Amendment0002DOC.rtf

RTF text file 340 KB Posted

Attached to
Install DOC at building 221, BGS, Lexington KY
Solicitation number
H92254-10-T-0006
Issued by

About this file

Amendment 0002

Text of this file

file_0.wmf file_1.wmf

H92254-10-T-0006

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The following have been modified:

SCHEDULE

The Contractor’s quote shall include all labor, material, supplies, transportation, supervision and all other necessary items for a complete and usable facility. Performing all work in a workman like manner in complete compliance with all plans, drawings, and specifications approved for use by Special Operations Forces Activity.

DESIGN/MEASUREMENTS: The contractor shall be responsible for all design, measurements, take offs, and technical requirements associated with this project. A concept drawing is provded in Section J. The contractor receiving contract award is expected to provide a design/drawing to scale for the project.
SITE VISIT: The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site investigations and conditions affecting the work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed. Due to mission requirements, there will be one (1) formal site visit scheduled. All interested offerors are encouraged to attend the site visit at the scheduled date and time.

The site visit is scheduled for;

DATE: 23 June 2010

TIME: 12:30 P.M.

All interested contractors must contact Mr. Mark Degroat at (859) 566-5011 for instructions and installation entry procedures to attend the site visit.

Magnitude of Construction: The magnitude of Construction for this project is between $25,000.00 and $100,000.00 NOTICE: If awarded this contract, FAR 52.228-13 -- Alternative Payment Protections apply:

(a) The Contractor shall submit one of the following payment protections:

A Payment Bond An Irrevocable Letter of Credit (ILC)

(b) The amount of the payment protection shall be 100 percent of the contract price.

(c) The submission of the payment protection is required within 5 days of contract award.

(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.

(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the Contracting Officer is authorized to access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement. (End of Clause)

SECTION I - CONTRACT CLAUSES

The following have been modified:

CONTRACT

CLAUSES INCORPORATED BY REFERENCE

52.204-7 Central Contractor Registration

APR 2008

52.204-9 Personal Identity Verification of Contractor Personnel

SEP 2007

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment

SEP 2006

52.215-8 Order of Precedence--Uniform Contract Format

OCT 1997

52.222-3 52.222-4 Convict Labor Contract Work Hours-Safety Standards Act Overtime Compensation

JUN 2003

JUL 2005

52.222-6 Davis Bacon Act

JUL 2005

52.222-7 Withholding of Funds

FEB 1988

52.222-8 Payrolls and Basic Records

FEB 1988

52.222-9 Apprentices and Trainees

JUL 2005

52.222-10 Compliance with Copeland Act Requirements

FEB 1988

52.222-11 Subcontracts (Labor Standards)

JUL 2005

52.222-12 Contract Termination-Debarment

FEB 1988

52.222-13 Compliance with Davis-Bacon and Related Act Regulations.

FEB 1988

52.222-14 Disputes Concerning Labor Standards

FEB 1988

52.222-15 Certification of Eligibility

FEB 1988

52.222-21 Prohibition Of Segregated Facilities

FEB 1999

52.222-26 Equal Opportunity

MAR 2007

52.222-27 Affirmative Action Compliance Requirements for Construction

FEB 1999

52.222-50 Combating Trafficking in Persons

FEB 2009

52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts

DEC 2007

52.223-3 Hazardous Material Identification And Material Safety Data

JAN 1997

52.223-5 Pollution Prevention and Right-to-Know Information

AUG 2003

52.223-12 Refrigeration Equipment and Air Conditioners

MAY 1995

52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts

MAY 2008

52.225-11 Alt I Buy American Act--Construction Materials Under Trade Agreements (Aug 2009) Alternate I

JUN 2009

52.225-13 Restrictions on Certain Foreign Purchases

JUN 2008

52.227-1 52.228-13 52.228-14 Authorization and Consent Alternative Payment Protections Irrevocable Letter of Credit

DEC 2007

JUL 2000

DEC 1999

52.232-5 Payments under Fixed-Price Construction Contracts

SEP 2002

52.232-23 Assignment Of Claims

JAN 1986

52.232-27 Prompt Payment for Construction Contracts

OCT 2008

52.232-33 Payment by Electronic Funds Transfer--Central Contractor Registration

OCT 2003

52.233-1 Disputes

JUL 2002

52.233-3 Protest After Award

AUG 1996

52.236-2 Differing Site Conditions

APR 1984

52.236-3 Site Investigation and Conditions Affecting the Work

APR 1984

52.236-5 Material and Workmanship

APR 1984

52.236-6 Superintendence by the Contractor

APR 1984

52.236-7 Permits and Responsibilities

NOV 1991

52.236-8 Other Contracts

APR 1984

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

APR 1984

52.236-10 Operations and Storage Areas

APR 1984

52.236-11 Use and Possession Prior to Completion

APR 1984

52.236-12 Cleaning Up

APR 1984

52.236-13 Accident Prevention

NOV 1991

52.236-14 52.236-15 Availability and Use of Utility Services Schedules for Construction

APR 1984

APR 1984

52.236-17 Layout of Work

APR 1984

52.236-21 Specifications and Drawings for Construction

FEB 1997

52.236-26 52.236-27 52.236-28 Preconstruction Conference Site Visit (Construction) Preparation of Proposals Construction

FEB 1995

FEB 1995

FEB 1997

52.243-5 Changes and Changed Conditions

APR 1984

52.245-1 Government Property

JUN 2007

52.245-9 Use And Charges

JUN 2007

52.249-1 Termination For Convenience Of The Government (Fixed Price) (Short Form)

APR 1984

52.249-10 Default (Fixed-Price Construction)

APR 1984

52.253-1 Computer Generated Forms

JAN 1991

252.236-7000 Modification Proposals-Price Breakdown DEC 1991

Other files

File Type Posted
List of Attendees.pdf PDF
Q AAmd0002.doc DOC document
Q AExt.doc DOC document
Amendment 1.doc DOC document
DOC SOL.rtf RTF text file
Atch 3 and 4 Doc 1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .