This is a construction contract template between the City of Bridgeport, Connecticut and a named contractor for lower-level renovation services, specifically building upgrades and window replacement at an unspecified service location in Bridgeport. The scope of work requires the contractor to furnish all labor, services, equipment, materials, supplies, transportation, and incidentals necessary to complete the project in a satisfactory manner in compliance with all applicable local, state, and federal laws and professional standards. The contract establishes a Substantial Completion deadline of 100 consecutive calendar days from the City's written Notice to Proceed and a Final Completion deadline of 120 consecutive calendar days, with monthly progress reports required. The contract documents are structured in a hierarchy of precedence beginning with contract amendments and change orders, followed by the base contract, bid addenda, contractor's quote, special conditions, general conditions, technical specifications, and applicable federal, state, and local laws.
Compensation is limited to a not-to-exceed amount specified in the contractor's bid dated May 15, 2024, with funding sourced from a U.S. Department of Housing and Urban Development grant and customer contracting services. The City reserves the right to withhold five percent retainage until project completion and acceptance. The contractor is subject to delay damages of $1,500 per calendar day for failure to meet milestone, substantial completion, or final completion dates. The contract requires performance and payment bonds equal to the total compensation, comprehensive insurance coverage including general liability of $1,000,000 per occurrence, workers' compensation at statutory limits, and excess/umbrella coverage of $5,000,000. The contractor must comply with prevailing wage requirements under Connecticut General Statutes Section 31-53, federal Davis-Bacon Act provisions, HUD Section 3 employment preferences, Connecticut's 25 percent minority business enterprise set-aside requirements for contracts exceeding $50,000, and the City's requirement that contractors self-perform at least 30 percent of labor or obtain a written waiver. The contract is governed by Connecticut law and disputes shall be resolved in Fairfield County courts.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION CONTRACT
For
[CONTRACTED SERVICES]
At
[Service Location] [Services Street Address], Bridgeport, CT for
[Customer Contracting Services]
BETWEEN
THE CITY OF BRIDGEPORT
AND
[NAMED CONTRACTOR]
THIS AGREEMENT, effective upon its execution by a duly authorized representative of the City of Bridgeport (“City”) with its principal place of business located 45 Lyons Terrace, Bridgeport, Connecticut 06604, and [NAMED CONTRACTOR], located at [Contractor
Address], a [____________] Company duly registered in the State of Connecticut
(“Contractor”); the City and Contractor each being a “Party” and collectively, the “Parties”.
WHEREAS, the Contractor submitted a bid to the City in response to a solicitation for lower-level renovation services, which includes [Contracted Services] at [SERVICE LOCATION], [Services Street Address], Bridgeport, CT
WHEREAS, the City accepted the Contractor’s bid for the Project; and
WHEREAS, the City desires to obtain the Contractor's services for said Project pursuant to the terms set forth in this Contract and the Attachments hereto (the “Project”).
NOW THEREFORE, THE PARTIES AGREE AND COVENANT AS FOLLOWS:
1. Scope of Services. The Contractor shall furnish all of the labor, services, equipment, materials, supplies, transportation, and incidentals necessary to complete the Project as specified in this Agreement (also referred to herein as "Contract") and such shall be completed in a satisfactory manner, as reasonably determined by the City. All labor, services, equipment, materials, supplies, transportation, and incidentals shall comply with (i) any and all applicable local, state and federal laws, statutes, ordinances, rules and regulations, including without limitation all notice requirements thereunder, and (ii) generally accepted professional standards.
1.1. The Project consists of the building upgrade and window replacement, all as described in the Bid Documents, which are hereby made material provisions of this
Contract.
1.2. The entirety of the Bid Documents plus this executed instrument are together deemed the Contract Documents (hereinafter collectively referred to as "Contract
Documents"), certain of which are attached hereto. The City’s record copy of the
Contract Documents shall control and shall be effective and binding on the Contractor.
In the event that any provision in the Contract Documents conflict with any other provision therein, the provision in the component part of the Contract Document first enumerated below shall govern over any other component part which follows it numerically.
1.2.1. Contract Amendment(s) and Change Orders
1.2.2 Contract
1.2.3 Bid Addenda
1.2.4 Contractor’s Quote
1.2.5 Special Conditions
1.2.6 General Conditions
1.2.7 Technical Specifications
1.2.8 Federal, State, and local laws, regulations, charter and ordinances
2. Representations Regarding Qualification and Accreditation. The Contractor represents that its employees are licensed to perform the scope of work set forth in this Contract.
The Contractor further represents that its employees have the requisite skill, expertise and knowledge necessary to perform the scope of work required under the terms of this Contract, including any supplementary work and the City relies upon Contractor’s representations.
2.1. Representations regarding Personnel. The Contractor represents that it has, or will secure at its own expense, all personnel required to perform the services under this
Contract. Such personnel shall not be employees of or have any contractual relationship with the City, unless use of the City employees or of personnel having a contractual relationship with the City is approved in writing. As set forth above, all the services required hereunder shall be performed by the Contractor or under its supervision and all personnel engaged in the work shall be fully qualified and shall be authorized or permitted under state or local law to perform such services.
2.2. Representations regarding Qualifications. The Contractor hereby represents that, to the extent required by Federal, State and Local statutes, regulations, codes, ordinances, and policies, that the Contractor and/or its employees be licensed, certified, registered, or otherwise qualified, the Contractor and all employees providing services under this Contract, are in full compliance with those statutes, regulations and ordinances. Upon the City’s request, the Contractor shall provide to the City a copy of the Contractor’s licenses, certifications, registrations, etc.
3. Responsibilities of the Contractor. The Contractor agrees to properly implement the services required in the manner herein provided. The Contractor shall, in addition to any other responsibilities set forth in this Contract and the Schedules and Attachments hereto, perform the following coincident with the performance of this Contract:
3.1. Due Diligence Obligation. The Contractor acknowledges its responsibility to examine and to be thoroughly familiar with the City’s documents, including, but not limited to the plans, specifications, drawings and any addenda thereto. The Contractor hereby warrants and represents that prior to the submission of its quote it reviewed or was afforded opportunity, by the City, to review all physical items, facilities, services and functions essential to the satisfactory performance of the services required (“Due
Diligence”) and thereby certifies that all such items facilities, services and functions are included in this Contract and thereby warrants that:
3.1.1 it conducted or had opportunity to conduct all due diligence prior to the submission of its quote and, accordingly, any additional costs, services or products resulting from the failure of the Contractor to complete Due Diligence prior to submission of its proposal shall be borne by the Contractor. Furthermore, the Contractor had the opportunity to ask questions it saw fit and to review the responses from the City;
3.1.2 its failure or omission to make investigation and verification of data shall, in no way, be cause for future claim of ignorance of such data or conditions nor shall such failure to investigate and verify be the basis for any claim whatsoever, monetary or otherwise;
3.1.3 it is solely responsible for resolving any issues resulting from its failure to conduct due diligence and it shall assume any and all resulting costs it incurs during the Project;
3.1.4 it was responsible for specifying any changes and disclosing any associated new costs prior to submittal of its quote. In the event the Contractor failed to disclose any such new cost prior to the submittal of its quote, the
Contractor hereby covenants that it shall remain solely responsible for, and shall absorb, those non-disclosed costs;
3.1.5 it has familiarized itself with the nature and extent of the Contract
Documents, Project, locality, and with all local conditions and Federal, State and local laws, ordinances, rules and regulations that in any manner may affect cost, progress or performance of the Project;
3.1.6 it has given the City written notice of any conflict, error or discrepancy that the Contractor discovered in the City's bid documents and other documents for [Bid Number XXXX] (collectively "Bid Documents");
3.1.7. it agrees that the Bid Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance of the Project;
3.1.8. it has studied carefully any and all reports of investigations and tests of subsurface and latent physical conditions at the site or otherwise affecting cost, progress or performance of the Scope of Services which were utilized in the preparation of any plans and specifications;
3.1.9 it has made or caused to be made examinations, investigations, measurements and tests and studies of any applicable reports and related data as it deems necessary for ensuring performance of the Scope of Services at the
Contract Price within the Contract Time and in accordance with the other terms and conditions of the Contracts; and certifies no additional examinations, investigations, tests, reports or similar data are or will be required by Contractor for such purposes;
3.1.10 it will remove all contaminated rubbish, debris from the Premises and legally dispose of the same in conformance with all applicable local, state and federal health and safety regulations.
3.1.11 The Contractor shall not take advantage of any obvious error or apparent discrepancy in the Contract. Notice of any error or discrepancy discovered shall be given immediately in writing to the City, who shall make such corrections and interpretations as it may deem necessary for the completion of the Project in a satisfactory and acceptable manner.
3.2. Safety. Throughout its work on the Project, the Contractor shall keep the
Premises clean and orderly at all times. Contractor shall immediately correct any dangerous condition caused by or resulting from its work. If it fails to correct, or to act diligently to correct, any condition which the City reasonably believes to be a hazard to persons or property, then immediately upon oral or written notice to any supervisory or similar personnel of Contractor, the City may, but shall not be required to, correct same at Contractor's expense. The City shall confirm in writing any oral notice given within five (5) business days thereafter.
3.3. Storage. In the event the Project site has insufficient, inadequate, and/or improper storage space, it shall be the responsibility of the Contractor to secure, provide and maintain at the Contractor’s sole cost and expense (i) adequate off-site storage space for equipment, materials, incidentals, etc., and (ii) all associated delivery and transportation services. In either event, the Contractor shall assume full responsibility for equipment, materials, incidentals, etc. until both title and risk of loss pass to the City pursuant to Section 8 of this Contract.
3.4. Working Hours. To the extent the Contractor is required to be on City property to render the Contractor's services hereunder, the Contractor shall coordinate its schedule so that work on and at the Project site is performed during the hours of 7:00 a.m. and
3:30 p.m. Monday through Friday and, with advance approval by the City, on Saturday, Sunday and legal holidays unless more exactly specified elsewhere in this Contract or
Attachment B or unless prior written permission is obtained from the City to work during other times. This provision shall not excuse the Contractor from timely performance under the Contract.
3.5. Cleaning Up. The Contractor shall at all times keep the Project site free from accumulation of waste materials or rubbish caused by Contractor's employees or subcontractors, and at the completion of the work shall remove all rubbish from and about the Project and all tools, scaffolding and surplus materials and shall leave the
Project site "broom clean" or its equivalent, unless more exactly specified. In case of dispute, the City may remove the rubbish and charge the cost to the Contractor.
