H.08.04 Specifications W912DR22B0011 6.16.2022.pdf
PDF 5 MB Posted
- Attached to
- Letterkenny Army Depot (LEAD) Building 370 Interior Renovations Task 1, LEAD, Chambersburg, PA
- Solicitation number
- W912DR22B0011
About this file
This solicitation is for interior renovations to Building 370 at Letterkenny Army Depot in Chambersburg, Pennsylvania. Key details include full gut renovation of the second floor totaling approximately 40,000 square feet to accommodate a multipurpose "pod" layout with raised access flooring, power strips, and desk space. Fire alarm, mass notification, and sprinkler systems will be removed and replaced building-wide. Hazardous material remediation is included for areas impacted by construction. The opportunity is designated as 100% small business set-aside. The solicitation number is W912DR22B0011 and was issued by the Department of the Army Corps of Engineers Baltimore District for renovations defined as Task 1. The response due date is not specified in this document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Army Corps of Engineers Baltimore District
CONSTRUCTION
SPECIFICATIONS
BUILDING 370 INTERIOR
RENOVATION – TASK 1
LETTERKENNY ARMY DEPOT,
CHAMBERSBURG, PENNSYLVANIA
INVITATION FOR BIDS. W912DR-22-B-0011
DATE: JUL 8, 2022
Bldg 370 Interior Renovation - Task 1 LEADB370TASK1
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 91 00.15 10 TOTAL BUILDING COMMISSIONING
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 DEMOLITION
02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS
02 82 00 ASBESTOS REMEDIATION
02 83 00 LEAD REMEDIATION
02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs
AND MERCURY
02 85 00 MOLD REMEDIATION
DI VI SI ON 05 - METALS
05 05 20.00 27 POST-INSTALLED CONCRETE AND MASONRY ANCHORS
05 12 00 STRUCTURAL STEEL
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 52 00 METAL RAILINGS
DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES
06 10 00 ROUGH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID SURFACING FABRICATIONS
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 21 16 MINERAL FIBER BLANKET INSULATION
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DI VI SI ON 08 - OPENI NGS
08 11 13 STEEL DOORS AND FRAMES
08 14 00 WOOD DOORS
08 71 00 DOOR HARDWARE
PROJECT TABLE OF CONTENTS Page 1
08 81 00 GLAZING
DI VI SI ON 09 - FI NI SHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 69 13 RIGID GRID ACCESS FLOORING
09 90 00 PAINTS AND COATINGS
DI VI SI ON 10 - SPECI ALTI ES
10 11 00 VISUAL DISPLAY UNITS
10 14 00.20 INTERIOR SIGNAGE
10 22 39 FOLDING PANEL PARTITIONS
10 26 00 WALL AND DOOR PROTECTION
10 56 13 STEEL SHELVING
DI VI SI ON 21 - FI RE SUPPRESSI ON
21 12 00 STANDPIPE SYSTEMS
21 13 13 WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
21 30 00 FIRE PUMPS
DI VI SI ON 22 - PLUMBI NG
22 00 00 PLUMBING, GENERAL PURPOSE
DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)
23 05 15 COMMON PIPING FOR HVAC
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 30 00 HVAC AIR DISTRIBUTION
DI VI SI ON 25 - I NTEGRATED AUTOMATI ON
25 05 11.02 CYBERSECURITY FOR FACILITY-RELATED FIRE ALARM/MASS
NOTIFICATION CONTROL SYSTEMS
DI VI SI ON 26 - ELECTRI CAL
26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
26 08 00 APPARATUS INSPECTION AND TESTING
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 51 00 INTERIOR LIGHTING
DI VI SI ON 27 - COMMUNI CATI ONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY
PROJECT TABLE OF CONTENTS Page 2
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM,
ADDRESSABLE
DI VI SI ON 33 - UTI LI TI ES
33 11 00 WATER DISTRIBUTION
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 3
SECTION 01 11 00
SUMMARY OF WORK
08/ 15, CHG 2: 08/ 21
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Utility Outage Requests
Phasing Plan; G RO
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 General Project Description
The work includes Renovation of the east side of the second floor of Building 370 incorporating a simplified layout to include new walls, doors & frames, raised floor cable management system, ceiling systems as well as upgrades to electrical, communications, lighting, finishes HVAC and hazardous materials remediation. This also includes a comprehensive fire suppression, fire alarm and mass notification systems for the entire facility (1st and 2nd Floor).
