This document contains the construction specifications for the Henry Horton State Park Greenway project, which is partially funded by the Federal Recreation Trails Program. The scope of work requires a contractor to install a 1.5-mile long, 60-inch wide, flexible porous pavement trail with specific performance and material requirements. The contractor must utilize a mechanized paver, source Tennessee-allocated granulated tire rubber, and ensure the trail meets ADA compliance. The State will prepare the surface for paving, and the contractor is responsible for maintaining a clean and safe work area, as well as providing weekly progress updates. The contractor must provide a 3-year warranty covering all parts of the trail and begin construction within 90 business days of receiving the purchase order approval, completing the work within 120 days unless otherwise approved.

The contract also includes various federal requirements, such as administrative, contractual, and legal remedies for contractor violations, termination provisions, equal employment opportunity, compliance with the Davis-Bacon Act, the Contract Work Hours and Safety Standards Act, and the Clean Air Act and Federal Water Pollution Control Act. The contractor must also comply with debarment and suspension regulations and the Byrd Anti-Lobbying Amendment.

View the file

Other files

File Type Posted
HHSP_Greenway_Trail.pdf PDF
Attachment_B_Payment_Bond_Template.pdf PDF
Event_13393_Spec_map.pdf PDF
Federal_Requirements.pdf PDF
Event_13393_Terms_Conditions.pdf PDF
Henry_Horton_Greenway_Map.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Henry Horton State Park Greenway Contractor Specifications

A. Licensing requirements are BC-13 (Site Work), BC-28 (Excavation), HC-5 (Clearing, Grubbing, Snagging or Rip Rap), HRA-B (Base and Paving) or a BC-B, BC-bsm, BC (Commercial).

B. Scope

1. Contractor shall install a flexible porous pavement trail on top of the path prepped by park staff for paving.

a. Trail must be a minimum of 1.5 miles (7920 feet) long.

b. Trail shall be 60 inches wide.

c. Trail must be a minimum of 1.5 inches thick installed over gravel base.

d. Trail must have a beveled edge.

e. Trail surfacing must be porous to water, with a minimum of 2,250 gallons per hour per square foot.

f. Trail surfacing must have at least 20% inner void space.

g. Trail surfacing must be slip resistant, meeting ASTM D-2047 slip resistant test.

h. Trail surfacing will be flexible and resistant to cracking and heaving due to normal environmental conditions.

i. Trail surfacing must have a minimum of NFPA Class “C” fire rating.

j. Trail surfacing must be resistant to UV rays, oil, fuel (including gasoline and diesel), transmission fluid, hydraulic fluid, and other common commercial chemicals.

k. Trail surface must meet the EPA’s Synthetic Precipitation Leaching Procedure method

1312 test.

l. Trail surface must meet standards for ASTM C 666 freeze/thaw test.

m. Trail surface must meet standards for ASTM D 4798 Cycle A and ASTM G155 accelerated weathering tests.

2. Contractor shall provide tools and equipment needed for completing the entire scope of work.

a. It is required for the contractor to utilize a mechanized paver to complete the installation in one mobilization.

3. Contractor shall supply Tennessee allocated granulated tire rubber.

**Vendor shall provide a letter detailing the amount of tires that are taken in at the recycling facility where they source their rubber from. The tires have to be sourced from Tennessee.**

a. Contractor must ensure that crumb rubber stays dry.

4. Contractor shall provide clean and dust free stone for surfacing mixture.

5. Contractor shall provide polyurethane binding agent for surfacing that is moisture cured and non-toxic.

6. Contractor shall ensure that the trail meets State specifications as ADA Compliant.

a. Trail will meet all ADA specifications as outlined by the 2010 ADA Standards for Accessible Design and by the State of Tennessee.

b. Trail will connect with existing ADA accessible parking at the Henry Horton State Park Visitor Center Parking Lot, Blue Cross Healthy Place Playground, and Storybook Trail, identified on the attached map.

7. The State will correctly prepare the surface for paving based on specifications provided by Contractor.

a. Contractor is responsible for ensuring the slope prepared by the State remains intact during the laying of the porous pavement material.

8. Contractor shall keep a tidy and clean work area.

a. All mechanized equipment is to be safely stored and parked each night so as not to endanger the public.

b. All storage containers will be locked at the end of each workday.

9. Contractor shall update state representatives on the progress of the job on a weekly basis via email.

a. Shaun Rainone, Park Manager, Henry Horton State Park – shaun.rainone@tn.gov

b. Carson Cooper, Grant Manager, TN State Parks – carson.cooper@tn.gov

10. Contractor shall keep work area safe and in compliance with all OSHA requirements, including safety to the general public.

11. Contractor shall be responsible for proper disposal, in accordance with all applicable laws and regulations, of any waste material generated during construction and installation.

12. Contractor shall be able to work while meeting all federal regulations, as this project is partially funded by monies from the Federal Recreation Trails Program.

13. Contractor shall not remove any vegetation other than grass without prior permission from the State regarding the removal of a specific specimen.

14. Contractor shall construct a trail that is long lasting, sustainable, and safe.

15. Contractor shall bill the State no more than one time per month.

a. Contractor shall bill for complete sections of no less than 1000 ft.

i. Multiple sections of 1000 ft on one invoice is allowable.

ii. The final billing may be for a complete section of less than 1000 ft.