3.6. Publicity. Contractor agrees not to deliberately disclose the fact that the City has entered into or terminated this Contract or disclose any of the terms of the Contract or use the City’s name in connection with any publicity including, but not limited to, its marketing materials unless the City gives prior written consent to such use of the City’s name in each instance.
3.7. Standard of Performance. All Contractor labor, materials, supplies, components, equipment, reports, plans, specifications, drawings, deliverables, incidentals, etc., required to be furnished or delivered under this Contract shall conform in all respects with the requirements set forth in this Contract and shall meet or exceed those standards generally recognized in the Contractor's craft and trade in the State of
Connecticut. City specified manufacturer and/or brand name substitution desired by the
Contractor shall be made only with the prior written consent of an authorized representative of the City.
3.7.1 In carrying out the Project, the Contractor must employ such methods or means as will not cause any interruption of or interference with the work of any other contractor, nor with the normal routine of the institution or agency operating at the Project site.
3.8. Contractor’s Employees. The Contractor shall at all times enforce strict discipline and good order among its employees and shall not employ on the work any unfit person or anyone not skilled in the work assigned. The Contractor shall not, without the prior written approval of the City substitute, terminate, replace or otherwise remove any Contractor employee expressly named, identified or required in this Contract.
3.9. Subsurface/Unknown Site Conditions. If Project site conditions are encountered which are (i) subsurface or otherwise concealed physical conditions or other conditions which differ materially from those indicated in the Contract Documents, or
(ii) unknown conditions of an unusual nature which differ materially from those ordinarily found to exist and generally recognized as inherent or common in construction activities of the character provided for in this Contract, then prompt notice by the observing party shall be given to the other party to this Contract before Project site conditions may be disturbed. The Contractor shall thereafter wait for written instructions from the City before proceeding with regard to such conditions.
3.10. Surveys. All surveys required under this Contract shall be performed by a State of Connecticut duly licensed land surveyor. Unless expressly stated to the contrary in
Section 1 of this Contract and Attachment B, the Contractor shall perform all layout work, all field measurements and all construction staking required, necessary or prudent for the satisfactory prosecution of the Contractor’s obligations under this Contract.
3.11. Permits and Licenses. Unless expressly stated to the contrary in Section 1 of this Contract and Attachment B, the Contractor shall secure and obtain all permits and all licenses required, or necessary, or prudent for the performance of the Contractor’s obligations under this Contract, and for the City’s occupancy, use, and operation of the
Project.
3.12. Manufacturer's Directions. Where it is required in this Contract that materials, products, processes, equipment or the like be installed or applied in accord with manufacturer's directions, specifications or instructions, it shall be construed to mean that the said application or installation by the Contractor shall be in strict accord with printed instructions furnished by the manufacturer of the material concerned for use under conditions similar to those at the Project site. One (1) copy of such instructions shall be furnished to the City.
3.13. Review by the City. The Contractor shall permit the City and the City’s duly authorized representatives and agents to review, at any time, all work performed under the terms of this Contract at any stage of the Project.
3.14. Records Maintenance. The Contractor shall maintain or cause to be maintained all records, books or other documents relative to charges, costs, expenses, fees, alleged breaches of the Contract, settlement of claims or any other matter pertaining to the
Contractor’s demand for payment.
3.15. Anti-Pass Through. Pursuant to the Code of Ordinance of the City, Chapter
3.08.070.B.7, for all city contracts having a labor component, the contracting entity
(whether prime or subcontractor) must self-perform at least thirty (30) percent of the labor (which may and should include site management) or obtain a written waiver from the purchasing agent and city's chief administrative officer.
4. Responsibilities of the City and the City Reservation of Rights. Upon the City’s receipt of Contractor's written request for specific information, the City will provide the
Contractor with existing documents, data and other materials the City agrees are necessary and appropriate to the services to be performed by the Contractor hereunder and the City will endeavor to secure, where feasible and where the City agrees it is necessary and appropriate, materials or information from other sources requested by the Contractor for the purpose of carrying out the services under this Contract.
4.1. The City may, in its sole discretion, designate person(s) to act as the City’s
Project Engineer(s) and/or Manager(s) and the City may, in its sole discretion, define such person(s) authority and responsibilities.
4.2. The City reserves the right to (i) perform work related or unrelated to the Project with the City’s own forces adjoining, adjacent to, or in the vicinity of, the
Project site and/or (ii) let separate contracts related or unrelated to the Project for work and services adjoining, adjacent to, or in the vicinity of, the Project site. In such event, the Contractor shall afford all such parties reasonable opportunity for storage of materials and equipment and for the uninterrupted provision and delivery of such parties' work and/or services. The Contractor shall cooperate with such parties and in the case of a dispute, the decision of the City shall be complied with by all.
5. Contract Time. The Contractor shall Substantially Complete all work and services required under this Contract within One Hundred (100) consecutive calendar days of the
City’s written Notice to Proceed and shall reach Final Completion within One Hundred
Twenty (120) consecutive calendar days of the City’s written Notice to Proceed and in accordance with the following Project Milestones (all hereinafter referred to as "Contract
Time"):
5.1. Within one (1) week of the City’s issuance of its written notice to proceed, and prior to the commencement of any work on the Project site, the Contractor shall submit for the City’s written approval a construction progress schedule. On a monthly basis, the
Contractor shall deliver to the City a written status report setting forth an analysis and critique of the Contractor's compliance with said schedule.
