GSA SOW 66518 MARAD DOT Warehouse 2143350 (2).pdf

PDF 13 MB Posted

Attached to
MARAD 2 DOT NDRF WHARF
Solicitation number
47PH0524R0093
Issued by

About this file

This document is a Statement of Work (SOW) for the renovation of a two-story office area within a 1930s DOT warehouse for the relocation of the Maritime Administration (MARAD) from the Hale Boggs Building. The work includes demolition of interior finishes, partial removal of exterior cladding, and removal of MEP, fire sprinkler, and other systems within the renovation area. New work includes interior finishes, exterior cladding, MEP systems and fixtures, fire sprinklers, and other systems related to the office area renovation. Minor site work is also included.

This is a 100% Small Business Set-Aside procurement with an estimated construction cost between $1,000,000 and $5,000,000. The applicable NAICS code is 236220 Commercial and Institutional Building Construction, with a $45 million size standard. The source selection will be based on the Lowest Price Technically Acceptable process. A mandatory site visit is scheduled for July 25, 2024, and the solicitation closing date is August 29, 2024. All questions and answers will be posted as amendments to the solicitation on SAM.gov.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. General Services Administration Public Buildings Service Greater Southwest Region

Sunday, September 10, 2023

Construction Scope of Work

1. Project Title: 1996 [66518] HB MARAD 2 DOT NDRF, Wharf 2143350

Project Location: LA9901 Office Building 38 Poland Wharf New Orleans, LA

2. Building Location Hours: Use of building facilities shall be limited to the immediate area where the work is to be performed. Work may be performed during normal working hours; however, work may not disrupt normal building operations. After hours work may be necessary to reduce noise and allow for normal Warehouse Building operations, this is to be accounted for in the submitted price. The Wharf /Dock and Ship schedules will also determine when the work may be done and will need to be coordinated through the GSA Representative accordingly. Normal business hours are generally defined from 8:00 a.m. to 5:00 p.m. Monday through Friday. The Contractor shall work with the GSA Representative and the Agency to establish the working hours at the start of the project.

3. Pre-bid Site Visit: Site visits shall be conducted to allow prospective bidders the opportunity to see onsite conditions. COVID guidance from CDC and local building operation procedures must be adhered to during the Pre-Bid site visit.

Purpose: The General Services Administration requests a proposal for Construction Services for turnkey Building /Space Buildout /renovations to subject project: MARAD DOT NDRF.

REVIEW CONSTRUCTION DRAWINGS, FURNITURE PACKAGE AND SPECIFICATIONS.

4. Points of Contact:

4.1 Contracting Officer: Rod Blouin

500 Poydras Street, Suite 1010 New Orleans, LA 70130 Phone #: 713-875-0632 rod.blouin@gsa.gov

4.2 Contract Specialists: Sandy Cyres / Mark Blanco

500 Poydras Street, Suite 1010 New Orleans, LA 70130 Phone #: 504-206-5560 sandy.cyres@gsa.gov

Phone #: 504-432-9239 mark.blanco@gsa.gov

1996 [66518] HB MARAD 2 DOT NDRF, Wharf 2143350

1 Last updated 8/13/2021

Planning Execution

4.3 Senior Project Manager: Peter Leonardo Longerich, AAIA

500 Poydras Street, Suite 1010 New Orleans, LA 70130

Phone #: 504-239-peter.longerich@gsa.gov

Agency contact: Tommy A. Johnson Chief, Division of Property Management

Phone #: 202-997-tommy.a.johnson@dot.g ov

4.4 Property Manager: Dean Baldus

500 Poydras Street, Suite

1200 MARAD

New Orleans, LA 70130 Phone #: 504-312-

Dean.Baldus@dot.gov

4.5 Other: R7 Security Clearance

Coordinators r7clearance@gsa.gov.

• NOT APPLICABLE.

5. Notice to Proceed:

5.1 The Contracting Officer is the ONLY individual from the Government that can give the contractor a notice to proceed.

5.2 Before any of the work within the scope of the contract is started, the Contractor shall confer with the COR (Contracting Officer’s Representative) and agree on a sequence of procedure; means of access to premises and building; delivery of material and use of approaches; use of corridors, stairways, elevators, and similar means of communications; and the location partitions, eating spaces for Contractor’s employees and the like.

5.3 After a Notice to Proceed is given the Contractor has 7 days to provide a final schedule.

6. Period of Performance: The total period of performance for this task order is 210 days or less.

LD’s are subject beyond official Extensions.

7. Description of Work: REVIEW CONSTRUCTION DRAWINGS, FURNITURE PACKAGE, SPECIFICATIONS.

And all other Items after Appendix.

Contractor shall provide all materials, labor, tools, equipment, and daily supervision to accomplish tasks as outlined in contract documents. Contractor is also responsible for all necessary safety measures.

7.1 Division 1 General Requirements

7.1.1 Daily clean up. All workspace, staging areas, areas used for moving materials, trash, tools, etc. are to be kept clean at all times. All trash from the day’s work is to be removed and work site clean and orderly.

7.1.2 Protection. Contractor is responsible for protection of existing finishes, utilities, etc. in the facility, and must maintain a separation of work area from adjacent spaces. Site is to be secured at end of day. Contactor shall be responsible for the security of the work site.

7.1.3 Progress Meetings and Calls. The Contactor shall be responsible for providing an updated agenda, RFI and Submittal Logs no later than 24 hours before the Progress Calls or Meetings and shall provide Minutes no later than 48 hours after the Progress Calls or Meetings. Agenda content and Log format shall be reviewed and approved by the PM. Meetings for this Project shall be 1x for each 30-Day Period. With a minimum of 9 Meetings for total Period of Performance.

7.2 Division 2: Existing Conditions

7.2.1 In Addition to the Demolition Scope /portion, the Project includes moving the

Agency from existing 500 Poydras to new 38 Poland. Customer is US MARAD.

GC, to Coordinate construction effort close to substantial completion for this task.

7.2.2 The Resource for this Effort shall be BART’S. 2838 Elysian Fields Avenue, NOLA, LA 70122. POC is Angela B. Weidel at 225-803-0290 at angie@barts-office.com;

7.2.3 OR A FIRM /COMPANY EQUAL OF REQUIEREMTNS AND EXPERIENCE.

7.2.4 Excess of items not being moved, shall be Subject to GSA Excess Policy. Federal, State and Local Governments, Schools and First Responders, non-profit Entities.

7.2.5 Please review itemized List of this requirement.

7.2.6 The cost for this effort shall be shown on line item 34000001 /34 on the Form as provided. And the Vendors standard Proposal Form.

7.2.7 This Project requires Abatement. Contractor shall review enclosed Report, which is to be included in the Construction Build-out as a turnkey Effort.

7.2.8 The Resource for this Effort shall be a qualified Environmental Remedial Outfit.

7.2.9

7.3 Division 3: Concrete

7.3.1 N/A.

7.4 Division 4: Masonry

7.4.1 N/A.

7.5 Division 5: Metals

7.5.1 N/A.

7.6 Division 6: Wood, Plastics, and Composites

7.6.1 N/A.

7.7 Division 7: Thermal and Moisture Protection

7.7.1 N/A.

7.8 Division 8: Openings

7.8.1 N/A.

7.9 Division 9: Finishes (Flooring)

7.9.1 N/A.

7.10 Division 9: Finishes (Carpentry)

7.10.1 N/A.

7.11 Division 10: Specialties

7.11.1 N/A.

7.12 Division 11: Equipment

7.12.1 N/A.

7.13 Division 12: Furnishings

7.13.1 Contractor shall review enclosed Scope for Furniture Plans, to be included in the

Construction Build-out as a turnkey Effort.

7.13.2 The Resource for this Effort shall be BART’S. 2838 Elysian Fields Avenue, NOLA, LA 70122. POC is Angela B. Weidel at 225-803-0290 at angie@barts-office.com;

7.13.3 OR A FIRM /COMPANY EQUAL OF REQUIEREMTNS AND EXPERIENCE AND

BUDGET CAP.

7.13.4 The cost for this effort shall be shown on line item 12000001 /12 on the Form as provided. And the Vendors standard Proposal Form.

7.13.5 Division 13: Special Construction.

7.13.7 N/A.

7.14 Division 14: Conveying Equipment

7.14.7 N/A.

7.15 Division 21: Fire Suppression

7.15.7 N/A.

7.16 Division 22: Plumbing

7.16.7 N/A.

7.17 Division 23: Heating, Ventilation, and Air Conditioning

7.17.7 N/A.

7.18 Division 25: Integrated Automation

7.18.7 N/A.

7.19 Division 26: Electrical

7.19.7 N/A.

7.20 Division 27: Communications

7.20.7 IT /Data and Equipment is included in this Project, refer to CD’s and Specs.

7.21 Division 28: Electronic Safety and Security

7.21.7 N/A.

7.22 Division 31: Earthwork

7.22.7 N/A.

7.23 Division 32: Exterior Improvements

7.23.7 N/A.

7.24 Division 33: Utilities

7.24.7 N/A.

REVIEW CONSTRUCTION DRAWINGS, FURNITURE PACKAGE, SPECIFICATIONS. And all other Items after

Appendix.

8. Liquidated Damages: $250.00 per day may be assessed by the Contracting Officer each day past the substantial completion date and will be deducted from the contractor’s final payment application.

9. Sustainability:

9.13 Green Purchasing: See Appendix 1: Green Purchasing Requirements

9.14 Waste Diversion: Fourteen days from Notice to Proceed, the Contractor shall submit to the Project Manager an updated Non-Hazardous Solid Waste Management Plan (Attachment 2: Waste Diversion Plan), to include (not limited to):

a) List of materials Contractor will reuse.

b) List of materials the Contractor will donate and name and address of donation recipient.

c) List of materials the Contractor will recycle and the name and address of the recycler. If Contractor receives recycling revenue, Contractor shall keep revenue and provide receipt for GSA for reference.

10. Name and location of solid waste landfill for non-diverted material. Other Requirements to be discussed at Pre-Bid /Pre-Con:

10.13 Purchase of Equipment

10.14 Building Specific Requirements

10.14.7 Parking

10.14.8 Building Specific Access Requirements

10.14.9 After-Hours Coordination

10.14.10 Loading Dock Use (During Duty & After-Hours)

10.14.11 Common Area Cleaning

10.14.12 Utility Outages

10.14.13 Hot Work Permits

10.14.14 Key Control

11. Submittals:

11.13 Submittal Log - List of Submittals

11.14 Critical Path Method Cost Loaded Gantt Schedule that accounts for potential impacts.

11.15 Waste Diversion Submittal: Preconstruction

11.16 Waste Diversion Submittal: Post Construction

11.17 Green Purchasing items

11.18 Product Brochure information

11.19 Finish Schedule

11.20 Shop Drawings

11.21 Safety Plan

12. Attachments:

12.13 Attachment 1: Waste Diversion Plan

12.14 Attachment 2: Space Layouts.

12.15 Furniture Package.

13. Closeout Plan:

13.13 Final Punch list complete

13.14 Customer Acceptance

13.15 Dimensioned Redline Drawing

13.16 Close Out Documents (O&M Manuals, Warranty, Certified payrolls and Release of Claims, Waste Diversion documentation)

13.17 All Government Furnished Equipment and Property returned including, but not limited to:

GSA PIV cards, Building keys, Government IT equipment, etc.

13.18 SBU/CUI Documentation - Reference Paragraph III.N in base contract

13.18.7 Provide list of all entities to which SBU/CUI is disseminated.

13.18.8 Provide notification SBU/CUI has been returned or destroyed.

13.19 Final Payment - CO may withhold payment until all Closeout items are received.

5 Last updated 8/13/2021

Sustainability:

● Green Purchasing:

o The contractor shall refer to the “Green Procurement Compilation” for all products being installed in federal facilities. The Green Procurement Compilation can be found at https://sftool.gov/greenprocurement. The standards found in this compilation shall guide all product purchasing decisions as they relate to federal facilities.

o The use of the following standards (“Key Sustainable Product” or “KSP” standards) is mandatory for all contracts and task orders. See https://sftool.gov/green-products/1037/key-sustainable-products for more details.

▪ Nylon Carpet: NSF-140 Platinum or Cradle to Cradle Bronze.

▪ Resilient Flooring (e.g., vinyl and linoleum): NSF-332 (any level) or Cradle to

Cradle (any level)

▪ Interior Latex Paint: Master Painters Institute (MPI) Extreme Green or Green

Seal 11.

▪ Acoustical Ceiling Tiles: > 15% post-consumer recycled content.

▪ Water-Consuming Equipment: Water Sense Certified.