1.2.2 Location
The work is located at Letterkenny Army Depot, Chambersburg, Pennsylvania. The exact location is on Sheet GI001 of the drawings. See also https://www.letterkenny.army.mil/
1.3 OCCUPANCY OF PREMISES
Area "A" is expected to be vacated for hazmat remediation, but if required submit to the Contracting Officer for approval a detailed proposed phasing plan, consisting of narrative, drawings, and charts, as applicable, describing the work. Become familiar with building operations to knowledgeably complete the plan. The plan shall include sequence of construction and any potential inconveniences to personnel. The plan shall describe features of work where potential excessive noise may affect operations. Where unforeseen circumstances necessitate deviating from the approved plan, coordinate such in advance with the Contracting Officer.
1.4 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
SECTION 01 11 00 Page 1
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 REFERENCES
Publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2018; TIA 18-1) Standard for Portable Fire Extinguishers
NFPA 51B (2014) Standard for Fire Prevention During Welding, Cutting, and Other Hot Work
U.S. ARMY (DA)
DA AR 25-2 (2007; RAR 2009) Information Assurance
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. DEPARTMENT OF DEFENSE (DOD)
DoD 8570.01 Cyber Workforce Management Program
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Anti Terrorism (AT) Level 1; G RO
Level 1 OPSEC Training Certificates
List of Contact Personnel; G RO
Phasing Plan; G RO
1.3 PHASING FOR FIRE ALARM SYSTEM AND FIRE SUPPRESSION SYSTEM
Building 370 will be occupied during fire alarm system and fire suppression system upgrades under this Contract. Submit to the Contracting Officer for approval a detailed proposed phasing plan, consisting of narrative, drawings and charts, as applicable. Before renovation, become
SECTION 01 14 00 Page 1 familiar with building operations to knowledgeably complete the plan.
Plan shall include sequence of construction and expected inconveniences to personnel. Where unforeseen circumstances necessitate deviating from the approved plan, coordinate such with the Contracting Officer.
1.4 LETTERKENNY ARMY DEPOT (LEAD) SECURITY REQUIREMENTS AND GENERAL
PROVISIONS
1.4.1 General Requirements
All persons requiring access within the boundaries of the Government project site or restricted access areas therein, must comply with all security regulations established under this contract.
It is not necessary to have a secret clearance at any level.
Members if the LEAD Security Office will escort contractor personnel.
Coordinate this requirement with the Contracting Officer.
At the commencement of work under this contract, the security requirements and procedures described in the paragraphs below will be initiated.
All Letterkenny Army Depot (LEAD) documents referenced below are available from the appropriate LEAD office through the Contracting Officer.
1.4.2 Inspections Pedestrians/Vehicles
All items being carried into and out of the Government restricted areas are subject to physical inspection. Additionally, all vehicles are subject to this same inspection. The inspections will be accomplished by a Government Security Protective Force member. Vehicular mounted two way radios will be turned off and will not be used within the areas. Vehicles that enter the areas in connection with the construction project may not be routinely parked within the areas except while being unloaded, loaded or unless they are actually used in support of the construction work. This latter stipulation must receive prior approval of the Contracting Officer's representative and the Government Security Representative.
1.4.3 Badges
Identification badges will be issued for admittance of personnel before performing work or service on this contract. The identification badge is the property of the U.S. Government and must be returned upon termination or demand. The Contractor/vendor agrees that all badges issued to employees must be returned to the Directorate of Risk Management, Letterkenny Army Depot promptly on termination of need for access or on expiration, whichever occurs first.
Badge room is located in Building 2. Hours of operation are 7:00 A.M. to 3:00 P.M., Monday and Wednesday. These hours are effective except when closed for holidays. If Contractor's hours of work are different than those stated above, the Contractor will be required to obtain badges when the Badge Room is open.
Badge card forms will be provided to the Contractor to be completed for each employee and returned to the Government for processing at least 14 days prior to the requested access date. The Contractor is advised that a criminal background check will be performed for each employee based on the information provided on the badge card form. Identification badges will
SECTION 01 14 00 Page 2 not be issued to individuals that do not pass the background check, nor will such individuals be permitted permanent or temporary access to LEAD for any purpose.
All visitors, delivery personnel, and other non-badged personnel will be subject to and must pass an NCIC check in order to be admitted to LEAD.
1.4.4 Prohibited Items
Compounds are identified as those areas within the perimeter fence of the building. The following items will not be brought into any compound under any circumstances:
a. Firearms and ammunition.
b. Explosives or incendiary devices (except explosive powered tools), or highly volatile substances.
c. Cameras or photographic equipment or other equipment capable of receiving and recording intelligible images.
d. Unprocessed film of any kind.
e. Processed film, including movie films, TV kinescopes, photographic slides, film strips, microfilm and microfiche.
f. Transmitting or recording equipment (except when authorized in writing by the Government for limited usage in vehicles), microphones, TV receivers and radios.
g. Sound recording equipment, including magnetic tape, magnetic wire, amplifiers and speakers.