5.2 Delay Damages
5.2.1 Time is and shall be of the essence for all delay Milestones, Substantial and Final
Completion Date. The Contractor further agrees that the Project shall be prosecuted regularly, diligently and uninterruptedly and at such rate of progress as will ensure full completion thereof within the Contract time stated above. It is expressly understood and agreed, by and between the Contractor and City, that Milestones, Substantial and Final
Completion Date are reasonable for the completion of the Project.
5.2.1.1 The Contractor shall pay to the City the sum of the greater of One Thousand
Five Hundred 00/100 Dollars ($1,500.00) per calendar day for each and every calendar day for which the Contractor is in default in completing the work beyond the Final Completion Date, Substantial Completion Date and Milestones, as set forth in Section 5, or the actual damages incurred by the City caused by the delay.
The preceding sum is hereby agreed upon not as a penalty, but as delay damages for the delay that the City shall suffer due to such default.
5.2.1.2 The City shall have the right to recover all damages pursuant to any remedy at law or equity including but not limited to deducting the amount of any such damages from any monies due the Contractor under this Contract. The
Contractor understands that if the entire Work or of any portion of the Work that the City has agreed to accept separately, if any, is not attained by the applicable completion dates as set forth in the entire Section 5, the City will suffer damages, which are difficult to specify accurately and ascertain. Delay damages based upon delay shall be assessed to compensate the City for all actual loss sustained by the delay, including, but not limited to, loss of use, increased cost of material or services to complete the project, loss of State funding, all other another actual expense, and all other damages allowed by law.
5.3 No Damage for Delay
In no event shall the Contractor be entitled to any compensation or recovery of any damages in connection with any Delay, including, without limitation, consequential damages, lost opportunity damages, attorney’s fees or other, similar remuneration. The City’s exercise of any of its rights or remedies under the Contract Documents, including without limitation, ordering changes in the
Work, or directing suspension, rescheduling or correction of the Work, regardless of the extent or frequency of the City’s exercise of these rights has been contemplated by the parties and shall not be construed as an exception.
6. Compensation. The City shall compensate the Contractor for satisfactory provision of all of the goods and services set forth in this Contract as follows in this Section 6. No claims for additional compensation will be considered for conditions made known to the Contractor prior to bidding. No claims for additional compensation will be considered on account of failure of the Contractor to completely inform itself as required herein above.
6.1. Fee Schedule. Subject to retainage, limitations, etc. set forth below in this Section
6, the fee payable to the Contractor shall not exceed _________ and 00/100 Dollars
($___,000.00) (hereinafter referred to as “Total Compensation”), with the basis for payment being Contractor’s Bid set forth in Attachment A’s “Contractor’s Bid, dated
May 15, 2024.”
The source of funds for the payment of the fee is comprise the following:
6.1.1. U. Department of Housing and Urban Development Grant to the
City for $_________,000.00
6.1.2. [Customer Contracting Services] for $_______00.00
6.2. Retainage. At the City's sole discretion, it hereby reserves the right to withhold as retainage five percent (5%) of any payment (or monetary sum otherwise required by law) owed to the Contractor to be withheld from payments to the Contractor otherwise payable to the Contractor until such time as the Contractor's work and services to be provided under this Contact are fully completed and accepted in writing by the City. The retainage does not include additional sums that the City may withhold due to the
Contractor's failure to comply with provisions of this Contract.
6.3. Limitation of Payment. Compensation to the Contractor is limited to those fees set forth in Section 6.1. of this Contract and is further limited to work (i) performed in fact, (ii) conforming with this Contract, and (iii) accepted in writing by a duly authorized
City employee. Such compensation shall be paid by the City upon its review and approval of the Contractor’s invoices for payment and review of the Contractor’s work.
6.3.1 Funding. In the event this Contract is funded, in whole or in part, by
Federal and/or State monies, grants, loans, etc., all the City payment(s) shall fully comply with all relevant Federal and State statutes and regulations. In the event this Contract is 100% funded by Federal and/or State monies, grants, loans, etc., the aggregate sum of all the City payments shall not exceed the aggregate sum of such funding.
6.3.2 The Contractor and its affiliates are hereby provided with notice that the
City reserves the right, in the City’s sole discretion, to offset, withhold, or otherwise reduce the City payment(s) to the Contractor, in an amount equaling the sum or sums of money the Contractor and/or its affiliates is/are, or become delinquent or in arrears on, regarding the Contractor’s and/or its affiliates real and personal property taxes and other payment obligations to the City.
6.4. Bid Costs. All costs of the Contractor in preparing its bid for [Bid Number XXXX] shall be solely borne by the Contractor and are not included in the compensation to be paid by the City to the Contractor under this Contract or any other agreement.
6.5. Payment for Services, Materials, Appliances, Employees. The Contractor shall be responsible to the City for the suitability of services, materials and equipment furnished to comply fully with the requirements set forth in this Contract. The Contractor shall promptly pay all employees as their pay falls due, shall pay promptly as they fall due all bills for subcontractors, materials, supplies and services going into the work, and all bills for insurance, bonds, Worker's Compensation coverage, Federal and State Unemployment
Compensation, and Social Security charges applicable to this Project. Before final City payment is made, the Contractor shall furnish to the City a sworn, notarized, affidavit stating that all of the foregoing payment obligations have been fully completed.
