H. Schedule of Submittals.xlsx

XLSX spreadsheet 31 KB Posted

Attached to
Demolition Services B15 and B54
Solicitation number
FA309926Q0008
Issued by

About this file

This is a Schedule of Submittals document for the demolition of Aircraft Maintenance Shop Buildings B15 and B54 at Laughlin Air Force Base, Texas (Project #23-1101 and 23-1102). The schedule outlines all required contractor submittals organized into pre-construction (prior to NTP 1), construction mobilization (prior to NTP 2), and active construction phases. Pre-construction submittals due within two weeks to 70 days after NTP 1 include entry access lists, training certifications, demolition plans, statements of work, progress schedules, safety plans, quality control documentation, and site plans. Submittals required prior to NTP 2 include hazardous material and waste procedures, asbestos abatement plans, stormwater pollution prevention plans, FOD and dust control plans, and traffic control plans. Additionally, the contractor must submit TCEQ forms and certifications related to water systems and clean water compliance.

During the active construction phase, the contractor must submit non-hazardous and hazardous waste disposal manifests, materials testing results, daily quality control inspection reports, and records of existing conditions. Final submittals include completion inspection punchlist documentation, DD Form 1354 (draft and final), and a construction warranty management plan due within two weeks after final inspection. Monthly hazmat usage logs are required throughout construction, with weekly meeting minutes due within three days of each meeting. The schedule references specific specification sections, contract requirements, and indicates that some submittals are conditional (marked "as required"). This document serves as the contractual framework for managing all deliverable documentation throughout the demolition project lifecycle.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # 23-1101 + 23-1102 PROJECT TITLE Demolish Aircraft Maintenance Shop B15 + B54 SOLICITATION / CONTRACT NO.

(To be completed by Project Engineer)(To be completed by Contract Administrator)
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALC = Construction Project D = Design ProjectLAUGHLIN DIV 01 SPECIFICATIONSENVIRONMENTAL QUALITY CONSTRUCTION SPECIFICATIONS LAFBSTATEMENT OF WORKNUMBER OF PAPER COPIES REQUIRED. DIGITAL COPIES ARE REQUIRED FOR ALL SUBMITTALSREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS

APPR

fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

DIS

fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

NTP 1 - Pre-Construction
Entry Access List (EAL)C1.8.22 Weeks prior to base access
Proof of OPSEC TrainingC2.42 Weeks prior to base access
Antiterrorism Level I Awareness TrainingC2.42 Weeks prior to base access
Summary of site investigation/Trip ReportC4.2NLT 14 Days after NTP 1
Demolition PlanC2.6.1NLT 45 Days after NTP 1
Statement of WorkC2.5.4, 3.2NLT 45 Days after NTP 1
Progress Schedule Form and Contract Progress ReportC6.1.1Weekly
Meeting MinutesC6.2.1NLT 3 Days after meeting
AF Form 103, Work Clearance RequestC2.23.3.12.5.3NLT 7 days after NTP 1
Contractor Safety PlanC3.2.23.4.2.2NLT 60 days after NTP 1 (as required)
Certificate of Contractor Safety Compliance3.2.3NLT 7 days after NTP 1
QC Manager QualificationsC4.2.33.1.2NLT 7 days after NTP 1
QC PlanC4.2.4NLT 60 days after NTP 1 (as required)
Construction Site Plan12.1NLT 60 days after NTP 1 (as required)
Hazardous Material Approval (Safety Data Sheets)C3.2.1NLT 60 days after NTP 1 (as required)
Hazardous Waste Training Certificate3.2.2Prior to NTP 2

(as required) Hazardous Waste / Material Procedures 3.2.2 Prior to NTP 2 (as required) Customer Service Inspection Certificate (TCEQ Form 20699) 3.4.1 Prior to NTP 2 (as required) TCEQ Public water system plan review submittal form (TCEQ Form 10233) 3.4.1 Prior to NTP 2 (as required) Clean Water Act TCEQ’s General Permit 3.4.2 Prior to NTP 2 (as required) Stormwater Pollution Prevention Plan 2.7.6.2 ; 3.3 Prior to NTP 2 (as required) Asbestos Hazard Abatement Plan 3.5.2.1 Prior to NTP 2 (as required) Copy of notification to Department of State Health Services 3.5.2.1 Prior to NTP 2 (as required) Worker/Area Protection Plan 3.5.2.2 Prior to NTP 2 (as required) FOD Plan C 2.7.6.1 Prior to NTP 2 (as required) Dust/Debris Control Plan C 2.7.6.1 Prior to NTP 2 (as required)

Phase PlanC6.1.2NLT 70 Days after NTP 1
Traffic Control PlanC12.25.3, 5.5NLT 70 Days after NTP 1
Submittals per Contractor's SOWC10.4.4 through 10.4.11TBD
NTP 2 - Construction
Non-Hazardous Waste Disposal Manifest and/or Waste Shipment RecordC5.1 / 6.2NLT 45 days from the date of signature of receiving facility
Hazardous Waste Disposal ManifestsC5.2 / 6.2As required, prior to removal from Government property
Hazmat Usage LogC6.1End of each month during construction
QC Daily Inspection ReportsC4.2.6Weekly
Records of Existing ConditionsC7.1.1NLT 7 days after NTP 2
Materials Testing + ResultsC7.1.3As required, within 7 days of test
Completion Inspection (QC Manager Punchlist)C13.4NLT 3 days after Pre-Final Inspection
Draft DD Form 1354C13.33.5Prior to Pre-Final Inspection
Final DD Form 1354C13.33.5At Final Inspection
Other submittals per Contractor's SOWCTBD
Construction Warranty Management PlanC13.2NLT 2 weeks after Final Inspection
Schedule of Submittals Template, Feb 05 (SAF/AQCP)