A. For each KSP listed, the Contractor shall submit proof of compliance to the CO or his designee prior to the installation of the product or material. The CO’s designee shall verify compliance.

B. If the KSP materials listed above are 1) not reasonably available within a reasonable period of time; 2) fail to meet the performance standards set forth in the specification or fail to meet reasonable performance standards of GSA; or 3) are available only at an unreasonable price, only then can the Contractor use other types of products. In these cases, the Contractor shall select products and materials, to the extent possible, which are the safest and most environmentally friendly. Exemptions must be submitted in writing and can only be approved by the CO.

APPENDIX.

Technical EVALUATION FACTORS within Proposal and Management Plan including Examples and Documentation shall consist of:

Offeror shall provide a Cost Loaded Critical Path Method Schedule. Reference SOW for Example.

Offeror shall have Site Development and Exterior Security Fencing experience.

Offeror shall have Environmental, Abatement, Selective Demolition experience, specific to various occupancy type Buildings.

Offeror shall have past experience with Historic, 80 -100 yr. Buildings and Structure renovations within the City of

New Orleans, surrounding areas within South Louisiana. Or similar Cities with historic Building districts and Architecture in surrounding States of the greater South West.

Offeror shall have mixed use and multi-use Occupancy experience, Office Space, Classroom and Presentation

Space, Galley Space, multipurpose Kitchen, unisex Bathroom and Shower Spaces. Experience with COOP space (Continuity of Operations). Conversions from other Occupancies to temporary Housing or Living Spaces.

Offeror shall have integrated Security and Access Control experience. Telecom and Data experience specific to distribution and redundancy, and requirements for MDF, IDF Rooms and point to point Cat 6 /Fiber terminations.

Offeror shall have Sustainability experience specific to Energy, Conservation and off the Grid Systems and

Technologies. Reference SOW for additional Information.

Price proposal shall consist of Price Breakout using the proposal format included in the SOW and RFP.

Activity ID Activity Name Original Duration

Activity % Complete

Actual Total Cost Budgeted Total Cost

Start Finish

Baton Rouge Courthouse First Floor RenovationBaton Rouge Courthouse First Floor Renovation 263 $27,940.00 $819,592.26 26-Jun-18 A 28-Jun-19

A1000 NTP 0 100% $0.00 $0.00 26-Jun-18 A

A1070 Badging 45 50% $0.00 $0.00 26-Jun-18 A 30-Aug-18

A1470 Submittals 42 30% $6,375.00 $21,250.00 26-Jun-18 A 10-Sep-18

A1490 P&P Bonds 1 100% $21,565.00 $21,565.00 26-Jun-18 A 26-Jun-18 A

A1050 Pre-Move Meeting 1 0% $0.00 $1,250.00 23-Aug-18* 24-Aug-18

A1060 Room 326 Temp Wall 5 0% $0.00 $1,090.00 24-Aug-18 31-Aug-18

A1080 Room 326 Tenant Inspection Acceptance 1 0% $0.00 $0.00 31-Aug-18 03-Sep-18

A1010 Relocate FPS-1st Floor to 3rd Floor 5 0% $0.00 $2,500.00 03-Sep-18 10-Sep-18

A1020 Relocate HCF-1st Floor to 3rd Floor 5 0% $0.00 $2,500.00 10-Sep-18 17-Sep-18

A1090 LADEQ Asbestos Notice 10 0% $0.00 $2,750.00 10-Sep-18 24-Sep-18

A1110 Mobilization 5 0% $0.00 $9,850.00 17-Sep-18 24-Sep-18

A1100 Build Dustproof Containment 2 0% $0.00 $775.00 24-Sep-18 26-Sep-18

A1170 Demo & Salvage Wainscot 4 0% $0.00 $1,855.00 26-Sep-18 02-Oct-18

A1220 Demo & Salvage Mini Blinds 2 0% $0.00 $555.00 26-Sep-18 28-Sep-18

A1180 Demo & Salvage Railing 2 0% $0.00 $1,100.00 02-Oct-18 04-Oct-18

A1160 Asbestos Remediation & Demolition 12 0% $0.00 $51,458.00 04-Oct-18 22-Oct-18

A1190 Demo & Salvage Doors/Frames 3 0% $0.00 $1,755.00 22-Oct-18 25-Oct-18

A1210 Demo Existing Acoustical Ceiling 5 0% $0.00 $7,825.26 25-Oct-18 01-Nov-18

A1500 Supply Doors/Frames/Hardware 5 0% $0.00 $27,323.00 29-Oct-18 05-Nov-18

A1200 Demo Partition Walls 3 0% $0.00 $10,990.00 01-Nov-18 06-Nov-18

A1230 Demo existing mechanical 10 0% $0.00 $43,867.00 06-Nov-18 20-Nov-18

A1240 Demo existing lighting 3 0% $0.00 $11,800.00 06-Nov-18 09-Nov-18

A1250 Demo existing power/data/FA 5 0% $0.00 $9,530.00 09-Nov-18 16-Nov-18

A1260 Demo existing plumbing 3 0% $0.00 $1,713.00 16-Nov-18 21-Nov-18

A1270 OH Mechanical Rough-In 15 0% $0.00 $91,630.00 21-Nov-18 12-Dec-18

A1280 Layout & Frame New Partition Walls 10 0% $0.00 $28,000.00 12-Dec-18 26-Dec-18

A1290 Electrical/Data/FA Rough-In 15 0% $0.00 $117,798.00 26-Dec-18 16-Jan-19

A1440 Install New & Salvaged Door Frames 3 0% $0.00 $4,495.00 26-Dec-18 31-Dec-18

A1300 ACT Grid 10 0% $0.00 $16,250.00 16-Jan-19 30-Jan-19

A1310 Fire Sprinkler Trim-Out 5 0% $0.00 $42,920.00 30-Jan-19 06-Feb-19

A1320 Drywall 10 0% $0.00 $18,037.00 06-Feb-19 20-Feb-19

A1330 Tape/Bed/Paint Drywall 20 0% $0.00 $32,960.00 20-Feb-19 20-Mar-19

A1340 Electrical/Data/FA Trim-Out 10 0% $0.00 $131,121.00 20-Mar-19 03-Apr-19

A1350 Mechanical Trim-Out 5 0% $0.00 $36,500.00 03-Apr-19 10-Apr-19

A1380 Drop ACT Tiles 5 0% $0.00 $8,220.00 10-Apr-19 17-Apr-19

A1360 Flooring Prep 5 0% $0.00 $14,450.00 17-Apr-19 24-Apr-19

A1370 VCT & Carpet Tile Installation 6 0% $0.00 $24,252.00 24-Apr-19 02-May-19

A1420 Install Doors & Harware 4 0% $0.00 $6,400.00 02-May-19 08-May-19

A1430 Install Millwork & Salvaged Bookcases 2 0% $0.00 $1,155.00 08-May-19 10-May-19

A1450 Punch List Walkthrough 1 0% $0.00 $0.00 10-May-19 13-May-19

A1460 Punch List Correction 5 0% $0.00 $0.00 13-May-19 20-May-19

A1390 Fire Alarm Testing 3 0% $0.00 $0.00 20-May-19 23-May-19

A1400 Test/Adjust/Balancing 3 0% $0.00 $10,593.00 23-May-19 28-May-19

A1120 Owner Training 2 0% $0.00 $0.00 28-May-19 30-May-19

A1130 Submit O&M Manuals 1 0% $0.00 $0.00 29-May-19 30-May-19

A1140 Submit As-Builts 1 0% $0.00 $0.00 29-May-19 30-May-19

A1150 Submit Warranties 1 0% $0.00 $0.00 29-May-19 30-May-19

A1410 Final Inspection 1 0% $0.00 $0.00 30-May-19 31-May-19

A1030 Relocate FPS-3rd Floor to 1st Floor 10 0% $0.00 $755.00 31-May-19 14-Jun-19

A1040 Relocate HCF-3rd Floor to 1st Floor 10 0% $0.00 $755.00 14-Jun-19 28-Jun-19

A1480 Final Space Acceptance 0 0% $0.00 $0.00 28-Jun-19

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug

2018 2019

28-Jun-19, Baton Rouge Courthouse First Floor Renovation

NTP

Badging

Submittals

P&P Bonds

Pre-Move Meeting

Room 326 Temp Wall

Room 326 Tenant Inspection Acceptance

Relocate FPS-1st Floor to 3rd Floor

Relocate HCF-1st Floor to 3rd Floor

LADEQ Asbestos Notice

Mobilization

Build Dustproof Containment

Demo & Salvage Wainscot

Demo & Salvage Mini Blinds

Demo & Salvage Railing

Asbestos Remediation & Demolition

Demo & Salvage Doors/Frames

Demo Existing Acoustical Ceiling

Supply Doors/Frames/Hardware

Demo Partition Walls

Demo existing mechanical

Demo existing lighting

Demo existing power/data/FA

Demo existing plumbing

OH Mechanical Rough-In

Layout & Frame New Partition Walls

Electrical/Data/FA Rough-In

Install New & Salvaged Door Frames

ACT Grid

Fire Sprinkler Trim-Out

Drywall

Tape/Bed/Paint Drywall

Electrical/Data/FA Trim-Out

Mechanical Trim-Out

Drop ACT Tiles

Flooring Prep

VCT & Carpet Tile Installation

Install Doors & Harware

Install Millwork & Salvaged Bookcases

Punch List Walkthrough

Punch List Correction

Fire Alarm Testing

Test/Adjust/Balancing

Owner Training

Submit O&M Manuals

Submit As-Builts

Submit Warranties

Final Inspection

Relocate FPS-3rd Floor to 1st Floor

Relocate HCF-3rd Floor to 1st Floor

Final Space Acceptance

Baton Rouge Courthouse First Floor Renovation Classic Schedule Layout 03-Aug-18 08:02

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 1 of 1 TASK filter: All Activities

© Oracle Corporation

PeterLLongerich Stamp EXAMPLE

1996 66518 MARAD DOT Warehouse 2143350

RS Means CSI Div. Category 0.00% NOTES

10000001 1 GENERAL CONDITIONS

20000001 2 EXISTING CONDITIONS

30000001 3 CONCRETE

40000001 4 MASONRY

50000001 5 METALS

60000001 6 WOOD AND PLASTICS

70000001 7 THERMAL/MOISTURE PROTECTION

80000001 8 DOORS / WINDOWS

90000001 9 FINISHES

10000001 10 SPECIALTIES

11000001 11 EQUIPMENT

12000001 12 FURNISHINGS Vendor

13000001 13 SPECIAL CONSTRUCTION

14000001 14 CONVEYING SYSTEMS

21000001 21 FIRE SUPPRESSION

22000001 22 PLUMBING

23000001 23 HVAC

25000001 25 INTEGRATED AUTOMATION

26000001 26 ELECTRICAL

27000001 27 COMMUNICATIONS

28000001 28 ELECTRICAL SAFTEY & SECURITY

31000001 31 EARTHWORK

32000001 32 EXTERIOR IMPROVEMENTS

33000001 33 UTILITIES

34000001 34 MOVING EXCESSING, DISPOSAL Vendor

0.00%

SUBTOTAL item 1-34 -$

TOTAL

MEMO

10000 RICHMOND | SUITE 100 | HOUSTON, TX 77042

713.629.6100

P D G A R C H I T E C T S . C O M

66518 Boggs MARAD to DOT Warehouse

Green and Energy Saving Features

March 29, 2023

The following is a partial list of green and energy items that will be incorporated into the design of the facility:

ARCHITECTURE

Upgrade Building envelope Insulation R-19 walls and R-30 Roof

Retain existing exterior plaster walls

Request contractor to recycle demolished items as much as possible

Request Contractor to recycle material packaging as much as possible

Low VOC Finishes and Compounds

Utilize construction materials with significant recycled content such as steel studs

Operable windows for natural ventilation

Double pane windows with thermally broken frames

Windows to allow in natural light

Carbon Capturing materials such as wood and carpet tiles

ELECTRICAL

High efficiency LED Light fixtures

Occupancy sensor light controls

Rough-in for future electric car charging stations

Rough-in for future roof mounted solar arrays

Metering power use to track energy usage

All electric devices (no natural gas)

HVAC

High SEER HVAC Units zoned for first and second floors

Ductwork in conditioned space instead of an attic

Separate split HVAC system for IT room

Programmable thermostats

Wharf Project Green and Energy Saving Features

PLUMBING

On demand water heaters

High-Efficiency Toilets

Performance Showerhead

Water-Saving Faucets

Jason W. Beal, AIA Senior Vice President, PDG architects

NARRATIVE

75% Design Submittal Relocation of MARAD to DOT Warehouse

2143350 Wharf 3, Bay 43, 44, 45

38 Poland Ave. and Chartres New Orleans, LA

Prepared For:

General Services Administration June 22, 2023

10 000 Richmond, suite 100 Houston, TX 77042 www. pdgarchitects.com

RELOCATION OF MARAD TO DOT WAREHOUSE GENERAL SERVICES ADMINISTRATION

NEW ORLEANS, LA PDG ARCHITECTS

75% DESIGN SUBMITTAL

June 22, 2023 Page 2

TABLE OF CONTENTS

TABLE OF CONTENTS

PART A – CONTRACT INFORMATION

DESIGN CONTRACT

DESIGN TEAM

CODES, REGULATION AND GUIDELINES

PART B – PROJECT INFORMATION

PROJECT DESCRIPTION

SITE INVESTIGATION REPORT

EXISTING CONDITIONS

PART C- ARCHITECTURAL DESIGN

EXTERIOR

INTERIOR

SUSTAINABILITY

LIFE SAFETY

PART D- MEP DESIGN NARRATIVE

MECHANICAL SYSTEMS

ELECTRICAL SYSTEMS

PLUMBING SYSTEMS

APPENDIX

June 22, 2023 Page 3

PART A- CONTRACT INFORMATION

DESIGN CONTRACT

PDG Architects’ GSA Contract this document has been prepared to establish and record the scope and level of quality anticipated for the project at the 75% Design Phase. This document is also intended to get feedback from stakeholders and aid in the preparation of cost estimates.

DESIGN TEAM

Under this Task Order the following consultants are provided supporting documentation and design services:

• ARCHITECT - PDG Architects- Houston, TX

• MEP ENGINEERS - IMC Consulting Engineers- New Orleans, LA

• STRUCTURAL ENGINEER - EHC Engineering- New Orleans, LA

• COST ESTIMATING - Project Cost Resources- Houston, TX

CODES, REGULATIONS AND GUIDELINES

Per the Scope of Work the design of the project is required to comply with the following codes and regulations to the fullest extent possible within the physical scope and fiscal constraints of the project:

• The following codes by reference:

• Structural: IBC, 2018 Edition

• Life Safety: NFPA 101, 2018 Edition

• Electrical: NEC, 2017 Edition (NFPA 70)

• Energy Conservation: IECC, 2015 Edition

• Plumbing: IPC, 2015 Edition

• Mechanical: IMC, 2015 Edition

• Sprinkler System: NFPA 13, 2016 Edition

• Fire Alarm System: NFPA 72, 2016 Edition

• Fire Extinguishers: NFPA 10, 2018 Edition

• Standpipe System: NFPA 14. 2016 Edition

• Architectural Barriers Act Accessibility Standard (ABAAS) 2005.

June 22, 2023 Page 4

PART B- PROJECT INFORMATION

PROJECT DESCRIPTION

The goal of the project is to renovate an existing space located inside a warehouse to provide office spaces for the Division of Gulf Operations of the U.S. Department of Transportation Maritime Administration.

EXISTING CONDITIONS

PDG Architects conducted a site visit Thursday, February 3, 2022, to visually investigate existing conditions of the space and to acquire measurements of the space using a laser scanner.

Subsequent trips have been taken to review the existing conditions in more detail.

PRE-ALTERATION ASSESSMENT OF HAZARDOUS MATERIALS

An existing asbestos/ lead/ PCB’s containing materials survey for the space has been completed by PSI. The report is included in the specifications. The survey revealed that there is lead based paint in the building and that the floor tiles on the first and second floors contain ACMs.

The design team anticipates all materials containing hazardous materials will be removed from the site during demolition activities for this project. All hazardous material handling will have to be done by specialized subcontractors, and in conformance with all local and federal regulations.

HISTORICAL PRESERVATION

After discussions with SHPO and the GSA Historic Team, the building is not of historic significance nor registered on the National Registry of Historic Places.

EXISTING CONDITIONS

Area to be occupied by the Gulf Operations of MARAD is a two-story enclosed space located in the north-eastern corner of a wharf warehouse on the north bank of the Mississippi River.

STRUCTURE

The structure of the warehouse building is composed of steel columns, steel trusses and plywood roof deck. Structural elements appeared to be in sound condition.

Structural elements supporting the second floor of the office space appear to be round steel columns supporting wide flange steel beams supporting wood joists with wood decking. These elements are currently partially enclosed in partitions and ceiling finishes on the first floor.

The structural engineer reviewed the condition of the wood structure and stated it appears to be structurally sound. However all of the first floor ceiling materials need to be removed to expose the wood joists to look for any damage that needs to be repaired.

ACESSIBILITY AND EGRESS

The first floor of the office space is elevated 6” above adjacent warehouse floor, and 12” above the structural concrete wharf deck abutting the building. Currently the access to the first floor is via concrete steps that do not meet accessibility guidelines. Ramps with guardrails will have to be added at the entrances into the first-floor office space to make the space handicap- accessible.

June 22, 2023 Page 5

Access to the second floor from the first is through an interior stair that does not meet current life safety codes. An outdoor metal ladder serves as a second means of egress from the second floor. This ladder is rusting and its guardrails do not meet current codes.

ENVELOPE

The office space is currently separated from the warehouse by partial height plaster walls. These appeared to be original to the building. Walls were made of a layer of plaster on metal lath on both sides of steel channels. Single pane steel windows were installed in these plaster walls. On the second floor wood framed ceilings once present have been removed.

The envelope enclosing the office space appears structurally sound, but it does not meet current energy codes and will have to be upgraded with continuous insulation and a continuous air barrier. All fenestration and doors that are part of the envelope will have to be upgraded to meet current energy standards.

INTERIOR FINISHES AND FIXTURES

All interior finishes and fixtures are aging and will be demolished.

PHOTOGRAPHS

June 22, 2023 Page 6

PART C- ARCHITECTURAL DESIGN

EXTERIOR

EXTERIOR FINISHES

The tenant has requested an upgrade to the exterior of the building. The entry R panel and fiberglass cladding will be removed and replaced with new exterior metal studs with insulated cavity with treated plywood sheathing and an applied air barrier. The exterior finish will be a combination of wood siding, brick, and metal. The same treatment will be wrapped on the side of the building at the new exit.

New thermally broken fixed and single hung windows will be installed.

EXTERIOR WAREHOUSE FINISHES

The existing plaster/stud walls will be enclosed with new exterior metal studs with insulated cavity with treated plywood sheathing and an applied air barrier. The exterior finish of the warehouse facade will be a combination of wood siding and brick.

New thermally broken fixed and single hung windows will be installed.

The existing west wall of the warehouse will be insulated with rigid insulation to create a semi conditioned space for utilities and infrastructure.

ACCESSIBILITY

Ramps are provided at the access doors to the first floor, in compliance with accessibility guidelines.

Design of the new interior first floor space layout is compliant with accessibility rules. However the second floor is not accessible, but equal facilities are provided on the first floor.

EGRESS

New layout developed for this phase indicates a new access door on the north wall, directly from outside of the building, per discussions with MARAD representatives during the kick-off meeting. A secondary egress door is placed on the south -west corner of the office, exiting into the warehouse.

Access to the second floor will be though a new code-compliant staircase enclosed with new 1-hour fire rated walls. The proposed layout shows a single means of egress from the second floor, for an occupant load of the second floor of maximum 49 people. A maximum capacity sign will be posted for the second floor.

INTERIOR

INTERIOR FINISHES

Remaining perimeter plaster walls will have to be furred out with gypsum board on metal studs to allow concealed installation of electrical and communication conduits.

New interior walls will consist of typical metal studs and gypsum board walls. Wood doors with hollow metal frames and sidelights will be installed. Interior glazed partitions for conference rooms are proposed.

New finishes will be installed throughout. Anticipated finishes are typical of an office environment:

carpet tiles, luxury vinyl tile, painted gypsum board walls, plastic laminate cabinetry with solid surface counters, porcelain tile for the wet floor and wall areas in the restrooms and showers. Moisture content of the first-floor slab will have to be evaluated for the suitability of installation of glued down finishes.

June 22, 2023 Page 7

Treatment of the first ceilings will pose some challenges, due to the low head heights below the structural elements. Gypsum board dropped ceilings are scheduled to hide the HVAC ductwork. Where possible the ceilings will be attached to the existing wood decking, elsewhere lay-in ceilings will be added held as close as possible to the existing joisrs.

EXISTING ROOF TREATMENT

Closed cell foam insulation will sprayed to the underside of the roof deck to meet current energy codes.

The insulation will be finished with a fire code compliant colored spray foam. Steel trusses and purlins running through the second floor of the space will be painted and left exposed.

SYSTEMS, EQUIPEMENT AND FURNITURE

All equipment and furniture are anticipated to be moved from the current lease in the Hale Boggs Federal Building.

A new access control system per MARAD’s specifications will be installed.

New data cables and fiber will be brought to the proposed LAN room from the demarcation point.

Contractor will install raceways and MARAD will install equipment and pull cables.

SUSTAINABILITY

LEED

The project will not seek LEED certification; however, incorporating in the design sustainability guidelines described in the LEED certification system is highly desirable to MARAD. The design team will focus on optimization of energy performance of the space, reduction of potable water consumption, and enhancing the indoor air quality environment per LEED guidelines. Interior finishes with recycled content and low VOC’s will be specified. GSA’s sustainability requirements will be incorporated in the project specifications. The contractor will be required to divert minimum 50% of the waste from landfill, green purchasing measures will be adopted.

SUSTAINABLE DESIGN ELEMENTS

The following design elements have been incorporated into the project:

Architecture

• Upgrade Building envelope Insulation R-19 walls and R-30 Roof

• Retain existing exterior plaster walls and encapsulate the probable lead paint

• Request contractor to recycle demolished items as much as possible and submit the quantities

(percentage) of demolished items that were recycled.

• Request Contractor to recycle material packaging as much as possible and submit the quantities of items that were recycled.

• Low VOC Finishes and Compounds

• Utilize construction materials with significant recycled content such as steel studs

• Operable windows for natural ventilation.

• Windows will be hurricane resistant

• Double pane windows with thermally broken frames

• Windows to allow in natural light

• Carbon Capturing materials such as wood and carpet tiles

Electrical

• High efficiency LED Light fixtures

• Occupancy sensor light controls

June 22, 2023 Page 8

• Rough-in for future electric car charging stations

• Rough-in for future canopy mounted solar arrays

• Metering power use to track energy usage

• All electric devices (no natural gas)

HVAC

• High SEER HVAC Units zoned for first and second floors

• Ductwork in conditioned space instead of an attic

• Separate split HVAC system for IT and security rooms

• Programmable thermostats

Plumbing

• Water metering

• On demand undercounter water heater for first floor break room

• Central electric on demand water heater for restrooms and shower

• High-Efficiency low flow toilets

• Performance low flow showerhead

• Water-Saving low flow faucets

LIFE SAFETY

FIRE SPRINKLER SYSTEM

The existing fire sprinkler system will be removed back to the connection to the main. A new system will be installed throughout the office spaces.

FIRE ALARM SYSTEM

A new code required fire alarm system will be installed.

June 22, 2023 Page 9

PART D- MEP DESIGN NARRATIVE

MECHANICAL SYSTEMS

PROPOSED MECHANICAL DESIGN

The existing HVAC systems serving the building will be removed in their entirety. The renovated building will be served by a new, high efficiency, variable refrigerant flow (VRF) heat pump system.

The second floor will be served by (1) 5-ton vertical air handling unit and the first floor with (1) 6-ton vertical air handling unit, both with ducted supply and return. Each indoor unit will be served by a dedicated heat pump located inside the warehouse on the river side of the building with bollard protection. The VRF system will be equipped with a direct digital control system capable of both local and remote web-based access. Remote access will be subject to the agency’s LAN access restrictions.

The bathrooms will be exhausted via individual fans equipped with motion control sensors to limit the operation time.

ELECTRICAL SYSTEMS

EXISTING CONDITIONS

The primary electrical service voltage is 480 volt, 3 phase. An existing transformer steps down the voltage to 208Y/120 supplied to this space. A 150KW diesel generator and 400 amp main service disconnect and automatic transfer switch provide standby back-up power.

The existing electrical infrastructure (including panels and equipment serving other areas/buildings) is located on the front (west) face of the building.

Aside from the main electrical panel and upstream components, all existing electrical systems, devices, fixtures, and related electrical within the scope area are to be demolished.

PROPOSED ELECTRICAL DESIGN

All existing electrical infrastructure serving the tenant space is to be demolished. A new 480V panel, 480Y/120V transformer, and 208Y/120V panel are to be installed to serve the tenant electrical loads.

The 480V panel will be served from a new 150A/3P breaker in the existing generator distribution panel, meaning the entirety of the tenant space will be served by the existing diesel generator. Generator capacity to serve this space was confirmed by the Beaumont Fleet electricians on a recent site investigative visit. All new electrical panels/equipment are to be located in the dedicated tenant electrical room.

New branch circuit conductors shall be copper, #12 minimum and run in metal conduit, type EMT indoors and rigid galvanized steel outdoors.

Duplex receptacles shall be 20 ampere grounding type. Ground fault circuit interrupting (GFCI) type devices (20 A) shall be installed where required by NEC.

No more than 6 general purpose receptacles will be connected on any circuit and no more than 4 computers will be connected on any circuit. All 120 volt branch circuits shall be provided with a dedicated neutral.

All known equipment (refrigerators, microwaves, copiers, etc.) shall have dedicated 20 amp, 120 volt receptacles, or as required by equipment specifications.

A 4”x4” square box shall be provided for each communications outlet and a 3/4” conduit shall be routed from box to above accessible ceilings. Where accessible ceilings are not present, rigid conduit shall be neatly routed back to destination and painted to match ceiling.

Any new lighting will be LED and associated wiring shall be in conduit, type EMT.

June 22, 2023 Page 10

Occupancy sensors shall be provided in all offices, restrooms, and closets. Corridors and assembly areas shall include “sweep off” lighting controls for after-hours control of the areas.

Emergency lighting shall be designed in all paths of egress, in assembly areas, in group restrooms, and interior areas without natural illuminations. The emergency lighting shall be designed to provide at least 1 foot-candle average and at any point not less than .1 foot-candle. A maximum to minimum illumination uniformity ratio of 40 to 1 shall not be exceeded per NFPA 101 7.9.2.1. Exterior exit points shall have emergency lighting. Battery back-up shall be provided for emergency fixtures.

Contractor will provide raceway for data and fiber to be pulled by DOT. The demarcation point is located at the northwest corner of the warehouse.

Two 4” capped conduit sleeves will be provided in the tenant electrical room to below the wharf to intercept for future solar power scope.

PLUMBING SYSTEMS

PROPOSED PLUMBING DESIGN

The existing plumbing systems will be replaced in their entirety up to the point of connection to the existing lift station, which shall remain. The domestic water system shall be connected to the existing domestic water main on the east side of the warehouse and to the extent possible the new plumbing run on the exterior of the building as is currently the case. A new tank type electric water heater will be provided for the shower and point of use electric water heaters for all lavatories and sinks. All domestic water piping will be insulated copper.

The sanitary waste piping will be run beneath the wharf and connected to the existing lift station. All new piping above the wharf will be solid wall PVC and the piping below the wharf will be schedule 80 solid wall PVC for improved damage resistance. The sanitary waste above the wharf shall be run on the exterior of the building.

All new plumbing fixtures will be commercial grade with low consumption solid brass trim. Unless directed otherwise all fixtures will be manual operated.

The abandoned air compressor system shall be removed.

June 22, 2023 Page 11

APPENDIX

The following information is attached for references:

• Electric Vehicle Charging Station

• Light Fixtures

• HVAC Load Calculations

• Plumbing Fixtures

CT4000

Networked Charging Station

Site Design Guide ii

IMPORTANT SAFETY INSTRUCTIONS:

SAVE THESE INSTRUCTIONS

Product Disposal Follow proper disposal methods according to local authorities. Re-using, recycling, or correctly processing obsolete devices is an important contribution to environmental protection. Product materials are recyclable as marked.

No Accuracy Guarantee Commercially reasonable efforts were made to ensure that the specifications and other information in this manual are accurate and complete at the time of its publication. However, the specifications and other information in this manual are subject to change at any time without prior notice.

Copyright and Trademarks ©2013-2019 ChargePoint, Inc. All rights reserved. This material is protected by the copyright laws of the United States and other countries. It may not be modified, reproduced or distributed without the prior, express written consent of ChargePoint, Inc. CHARGEPOINT is a U.S. and European Union registered trademark and service mark of ChargePoint, Inc. and cannot be used without the prior written consent of ChargePoint.

WARNING:

1. Read and follow all warnings and instructions before installing and operating the ChargePoint® Charging Station. Install and operate only as instructed. Failure to do so may lead to death, injury, or property damage, and will void the Limited Warranty.

2. Only use licensed professionals to install your ChargePoint® Charging Station and adhere to all national and local building codes and standards. Before installing the ChargePoint® Charging Station, consult with a licensed contractor, such as a licensed electrician, and use a trained installation expert to ensure compliance with local building and electrical codes and standards, climate conditions, safety standards, and all applicable codes and ordinances. Inspect the Charging Station for proper installation before use.

3. Always ground the ChargePoint® Charging Station. Failure to ground the Charging Station can lead to risk of electrocution or fire. The Charging Station must be connected to a grounded, metal, permanent wiring system, or an equipment grounding conductor shall be run with circuit conductors and connected to the equipment grounding terminal or lead on the Electric Vehicle Supply Equipment (EVSE). Connections to the EVSE shall comply with all applicable codes and ordinances.

4. Install the ChargePoint® Charging Station using a ChargePoint approved method. Failure to install on a surface that can support the full weight of the Charging Station can result in death, personal injury, or property damage. Inspect the Charging Station for proper installation before use.

5. This charging station is not suitable for use in hazardous locations.

6. This device should be supervised when used around children.

7. Do not put fingers into the electric vehicle connector.

8. Do not use this product if the flexible power cord or EV cable is frayed, has broken insulation, or any other signs of damage.

9. Do not use this product if the enclosure or the EV connector is broken, cracked, open, or shows any other indication of damage.

10. Use 75°C or 90°C wire copper conductors only.

Important: Under no circumstances will compliance with the information in this manual relieve the user of his/ her responsibility to comply with all applicable codes or safety standards. This document describes the most commonly-used installation and mounting scenarios. If situations arise in which it is not possible to perform an installation following the procedures provided in this document, contact ChargePoint, Inc. ChargePoint, Inc. is not responsible for any damages that may result from custom installations that are not described in this document or for any failure to adhere to installation recommendations.

iii

Symbols Used in This Document

This guide and product use the following symbols:

DANGER: Risk of electric shock.

WARNING: Risk of personal harm or death.

CAUTION: Risk of equipment or property damage.

Important: Crucial step for installation success.

Read the manual for instructions.

Ground/protective earth.

iv iii

Contents

1 Site Design Guidelines Initial Site Guidelines Charging Station Placement

2 Civil and Mechanical Design Wall Mount Stations Pedestal Mount Stations Drainage Clearances Accessibility

3 Electrical Design Upstream Components Conduit Wiring Requirements Wiring Diagram Grounding Requirements Cellular Connectivity

4 CT4000 Pedestal Mount Concrete Preparation Concrete Mount Kit Installation into New Concrete Installing on Existing Concrete iv

1Site Design Guidelines

This document describes how to design a project site for the ChargePoint® CT4000 networked charging station for electric vehicles. This includes guidelines and best practices for electrical infrastructure and capacity planning, construction and concrete work required prior to installation of charging stations, and cellular signal requirements.

For full specifications and certifications for CT4000 charging stations, refer to the CT4000 Data Sheet found online at: chargepoint.com/products/guides.

Initial Site Guidelines ChargePoint recommends that you plan to install charging stations for 5-10% of parking spaces at commercial buildings, or 10-20% for high EV adoption areas like California. Designing electrical infrastructure to support current and future needs for EV charging helps avoid costly upgrades later as demands for EV charging grows.

Electrical Requirements

An onsite evaluation is needed to determine conduit and wiring requirements from the panel to the proposed parking spaces, construction and concrete requirements for mounting the charging stations, as well as to measure cellular signal levels and identify suitable locations for any necessary cellular signal booster equipment.

Review the CT4000 Data Sheet at chargepoint.com/products/guides.

Each Level 2 charging port requires:

• a dedicated single-phase electrical circuit (32 A at 208/240 V).

• a new dual pole breaker 40 A circuit breaker at the electrical panel. (Used breakers can damage equipment and cause a fire risk.)

• Conductor wiring sized in accordance with the National Electric Code requirement for 125% capacity for continuous load for all branch circuits from panel to stations via raceway or conduit.

Consequently, a CT4000 charging station with two charge ports requires two circuits and two new dual pole 40 A circuit breakers. If power capacity is limited at a site or to reduce costs for electrical infrastructure, consider ChargePoint Power Management options for power sharing at the circuit level, panel level, transformer, or site level.

https://www.chargepoint.com/products/guides/ https://www.chargepoint.com/products/guides/ https://www.chargepoint.com/files/datasheets/ds-ct4000.pdf http://www.chargepoint.com/support/guides

Cellular Connectivity

The CT4000 charging station needs strong cellular connectivity to allow ChargePoint to communicate with the station. A connection is needed for station owners and operators to access these features:

• User authentication, access control, and billing

• Energy usage reporting

• Charging station utilization and charging session details for analytical reporting

• Real-time charging status to drivers using the ChargePoint mobile app or web portal

• Ability for drivers to use the ChargePoint mobile app and Tap to Charge, Apple Pay, or Android Pay on their smartphone to start and stop sessions

• Text or email notifications to drivers when vehicle battery is full or stops charging

• Notifications to drivers prior to pricing increases for overstay of parking at EV spots

• Station fault alarms and remote diagnostic capability

• Over-the-air software upgrades for new station features or enhancements

If you have preexisting infrastructure or are using your own preferred electrical contractor to prepare your site, a Site Validation by a ChargePoint Operations and Maintenance (O&M) partner is required to certify compliance with electrical specification requirements, and to ensure everything was prepared to ChargePoint specifications.

Charging Station Placement To help minimize costs, choose station locations that are as close as possible to the available electrical infrastructure. Selecting these types of locations helps minimize long conduit and wire runs, as well as any trenching work.

Layout Considerations

• Identify station locations for EV charging spots.

• To help minimize costs, choose station locations that are as close as possible to the available electrical infrastructure.

• Consider locations where it will be easy to add future stations.

Important: Always check local codes or consult an engineer to ensure the site is prepared in compliance with all applicable regulations. Local authorities might not allow a unit to operate if it is not installed to code.

WARNING: The ChargePoint Charging Station must be installed on a level concrete base or attached to a flat wall. Asphalt cannot support the full weight of the Charging Station.

Failure to install the ChargePoint Charging Station on a level concrete base or a flat wall may cause the Charging Station to tip over, resulting in death, personal injury, or property damage.

• Consider how easily drivers can find the stations they need to access.

• Identify suitable locations with smooth, plumb surfaces for wall mount stations or suitable floor surfaces for pedestal mount stations.

• Determine raceway or conduit runs for electrical wiring from the electrical panel. Consider a layout to minimize linear conduit costs to all proposed EV parking spaces. If possible, avoid or minimize trenching requirements, especially more costly trenching to run conduit under asphalt surfaces.

• Consider ADA compliance. The charging station should not block ramps or pathways and the bottom of the screen cannot be more than 48 inches above the level of the parking stall.

• Choose adjacent parking spaces in an area with adequate lighting.

• For stall parking, ChargePoint prefers using perpendicular parking stalls to better accommodate EVs with front and rear charge ports.

Note: While ChargePoint tests charging stations with a majority of upcoming vehicles, ChargePoint cannot guarantee the port locations of future vehicles and cannot warrant the configurations proposed will work for all vehicles.

• Use dual-port pedestal mount stations where possible in open areas for adjacent parking or adjoining parking spaces.

• Consider protective bollards and wheel blocks where appropriate, especially for open tandem parking spaces.

Electrical Considerations

• Evaluate existing electrical infrastructure to determine if the existing utility service and electrical panel capacity is sufficient. Ensure the electrical wiring, overcurrent circuit protection, and metering (if required) is in place by reviewing the data sheet, as well as the wiring diagram and grounding requirements in this document.

• Ensure the electrical wiring, overcurrent circuit protection, and metering (if required) is in place by reviewing the data sheet, as well as the wiring diagram and grounding requirements in this document.

• Ensure that you use 16 mm2 (6 AWG) or 10 mm2 (8 AWG) wire to the station. If you will be feeding the station with larger wire (like 25 mm2 (4 AWG), you will need to splice the wire for 16 mm2 (6 AWG) or 10 mm2 (8 AWG). For each charging port, only three wires are required: L1, L2, and Ground. For dual port stations, only five wires are required as both ports share the same Ground wire.

Note: Neutral must be bonded to Ground upstream at the transformer or panel for each separately derived system.

• Identify costs for any necessary upgrades and/or a new dedicated electrical panel.

This is the start of the file's text. The full file is on GovTribe.