6.6. Liens. Neither the City's final payment nor any part of the retained percentage, if any, shall become due until the Contractor, if required by the City, shall deliver to the
City a complete release of all liens arising out of this Contract, or receipts in full in lieu thereof, and, if required, in either case, an affidavit that so far as the Contractor has knowledge or information, the releases and receipts include all the labor and material for which a lien could be filed; but the Contractor may, if any subcontractor refuses to furnish a release or receipt in full, furnish a bond satisfactory to the City, to indemnify it against any lien. If any lien remains unsatisfied after all payments are made, the
Contractor shall refund to the City all moneys that the City may be compelled to pay in discharging such a lien, including all costs and a reasonable attorney's fee.
6.7. Contractor’s Certificate of Completion. Upon the Contractor's (i) completion of all Project milestones, and (ii) Substantial Completion of the Project, and (iii) Final
Completion of the Project, the Contractor shall, in each instance, file with the City a written, notarized affidavit setting forth the amount of Project work performed. The City reserves the right to verify or challenge by any reasonable means the accuracy of said affidavit.
6.8. Final Payment. All prior estimates and the City payments, including those relating to extra or additional work, retainage(s), and holdback(s), shall be subject to correction by this final payment which is throughout this Contract called "Final
Payment". No payment, final or partial, shall act as a release to the Contractor or its surety from any Contractor obligation(s) under this Contract.
6.9. Clean Water Fund Project Requirements. In the event this Contract is funded in whole or in part, is reliant upon, or falls within the jurisdiction of the Clean Water
Fund and its statutes, regulations and rules, the Contractor shall:
6.9.1 submit Applications for Payment in accordance with the following:
The City must receive the Contractor’s Application for Payment by the City’s or its designee’s, review and recommendation for payment, by the fifteenth calendar day of the month to receive payment within the next 50 days. If not received by the fifteenth calendar day of the month, payment cannot be made until 50 days after the fifteenth calendar day of the subsequent month. The Contractor shall provide at the City’s request, reasonable documentation to substantiate
Contractor’s Application for Payment.
6.9.2 Progress and Final Payments
The City will make progress payments on account of the Contract Price on the basis of the Contractor's Applications for Payment, monthly during construction as provided below. All progress payments will be on the basis of the progress of the Scope of Services as determined by the City, according to the schedule of values provided for in the Contract Documents, and approved by the City. Prior to Substantial Completion, progress payments will be limited to an amount equal to 95 percent of the value of the Scope of Services completed. Upon Substantial
Completion, the City will pay the amount as specified in the Contract Documents.
7. Warranty of the Contractor. The Contractor warrants to the City that all materials, supplies, components, equipment, etc. furnished under this Contract shall be new and of good quality, except as otherwise expressly stated and permitted by the City elsewhere in this
Contract. The Contractor warrants that none of its work shall be defective. The Contractor shall be liable to repair and install and/or replace without charge any service, component, equipment or part thereof which is defective or does not conform with this Contract within the greater of
(i) 90 calendar days after the City delivers its written notice of its acceptance of the Project and statement therein establishing the final completion date, or (ii) that time period or date expressly stated elsewhere in this Contract or Attachment A.
7.1. The Contractor further warrants that all materials, supplies, services, components, equipment, reports, plans, drawings, deliverables, incidentals, etc., shall be free from any and all defects caused by faulty design, faulty material or poor workmanship. The Contractor shall supply to the City copies of any written manufacturer’s warranties and guarantees. The Contractor's foregoing warranty obligations are in addition to, and not a limitation of, all manufacturer’s warranties and guarantees, and any other remedy stated in this contract or otherwise available to the City under applicable law.
8. Passing of Title and Risk of Loss.
8.1. City beneficial use of Project equipment, materials, site-work, etc. prior to the
Contractor's final completion of the Project or prior to the City's final payment for the
Project shall neither act to vest title in the City nor act to transfer risk of loss from the
Contractor to the City or to the City. Said title and risk shall pass to the City upon the
City's final payment for the Project.
8.2. Contractor and its insurer shall assume the risks of loss or damage to the equipment up to and including the date title passes, except that City shall be responsible for loss or damage caused by City's gross negligence.
8.3. After Project equipment, materials, etc. are delivered to the Project work-site and become operable or functional, the Contractor shall not thereafter remove any such equipment, materials, etc. from the Project work-site without securing the prior written consent of an authorized the City employee.
9. Indemnification.
9.1. The Contractor shall indemnify, defend, and hold harmless the State of
Connecticut and the City, and their respective boards, commissions, agents, officials and employees from and against all claims, suits, damages, losses, judgments, costs and expenses including attorney's fees arising out of or resulting from the delivery of the labor, services, equipment, materials, reports, plans, specifications, design, drawings, deliverables, incidentals, etc. provided that any such claims, suits, damages, losses, judgments, costs or expenses (i) are attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property, including the loss of use resulting there from, (ii) are alleged to be caused in whole or in part by any willful, intentional, negligent, or reckless act or omission of the Contractor, its employees, any subcontractor or consultant, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, regardless of whether or not it is caused in part by a party indemnified hereunder; (iii) enforcement action or any claim for breach of the Contractor ’s duties hereunder or (iv) claim for intangible loss(es) including but not limited to business losses, lost profits or revenue, regardless of whether or not it is caused in part by a party indemnified hereunder.