1.4.5 Storage
Do not store supplies or equipmen within present Government compounds or buildings unless approved in writing by the Contracting Officer. If approved, no storage will be permitted within 20 feet of existing buildings or security fences.
1.4.6 Photographs
No photographing of construction, of existing buildings, or of any Government facility or feature adjacent thereto, will be permitted.
1.4.7 Personnel Removal
Government reserves the right to exclude or remove from the project site any employee of the Contractor or subcontractor that the Government deems incompetent, careless, insubordinate, who continuously violates security procedures, or whose continued employment at the work site is deemed by the Government to be contrary to public and security interests.
1.4.8 Government Surveillance
During construction, the Government may maintain security surveillance of the construction site. This surveillance may include radio controlled vehicular patrols, CCTV, Government Security Representatives maintaining visual coverage of the site, illumination of the construction site, or by
SECTION 01 14 00 Page 3 other means at the option of the Government. The purpose of such surveillance is to provide adequate security for the Government buildings and facilities to preclude unauthorized access to existing buildings and compounds. The security protection is not designed to prevent pilferage of contractor building supplies and equipment, nor can the Government be responsible for such losses.
1.4.9 Security, Safety and Fire Prevention
Comply with LEAD Pamphlet 385-4, Safety Requirements For Security, Safety, and Fire Prevention for Contractors Performing Work on LEAD, and LEAD Regulation 385-1, LEAD Safety and Occupational Health Program, available from the Contracting Officer. In the event of conflicts between LEAD Pamphlet 385-4, LEAD Regulation 385-4, EM 385-1-1 , and applicable OSHA regulations, the most stringent will apply.
1.4.10 Emergency Notifications
Contact the Contracting Officer to sign up for notifications of emergencies such as weather, active shooters, etc., which may affect construction.
1.4.11 Damage to Property
Take measures as necessary to assure that dirt and dust generated from work outside and inside the building will not interfere with operations in the building. Immediately clean-up of dust, dirt, or water that enters the building. Repair or replace any damaged Government property as determined and directed by the Contracting Officer.
1.4.12 Emergency Repairs
Provide to the Contracting Officer a list of names and phone numbers of persons to be notified in case of emergencies that may occur during the progress of the work. The names on the list shall be available on a seven-days-per-week basis. Once notified, send a crew to make necessary repairs as soon as possible. Arrive on site within two hours of notification; otherwise, the Government will have the option of utilizing other means for making repairs for which the Contractor will be charged accordingly.
1.4.13 Fire Extinguishers
The Letterkenny Fire Department must be contacted through the Contracting Officer for the proper type and number of extinguishers needed prior to beginning the contracted work. The Letterkenny Fire Department will not provide any extinguishers to the Contractor. The Contractor can gain the information in this paragraph through a pre-construction conference or phoning Extension 9101. Take necessary precautions to prevent fires in accordance with NFPA 10 and LEAD Pamphlet 420-1.
1.4.14 Delivery and Storage
The Government will not be responsible for accepting, signing for, loading, unloading, or providing covered storage for materials or equipment provided by the Contractor as a part of this contract.
SECTION 01 14 00 Page 4
1.4.15 Use of Portable Gas or Arc Equipment
Obtain from the Fire Department, through the Contracting Officer, a permit to use portable gas or arc equipment for cutting, welding, or open flame operations. The Fire Department will require one day advance notice to permit necessary inspection, notification before actually starting work, and notification when work is finished to allow re-inspection. The Fire Department can be notified by calling Extension 9101. Take necessary precautions to prevent fires in accordance with NFPA 51B and LEAD Regulation 420-13 available through the Contracting Officer.
1.5 AT/OPSEC REQUIREMENTS
Comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). Provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy.
Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
1.5.1 Physical Security
Safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials must be secured.
1.5.2 Key Control
Establish and implement methods of ensuring all keys/key cards issued by the Government are not lost or misplaced and are not used by unauthorized persons. NOTE: All references to keys include key cards. No keys issued by the Government shall be duplicated. Develop procedures covering key control that must be included in the QC Plan. Such procedures must include turn-in of any issued keys by personnel who no longer require access to locked areas. Immediately report any occurrences of lost or duplicated keys/key cards to the Contracting Officer.
In the event keys, other than master keys, are lost or duplicated the contractor shall, upon direction by the Contracting Officer, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks will be deducted from the monthly payment due the contractor. In the event a master key is lost or duplicated, all locks and keys for that system must be replaced by the Government and the total cost deducted from the monthly payment due the contractor.