16. Contractor shall issue a warranty of 3 years that covers all parts of the trail, including materials, workmanship, and safety.

a. If, at any time within 3 years from the completion date of construction, the trail is found to be compromised in any way due to material failure or installer error, the Contractor shall correct the issue to the approval of the State within 90 days.

17. Contractor shall begin construction within 90 business days of receiving PO approval.

18. Contractor shall complete construction within 120 days unless otherwise approved upon by approved representative of the State of Tennessee.

mailto:shaun.rainone@tn.gov mailto:carson.cooper@tn.gov

Appendix II to Part 200 Contract Provisions for Non-Federal Entity Contracts Under Federal Awards In addition to other provisions required by the Federal agency or non-Federal entity, all contracts made by the non-Federal entity under the Federal award must contain provisions covering the following, as applicable.

(A) Contracts for more than the simplified acquisition threshold currently set at $150,000, which is the inflation adjusted amount determined by the Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council (Councils) as authorized by 41 U.S.C. 1908, must address administrative, contractual, or legal remedies in instances where contractors violate or breach contract terms, and provide for such sanctions and penalties as appropriate.

(B) All contracts in excess of $10,000 must address termination for cause and for convenience by the non-Federal entity including the manner by which it will be effected and the basis for settlement.

(C) Equal Employment Opportunity. Except as otherwise provided under 41 CFR Part 60, all

60-1.3 must include the equal opportunity clause provided under 41 CFR 60-1.4(b), in

12935, 3 CFR Part, 1964-1965 Comp., p. 339), as amended by Executive Order 11375, implem

(D) Davis-Bacon Act, as amended (40 U.S.C. 3141-3148). When required by Federal program legislation, all prime construction contracts in excess of $2,000 awarded by non-Federal entities must include a provision for compliance with the Davis-Bacon Act (40 U.S.C. 3141-3144, and 3146-

Standards Provisions Applicable to Contracts Covering Federally Financed and Assisted laborers and mechanics at a rate not less than the prevailing wages specified in a wage determination made by the Secretary of Labor. In addition, contractors must be required to pay wages not less than once a week. The non-Federal entity must place a copy of the current prevailing wage determination issued by the Department of Labor in each solicitation. The decision to award a contract or subcontract must be conditioned upon the acceptance of the wage determination. The non-Federal entity must report all suspected or reported violations to the Federal awarding agency. The contracts must also include a provision for compliance with

Financed in Whole or each contractor or subrecipient must be prohibited from inducing, by any means, any person employed in the construction, completion, or repair of public work, to give up any part of the compensation to which he or she is otherwise entitled. The non-Federal entity must report all suspected or reported violations to the Federal awarding agency.

(E) Contract Work Hours and Safety Standards Act (40 U.S.C. 3701-3708). Where applicable, all contracts awarded by the non-Federal entity in excess of $100,000 that involve the employment of mechanics or laborers must include a provision for compliance with 40 U.S.C.

3702 and 3704, as supplemented by Department of Labor regulations (29 CFR Part 5). Under 40 U.S.C. 3702 of the Act, each contractor must be required to compute the wages of every mechanic and laborer on the basis of a standard work week of 40 hours. Work in excess of the standard work week is permissible provided that the worker is compensated at a rate of not less than one and a half times the basic rate of pay for all hours worked in excess of 40 hours in the work week. The requirements of 40 U.S.C. 3704 are applicable to construction work and provide that no laborer or mechanic must be required to work in surroundings or under working conditions which are unsanitary, hazardous or dangerous. These requirements do not apply to the purchases of supplies or materials or articles ordinarily available on the open market, or contracts for transportation or transmission of intelligence.

(F) Rights to Inventions Made Under a Contract or Agreement. If the Federal award meets the wishes to enter into a contract with a small business firm or nonprofit organization regarding the substitution of parties, assignment or performance of experimental, developmental, or comply with and any implementing regulations issued by the awarding agency.

(G) Clean Air Act (42 U.S.C. 7401-7671q.) and the Federal Water Pollution Control Act (33 U.S.C.

1251-1387), as amended Contracts and subgrants of amounts in excess of $150,000 must contain a provision that requires the non-Federal award to agree to comply with all applicable standards, orders or regulations issued pursuant to the Clean Air Act (42 U.S.C. 7401-7671q) and the Federal Water Pollution Control Act as amended (33 U.S.C. 1251-1387). Violations must be reported to the Federal awarding agency and the Regional Office of the Environmental Protection Agency (EPA).

(H) Debarment and Suspension (Executive Orders 12549 and 12689) A contract award (see 2 CFR 180.220) must not be made to parties listed on the governmentwide exclusions in the System for Award Management (SAM), in accordance with the OMB guidelines at 2 CFR 180 that implement Executive Orders 12549 (3 CFR part 1986 Comp., p. 189) and 12689 (3 CFR part parties debarred, suspended, or otherwise excluded by agencies, as well as parties declared ineligible under statutory or regulatory authority other than Executive Order 12549.

(I) Byrd Anti-Lobbying Amendment (31 U.S.C. 1352) Contractors that apply or bid for an award exceeding $100,000 must file the required certification. Each tier certifies to the tier above that it will not and has not used Federal appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a member of Congress, officer or employee of Congress, or an employee of a member of Congress in connection with obtaining any Federal contract, grant or any other award covered by 31 U.S.C.

1352. Each tier must also disclose any lobbying with non-Federal funds that takes place in connection with obtaining any Federal award. Such disclosures are forwarded from tier to tier up to the non-Federal award.

HHSP Greenway Construction Specifications_Final
Federal Requirements