9.2. In any and all claims against the State of Connecticut and/or the City, and/or any of their respective boards, agents, employees or officers by the Contractor or any employee of the Contractor, any subcontractor or consultant, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, the indemnification obligation under Paragraph 9 above, shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for the Contractor or any subcontractor under Worker's Compensation Acts, disability benefit acts or other employee benefit acts.
9.3. The Contractor understands and agrees that any insurance required by this
Contract, or otherwise provided by the Contractor, shall in no way limit the responsibility to indemnify, defend, keep and hold harmless the State of Connecticut and/or the City and/or their respective boards, agents, employees as provided in this Contract.
9.4. The Contractor expressly understands and agrees that any performance bond or insurance protection required by this Contract, or otherwise provided by the Contractor, shall in no way limit the responsibility to indemnify, keep and save harmless and defend the State of Connecticut and the City and their respective boards, agents, employees or officers as provided herein.
9.5. Royalties and Patents. The Contractor shall, for all time, secure to , the City the free and undisputed right to the use of any and all patented articles and methods used in the work and shall defend, at Contractor's own expense, any and all suits for infringement or alleged infringement of such patents, and in the event of adverse award under patent suits, the Contractor shall pay such awards and hold, the City harmless in connection with any patent suits that may arise as a result of installations made by the Contractor and as to any award made thereunder.
9.6. In the event this Contract and/or the Contractor's, or its subcontractor, work and services provisioned hereunder is/are subject to the provisions of any Federal or State statute or regulations, or the City Charter or City Ordinance, the Contractor shall indemnify, defend and hold harmless the City from any fine, penalty or other amounts imposed on the City under said statutes, regulations, Charter or Ordinances, if caused by
Contractor, or its subcontractor, omission or commission.
10. Contract Bonds. The Contractor shall furnish to the City, prior to the execution of this
Contract by the City, both a performance bond and a payment bond, each bond written for a penal sum equaling the Section 6 "Total Compensation" amount in a form and with a surety acceptable to the City. The bonds shall continue in effect for the greater of (i) the warranty period set forth in Section 7 of this Contract, or (ii) 365 calendar days after the Final Completion Date referenced elsewhere in this Contract.
11. Contractor's Insurance.
11.1. The Contractor shall not commence work under this Contract until all insurance required under this Section 11 has been obtained by the Contractor and such insurance has been approved by the City. The Contractor shall not allow any subcontractor to commence work on any subcontract until all insurance required of any such subcontractor has been so obtained and approved by the City. Insurance shall be provided by insurers, satisfactory to the City and authorized to do business in the State of
Connecticut, an "A-" Best's Rating and at least a Class V3 or better financial size category as shown in the most current A.M. Best Company ratings.
11.2. At no additional cost to the City, the Contractor shall purchase and maintain the insurance coverages set forth below which shall protect the City from claims which may arise out of or result from the Contractor’s obligation under this Contract, whether such obligations are the Contractor’s or subcontractor or person or entity directly or indirectly employed by said Contractor or subcontractor, or by any person or entity for whose acts said Contractor or subcontractor may be liable.
11.3. Each insurance policy shall state that the insurance company shall agree to investigate and defend the insured against all claims for damages, even if groundless.
If any policy is written on a “Claims Made” basis, the policy must be continually renewed for a minimum of two (2) years from the completion date of this contract. If the policy is replaced and/or the retroactive date is changed, then the expiring policy must be endorsed to extend the reporting period for claims for the policy in effect during the contract for two (2) years from the completion date.
11.4. The following policies with stated limits shall be maintained, if applicable, in full force and effect, at all times during which the services are to be performed by the
Contractor:
11.4.1 General Liability Insurance:
$1,000,000 each Occurrence
$2,000,000 General Aggregate
$2,000,000 Products/Completed Operations Aggregate
Providing coverage to protect the City for all damages arising out of bodily injuries, sickness to or death of all persons in any one accident or occurrence and for all damages arising out of destruction of property in any one accident or occurrence. Policy must contain no exclusion for Explosion, Collapse and
Underground Hazard (XC & U)
11.4.2 Automobile Liability Insurance:
$1,000,000 Combined Single Limit (CSL) Each Accident. Including
Endorsements MCS-90 and Pollution Liability (CA9948)
Any Auto, All Owned and Hired Autos
Providing coverage to protect the City with respect to claims for damage for bodily injury and/or property damage arising out of ownership, maintenance, operation, use or loading and unloading of any auto including hired & non-owned autos.
11.4.3 Workers’ Compensation:
Statutory Limits within the State of Connecticut: Employers’ Liability (EL):
EL Each Accident $1,000,000
EL Disease Each Employee $1,000,000
EL Disease Policy Limit $1,000,000
Contractor shall comply with all State of Connecticut statutes as it relates to workers’ compensation.
11.4.4 Excess/Umbrella Liability Insurance:
$5,000,000 each Occurrence
$5,000,000 Aggregate
Excess or Umbrella insurance coverage that follows form or sits over General
Liability, Automobile Liability and Workers Compensation insurances.
