Hazardous Material Requirements for Short-Term Contractors.pdf
PDF 241 KB Posted
- Attached to
- MHMV 210010, Site Preparation for Temporary Squad Operations Facility Federal contract opportunity
- Solicitation number
- FA940124B0002
About this file
This document is a memorandum from the 377th Air Base Wing at Kirtland Air Force Base (AFB) providing requirements for the use of hazardous materials by short-term construction contractors on the base. Key details include:
Contractors working less than one year on Kirtland AFB must have hazardous materials approved for use by the base's Hazardous Material (HM) Program. This process requires completing a Contractor HM Worksheet, providing Safety Data Sheets, and allowing for site visits to verify material inventory. Contractors are responsible for removing all excess hazardous materials from the base upon completion of the project. If working with pesticides or herbicides, contractors must coordinate with the Pesticide Management Shop. The point of contact for questions is Mr. Matthew Lujan in the HM Program.
The related federal contract opportunity is a pre-solicitation notice for a design-build requirement to provide site preparation for a Temporary Squad Operations Facility at Kirtland AFB. The North American Industry Classification Systems (NAICS) code is 238910, with a $19M size standard. A site visit is scheduled for 9 May 2024, and responses are due by 1:00 PM MST on 16 May 2024. The government is conducting market research to determine interested sources and their capabilities.
View the file
Other files for this federal contract opportunity
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DDEPARTMENT OF THE AIR FORCE
377TH AIR BASE WING (AFGSC)
12 January 2024
MEMORANDUM FOR KIRTLAND AFB PERSONNEL
FROM: 377 MSG/CEIE
SUBJECT: Hazardous Material (HM) Requirements for Short-Term Construction Contractors
1. Short-term contractors working less than one year on Kirtland Air Force Base (AFB) must have hazardous materials approved for use by the HM Program, and in accordance with AFMAN 32-7002, Chapter 3, Hazardous Material Management. This process includes the following:
a. Complete the Contractor HM Worksheet and return the worksheet to the HM Program, Building 20685 prior to hazardous materials arriving on Kirtland AFB.
b. Contractor will supply the HM Program with the manufacturer’s Safety Data Sheet (SDS) for each material. SDSs are manufacturer specific and must match all material on-site.
c. The HM Program may conduct a site visit verifying the hazardous material inventory upon arrival and an inventory upon contract completion.
d. Units are not allowed to keep excess materials for touchup or continuing needs, so short-term construction contractors must remove all excess materials from Kirtland AFB at the end of the project.
e. If the contractor is to be working with pesticides or herbicides, they must contact the 377 MSG/CEO Pesticide Management Shop at 846-5842 to coordinate Air Force reporting and management procedures.
2. My point of contact for any questions and/or submittals regarding hazardous material requirements for short-term construction contractors is Mr. Matthew Lujan, at DSN 246-2509, commercial (505) 846-2509, or by email kirtlandhazmat@us.af.mil.
ISREAL TAVAREZ, DAF
Chief, Environmental Management
Attachment:
1. Contractor Hazardous Material Worksheet
2. Hazardous Material Inventory Sheet
TAVAREZ.ISREA
L.L.1612773510
Digitally signed by
TAVAREZ.ISREAL.L.16127
73510 Date: 2024.01.12 14:22:07 -07'00'
HM1
CONTRACTOR HAZARDOUS MATERIAL WORKSHEET
SECTION 1. Contract Information
1. Contract Type:
[ ] Construction [ ] Services [ ] Aircraft Maintenance [ ] Maintenance
2. Contract Office [ ] Base Contracting
[ ] AFCEC
[ ] COE
[ ] CIMS
[ ] Other
3. Prime Contractor
4. Subcontract Number/ Work Order
5. Contract Start Date: 6. Contract End Date:
7. Project Title and Description:
8. Contractor Name and Full Address:
Name Email Phone
9. Contracting Officer
10.Quality Assurance Evaluator
SECTION II. Hazardous Materials Information
11. Will hazardous materials be used in the performance of this contract? [ ] Yes [ ] No
11a. If yes, location where work will be accomplished :
12. Will material be stored overnight on base? [ ] Yes [ ] No
12a If yes, location where material will be stored and how it will be stored:
SECTION III. Hazardous Waste Information
13. Will hazardous waste potentially be generated during the performance of the contract? [ ] Yes [ ] No
13a. If yes, location where waste will be collected:
14. If yes, contact 377 MSG/CEIEC Hazardous Waste Section@ 846-2509, annotate date contacted
CERTIFICATION
15. Contractor will sign below verifying that all excess materials will be removed from the base upon completion and that all hazardous materials have been inventoried and approved with Safety Data Sheets (SDSs) by 377 MSG /CEIEC Hazardous Material Contact
Contractor Signature:
16. 377 MSG/ CEIEC Hazardous Material Contact Signature:
HM1 (page 2 of 5)
HAZARDOUS MATERIAL INVENTORY SHEET
Part Number/Trade Name Manufacturer Container Size SDS QTYs
HM1 (page 3 of 5)
Block No Block Description Action Required
Purpose: This worksheet is to annotate basic contractor information and will serve as a record that contractors were assessed for reporting requirements per AFMAN 32-7002, Chapter 3.
Section I. Contract Information Block No Block Description Action Required
1 Contract Type Check the type of Contract.
2 Contract Office Check the contracting office managing the contract.
3. Prime Contractor Main Contractor responsible for the contract.
4. Subcontractor/ Work Order Name of subcontractor if applicable or work order number.
5. Contract Start Date The date work will actually begin on site.
6. Contract End Date The date work will actually end on site
7. Project Description Describe the general scope of the project
8. Contractor Name and Full Address Enter the Contractor Company name and full address
9. Contracting Officer Enter name, email and phone for the Contracting Officer
10. QAE Quality Assurance Evaluator (QAE), Section II. Hazardous Material Information Block No Block Description Action Required
11. Will Hazardous materials be used in the Check yes or no.
performance of this contract
11a. Location where work will be accomplished Please provide building number / area/ street
12. Will material be stored overnight on base Answer Yes or No 12a. If yes, location where material will be stored Please provide building number / area/ street and how will material be stored. Flammable lockers/ storage units
Section III. Hazardous Waste Information Block No Block Description Action Required
13. Will hazardous waste potentially be generated Check yes or no. Hazardous waste is generated when during the performance of the contract hazardous materials are used in a process that will result in waste that have the characteristics of ignitability, corrosivity, reactivity, or toxicity.
13a. If yes, location where waste will be collected Please provide building number / area/ street
14. If yes, contact 377 MSG/CEIEC Hazardous Waste Annotate Date Contacted 377 MSG/CEIEC Hazardous
Waste
Certification
15. Contractor will sign verifying that all Contractor signs statement excess materials will be removed from the base upon completion.
16. 377 MSG/CEIEC Hazardous Material Contact Signature HM Contact Signs after inspecting form and SDS.
HM1 (page 4 of 5)
Block Description Action Required Hazardous Material Inventory Sheet
Part Number/Trade name Enter the part number and/or trade name of the material used.
Manufacture Enter the manufacturer name of the material
Container Size Enter the container unit quantity, unit descriptor, and type of package for the material, e.g. 55 GL DR, 1 LB CN
SDS Safety Data Sheet available Yes/ No and revision date
QTY Quantity is the amount of material stored on site
HM1 (page 5 of 5)