LA_ESPC_Q A_2-22-2013.pdf
PDF 62 KB Posted
- Attached to
- Los Angeles ESPC Federal contract opportunity
- Solicitation number
- GS-09P-12-KS-C-0023
About this file
LA ESPC Questions and Answers dated Feb 22 2013
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS AND ANSWERS
2-22-2013
QUESTION: Which agency is the actual Owner of the building?
ANSWER: GSA controls the buildings covered under this solicitation on behalf of the U.S.
Government.
QUESTION: I have a question about the bid bond requirement. We weren’t quite sure what the RFP was looking for. Is it for the IGA? Also, typically the standard federal forms are filled out by KO. The copy we have is blank. Are you guys going to fill that in?
ANSWER: The form is blank and is to be completed by Offeror. Principal - list legal name and the business address. Type of organization - check one if your business is individual/partnership/joint venture/corporation. Surety - list the name and business address of your surety. Penal sum of bond - either 20% of bid price or $3MIL, whichever is greater. Bid
Date: list the date of your submission. Invitation No.: List the Solicitation Number GS-09P-12-
KS-C-0023. In case you need to list the certificate holder name, you may use the following information:
GSA/PBS Energy and Sustainability Branch
450 Golden Gate Ave, 4th Floor East
San Francisco, CA 94102
Note that the “bid price” for this purpose should be the capital amount proposed for all mandatory measures. This solicitation requires bidding against all mandatory measures, and does not have a separate IGA stage. For purposes of the bid bond the “bid price” does not need to include the O&M price.
QUESTION: We currently only have 6 months of metering for the central plant. We need a full 12 months of continuous operations and metering in order to establish a baseline for your current energy consumption. Once we have 12 months of metering bills we will be able to calculate any potential energy savings in upgrading the central plant.
ANSWER: This is not available. We are posting a zip file that has 2 weeks of chiller plant trend data that was used to validate the last project. We are also providing the resulting M&V report.
QUESTION: In order to do a proper mechanical material take off we need a scaled mechanical drawing of the chiller room. Is there any way an electronic drawing either
PDF or Auto Cad can be provided?
ANSWER: We are posting a zip file that contains record documents (PDF) from the last chiller project.
File details come from the government source that posted it. Updated .