11.4.5 Professional Liability Insurance:
Each Claim or Each Occurrence: $1,000,000
Aggregate $1,000,000
11.4.6 Contractors Pollution Liability Insurance:
$3,000,000 each Occurrence/Claim
$3,000,000 Aggregate
The foregoing coverage plus appropriate aggregate coverage depending on the size of the job for contractor caused pollution events.
11.4.7 Builders Risk Insurance for Fire and Extended Coverage: All Risk with
Replacement Cost Coverage Form shall be maintained by the Contractor upon the entire part of any structure on which the Work is to be done in one hundred (100%) percent of the insurable value of the Contract amount thereof, including terms of labor and materials connected therewith. This insurance includes the interests of the City of Bridgeport, Contractor, subcontractors, sub-subcontractors and shall insure against the perils of fire and extended coverage and shall include “all risk” insurance for physical damage, including but not limited to, windstorm, hailstorm, tornado, theft, vandalism, and malicious mischief coverage. The property insurance shall include the fees of an architect necessary to be incurred in repairs or reconstruction of the Work.
11.5. Failure to Maintain Insurance: In the event the Contractor fails to maintain the minimum required coverage as set forth herein, the City may at its option purchase same, and offset the Contractor’s invoices for the cost of said insurance.
11.6. Cancellation: the City shall receive written notice of cancellation from the
Contractor at least thirty (30) calendar days prior to the date of actual cancellation, regardless of the reason for such cancellation.
11.7. Certificates of Insurance: All of the Contractor’s Insurance policies, as above-referenced, except Workers’ Compensation, shall be endorsed to add the City as additional insured. All policies shall include a waiver of subrogation. The insurance afforded the additional insured shall be primary and non-contributory insurance and the coverage and limits provided under the Contractor’s policies shall not be reduced or prorated by the existence of any other insurance applicable to any loss the additional insured may have suffered. Prior to the execution of this Contract by the City, the
Contractor shall furnish to the City, subject to the City’s approval, certificate(s) of insurance and Additional Insured Endorsement and Waiver of Subrogation Endorsement verifying the above coverages, including the naming of the City of Bridgeport, as follows: “The City of Bridgeport is listed as additional insured on all lines of coverage except Workers’ Compensation and waiver of subrogation applies to all lines of coverage as their interest may appear”. The Project description must be shown on the certificate of insurance to assure correct filing. The Contractor must supply replacement/renewal certificates at least 30 days prior to the expiration of the policy(ies).
Said certificates shall contain a provision that coverage afforded under the policies shall not be cancelled or reduced for any reasons unless notice of than thirty (30) calendar days has been mailed to the City and a copy to the City’s Purchasing Department, 999
Broad Street, Bridgeport, CT 06604.
11.8. No later than thirty (30) calendar days after Contractor receipt, the Contractor shall deliver to the City a copy of the Contractor's insurance policies and endorsements and riders.
12. Conformance with Federal, State and Other Jurisdictional Requirements. By executing this Contract, the Contractor represents and warrants that, at all pertinent and relevant times to the Contract, it has been, is and will continue to be in full compliance with all applicable statutes, acts, ordinances, guidelines, resolutions, orders, judgments, decrees, injunctions, rules, and regulations of all government authorities applicable to performance by the Contractor of services hereunder, including those having jurisdiction over its registration and licensing to perform services hereunder; including, but not limited to, the following: the current STATE OF
CONNECTICUT DEPARTMENT OF ECONOMIC AND COMMUNITY DEVELOPMENT
BIDDING, CONTRACTING & CONSTRUCTION GUIDELINES FOR STATE
PROGRAMS; EQUAL EMPLOYMENT OPPORTUNITY; COPELAND ANTI- KICKBACK
ACT, as supplemented in the Department of Labor Regulations (29 CFR, Part 3); DAVIS
BACON ACT as supplemented by Department of Labor Regulations (29 CFR Part 5); Section 103 and
107 of the Contract Work Hours and Safety Standards Act, as supplemented by the Department of Labor
Regulations (29 CFR Part 5); the HOUSING and COMMUNITY DEVELOPMENT ACT of 1974, as amended; TITLE 31 and Section 12-430(7) of the State of Connecticut General Statutes. All applicable sections of the City Charter and Code of Ordinances are incorporated by reference made a part hereof.
12.1. Taxes-Federal, State and Local. The City is exempt from Federal Excise and
Transportation, State and Local Sales and Use Taxes, including without limitation, taxes that would otherwise be imposed upon the Contractor for transactions required or necessitated hereunder between it and its subcontractors, suppliers, etc. The Contractor remains liable, however, for any applicable tax obligations it incurs. Moreover, the
Contractor represents that the quote and pricing contained in this Contract do not include the amount payable for said taxes.
12.2. Labor and Wages-Federal and State. The Contractor and its subcontractors shall conform to Federal and State of Connecticut labor laws, and all other laws, ordinances, and legal requirements affecting the work in Connecticut.
12.2.1 The Contractor is aware of, and shall comply with, the provisions of Title
31, §53 of the Connecticut General Statutes, latest revision (the “Act”), concerning the payment of minimum wages for work on public facilities. The provisions of the Act are hereby incorporated by reference and made a part of this Contract. The Act provides that the Connecticut prevailing wage law applies to certain remodeling, refurbishing, alteration, repair and new construction. The wages paid on an hourly basis to any person performing the work of any mechanic, laborer or worker on the work herein contracted to be done and the amount of payment or contribution paid or payable on behalf of each such person to any employee welfare fund, as defined in Conn.Gen.Statute 31-53(i), shall be at a rate equal to the rate customary or prevailing for the same work in the same trade or occupation in the town in which such public works project is being constructed. Any contractor who is not obligated by agreement to make payment or contribution on behalf of such persons to any such employee welfare fund shall pay to each mechanic, laborer or worker as part of such person's wages the amount of payment or contribution for such person's classification on each pay day.
12.2.2 The Contractor is aware of, and shall comply with, the provisions of both the Federal Davis-Bacon Act and the Federal American Recovery and
Reinvestment Act of 2009, the provisions of both acts hereby incorporated by reference and made a part of this Contract. The Federal Davis-Bacon Act provides that Federal wage rate laws apply to certain federally funded contracts.
The American Recovery and Reinvestment Act ("ARRA") provides that Federal wage rate laws apply to all ARRA funded contracts regardless of the contract's dollar value.
12.3. Compliance with Chapters 3.08. et seq. City of Bridgeport Ordinances, Contract and Purchasing Procedure, and Compliance with Section 2.38 and 2.39
Code of Ordinance, City of Bridgeport, Ethics. By executing this Contract, Contractor represents and warrants that, at all pertinent and relevant times to the Contract, it has been, is and will continue to be in full compliance with the provisions of Chapters 3.08.
et seq. City of Bridgeport Code of Ordinances, Contract and Purchasing Procedure, and
Chapter 2.38 Code of Ordnances, Ethics as well as any other relevant provisions of the
Charter and the Code of Ordinances, which may be found at :
https://library.municode.com/.
12.4. Compliance with CONN. GEN. STAT. § 4a-60g, as amended by June 2015
Special Session Public Act 15-5.
12.4.1 Definitions – For purposes of this paragraph:
i. "Small contractor" means any contractor, subcontractor, manufacturer, service company or nonprofit corporation (A) that maintains its principal place of business in the state, (B) that had gross revenues not exceeding fifteen million dollars in the most recently completed fiscal year prior to such application, and (C) that is independent. "Small contractor" does not include any person who is affiliated with another person if both persons considered together have a gross revenue exceeding fifteen million dollars.
ii. "Minority business enterprise" means any small contractor (A) fifty-one per cent or more of the capital stock, if any, or assets of which are owned by a person or persons who (i) exercise operational authority over the daily affairs of the enterprise, (ii) have the power to direct the management and policies and receive the beneficial interest of the enterprise, (iii) possess managerial and technical competence and experience directly related to the principal business https://library.municode.com/ activities of the enterprise, and (iv) are members of a minority, as such term is defined in subsection (a) of section 32-9n, or are individuals with a disability, or
(B) which is a nonprofit corporation in which fifty-one per cent or more of the persons who (i) exercise operational authority over the enterprise, (ii) possess managerial and technical competence and experience directly related to the principal business activities of the enterprise,
(iii) have the power to direct the management and policies of the enterprise, and
(iv) are members of a minority, as defined in this subsection, or are individuals with a disability.
iii. "Municipal public works contract" means that portion of an agreement entered into on or after October 1, 2015, between any individual, Contractor or corporation and a municipality for the construction, rehabilitation, conversion, extension, demolition or repair of a public building, highway or other changes or improvements in real property, which is financed in whole or in part by the state, including, but not limited to, matching expenditures, grants, loans, insurance or guarantees but excluding any project of an alliance district, as defined in section 10-262u, as amended by this act, financed by state funding in an amount equal to fifty thousand dollars or less.
12.4.2 The Contractor and subcontractor shall comply with the specific requirements of the State of Connecticut Set Aside Program, CONN. GEN. STAT. § 4a-
60g, as amended by June 2015 Special Session Public Act 15-5, if the municipal public works contact awarded to the Contactor is funded in whole or in part by state funds.
12.4.3 The Contactor shall be subject to the following set-aside requirements if the municipal public works contact, is funded in whole or in part by the State of
Connecticut, and is in excess of FIFTY THOUSAND DOLLARS ($50,000.00), for the construction, rehabilitation, conversion, extension, demolition, or repairing of a public building or highway, or other changes or improvements in real property.
12.4.4 Set-Aside requirements – Any contractor awarded a municipal public works contract, on the basis of competitive bidding procedures, shall comply with the following Set –Aside requirements:
i. set aside at least twenty-five per cent (25%) of the total value of the state's financial assistance for such contract for award to subcontractors who are small contractors, and
ii. of that portion to be set aside in accordance with Subparagraph i.
of this subdivision, reserve a portion equivalent to twenty-five per cent (25%) of the total value of the contract or portion thereof to be set aside for awards to subcontractors who are minority business enterprises.
12.4.5 Failure of the Contractor or subcontractor to comply with the State of
Connecticut Set-Aside requirements shall be a material breach of this Contract.
13. Discriminatory Practices. In performing this Contract, the Contractor shall not discriminate against any…
This is the start of the file's text. The full file is on GovTribe.