U.S. General Services Administration
Pre-Proposal Conference Construction Manager as Constructor (CMc)
Repair and Alteration Project at the United States District Courthouse Solicitation Number: GS-04-P-17-BV-C-0008
GSA Southeast Sunbelt Region
Agenda
• 9:00 - 9:30 Registration
• 9:30-10:30 Conference
• 10:30 - 11:00 Site Tour Travel
1 N Palafox St Pensacola FL
• 11:00 - Noon Tour Site
• Noon: Conclude Site Visit
Purpose
• To introduce the project team; describe goals and objectives of the program; provide instructions about the solicitation process and design; provide a tour of the facility and site and discuss strategic plans
Project Team
• GSA Team:
– Michael Reece – Contracting Officer
– Rosalind Cherry – Contract Specialist
– Steven Smith – Project Manager/COR
– Kevin Dunham – Design Manager/COR
• Designer TTVArchitects, Inc
– Christopher Noel, AIA, LEED AP - Senior Vice President
• Construction Manager As Agent (CMa)
– TBD
Goals and Objectives Project Goals:
• Invest in the Pensacola community through civic architecture.
• Provide a safe, productive, and attractive space for employees and visitors.
• Provide the best value to GSA’s customer agencies and the American taxpayer.
• Complete construction operations in a safe, efficient, and effective manner.
• Maximize the project’s contributions to environmental sustainability and to national energy security, where practicable within the scope of the project.
Project Objectives:
• Resolve all current water intrusion and indoor air quality problems exhibited in the building.
• Mitigate risk of loss/further damage to interior finishes during façade demolition and construction and replacement of HVAC systems.
• Partner with GSA and the project Architect-Engineer (A/E) to improve project constructability, increase project value, and expedite project delivery wherever feasible.
• Meet all applicable federal energy and resource conservation goals and security requirements.
Solicitation Process
CMc Services Contract will be solicited through a Request for Proposal (RFP) in accordance with FAR 15 Source Selection. The objective of Source Selection is to select the proposal that represents the best value to the government.
Design
• Description of Project To Be Constructed
– See TTV Presentation
CMc Services
• Construction Manager as Constructor (CMc).
The CMc will provide professional, technical, administrative and clerical personnel as needed to perform all required services including, but not limited to, those described in this Request for Proposals.
CMc Contract Base Contract:
• Design phase services will be awarded as a firm fixed- price
Options:
• Construction Services at a Guaranteed Maximum Price (GMP Option)
Services:
• Services shall be as identified in the RFP and includes:
– Constructability reviews and cost estimating during design
– The GMP will be tracked through open book accounting that will be reviewed and monitored by GSA and a third party Construction Manager as Agent (CMa) until final design.
– A firm fixed price will be established prior to NTP for construction.
Schedule
• Proposals Due6/23/17
• Interviews 7/10-7/11(e)
• Award 8/15/17(e)
• 65% Construction Documents 8/7/17(e)
• 100% Construction Documents1/15/18 (e)
• Substantial Completion 9/30/19
Site Tour
• Travel to Site: 1 N Palafox, Lobby