Prohibit the use of the Government issued keys/key cards by any persons other than the contractor's employees. Prohibit the opening of locked areas by contractor employees to permit entrance of persons other than contactor employees engaged in the performance of services in those areas, or personnel authorized entrance by the Contracting Officer.
SECTION 01 14 00 Page 5
1.5.2.1 Lock Combination
Establish and implement methods of ensuring all lock combinations are not revealed to unauthorized persons. Ensure that lock combinations are changed when personnel having access to the combinations no longer have a need to know such combinations. These procedures must be included in the Contractor's QC Plan.
1.5.3 AT Level 1 Awareness Training
Employees requiring access to government facilities and controlled access areas must complete Anti Terrorism (AT) Level 1 awareness training within 30 days after the date of receipt of Notice To Proceed, and annually thereafter until project completion. Submit certificates of completion for each employee to the Contracting Officer within 5 calendar days after initial completion of training or annual refresher. AT Level I awareness training can be completed in approximately two (2) hours and is available at the following website: http://jko.jten.mil/courses/atl1/launch.html
Retain employee training certificates for the duration of the contract and maintain a current roster. The roster must contain the names of employees who have completed the training along with their most recent training completion date. Update the roster and resubmit to the Contracting Officer no later than 5 calendar days after completion of refresher training or a new employee completes certification.
1.5.4 iWATCH Training
This training is to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the security representative. Complete this training within 30 calendar days of the date of receipt of Notice To Proceed and within 30 calendar days of new employees commencing performance with the results reported to the Contracting Officer NLT 5 calendar days after the completion of the training.
a. iWATCH \ Website: http:://www.myarmyonesource.com/familyprogramsandservices/ iwatchprogram/default.aspx
1.5.5 Information Awareness
All employees must complete the DoD IA awareness training before issuance of network access and annually thereafter until project completion. All employees working IA/IT functions must comply with DoD and Army training requirements in DoD 8570.01 -M and DA AR 25-2 within six months of employment. Submit certificates of completion of training for each employee to the Contracting Officer within 5 calendar days after completion of the training.
Retain employee training certificates for the duration of the contract and maintain a current roster of the names of employees who have completed the training, including the most recent date that the training was completed, method of delivery of the training, and the name of the instructor if applicable. Update the roster and submit to the Contracting Officer no later than 5 calendar days after any changes.
SECTION 01 14 00 Page 6
1.5.6 OPSEC Training
All new employees must complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all employees must complete annual OPSEC awareness training until project completion. Submit Level 1 OPSEC training certificates of completion for each affected employee, to the Contracting Officer within 5 calendar days after completion of training.
OPSEC awareness training is available at the following websites:
https://www.iad.gov/ioss/ or http://www.cdse.edu/catalog/operations-security.html; or it can be provided by the OPSEC Officer in presentation form which will be documented via memorandum.
1.5.7 OPSEC SOP/Plan
Develop an OPSEC SOP/Plan within 90 days of the date of receipt of Notice To Proceed. The OPSEC SOP/Plan must be reviewed and approved by the OPSEC Officer. The SOP/Plan must include the government's critical information, why it needs to be protected, where it is located, who is responsible for it and how to protect it. In addition, identify an individual who will be an OPSEC Coordinator.
1.6 CONTRACTOR ACCESS AND USE OF PREMISES
1.6.1 Activity Regulations
In addition to provisions above, ensure that Contractor personnel employed at Letterkenny Army Depot become familiar with and obey Activity regulations including safety, fire, traffic and security regulations.
Keep within the limits of the work and avenues of ingress and egress.
Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.6.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.6.1.2 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.6.2 Working Hours
Regular working hours must consist of an 8 1/2 hour period between 7 a.m.
and 5 p.m., Monday through Friday, excluding holidays listed below.
New Year's Day Martin Luther King, Jr.'s Birthday
SECTION 01 14 00 Page 7
President's Day Memorial Day Juneteenth Independence Day Labor Day Columbus Day Veteran's Day Thanksgiving Day Christmas Day When an observed holiday falls on a Tuesday or Thursday, the Depot regularly schedules a closure on the corresponding Monday or Friday.
1.6.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
1.6.4 Occupied Buildings
The Contractor shall be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.
1.6.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. Such interruptions are further limited to hours specified by the Contracting Officer. This time limit includes time for deactivation and reactivation.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 8
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
08/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 QUALITY ASSURANCE
There are several references to quality assurance throughout these specifications. In several cases throughout these specifications, quality assurance is directly associated with Government action. In other cases in these specifications, quality assurance is in reference to Contractors' actions specifically performed by the Contractor as the quality control agent, with results to be provided to the Government for potential Government verification. In all regards, the Contractor is hereby responsible for quality management as designated by QA or QC in these specifications for and as a part of this contract.
1.3 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage as specified in FAR 52.228-5 Insurance - Work On A Government Installation.
1.4 SUPERVISION
1.4.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
1.4.2 Superintendent Qualifications
The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
SECTION 01 30 00 Page 1
1.4.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.4.3 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.5 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, clear expectations of the "Interim DD Form 1354" Submittal, and the processes for joint risk management between the Contractor and Government. Major subcontractors who will engage in the work must also attend.
1.6 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that includes joint risk management, is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.
The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.
1.6.1 Informal Partnering
The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.
The Initial Partnering session should be a part of the Pre-Construction Meeting. Partnering sessions will be held at a location agreed to by the
SECTION 01 30 00 Page 2
Contracting Officer and the Contractor (typically a conference room provided by the Resident Engineer office). The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer. The Partners will determine the frequency of the follow-on sessions, at no more than 3 to six month intervals.
1.7 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple email addresses are not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 3
SECTION 01 32 01.00 10
PROJECT SCHEDULE
02/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G RO
Preliminary Project Schedule; G RO
Initial Project Schedule; G RO
Periodic Schedule Update; G RO
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
SECTION 01 32 01.00 10 Page 1
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
2.1.1 Government Default Software
The Government intends to use Primavera P6.
2.1.2 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.
2.1.2.1 Primavera
If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.
2.1.2.2 Other Than Primavera
If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
SECTION 01 32 01.00 10 Page 2
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. OMITTED
c. Submission of mechanical/electrical/information systems layout drawings.
d. Long procurement activities
SECTION 01 32 01.00 10 Page 3
e. Submission and approval of O & M manuals.
f. Submission and approval of as-built drawings.
g. Submission and approval of DD1354 data and installed equipment lists.
h. Submission and approval of testing and air balance (TAB).
i. Submission of TAB specialist design review report.
j. Submission and approval of fire protection specialist.
k. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.
l. Air and water balancing.
m. Building commissioning - Functional Performance Testing.
n. Controls testing plan submission.
o. Controls testing.
p. Performance Verification testing.
q. Other systems testing, if required.
r. Contractor's pre-final inspection.
s. Correction of punch list from Contractor's pre-final inspection.
t. Government's pre-final inspection.
u. Correction of punch list from Government's pre-final inspection.
v. Final inspection.
3.3.5 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 . This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil .
The SDEF format is as follows:
SECTION 01 32 01.00 10 Page 4
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible party
3 AREA 4 Area of work
4 MODF 6 Modification Number
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of work
7 CATW 1 Category of work
8 FOW 20 Feature of work*
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.3.6.1 Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.
3.3.6.2 Responsible Party Coding (RESP)
Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.
a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.
b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);
ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).
3.3.6.3 Area of Work Coding (AREA)
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a
SECTION 01 32 01.00 10 Page 5 building, and different buildings within a complex of buildings.
Activities cannot have more than one Work Area Code.
Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.
3.3.6.4 Modification Number (MODF)
Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.
3.3.6.5 Bid Item Coding (BIDI)
Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.
3.3.6.6 Category of Work Coding (CATW)
Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.
3.3.6.7 Feature of Work Coding (FOW)
Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.
Definable Feature of Work is defined in Section 01 45 00.00 10 QUALITY CONTROL. An activity can have only one Feature of Work Code.
3.3.7 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
Mandatory constraints that ignore or effect network logic are prohibited.
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
3.3.7.1 Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.
3.3.7.2 End Project Finish Milestone and Constraint
The last activity in the schedule must be a finish milestone titled "End
SECTION 01 32 01.00 10 Page 6
Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.
3.3.8 Calendars
Schedule activities on a Calendar to which the activity logically belongs. Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop sSeasonal Calendar(s) and assign to seasonally affected activities as applicable.
If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated adverse weather delay work days below. Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends .
3.3.9 Time Extensions for Unusually Severe Weather
3.3.9.1 Procedure for Determination
This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance the contract clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.
3.3.9.2 Anticipated Adverse Weather Delays
The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
SECTION 01 32 01.00 10 Page 7
12 7 7 9 7 7 6 6 4 5 5 7
3.3.9.3 Impact
Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph "Anticipated Adverse Weather Delays", above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a contract modification.
3.3.10 Open Ended Logic
Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.
Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.
3.3.11 Default Progress Data Disallowed
Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.
3.3.12 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer.
Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.
3.3.13 Added and…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .