H1 and H2 Fence Move SOW.pdf

PDF 165 KB Posted

Attached to
Relocation of Airfield Fence Federal contract opportunity
Solicitation number
FA500022Q0063
Issued by
Department of the Air Force Pacific Air Forces

View the file

Other files for this federal contract opportunity

Other files attached to Relocation of Airfield Fence, newest first.
File Type Posted
Solicitation Amendment FA500022Q00630002 SF 30.pdf PDF
Updated Drawings.pdf PDF
Solicitation Amendment - FA500022Q00630002.pdf PDF
1. Relocate Airfield Fence_SOW_amd1.pdf PDF
Utility Map.pdf PDF
Standard Detail for Fence.pdf PDF
Cipher Lock Spec Sheet.pdf PDF
General Specifications.pdf PDF
Wage_Determination.pdf PDF
General Specifications.pdf PDF
Wage_Determination.pdf PDF
Fence Relocation_Site Drawings.pdf PDF
Solicitation - FA500022Q0063.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WT 8266910

Relocation of Airfield Fence near Hangar 1, Tower, and Hangar 2

(Buildings 11551, 11535, and 11525)

STATEMENT OF WORK

4/1/2022 (rev2 8/8/2022)

General overview: Remove existing airfield fence, vehicle gates and pedestrian gates and install/relocate new airfield fencing, vehicle and pedestrian gates as described below. Supply necessary power connections to relocated gates as needed for full functionality. Ensure fence is secure at building terminations. Patch holes in asphalt where fence posts were removed. Protect all existing utilities and facilities not included in scope of project.

At no point shall any portion of the airfield fence be unsecured. Contractor shall install new fence prior to removing old fence and/or use temporary fencing as required to maintain a secure airfield.

Building 11551 ‐ Elmendorf:

1. Supply materials, labor, and equipment necessary to furnish and install approximately 204 LF of 7’ 9 GA chain link fence with 3 strands of barbed wire between east side of Bldg 11551 and west side of Bldg 11535. Vehicle gate, and all necessary equipment for its use, currently in use in front of Bldg 11535 will be relocated to new fence. Fence will have 2‐7/8 terminal posts, 2‐

2/8 line posts, 1‐5/8 top rail with 7 GA coil spring bottom tension wire hog ringed to fence.

Building 11535 ‐ Elmendorf:

2. Supply materials, labor, and equipment necessary to furnish and install approximately 116 LF of 7’ 9 GA chain link fence with 3 strands of barbed wire between east side of Bldg 11535 and west side of Bldg 11525. Pedestrian gate, and all necessary equipment for its use, currently in use in front of Bldg 11551 will be relocated to new fence. Fence will have 2‐7/8 terminal posts, 2‐2/8 line posts, 1‐5/8 top rail with 7 GA coil spring bottom tension wire hog ringed to fence.

Building 11525 ‐ Elmendorf:

3. Supply materials, labor, and equipment necessary to furnish and install approximately 416 LF of 7’ 9 GA chain link fence with 3 strands of barbed wire between east side of Bldg 11535 and west side of Bldg 11525. Pedestrian gate, and all necessary equipment for its use, currently in use in front of Bldg 11525 will be relocated to new fence. Fence will have 2‐7/8 terminal posts, 2‐2/8 line posts, 1‐5/8 top rail with 7 GA coil spring bottom tension wire hog ringed to fence.

General Notes

1.1 WORKMANSHIP: Accomplish all work in accordance with all applicable building and fire codes. The

Contractor shall field verify all measurements, quantities, or values stated by the Government. The

Contractor shall prepare a project specific quality control plan and implement documented measures as a routine requirement of this task order (TO).

1.2 WORKSITE: The Contractor shall limit the work to the areas indicated by the government. The

Contractor shall make every effort not to disturb or obstruct portions of the facilities still occupied by the government. The Contractor shall coordinate and schedule work with the 673 CES/CENM &

Facility owner/CE offices prior to the start of any operation. The Contractor shall dispose of all construction debris off base at an approved disposal facility.

1.3 DIG PERMIT: Contractor will be responsible for completing the required dig permit for each work site location as it relates to their scope of work.

1.4 SITE SECURITY AND PROTECTION: The Contractor shall make every effort to secure the work site, allowing only authorized personnel to enter the work site. The contractor shall protect the site from damage from weather, vandalism, and/or theft.

1.5 DAMAGE TO EXISTING SITE CONDITIONS: The Contractor shall be responsible to repair all damage incurred to existing Real Property/Grounds at no cost to the government. The Contractor shall not park or drive on sidewalk or grassy/snowy areas.

1.6 HEALTH/SAFETY: The Contractor shall be responsible for compliance with OSHA and AFI standards.

The Contractor shall maintain a clean and debris free site at all times. The Contractor shall keep driveways and entrances into and around the work site clear at all times. The Contractor shall not use driveways or entrances as employee parking or storage of materials unless otherwise stated. The

Contractor shall minimize storage of materials and equipment on site.

1.7 ENVIRONMENTAL PROTECTION AND HAZARDOUS MATERIALS: Reference applicable laws and directives for requirements covering protection of land resources, protection of air and water quality, hazardous materials safety and general management, and storm water management. The Contractor shall reference specifications for the management of hazardous waste developed as a byproduct of this project.

1.8 GREEN PROCUREMENT: The Contractor must incorporate “green procurement” principles into the design of their projects. Specifically, consult the EPA’s web site at www.epa.gov/greenerproducts for a listing of the products mandated as green procurement requirements for purchases.

MACC Contractors are strongly encouraged to visit the site and get familiar with all the work related to the

Sewer Line repairs by CIPP prior to submitting a bid, to verify existing site condition and other information as noted in the scope of work and drawings, as well as to become familiar with the scope of work. Failure to visit the site does not relieve the Contractor from the responsibility of performing all work required to provide a complete and useable project in accordance with the Contract documents.