 |
| 14 | 330 | Removal of Gravel Washout | LS | 1 | 6,000.00 | 6,000.00 | 4,000.00 | $4,000.00 | $5,584.00 | $5,584.00 | $4,000.00 | $5,584.00 |
| 15 | 335 | Subgrade Geotextile | SY | 500 | 2.00 | 1,000.00 | 7.00 | $3,500.00 | $2.00 | $1,000.00 | $1,000.00 | $3,500.00 |
| Part 00500 - Bridges | ||||||||||||
| 16 | 595 | Hideaway Court Crossing Structure | LS | 1 | 300,000.00 | 300,000.00 | 315,931.00 | $315,931.00 | $358,000.00 | $358,000.00 | $315,931.00 | $358,000.00 |
| Part 00600 - Bases | 0.00 | |||||||||||
| 17 | 640 | Aggregate Base | CY | 160 | 70.00 | 11,200.00 | 70.00 | $11,200.00 | $92.00 | $14,720.00 | $11,200.00 | $14,720.00 |
| 18 | 640 | Temporary Aggregate Base for Stage-1 | CY | 50 | 70.00 | 3,500.00 | 70.00 | $3,500.00 | $123.00 | $6,150.00 | $3,500.00 | $6,150.00 |
| Part 01000 - Right of Way Development and Control | ||||||||||||
| 19 | 1030 | Permanent Seeding | ACRE | 0.30 | 5,000.00 | 1,500.00 | 1,000.00 | $0.00 | $2,000.00 | $0.00 | $0.00 | $0.00 |
| 20 | 1040 | Topsoil | CY | 20 | 60.00 | 1,200.00 | 200.00 | $4,000.00 | $166.00 | $3,320.00 | $3,320.00 | $4,000.00 |
| 21 | 1040 | Shrubs, #2 Container | Each | 60 | 25.00 | 1,500.00 | 60.00 | $3,600.00 | $80.00 | $4,800.00 | $3,600.00 | $4,800.00 |
| 22 | 1050 | Chain Link Fence with Black Vinyl Coating, 4-Ft. Fabric Height | LF | 92 | 65.00 | 5,980.00 | 40.00 | $3,680.00 | $100.00 | $9,200.00 | $3,680.00 | $9,200.00 |
| 23 | 1091 | Fish Cobble | LS | 1 | 12,000.00 | 12,000.00 | 3,000.00 | $3,000.00 | $13,735.00 | $13,735.00 | $3,000.00 | $13,735.00 |
| 547,680.00 | $544,211.00 | $624,533.00 |
File details come from the government source that posted it. Updated .