HE125419R2008_Q&A_Amendment_0004.pdf
PDF 100 KB Posted
- Attached to
- Student Transportation Services Daily Commute / Curricular Kaiserslautern, Germany Europe Federal contract opportunity
- Solicitation number
- HE1254-19-R-Kaiserslautern
- Issued by
- Department of Defense Education Activity
About this file
HE125419R2008 Amendment 0004 Kaiserslautern Questions and Answers
View the file
Other files for this federal contract opportunity
Show all 45
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Item
Subject RFP or
Attachment Reference
Question/Confirmation/Comment Answers/Responses
01 RFP SLIN
Quantities
Attachment 2 of
SF1449,
Supplies/Services
Attachment 2(b): Zone C Pricing Sheet CLIN 0002AA 45 Passanger Vehicle Unit Run: Quantity:
27000
We cannot understand the number of 27000 runs. How does the number consist?
The quantities reflected in Attachment 2 of the SF1449, Supplies/Services, are not based on the number of school days, runs, or buses. Rather, they are estimated quantities that will establish the maximum ceiling/quantity/amount of the resultant Indefinite Delivery/Indefinite Quantity (IDIQ) contract. Please see FAR Clause 52.216-22.
02 Air Conditioning
PWS Does all the buses/vans used for the normal daily commute in Kaiserslautern (NO SPED) must be equipped with air conditioning (see para. 3.3.5 PWS)?
Changed back to : Only special needs buses.
03 Certification SF1449 Concerning 52.222-56 Certification Regarding Trafficking in Persons Compliance Plan, I was wondering what is meant by submitting a certificate? Do we need to formulate it ourselves or apply for it? Please elaborate what exactly it is we need to do, so that we may comply.
Please refer to FAR 52.222-50 as it states "The certification shall cover the items in paragraph (h)(5) of this clause."
04 Requirements Attachment 2 of
SF1449,
Supplies/Services
Are the bus sizes correct in Zone C? Or are these the normal daily commute sizes and there are no SpecEd’s at all? ( Attachment 2(b) Zone C Pricing Sheet)
There are no special needs requirements on this solicitation.
05 Cellular Phone PWS Is it necessary for the contractor to provide a cellular with “ Smartphone” technology or is a regular cellular sufficient? ( PWS 3.1.5.2 in all solicitations)
A regular cellular phone can be used. Please reference updated
PWS.
06 Requirements PWS Could you please explain in detail the paragraph 2.3, paragraph 2.2, paragraph 2.3 in the Performance Work Statement, which transportation is meant? Is it possible that there is a mistake, because there is no CLIN provided?
Paragraph 2.2 is reserved for Special Needs and this requirement for SPED is not included in this solicitation. Paragraph 2.3 is for Curricular and cocurricular and the details of this requirement are included within the PWS.
07 Requirements SF1449, Supplies/Services
Concerning the Offeror Responsibility Determination, do we have to make statements pertaining to all points of the General and Special Standards or is providing the information asked for in 1) of General Standards enough?
Please address each standard. As stated in 52.212-1 Addendum, "In the absence of information clearly indicating that the prospective contractor is responsible, the contracting officer shall make a determination of non-responsibility."
08 Bus Size Attachment 2 of
SF1449,
Supplies/Services Could you please tell us what bus size has to be provided?
35 passenger buses for Curricular Career Practicum and Cisco runs and 45 passenger buses for Curricular school trips runs.
09 Runs Attachment 2 of
SF1449,
Supplies/Services Will the runs be paid per bus?
Each run will be paid at unit price.
10 Requirements PWS Paragraph 2.3 in the Performance Work Statement, Does the 120 km radius include the return trip?
No, 120km is one way.
12 Response Time SF1449, Supplies/Services
According to Attachment 3 the required response date and time has changed to 25 JUN 2019 / 4:00 PM. Is this correct , because the modification is not listed in the SF 30 Form block 14?
Yes, as shown on page 2 of Amendment 0003, "The required response date/time has changed from 18-Jun-2019 04:00 PM to 25- Jun-2019 04:00 PM."
13 Signatures SF 1449 & SF 30s Should all amendments be signed? Yes, please sign the SF 1449 along with all SF 30s.